This document is a Statement of Work (SOW) for a federal contract opportunity to replace the cove base at the Johnson Primary School located at Camp Lejeune, North Carolina.
The SOW requires the contractor to provide all labor, materials, equipment, and supervision to remove and dispose of the existing cove base and install approximately 3,000 linear feet of new 6" rubberized commercial grade cove base with bull nose type corners throughout the common areas of the school building. The work must be completed within 90 calendar days, scheduled Monday through Thursday from 7:00 am to 5:30 pm. All employees must pass background checks, and convicted felons will not be allowed to perform work on the project. The contractor is responsible for obtaining security badges for access to the military installation. The contract has a 1-year warranty on materials and workmanship. The related federal contract opportunity is solicitation number N4008524R2691 issued by the Department of the Navy Naval Facilities Engineering Command for the Bldg 2027 Replace Cove Base project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DoDEA Americas Mid-Atlantic District-Lejeune (Camp Lejeune Dependents Schools)
Replace Cove Base Johnson Primary School
STATEMENT OF WORK
Project Locations: Johnson Primary School, 2027 Stone St, Camp Lejeune, NC 28547
Scope: The Contractor shall provide all labor, materials, equipment, and supervision required to complete the work contained herein. Contractor will provide complete measurements after site visit. The contractor is responsible for the purchase, transportation, and storage of all equipment and supplies.
Upon receipt at the job site, all materials shall be checked to ensure that no damages occurred during shipping or handling. Existing areas that are damaged by the contractor shall be repaired at the Contractor’s expense. Contractor is responsible for verifying existing conditions and measurements prior to submission of bid.
Provide all equipment, materials, labor and supervision to install approx 3000 LF of new Cove Base in the common areas of building 2027. Due to deterioration of the existing tile base, it is necessary to dispose all existing Base and install New within the Areas on the attached Drawings. Contractor will:
Remove and Dispose of the existing cove base taking care not to damage adjacent floors and walls. See the attached plan for the location of work. Contractor will be responsible to dispose at an off base location in accordance with all applicable guidelines and regulations.
Repair and seal lower wall areas to receive new cove base as necessary for maximum adhesion. Wall must be smooth and straight so the cove base will have a smooth straight appearance with no gaps or holes along the top edge. Notify the Facility Maintenance Team for any anticipated delays in schedule due to excessive wall repair.
Install new cove base in all areas as shown on the attached Drawing. Cove base will be a 6” Rubberized commercial grade material with bull nose type corners. Must be a durable material to handle floor cleaning equipment. Provide cove base samples for approval prior to commencement of work. Adhesives used shall be in accordance with the flooring and cove base manufacturer’s recommendations.
All materials removed by contractor that are identified for disposal shall be disposed of by contractor at an approved off base location at the expense of the contractor.
Project Schedule & Hours of Work: The Contractor shall submit a milestone project schedule with the proposal indicating overall complete duration and major milestones such as submittals, installation, training, etc. for approval. Performance of work shall last no longer than 90 calendar days. All work is based on straight time hours: Monday through Thursday from 07:00 am to 17:30. All on site work, punchlist items, administrative procedures, and task order closeout shall be completed within 120 days from NTP. Weekend, recess period, and after-hours work will be authorized to accomplish the work within required timeframe. Work should be scheduled such that work does not interfere with school operations. The contractor is required to complete this project, ready for use, within the time period specified in the contract. Contractor shall staff project adequately to accomplish the work within the state timeframe.
Conditions of Work:
1. All areas will be clean and have debris removed at the end of each workday. When public traffic is present, all areas will be kept clean and free of obstruction at all times.
2. All work will be coordinated in advance with the DoDEA Americas Mid-Atlantic District-Lejeune Facilities Specialist or designee.
3. All materials and equipment shall be stored in a place that can be secured, to be provided by the Contractor.
4. A representative from the contractor must sign in at the School Reception Office at the beginning of each workday.
5. All personal protective equipment is the responsibility of the contractor and shall be worn as required by OSHA regulation. Failure to comply will be grounds for immediate STOP WORK at no additional cost to the Government.
6. All work SHALL comply with OSHA, NFPA, AHERA and Federal regulations as required.
Warranty: Installation workmanship materials and labor shall be warranted for a period of 1 year and repair of all defects shall be at no cost to the government.
Personnel Escort/Security Clearance: All employees proposed to work at these school facilities will be required to pass wants and warrants requirement of the police. This includes employees of any Subcontractors which may be hired. Background checks will be the responsibility of the Contractor and may be obtained through Rapid Gate (local only, if available) or from a company who does background checks as a business, is National Association of Professional Background Screeners (NAPBS) accredited, and is approved by the COR. Two levels of background checks are required. An initial local background check to determine if existing warrants are outstanding and a thorough background check with at least 10 years of history in all locations in which the potential employee has lived. The Contractor will keep records of background checks for all employees. The Contractor shall submit a copy of that Record for each employee to the Contracting Officer or COR before any access will be granted to DoDEA Americas MidAtlantic District-Lejeune school facilities and prior to the Notice to Proceed. Convicted felons will not be allowed to render any services defined in this Contract. The initial background check is to be completed within a maximum of 30 days. Any Contractor employee or sub-Contractor employee who has not had at least the local background check completed will only be allowed to work at DDESS facilities if accompanied by a person with background checks completed and acceptable. In addition, the Contractor shall be responsible for obtaining contractor badges via the MCIEAST/MCBCL Contractor Vetting Office, required for routine access to the installation.
Points of Contact: School District POC is Supervisory Facility Operations Specialist Thomas Clark, thomas.clark@dodea.edu, (910) 451-5361 or Maintenance Mechanic Supervisor ,Thomas Willox, thomas.willox@dodea.edu, (910)451-5361
| Replace Cove Base Johnson Primary School -SOW.pdf |
| Replace Cove Base Johnson Primary School |
| Tarawa Terrace Elementary School |
| MAP JPS |
| Slide Number 1 |
File details come from the government source that posted it. Updated .