Text version

vessel name

INSERT CONTRACTOR/COMPANY NAME HERE
Project =YD-248DATE: =
PRIMESUBCONTRACTORPRIME
Carney, Sean R CIV PSNS&IMF, Code 411: =MH*Labor Rate*G&APRIME

Carney, Sean R CIV PSNS&IMF, Code 411: =(Prime Material Price+Subcontractor Total)*Profit Rate

PARAGRAPH No.TITLEM/HMATERIAL PRICETOTAL
Carney, Sean R CIV PSNS&IMF, Code 411: =(MH*Labor Rate)+Material PriceLabor CostMaterial CostTOTAL

Carney, Sean R CIV PSNS&IMF, Code 411: =Sub Cost (F) Other Direct Cost (ODC)* G&A PROFIT Line Item Total Carney, Sean R CIV PSNS&IMF, Code 411: =SUM(Prime Total+Subcontractor Total+ODC+G&A+Profit)

1.4Arrival Conference$0.00$0.00$0.00$0.00$0.00
1.5Required Reports$0.00$0.00$0.00$0.00$0.00
1.6Progress Meeting$0.00$0.00$0.00$0.00$0.00
1.7Availabilty Requirements$0.00$0.00$0.00$0.00$0.00
1.8Care of Vessel$0.00$0.00$0.00$0.00$0.00
1.11Condition Found Reports$0.00$0.00$0.00$0.00$0.00
1.13Safety Requirements$0.00$0.00$0.00$0.00$0.00
1.17Environmental & Hazardous Waste$0.00$0.00$0.00$0.00$0.00
1.19Weight Control$0.00$0.00$0.00$0.00$0.00
1.21Logistics Product Data$0.00$0.00$0.00$0.00$0.00
1.22Gas Free$0.00$0.00$0.00$0.00$0.00
1.23General Requirements for Testing$0.00$0.00$0.00$0.00$0.00
3.1Docking/Undocking$0.00$0.00$0.00$0.00$0.00
3.1.2Docking Procedure$0.00$0.00$0.00$0.00$0.00
3.1.3Blocking Plan$0.00$0.00$0.00$0.00$0.00
3.1.4Crib & Brace Blocking$0.00$0.00$0.00$0.00$0.00
3.1.5Setting & Alignment of Blocks$0.00$0.00$0.00$0.00$0.00
3.1.6Docking Conference$0.00$0.00$0.00$0.00$0.00
3.1.7Docking the Vessel$0.00$0.00$0.00$0.00$0.00
3.1.8Post Docking$0.00$0.00$0.00$0.00$0.00
3.1.9Undock Vessel$0.00$0.00$0.00$0.00$0.00
3.2.1Identify Distinguishing Figures & Markings$0.00$0.00$0.00$0.00$0.00
3.2.2Rubber Fenders Clean$0.00$0.00$0.00$0.00$0.00
3.2.3Rubber Fenders Replace$0.00$0.00$0.00$0.00$0.00
3.2.4Zinc Anodes$0.00$0.00$0.00$0.00$0.00
3.2.5Hull Blast and Preservation$0.00$0.00$0.00$0.00$0.00
3.2.6Hull & Freeboard Inspection$0.00$0.00$0.00$0.00$0.00
3.2.7Hull & Freeboard UT$0.00$0.00$0.00$0.00$0.00
3.2.8Skeg Repair$0.00$0.00$0.00$0.00$0.00
3.4.1Tanks Open, Pump, Vent, Clean, Gas Free$0.00$0.00$0.00$0.00$0.00
3.4.2Tank Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.4.3Tank Identify Color & Markings$0.00$0.00$0.00$0.00$0.00
3.4.4Tank Air Test$0.00$0.00$0.00$0.00$0.00
3.4.5Tank Preservation$0.00$0.00$0.00$0.00$0.00
3.4.6Tank Final Air Test$0.00$0.00$0.00$0.00$0.00
3.4.7Tank Pre Closeout Inspeciton$0.00$0.00$0.00$0.00$0.00
3.4.8Tank Closeout Inspection$0.00$0.00$0.00$0.00$0.00
3.4.9On Load Fuel$0.00$0.00$0.00$0.00$0.00
3.5.1Main Deck Non-Skid$0.00$0.00$0.00$0.00$0.00
3.5.2Main Deck Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.5.3Main Deck UT$0.00$0.00$0.00$0.00$0.00
3.6.1Superstructure Preservation$0.00$0.00$0.00$0.00$0.00
3.6.2Superstructure Non-Skid Repairs$0.00$0.00$0.00$0.00$0.00
3.6.3Superstructure Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.7.1Main Diesel Engine Repairs$0.00$0.00$0.00$0.00$0.00
3.7.2Main Diesel Engine Exhuast Preservation$0.00$0.00$0.00$0.00$0.00
3.7.3Aux Diesel Engine Exhaust Preservation$0.00$0.00$0.00$0.00$0.00
3.10.1Wire Rope Maintenance$0.00$0.00$0.00$0.00$0.00
3.10.2Wire Rope Inpsections$0.00$0.00$0.00$0.00$0.00
3.10.3Wire Rope Hook Inspections$0.00$0.00$0.00$0.00$0.00
3.10.4Boom Hoist Motor Repairs$0.00$0.00$0.00$0.00$0.00
3.10.5Wire Rope Sheave Repairs$0.00$0.00$0.00$0.00$0.00
3.10.6Equalizer Bar Repairs$0.00$0.00$0.00$0.00$0.00
3.10.7Main Hoist Limit Switch OP Testing$0.00$0.00$0.00$0.00$0.00
3.10.8Boom Hoist Limit Switch OP Testing$0.00$0.00$0.00$0.00$0.00
3.10.9Aux Hoist Limit Switch OP Testing$0.00$0.00$0.00$0.00$0.00
3.10.10Whip Hoist Limit Switch OP Testing$0.00$0.00$0.00$0.00$0.00
3.10.11Spud Lock OP Testing$0.00$0.00$0.00$0.00$0.00
3.10.12Deadman Switch Testing$0.00$0.00$0.00$0.00$0.00
3.10.13Main Hoist Load Testing$0.00$0.00$0.00$0.00$0.00
3.10.14Boom Hoist Load Testing$0.00$0.00$0.00$0.00$0.00
3.10.15Aux Hoist Load Testing$0.00$0.00$0.00$0.00$0.00
3.10.16Whip Hoist Load Testing$0.00$0.00$0.00$0.00$0.00
3.11.1Bilge Preservation$0.00$0.00$0.00$0.00$0.00
3.12.2Dock Trial Baseline Testing$0.00$0.00$0.00$0.00$0.00
3.12.3Dock Trial Final Testing$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
$0.00$0.00$0.00$0.00$0.00
Column Totals0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00

Scope (SOW/PWS) Labor Rate/MH: G&A Rate: Profit Rate:

Non RT Total Bid: $0.00

PARAGRAPH No.TITLEM/HMATERIAL PRICETOTAL
Carney, Sean R CIV PSNS&IMF, Code 411: =(MH*Labor Rate)+Material PriceLabor CostMaterial CostTOTAL

Carney, Sean R CIV PSNS&IMF, Code 411: =Sub Cost (F) Other Direct Cost (ODC)* G&A PROFIT Line Item Total Carney, Sean R CIV PSNS&IMF, Code 411: =SUM(Prime Total+Subcontractor Total+ODC+G&A+Profit)

Carney, Sean R CIV PSNS&IMF, Code 411: =(MH*Labor Rate)+Material Price Carney, Sean R CIV PSNS&IMF, Code 411: =(MH*Labor Rate)+Material Price Carney, Sean R CIV PSNS&IMF, Code 411: =Sub Cost (F)

Carney, Sean R CIV PSNS&IMF, Code 411: =MH*Labor Rate*G&A Carney, Sean R CIV PSNS&IMF, Code 411: =(Prime Material Price+Subcontractor Total)*Profit Rate Carney, Sean R CIV PSNS&IMF, Code 411: =Sub Cost (F)

Carney, Sean R CIV PSNS&IMF, Code 411: =SUM(Prime Total+Subcontractor Total+ODC+G&A+Profit)3.2.9Hull Repairs Repairs Reservation Tasking600$3,942.00$3,942.00$0.00$0.00$0.00$0.00$0.00$0.00$3,942.00
3.4.10Tank Repairs (Reservation Tasking)400$758.00$758.00$0.00$0.00$0.00$0.00$0.00$0.00$758.00
3.5.4Main Deck Repairs (Reservation Tasking)600$1,369.00$1,369.00$0.00$0.00$0.00$0.00$0.00$0.00$1,369.00
Column Totals1600$6,069.00$6,069.00$0.00$0.00$0.00$0.00$0.00$0.00$6,069.00

Reservation Tasking (RT) Total Bid: $6,069.00

Total Bid: $6,069.00

********DOLLAR ENTRIES ARE AUTOMATICALLY ROUNDED UP TO THE NEAREST WHOLE DOLLAR*********

*ODC-Defined as anything other than labor, subcontracts, and/or material that is directly attributable to a contract per FAR 31.202. Examples include rental charges and travel etc.

NOTE: Please fill in within the yellow highlighted boxes, the fixed labor rate, proposed G&A and proposed Profit rates.

NOTE: Labor rates and Profit rates used to calculate for the overall price of the base contract award shall be the basis for pricing on all modifications under this contract.

File details come from the government source that posted it.