Amend 0001 20R6008 Final.pdf
PDF 258 KB Posted
- Attached to
- Construct UPO PEB, Camp Johnson
- Solicitation number
- N6247020R6008
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N4008519B0074 Drawings.pdf | ||
| N4008519B0074 Specs.pdf | ||
| RFP N6247020R6008.pdf | ||
| Master PPI Form Template.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
19-0074 Construct UPO PEB, Camp Johnson Solicitation N6247020R6008 Marine Corps Base Camp Lejeune, North Carolina Amendment 0001
Block 14. DESCRIPTION OF AMENDMENT (cont.)
A. The following provides the Government’s responses to pre-award inquiries:
REFERENCE QUESTION GOVERNMENT RESPONSE
Page Section Para.
A‐4 Plans Notes Drawing A‐4 indicates that the Standing
Seam Roof Panels are to be Pre‐Finished
Aluminum. However Spec Section 13 34
19, Paragraph 2.4 also indicates that the
Roof Panels are to be 22 Gauge Steel
Panels with a Kynar 500 Finish. Are Pre‐
Finished Kynar 500 Steel Panels also acceptable for use on the project if they can meet the warranty requirements indicated in Paragraph 1.10?
Provide steel standing seam roof as specified.
B. All other contract terms and conditions remain unchanged.
| Amnd 0001 20R6008 |
| Untitled |
| Untitled |
Pg2 Amnd 0001 20R6008
| IDCode: |
| Page: 1 |
| Pages: 2 |
| AmendNo: AMENDMENT NO. 0001 |
| EffDate: 06/01/20 |
| ReqNo: |
| ProjNo: 19-0074 |
| IssCode: ROICC81 |
| IssuedBy: OICC FLORENCE |
ROICC FLORENCE CAMP LEJEUNE
1121A HAMMOND ROAD
CAMP LEJEUNE, NC 28547
| AdmCode: |
| AdminBy: See Item 6 |
| ContName: |
| ContStrt: |
| ContCnty: |
| ContSt: |
| ContZIP: |
| Code: |
| FacCode: |
| SolChgYs: Yes |
| SolChgNo: Off |
| SolAmdNo: N6247020R6008 |
| AmendDate: 05/15/20 |
| ModNo: |
| ModDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Off |
| OffrNoEx: No |
| ApprData: |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: |
N6247020R6008 Construct UPO PEB, Camp Johnson
The date and the hour for the receipt of proposals remains 17 Jun 2020 no later than 2:00 pm (EST).
See continuation page(s).
| SignName: |
| SignTitl: |
| ContDate: |
| CoName: |
| CoTitle: |
| CODate: |
File details come from the government source that posted it. Updated .