Question and Answers.docx
DOCX document 15 KB Posted
- Attached to
- NSWCPD IMS/Project Management Request Federal contract opportunity
- Solicitation number
- N6449822Q5034
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6449822Q5034_0002 Solicitation Amendment.pdf | ||
| N6449822Q5034_0001.pdf | ||
| Question and Answers.docx | DOCX document | |
| 4c. - CDRL A003 - Technical Report-Study Services (Tech Support, Recommendations, Briefing Support).pdf | ||
| N6449822Q5034.pdf | ||
| 4b. - CDRL A002 - Technical Report Study - Services (IMS - Program-Program Management).pdf | ||
| 4a. - CDRL A001 - Contract Status Report.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question and Answers – 1/20/2022 N6449822Q5034 - IMS/Project Management Support Services
1. The requirement mentions 8 months, does the government expect the Project Manager III, Project Manager II to be available full-time during that period of time?
0. YES
1. Is there an incumbent currently performing these services? If there is, would the incumbent be available for this opportunity.
1. YES – MPR Associates – CAGE 6B701
1. Does the Service Contract Act apply to this contract?
2. No, exempt under 29 CFR 541.300 – Contracts for professional services
1. It seems there are certain hours allocated for a Project Manager III and Project Manager II, ideally could this be combined into 1 full-time person?
3. No – the hours may not be combined, we are seeking two separate personnel as specified in the SOW
1. What are the hours of operation for this role?
4. 9-5
1. Beyond the 8 moths, does the government intend to extend this contract?
5. No – if the further support is required, a new contract solicitation will be posted.
1. How often would the contractor team need to visit NSWCPD? Could the work be remote?
6. Work will be performed at both the contractor facility and at NSWCPD in accordance with the travel requirements specified in Section 8.2; any authorization of remote work (i.e. telework) will be determined by the contractor policy and not by the government.
1. When does the government anticipate an award? How long after the award does the government expect services to begin?
7. TBD
7. IMMEDIATELY
Question and Answers – 1/26/2022 N6449822Q5034 - IMS/Project Management Support Services
1. Since the role maybe remote or at contractor facility, does the government expect both roles to have an active secret level clearance?
0. No clearance required
1. Is it the expectation of the government to retain the existing incumbent employees performing this work?
1. NO. As this is a new competitive request, it is not the Government’s intention to retain current contractors.
1. In reading the Solicitation, listed on page 63, The offeror shall provide a copy of the GSA Schedule contract including the contractor’s pricelists. The proposed unit prices proposed shall be the Offerors Firm-Fixed-Price contract prices for each CLIN.
· Is it expected that this is a GSA requirement?
2. In the event a GSA schedule contract is available please notate the contract number. Otherwise this not applicable.
1. Would LOI’s count as part of the technical page count? Would the government consider removing the Volume II Page count so as to properly include the resume’s and LOI’s if applicable?
3. LOIs will not count towards page count.