Page Section Para. Dwg #

1 08/15/22

As discussed at the site visit, per one of our Mechanical subcontractors they are currently doing a project at B150 which appears to include some of the SOW as outlined in this RFP N4008522R2806.

The dupication of the work items appears to be the reinsulation/duct rework as outlined in this RFP for AHU-1 and AHU-

2. The other contract is between NAVFAC an d MIG-GOV. Is the replacement and insulation of the ductwork associated with AHU-1 and AHU-2 to remain in this RFP or will it be removed from the SOW for this RFP since some if not all of it is in the other contract with MIG-GOV?

The replacement and insulation of ductwork will remain in this RFP.

2 08/15/22

Has the steel foundations on the roof or the bar joist below been tested for Lead, Cadmium or Chromium? Has any HazMat surveys been performed?

This building was built in the early 90's. It is assumed there is no lead, cadmium or chromium.

3 08/15/22 Will the contractor be able to utilize the rear mezzanine to load out the demo debris?

Yes, the Contractor will be able to utilize the mezzanine to load out the demo debris.

Project Title: B150 Replace Rooftop Curbs, NASO

Solicitation / RFP#: N4008522R2806 - PPI Cut Off Date: 15 AUGUST 2022

Amend No.GOVERNMENT RESPONSE PPI No.

Date Submitted

REFERENCE

QUESTION

4 08/15/22

Will the historical documents and furnishings in Room 211 and furnishings or electronic equipment in Room 216 be moved out, stored and reinstalled by the government? This will be necessary as all rooms will need to be cleared out during any construction and or testing as required by the RFP.

The Activity will remove and/or protect items to provide space in Room 211 for the required work. The Activity will remove all Class 3 electrical equipment from Room 216. The Contractor must move and protect desks/furniture to other areas in the room to allow space for required work. The desks/furniture must be placed back in it's original location by the Contractor before the building is turned over.

5 8.15.22 Will a P6 construction schedule be required for this project.

Yes, refer to spec section 01 32 16.00 20

SMALL PROJECT CONSTRUCTION

PROGRESS SCHEDULES 1.3.1.

6 8.15.22 Will a cost loaded schedule be required for this project.

Yes, refer to spec section 01 32 16.00 20

SMALL PROJECT CONSTRUCTION

PROGRESS SCHEDULES 1.4.a.(4).