SynopsisQ A_Posting_7Aug09.pdf

PDF 17 KB Posted

Attached to
Fielded Training Systems Support (FTSS) III Federal contract opportunity
Solicitation number
N61339-09-R-0016
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

Questions and Answers

View the file

Other files for this federal contract opportunity

Other files attached to Fielded Training Systems Support (FTSS) III, newest first.
File Type Posted
Amendment_004.zip ZIP file
Amendment_003.zip ZIP file
Amendment_002.zip ZIP file
Amd01_N61339-09-R-0016.doc DOC document
FTSSIII_NASTP.zip ZIP file
FTSSIII_E-2C.zip ZIP file
FTSSIII_GENERAL.zip ZIP file
N61339-09-R-0016_FTSSIII_Official RFP.doc DOC document
Q107 - Multi-part question Rev 1_28Oct09.doc DOC document
Synopsis Posting_28Oct09.xls XLS spreadsheet
Synopsis Posting_14Oct09.xls XLS spreadsheet
Att 3_MOPAS QASP_FINAL_DRAFT.doc DOC document
Synopsis Posting_22Sept09.pdf PDF
FTSS III pre-solicitation conference brief_FINAL1.ppt PPT presentation
Jax_Information.pdf PDF
Norfolk_Information.pdf PDF
CherryPoint_Information.pdf PDF
PtMugu_Information.pdf PDF
FTSSIII_PreSolAgenda.pdf PDF
SBSA_MAC_FILES.zip ZIP file
UNRESTRICTED_MAC_FILES.zip ZIP file
GENERAL_RFP_DOCUMENTS.zip ZIP file
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Control # (if assigned)

Topic Question Question Reference Response Amendment/ Correction Required?

001 CIS Chart question Old version CIS chart had hours per week CIHWP, new chart has Type CI Req’t twice.

Please verify if this chart is in error.

Attachment L-3 CI Manning Charts

The Attachment Columns in the DRAFT version are incorrect.

The Final RFP version will replace the second column with

CIHPW.

The Government may add a third and fourth column for offerors to show CI hours per month and hours per quarter in order to denote the cyclic nature of the once-per-quarter scheduled surge requirement. This element is in work.

Yes

002 CIS Chart question Paragraph 2.2.1.b indicates we have to do one manning chart per LOT.

Manning Chart Notes state we can combine LOTS into one chart where there are no changes. I. E. LOTS III-V.

Please verify which is correct

RFP Paragraph 2.2.1.b RFP Section L 2.2.2.b is correct, one chart is required for each Lot/FY period. The Attachment L-3 Note has been revised for issuance in the Final RFP.

Yes

003 NFO Stair Step Chart 2.2.1.a-1 states 48 hrs/week for NFO. However, Appendix A does not show same hours in Table 5.2-2. Table shows 12, 24, 36 hour blocks. Please clarify which number we are to use.

RFP Paragraph 2.2.1.a and Appendix A chart 5.2.-2

The chart in RFP L 2.2.1.a will be revised in the Final RFP release. The format in the chart should have read hours per day, versus hours per week, and should have used 36 as in the associated CIS Appendix A.

The Government is working to finalize the user requirements for the late FY10 period. For purposes of this temporary Question response, the three hourly availability periods are 12, 24 and 36 hours per day.

However, the Government may choose to revise both the Section L 2.2.1.a table and the CIS Appendix A to provide pricing and support for 12, 24, 36 and 48 hours per day, or change the format to represent the flexibility desired by requesting hours per week, per month

Yes

8/7/2009 assigned)

Topic Question Question Reference Response Amendment/ Correction Required?

005 Additional Instruction

Section G.2 states “Additional instruction in excess of 15% per week per line item must have contractor concurrence.” The example given is 8 hr/day x 5days = 40 HPW x 15% = 6 additional hours instruction per week.

In Appendix A to Addendum B, Table 5.2-1 & 5.2-2, the Additional Instruction column exceeds the 15% on all stair steps except the 36 hr/day stair step in Table 5.2-2.

Please clarify this discrepancy. Does Section G.2 relate to the MAC and Appendix A to Addendum B tables relate only to the instant task order?

PAGE NUMBER: 23 of PARAGRAPH: Section G.2

PAGE NUMBER:

Appendix A to Addendum B, pgs A-3 & A-5 PARAGRAPH: Table 5.2-1 & 5.2-1

RFP Schedule G.2 is correct as written and applies at the MAC level. Within Appendix A to Addendum B, paragraph 5.2 and tables 5.2-1 and 5.2-2 will be revised in the Final RFP to state that they supersede the Schedule G.2 and establish the specific Additional Instruction limitations for this task order (that may be unilaterally implemented by the Government).

Yes

006 CTT Table 2.2.1.a-1 in section L lists NFO at 48 hours/week; Table 5.2-2 shows the NFO at 12, 24, and 36 hours/day.

Based on a 5 day work week, none of the hours/day shown equal 48 hours/week, 48 hours /week would equal 9.6 hours/day.

What “hours/day” should be used to build our staffing plan?

PAGE NUMBER: 98 of PARAGRAPH: L. Part B, Volume 2, Sect. 2.2.1.a PAGE NUMBER: Add. B, App A, pg A-5 PARAGRAPH: Table 5.2-2

Reference the Government’s answer in “DRAFT_RFP_003 Response”.

Yes

007 CTT Table 2.2.1.a-1 in Section L lists Pilot hours/week at 20; Table 5.2-1 has 2 hours/day “bold.”

Should the 4 hours/day be “bold” to match the 20 hours/week?

PAGE NUMBER: 98 of PARAGRAPH: L. Part B, Volume 2, Sect. 2.2.1.a PAGE NUMBER: Add. B, App A, pg A-3

The Government did not intend to have any bold text in the Addendum B table. The Final RFP will provide correlated requirements.

Yes

008 CTT Table 2.2.1.a-1 in Section L lists the PRISim device at 8.5 CTT.

Appendix M lists the PRISim device at 8

CTT.

Which is correct?

PAGE NUMBER: 98 of PARAGRAPH: L. Part B, Volume 2, Sect. 2.2.1.a PAGE NUMBER: Add. A, App M, pg M-4

PARAGRAPH: 4.1

The Appendix M is correct. Section L Table 2.2.1.a-1 will be revised in the Final RFP for 8.0 CTT.

Yes assigned)

Topic Question Question Reference Response Amendment/ Correction Required?

009 Provisioning Paragraph 4.12 tasks the contractor to buy new spare parts for new devices or modified devices. The statement at the end of the paragraph says the contractor is responsible for all costs associated with procurement and delivery, so we understand we are responsible for the cost.

Is it correct that the Government will reimburse the contractor?

PAGE NUMBER: Add A, page II-25

PARAGRAPH: 4.12

The Government anticipates that procurement of spares as described in SOW 4.12 would be accomplished as an Over and Above Work Request (OAWR), for which the Contractor would be funded. However, the specific process, mechanisms and funding considerations have not yet been fully developed and offerors should not assume the OAWR approach is the final position. Regardless of the process or mechanism, it is not intended for offerors to propose a price in this solicitation for anything associated with this provision.

Separate from the above response, the Government is also developing an approach to address the rapid obsolescence of spares for some COTS products, such as PC video cards.

The Government is aware that the historically stable material and spares baseline established at a training device initial delivery is becoming more dynamic as COTS product increase in the overall content of the training device. The Government anticipates inserting new language, potentially within this paragraph, to define a process to maintain the Government’s inventory value as the content within the invento

Yes

016 OHPD PRISim

Device Task 17B Specifies 10 OHPH. Can we assume that this is a typographical error that should be OHPD?

PBW, Task 17B The Offeror is correct; the PBW for Task 17B in all LOTs will be revised to read 10 OHPD.

Yes

In Process In Process In Process

In Process In Process In Process In Process In Process In Process

In Process assigned)

Topic Question Question Reference Response Amendment/ Correction Required?

021 Parts Consumption Data

Does NAVAIR plan to provide parts consumption and repair data for FTSS III training devices and support equipment? The following specific information would be helpful in estimating the cost of spares and repairs.

a. 6-12 months of maintenance action forms detailing what maintenance repairs were required and the corrective action.

b. A listing of equipment in the maintenance support package.

c. A listing of tools and support equipment that is to be supported under the E-2C contract.

d. A list of spares for any modified equipment.

REFERENCE: Addendum

A – E-2C COMS SOW

PAGE NUMBER:

PARAGRAPH 4.3, pages II- 15 through I-16

a. The Government is making available a one-year history of maintenance actions performed, as recorded by the incumbent. This data is planned to be provided at each site during the site visits phase. It may be posted later in the Government’s solicitation Technical Library.

b. The Government is making available the most recent material, spares, tools & test equipment and Government Furnished Equipment inventory in the format required by CDRL on the current contract. This data is planned to be provided at each site during the site visits phase. It may be posted later in the Government’s solicitation Technical Library.

c. See item b above.

d. See item b above.