This is an award notice for a firm-fixed-price construction contract valued at 428,640,229 Japanese yen awarded on November 15, 2022 to American Engineering Corporation. The contract is for smart grid and facility control work at Naval Air Facility Atsugi in Japan, including utilities and controls at multiple buildings. An option item is included. The completion period is 652 calendar days for the base work and 245 days for the option. The contract incorporates Federal Acquisition Regulation clauses and Defense Federal Acquisition Regulation Supplement clauses.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5937751
TITLE: SMART GRID AT NAF ATSUGI, JAPAN
a. All solicitation documents listed on Section 00 01 10: Table of Contents
b. Standard Form (SF) 1442 Attachments:
(1) NAVFAC Specif ications (eProject No. 1684820)
(2) NAVFAC Draw ings (NAVFAC DRAWING NO. 17285646 – 17285870)
(3) Site Visit Request Form
(4) Pre-Bid Inquiry Form
c. Bidders are required to complete and submit the follow ing items:
(1) SF1442 (Cover pages, Section 00 10 00, and Section 00 45 00 (as applicable))
(2) Bid Bond
d. In accordance w ith FAR 36.204, the magnitude of this project is betw een ¥100,000,000 and ¥500,000,000.
X
CHITO BONG F. CARABEO 315.264.3143
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
15-Nov-2022
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________652 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________09 Aug 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
N4008423C8000
7. ISSUED BY CODE
NAVFAC FAR EAST
FEAD ATSUGI
PSC 477 BOX 15
FPO UNITED STATES 96306-0001
N40084
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
N4008422B80030006 46
HOE.ERIN.Y
L.1374336874
Digitally signed by HOE.ERIN.Y L.1374336874 Date: 2022.11.15 13:28:00 +09'00'
See Item 7
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE
JS462
FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
SEE SCHEDULE
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
$3,856,266.60 See Schedule
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE HQ072127. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
DFAS JAPAN
DFAS-JRLG/JA
UNIT 5220
APO AP 96328-5220
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR
AMERICAN ENGINEERING CORPORATION
7-8-13, OYAMA
GINOWAN JAPAN
15. TELEPHONE NO. (Include area code) 098-897-6781
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
X 29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract. REF: Solicitation N40084-22-B-8003
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print) Erin Y. L. Hoe / Contract Specialist
TEL: 315-243-3418 EMAIL: erin.hoe@fe.navy.mil
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY 15-Nov-2022
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
N4008423C8000
Section SF 30 - Block 14 Continuation Page (SF 30)
AMENDMENT 0001
The purpose of this amendment is to clarify and revise information on FAR 52.236-27 SITE VISIT as follows:
FAR 52.236-27(b) – The start of the site visit has been revised FROM 10:00 AM (JST) TO 01:00 PM (JST).
All other terms and conditions remain unchanged.
AMENDMENT 0002
The purpose of this amendment is to:
1. Schedule a second site visit on 19 July 2022, Tuesday, from 1300 to 1600. Site visit request forms are due on 15 July 2022, Friday, at 1000.
2. Change the bid submission due date from 26 July 2022 at 1400 to 02 August 2022 at 1400.
3. All other terms and conditions remain unchanged.
AMENDMENT 0004
1. Provide the final design specifications, drawings, and environmental report.
2. Revise the list of attachments to reflect the changes.
All others terms and conditions remain unchanged.
AMENDMENT 0005
1. Extend the bid submission due date by one week. The bid submission due date has been changed from 02 August 2020 at 1400 to 09 August 2020 at 1400 local Japan standard time (JST)
2. Revise information on section 1.2 PUBLIC OPENING OF BIDS regarding submission of attendees information.
3. Revise information on section 1.9 PRE‐BID INQUIRIES regarding submission due date of inquiries.
4. Add Attachment 6 – Pre‐Bid Inquiries (ALL). This attachment compiles all inquiries and responses in a PDF file.
5. Provide government responses to additional inquiries received. Some inquiries included some images which has been omitted in the SF30 because of system constraints. These images are included in Attachment 6.
Question No.
Reference (Sect/Para/Page) QUESTION GOVERNMENT RESPONSE
Bldg.1300
MB604 MB605
Does this mean that the humidifier shall be just monitored and humidity shall be controlled on the humidifier side?
Humidifier must be monitored and controlled through the DDC system.
Bldg.1300
MB604 MB605
8.WHEN THE DUCT SMOKE
DETECTOR IS ACTIVATED,
THE DDC SYSTEM MUST
AUTOMATICALLY DISABLED
THE ACU FAN OPERATION,
OA-MD AND RA-MD MUST BE
CLOSED, EA-MD MUST BE
FULLY OPENED AND
RETURN FAN (FR-1) MUST
OPERATE AT FULL AIR
FLOW CAPACITY.
We would like to make a quotation for disaster prevention work including the main body of duct smoke detector and fire control separately.
Disaster prevention work is not in the scope of this project.
Bldg.1300
MB604 MB605
Regarding the temperature sensor for outside air temperature, there's a possibility it may not be able to take in the outside air when ACU stopped, so we would like to set 1 sensor for the outside temperature and humidity on the outside of the building instead of setting temperature sensor for each ACU.
Modification to provide 1 temperature and humidity sensor on the outside of the building instead of setting temperature sensor for each ACU is acceptable.
Note:
The schematic diagram shown is for Bldg 3076 not for Bldg.
Bldg.1300
MB602
There are 2 sensors, but is it possible to set only 1 sensor since the measurement points and the purpose are the same?
As indicated in the schematic diagram there are two measuring points with different purposes one is to modulate which is the two way motorized modulating valve and the other one is to open/close which is the motorized ball valve.
Note:
The schematic diagram shown is for Bldg 3076 not for Bldg.
Bldg.1300
MC002
It is mentioned that the same size valve shall be replaced as the existing ones as shown below, however, there are no manufacturers including our company that produce Φ100 x 80 valves currently. We would like to select control valves for port size and isolation valves, switching valves for valve diameter.
The indicated valve size of 3-way diverting valvewas taken from the as-built drawings.
Existing actual valve size must be check at the site prior to material submittal.
Bldg.1300MC002Same as the above
All control valves have spring return function, does it mean it is normally open (all bypass when closed) when spring return is actuating with 3-way valve?
This means a "fail-safe open position" actuator returns to a pre-set home position when power is removed from the actuator.
Bldg.1300
MC602
Is it considered as the air handling unit is cold/hot water coil?
Notations around chiller and air handling unit in the piping diagram show "C/CR" but it is written as cold/hot water in the control content.
AHU's are with cold/hot water coil.
Bldg.1300
MC603
Regarding the monitor of VAV, is the main body of VAV capable of responding to written input/output signal? Or, is it necessary to provide individual controller for VAV on JCI side? (If controllers to be provided by JCI this time, VAV temperature sensors need to be replaced by JCI as well)
The existing VAV's are not capable of providing I/O signals, a new controller module with associated accessories that are compatible and able to connect to DDC must be provided.
Bldg.1300
MC601
Is it considered as the unit control of these 2 chillers is the function provided? For JCI, just monitoring operation is necessary?
Chillers must be monitored and controlled through the DDC system.
Bid sumission data We believe the bid submission data has been pushed back to 02 August 2022, however still we need more time to make accurate quote. We would like to request to extend (2) more weeks?
Bid submission due date has been changed to 09 August 2022 at 1400 (02:00 PM) local Japan Standard time (JST).
Bldg.1440
MD602
Is it correct that measurement of load flow rate and heat on the secondary side is not necessary?
The indicated schematic diagram is based on the existing system configuration at site without load flow rate measurement.
Bldg.1440
MD603
It is necessary to replace the temperature sensor for FCU as well.
(Existing thermostat can not be used for FCU DDC.)
External input/output terminal provided for ACP and HEA? Or, is there manufacturer's BACNET
As indicated in dwg # MD101, provide fcu switch that are compatible and able to connect to the DDC.
For ACP and HEA requirements refer to dwg #
MD601.
interface available (or added)?
Bldg.1440
MD604
Regarding the temperature sensor for outside air temperature, there's a possibility it may not be able to take in the outside air when ACU stopped, so we would like to set 1 sensor for the outside temperature and humidity on the outside of the building instead of setting temperature sensor for each ACU.
Modification to provide 1 temperature and humidity sensor on the outside of the building instead of setting temperature sensor for each ACU is acceptable.
MD604 7. DUCT SMOKE DETECTOR
(SD) MUST PROVIDE SIGNAL
TO THE DDC SYSTEM AND
THE DDC SYSTEM MUST
AUTOMATICALLY STOP THE
SUPPLY FAN OPERATION
UPON CONFIRMATION THAT
THERE IS SMOKE IN THE AIR
DISTRIBUTION DUCT. THE
DDC SYSTEM MUST SEND
SIGNAL TO THE FIRE ALARM
CONTROL PANEL (FACP)
WHEN SMOKE IS DETECTED
IN THE AIR DISTRIBUTION
DUCT.
We would like to make a quotation for disaster prevention work including the main body of duct smoke detector and fire control separately.
Disaster prevention work is not in the scope of this project.
Bldg.1502
ME602
It is necessary to replace the temperature sensor for FCU as well.
(Existing thermostat can not be used for FCU DDC.)
External input/output terminal provided for ACP and HEA? Or, is there manufacturer's BACNET interface available (or added)?
Provide fcu switch that are compatible and able to connect to the DDC.
For ACP and HEA requirements refer to dwg #
ME601.
Bldg.1502
ME602
For which part shall temperature measurement be conducted?
Please refer to dwg #: ME101 for temperature measurement location.
Bldg.1502
ME603
What is the start condition for the pump?
Is it considered as optional operation, not controlled operation?
The recovery circulation pump is used during OAU hot water demand operation and it must be controlled and monitored thru DDC system.
Bldg.1502
MD604
7. DUCT SMOKE DETECTOR
(SD) MUST PROVIDE SIGNAL
TO THE DDC SYSTEM AND
THE DDC SYSTEM MUST
AUTOMATICALLY STOP THE
SUPPLY FAN OPERATION
UPON CONFIRMATION THAT
THERE IS SMOKE IN THE AIR
DISTRIBUTION DUCT. THE
DDC SYSTEM MUST SEND
SIGNAL TO THE FIRE ALARM
CONTROL PANEL (FACP)
WHEN SMOKE IS DETECTED
IN THE AIR DISTRIBUTION
DUCT.
We would like to make a quotation for disaster prevention work including the main body of duct smoke detector and fire control separately.
Disaster prevention work is not in the scope of this project.
Bldg.1524
MF602
Is it correct that measurement of load flow rate and heat on the secondary side is not necessary?
The indicated schematic diagram is based on the existing system configuration at site without load flow rate measurement.
Bldg.1524
MF603
It is necessary to replace the temperature sensor for FCU as well.
(Existing thermostat can not be used for FCU DDC.)
External input/output terminal provided for ACP and HEA? Or, is there manufacturer's BACNET interface available (or added)?
Provide fcu switch that are compatible and able to connect to the DDC.
For ACP and HEA requirements refer to dwg #
MF601.
Bldg.1524
MF605
Does this mean that the humidifier shall be just monitored and humidity shall be controlled on the humidifier side?
Humidifier must be monitored and controlled through the DDC system.
Bldg.1524
MF605-606
11. NIGHT SET-BACK
CONTROL DURING
UNOCCUPIED PERIODS THE
ROOM TEMPERATURE MUST
BE MAINAINED AT THE
DESIRED TEMPERATURE
THRU DDC.
What is the difference against
Difference against the operation during the day time must be determine during testing and commissioning stage in coordination with the actual site requirements.
the operation during the day time?
Bldg.3076
MB604
MB605
Does this mean that the humidifier shall be just monitored and humidity shall be controlled on the humidifier side?
Humidifier must be monitored and controlled through the DDC system.
Bldg.3076
MB604
MB605
8.WHEN THE DUCT SMOKE
DETECTOR IS ACTIVATED,
THE DDC SYSTEM MUST
AUTOMATICALLY DISABLED
THE ACU FAN OPERATION,
OA-MD AND RA-MD MUST BE
CLOSED, EA-MD MUST BE
FULLY OPENED AND
RETURN FAN (FR-1) MUST
OPERATE AT FULL AIR
FLOW CAPACITY.
We would like to make a quotation for disaster prevention work including the main body of duct smoke detector and fire control separately.
Disaster prevention work is not in the scope of this project.
Bldg.3076
MB604
MB605
Regarding the temperature sensor for outside air temperature, there's a possibility it may not be able to take in the outside air when ACU stopped, so we would like to set 1 sensor for the outside temperature and humidity on the outside of the building instead of setting temperature sensor for each ACU.
Modification to provide 1 temperature and humidity sensor on the outside of the building instead of setting temperature sensor for each ACU is acceptable.
Bldg.3076
MB602
There are 2 sensors, but is it possible to set only 1 sensor since the measurement points and the purpose are the same?
As indicated in the schematic diagram there are two measuring points with different purposes one is to modulate which is the two way motorized modulating valve and the other one is to open/close which is the motorized ball valve.
Bldg.3076
MB002
It is mentioned that the same size valve shall be replaced as the existing ones as shown below, however, there are no manufacturers including our company that produce Φ100 x 65 and Φ125 x 80 valves currently. We would like to provide control valves for port size and isolation valves, switching valves for valve diameter.
2. THE MOTORIZED VALVE TO
BE PROVIDED /INSTALLED
MUST BE THE
SAME SIZE WITH THE
EXISTING VALVE TO BE
REPLACED.
The indicated valve size of 3-way diverting valve was taken from the as-built drawings.
Existing actual valve size must be check at the site prior to material submittal.
Bid Due Date N40084-22-B-8003+0002
Request government consideration to extend proposal due date by two weeks due to U.S.
government fiscal year end solicitation surge, which places additional constraints on companies responding to solicitations.
Bid submission due date has been changed to 09 August 2022 at 1400 (02:00 PM) local Japan Standard time (JST).
48 TA601-603, TB601-603,
TC601-603, TD601-603,
TE601-603, TE601-603,
TG-601, TH-601 DWG
There seems some descrepancies the QTY of network equipment listed in
ONE-LINE DIAGRAM
against the one described in
NETWORK
ARCHITECTURE OF DDC
SYSTEM (For further information, please refer to the yellow highlighted portion described in the attached QTY sheet).
Please clarify which should be the priority for making the quotation.
This is to clarify that Cybersecurity drawings are shown as intended based on or as per UFC for Cybersecurity (4-010-06). Consulting a Cybersecurity specialist with regards to this matter is highly recommended in order to fully understand the concept and guidance for implementation.
Either way, as part of the requirement, Cybersecurity Representative is emphasized as specified in section 25 05 11
- 1.7.1.1. Cybersecurity is as much as priority as telecommunication equipment or devices. Cybersecurity and Telecommunications are two distinct disciplines. TA602-603, TB602-603, TC602-603, TD602-603, TE602-603, TF602-603 are mainly Cybersecurity related drawings. Please refer to drawings TA601, TB601, TC601, TD601, TE601, TF601, TG601 and TH601 respectively for detailed telecommunication equipement or devices required per building. Also refer to the attachment entitled "Reference 949" with mark ups as basis, it should be enough to figure out the other buildings.
49 TA603, TB603, TC603,
TD603, TE 603 DWG
Should we include the equipment between the Network SW and patch panel in our quotatation as scope of work? (i.e. Legend #D thru.OPS SINGLE
MODE FIBER PATCH
PANEL in TA603 DWG)
Yes, please also refer to OSP Fiber Cabling Site Plan (T-003) for building 949. To better understand, please see attachement entitled "Bldg 949 correlation".
50 TB101, TC101, TD101,
TE101, TF101 DWG
Please let us know the installation location of new workstation at Bldg.949, 1300, 1400, 1502, 1524 and 3076.
This is to clarify that there are no related work in providing workstation at building's 949, 1300, 1400, 1502, 1524 and 3076. The only related work for workstation is at building 1310 (GFGI workstation).
51 TG101 DWG There is a description that "V100-6/D46" in the TG101 DWG. May we consider this is a model name of workstation?
This is to clarify that "V100- 6/D46" is an existing One-Net work outlet tag provided by Base Communication Office (Navy's Telecommunications Manager).
52 SECTION 23 09 00,
INSTRUMENTATION AND
CONTROL FOR HVAC,
1.1.2.1 Proprietary
Systems Exempted From Open Protocol Requirements
SECTION 23 09 00,
INSTRUMENTATION AND
CONTROL FOR HVAC,
1.4.5 BACnet Building
Controller (B-BC) (BACnet)
As described in para 1.1.2 Proprietary Systems Exempted From Open Protocol Requirements, the definition of hardware device should be as a HMI and/or B-BC in BACnet. If we will conncet as SMART GRID, there need modifying to apply B-BC, and additional device installation will be necessary. Should we include this work in our quotation at Bldg.949, 1300, 1440, 1502, 1524 and 3076?
This is to confirm that HMI (Human Machine Interface) such as tablet to be added in the DDC Panel is not required in this project per the CIO's direction as was done in the other Smart Grid Projects.
Rather a maintenance laptap will be provided as required in this project. On the other hand, per SOW No. 3 in TA101 and similar to other buildings states "Provide a complete and operable DDC Smart Grid System. a. Establish the communications network and connections between the DDC and the building communications rack or WIC Box and to the outside plat fiber optic utility cable connections for the building side. Provide all necssary network components, equipment, devices and cablings for the DDC system netowrk." Also, per drawing TA601 and other Smart Grid One-Line Diagrams, Note 9 states "Ensure to provide necessary Equipments and wiring for a complete and operational DDC System."
AMENDMENT 0006
1. Update “Attachment 6 – Pre‐Bid Inquiries” as a result of additional inquiries and government responses.
2. Provide government responses to inquiries received below.
Question
No.
Reference
(Sect/Para/Page)
QUESTION GOVERNMENT
RESPONSE
Bid submission due date
We just got amendment 005 and and need to reflect those new information on our quote.
Also, we will have Obon holidays in middle of August, so we would really appreciate you if you can extend the due date by 8/23 Tuesday, then we believe we can provide you solid numbers.
Bid submission due date remains at 09 August 2022 at 1400 (02:00 PM) local Japan Standard time (JST).
Amendment
The environmental report was provided for the first time in Amend 4 issued on 7/26. We would like you to extend the bidding date about 10 days because it's not enough time to consider the estimation review period for asbestos and lead removal work by the bidding date.
7/26に発行されたアメンド4で初めて環境レ
ポートが提供された。アスベストや鉛の除去
作業についての見積検討期間が入札日までに
間に合わないため10日程度入札日を延長し
てほしい。
Bid submission due date remains at 09 August 2022 at 1400 (02:00 PM) local Japan Standard time (JST).
Amendment
Our subcontractor for the DDC who plays a major role in this project, has commented that they need more time to review the contents of Amendment 0005 for the bid.
Could you extend the bidding date to at least by 16 August 2022?
このプロジェクトで大きな役割を占める、
DDC業者より、Amendment 0005の内容を精
査し、積算するのに時間が足りないとの意見
があります。 入札日を最低でも8/16まで延長できないでし
ょうか?
Bid submission due date remains at 09 August 2022 at 1400 (02:00 PM) local Japan Standard time (JST).
AMENDMENT 0003
1. The purpose of this amendment is to provide Government’s response to the contractor’s inquiries.
Q No.
Reference (Sect/Para/Page)
QUESTION GOVERNMENT RESPONSE
Amend
No.
Each section Some submittals required in the specifications start from the Notice to Proceed for submissions. Does the NTP mean the award date, the date of pre-conference, or other? Could you clarify that?
仕様書の中の要求で提出物について、
Notice to Proceedを 起算日としているものがあります。
Notice to ProceedとはAward Dateで いいのでしょうか?それともプレコン
開催日でしょうか?それとも別にNTP
が発行されるのでしょうか?
Notice to Proceed will be the date of Award.
Sect 23 08
00.00 20 Para 1.4.1
We can't find a company with a Retro- Commissioning Firm qualification.
Is it possible for a company with Commissioning Firm and TAB Firm qualifications to make up for it if it currently has similar construction experience at other bases? Or is it required to meet the requirements according to the specifications?
Retro-Commissioning Firmの資格証を
持っている会社が見当たりません。
Commissioning Firm及びTAB Firmの
資格証を持っている会社であり、 さ らに現在、他の基地で同様の工事の実
績があればそれで補えるものでしょう
か?それとも仕様書通りの要求を満た
すことが求められるのでしょうか?
The specification requirements shall be met.
Sect 23 05 93 Para 3.3.3
A Duct air leakage test (DALT) is required for this project, but if DALT is performed and the required values are not obtained, do we need to repair the ducts and duct connections? In that case, should we bid with the estimated cost of repair? Or will the modification be issued after the contract?
このプロジェクトではDALTが要求さ
れていますが、もしDALTを実施して
要求を満たす数値が出ない場合はダク
トの接続部およびダクトの修理が要求
されますか?その場合その金額もある
程度想定した金額で入札するべきでし
ょうか?それともあとで契約変更が発
行されるのでしょうか?
DALT is not required for this project.
Sec 23 05 93 Para 3.4.6.2 Pgae 19
We would like to ask you to maintain the fairness of the bid.
In this paragraph, the contractor are requied to do TAB season 2, however, should we actually do TAB season 2?
入札の公平性を保つためお聞きしま
す。 このパラグラフではTAB season2を実
施するように書いてありますが、 実際にはTAB Season2を実施するべ
きでしょうか?
TAB Season 2 is required.
Sec 02 82 00 Para 1.3.1 Pgae 6
Although the specification mentions the handling of Asbestos containing material (ACM), we are not sure which material is ACM.
Could you tell us which material should be treated as ACM?
Or if available, could you provide us with the Sampling report for each building?
仕様書ではACM(Asbestos containing material)の取り扱いについて 言及されていますが、どの部材が
ACMであるかがわかりづらいです。
どの部材をACMとして取り扱うべき
か指示願います。 または各建物のSampling reportを提
供していただけますか?
Please refer to the Environmental/ Hazardous Material Report that was submitted to the government.
MA604 DWG,
Sequence of ACU Operation #5
It is described that SD (duct smoke detector) must provide signal to FACP via DDC. But we cannot calculate the QTY and/or type of conductor because there is no detail about EXST FACP. Please provide the information about FACPs (i.e.
Installation Location, OEM, Model, Type) at Bldg.949, 3076, 1524, 1300 and 1440.
As indicated in the design duct smoke detector must be directly integrated to the DDC system by means of providing signal to the DDC system and the DDC system must automatically stop the supply fan operation upon confirmation that there is smoke in the air distribution duct. The integration of duct smoke detector to FACP via DDC is not part of the project scope but at minimum for future connection ensure that DDC system has the capability to send signal to the FACP when smoke is detected in the air distribution duct.
AG101 DWG,
Bldg1310 SOW
It is uncertain about the requirement of task light. Could you provide the information about subject light (i.e.
Model, Type, Lux, Sketch)?
Please refer to the minimum requirements as specified in Section 27 10 00 attached herewith entitled "UPS requirement". This is part of the submittal as well and will be reviewed by the Command Information Office (CIO) prior to approval.
Specification, SECTION 26
05 00.00
Regarding the conduits for remote controller & switches to be replaced or renewed, may we use metal raceway (B-type) at riser/drop portion insted of conduit?
Metal raceway is acceptable.
IFB letter, 52.236-27
Since we could not check site condition at Bldg.1440, 1502 and 1524 on 11 July, so could you hold an additional site visit about Bldg.1440, An additional site investigation was held July19.
1502 and 1524? Or please provide site pictures about subject buildings.
SECTION 01
11 00, SUMMARY OF
WORK
1.1.1 Project
Description
SECTION 23
09 00, 1.4.2 Building Automation and Control Network (BACnet)
As described in the spec., this project will include the provision of new DDC System at six (6) facilities with BACNet openprotocol and an open license to be maintained by the installation. It is also described that the six (6) DDC buildings will be monitored at the Far East Facility Energy Operations Center (FEOC) at CFA Yokosuka in the future.
Is the BAC net ANSI/ASHRAE Standard 135-2012 (BACnet®-2012) acceptable as compliant version?
The latest BACNet protocol shall be followed: ANSI/ASHRAE 135- 2020.
TA601-603,
TB601-603,
TC601-603,
TD601-603,
TE601-603,
TE601-603,
TG-601, TH-
601 DWG
There seems some descrepancies the QTY of network equipment listed in ONE-LINE DIAGRAM against the one described in CYBERSECURITY 5-
LEVEL ARCHITECTURE OF DDC
SYSTEM. There is also a point where it is difficult to determine which is the scope of work or which is existing. If possible, please provide new equipment list which we can determine new or EXST.
This is to clarify that Cybersecurity 5-Level Architecture of DDC System was portrayed as described and depicted or shown in the UFC for Cybersecurity (UFC 4-010-06), please refer to the attachement entitled "UFC 4-010-06".
Cybersecurity involves an in depth or comprehensive understanding and implimentation of the logical configurations for the related control system network devices, hence a Cybersecurity Specialist is required (key person) in order to properly guide, implement and manage the cybersecurity related control systems in coordination with the Command Information Officers (CIO2 & CIO4), also emphasized in specs section 25 05 11 - 1.7.1.1 Cybersecurity Representative. The scope is pretty much straight forward and almost typical per building. Major network components or devices were covered, drawing annotations and notes are also provided.
TA601-603,
TB601-603,
TC601-603,
TD601-603,
TE601-603,
TE601-603,
TG-601, TH-
601 DWG
Please provide detail information about UPS (i.e. Capacity, Duration of power disconnection, Shutdown method, Power supply control method, Power supply switching method, outlet spec., etc), and power strip (i.e. QTY of ports, 2/3 pin, source etc)
Please refer to the minimum requirements as specified in Section 27 10 00 attached herewith entitled "UPS requirement". This is part of the submittal as well and will be reviewed by the Command Information Office (CIO) prior to approval.
TA601-603,
TB601-603,
TC601-603,
TD601-603,
TE601-603,
TE601-603,
TG-601, TH-
601 DWG
New network equipment made by CiSco needs periodrical maintenance service. Should we include the PMIS cost within warranty period?
Recommend including cost estimate for planning/budget purposes.
Cisco equipment will be registered into Cisco Global Enterprise Modernization Software and Services (GEMSS) formerly Joint Enterprise License Agreement (JELA). This will provide Navy with required levels of product support...but each Command will be billed separately so cost estimate data needs captured.
TA601-603,
TB601-603,
TC601-603,
TD601-603,
TE601-603,
TE601-603,
TG-601, TH-
601 DWG
May we consider required software for "Cisco C3172PQ" as shown below?
Are there any other special requirements?
Comprehensive Layer 2 feature set:
VLAN, IEEE 802.1Q Trunking, vPC, Link Aggregation Control Protocol (LACP), Unidirectional Link Detection UDLD (standard and aggressive), Multiple Spanning Tree Protocol (MSTP), Rapid Spanning Tree Protocol (RSTP), spanning-tree guards, and Transparent VLAN Trunk Protocol (TVTP)
- Security: Authentication, authorization, and accounting (AAA);
access control lists (ACLs), Dynamic Host Configuration Protocol (DHCP) snooping, storm control, private VLAN (PVLAN), and configurable Control- Plane Policing (CoPP)
- Management features: Cisco Data Center Network Manager (DCNM) support, console, Secure Shell Version 2 (SSHv2) access, Cisco Discovery Protocol, SNMP, and syslog
- Layer 3 IP routing: inter-VLAN routing (IVR), static routes, RIPv2, ACLs, OSPFv2, EIGRP stub, Hot Standby Router Protocol (HSRP), Virtual Router Redundancy Protocol (VRRP), and Unicast Reverse-Path Forwarding (uRPF)
- Multicast: PIM SM, SSM, and
MSDP
Previously commented on this...Cisco C3172PQ is a Data Center level model. Consideration of Catalyst series model such as the C90300-24P-A being proposed in SCADA project would be a more cost efficient model to meet the requirements.
Salient characteristics are listed below:
Ethernet network IP switch - Climate-controlled environment
- Key Features:
i. Location: Lockable ICS cabinet in the main GTR
ii. Form Factor: Rack-Mountable
iii. Minimum Required Protocol Support: CDP, EIGRP
iv. Software-Defined Access Compatible
v. Stackable
vi. Advanced Switching Layer 3
vii. Managed-type
viii. Trade Agreements Act (TAA) compliant
ix. Listed on DISA’s Approved Products List Integrated Tracking System (APLITS) or National Information Assurance Partnership (NIAP).
x. The construction contractor should contact NAVFAC Far East CIO for review/approval of proposed model and/or most recent product equivalents list in
AOR.
T602 DWG,
SCADA
Network Configuration Diagram
May we consider the EXST equipment seems like router at Bldg.971 (Not Equipment #9) is out of scope in this project? If so, please provide the information about this equipment such as specification, connection method and so one.
This is to clarify that the equipment or device in drawing T602 beside equipment #9 is the Existing Cisco 4510 R+E. This was identified as the Control System Platform Enclave (CSPE) in coordiantion with the Command Information Office (CIO). Please refer to the related drawing TH601 attached herewith entitled "BLDG 971". Thorough coordination with the Command Information Office (CIO) and Base Communication Office (Navy's Telecommunications Manager) is a must in order to established the network or circuit through cable patching. Also, Cybersecurity requires a Cybersecurity specialist (key person) in order to properly guide, implement and manage the cybersecurity related control systems in coordination with the Command Information Officers (CIO2 & CIO4).
T602 DWG,
SCADA
Network Configuration Diagram
Are the equipment #1(CISCO:IE- 4000-16GT4-E and #2 (CICSCO:C9300-24P-A) also out of scope in this project? May we condider that any installation, testing and adjustment for these equipment will not be included in?
Cybersecurity of installed equipment for SCADA project is the requirement and should be in-scope. 0003
Specification Section 23 09 00, Paragraph 1.1.1
It states that the control system provided must be Johnson Controls Inc. Metasys BAS. Would the Government be willing to accept an approved alternate so long as the system is based on an open BACnet platform and capable of being integrated into the Control System Platform Enclave (CSPE)?
A Class Justification and Approval (CJ&A) has been provided to specify Facilities Related Control Systems (FRCS) that are peculiar to one manufacturer, Johnson Controls Incorporated (JCI). All new construction and renovation projects must adhere to FRCS Standardization in accordance with Reference (w) NAVINST 11000.2.
Specification Section 02 82
00 ASBESTOS
& 02 83 00 LEAD and All Drawings (17285646- 870)
There seem no drawings that show the specific location for ACM / Lead to be removed. If these removal work is included in this contract, please clarify the ACM/lead locations and the estimated quantity in order for us to make quotation.
The removal of ACM or lead pertains or is associated only to the drilling of wall when installing new conduit in order to protect the workers and inhabitants of the facility. However, this project does not refer to the removal of all ACM or lead in all locations.
Please use the design drawings and Environmental Report to assess the location and quantity.
The environmental report should be included in the design package.
Drawings EA101 (Page 92 of 225) through EG601 (161 of 225)
Regarding the replacement of existing wiring, should the wiring conduit be replaced at the same time as the wiring replacement?
Or if the existing conduit can be reuseful, can it be reused?
It is recommended to replace the conduit with new. However, if it is difficult to install new conduits due to existing site conditions or unforseen site conditions, it is permitted to reuse existing metal conduits.
2. All other terms and conditions of this solicitation remain unchanged.
Section 00 10 00 - Solicitation
LIST OF ATTACHMENTS
Document Type Description Pages Date Attachment 1 NAVFAC Specifications Final Design (WON: 1684820) 545 July 2022 Attachment 2 NAVFAC Drawings Final Design(17285646 – 17285870) 225 June 2022
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Project $3,856,266.60 $3,856,266.60
NAF ATSUGI SMART GRID
FFP
The contractor shall provide all labor material, equipment, transportation, supervision, quality control and insurance necessary for "Naval Air Facility Atsugi Smart Grid for Utilities and Facility Controls" in accordance with Attachment 1 NAVFAC Specifications (WON 1684820), Attachment 2 NAVFAC Drawings (17285646 - 17285870).
See NAVFAC Specifications Section 01 11 00 Part 1.1.1.1 Base Item
CITING U.S. DOLLARS
The price of this contract is expressed in U.S. dollars for the administrative convenience for the U.S. Government. Payment will be made in yen in the total amount of 428,640,229 JPY at the FY20 Budget Exchange Rate of Y111.1542/$.
FOB: Destination
PURCHASE REQUEST NUMBER: ACQR5937751
PSC CD: Y1PZ
NET AMT $3,856,266.60
000101 $0.00
FUND ACRN AA
FFP
Funding Doc. No. N4008423PRWA001 Customer ACRN: AA
MILSTRIP: N4008423PRWA001
NET AMT $0.00
ACRN AA
CIN: 000000000000000000000000000000
$3,856,266.60
0002 1 Project $0.00
OPTION OPTION NAF ATSUGI SMART GRID
FFP
Option Item: The contractor shall provide all labor material, equipment, transportation, supervision, quality control and insurance necessary for "Naval Air Facility Atsugi Smart Grid for Utilities and Facility Controls" in accordance with Attachment 1 NAVFAC Specifications (WON 1684820), Attachment 2 NAVFAC Drawings (17285646 - 17285870).
See NAVFAC Specifications Section 01 11 00 Part 1.1.1.2 Option Item FOB: Destination
PSC CD: Y1PZ
NET AMT $0.00
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 28-AUG-2024 1 NAVFAC FAR EAST
INSPECTOR OF RECORD
FEAD ATSUGI
PSC 477 BOX 15
FPO AP 96306-0001
N40084
000101 N/A N/A N/A N/A
0002 245 dys. AOE 1 NAVFAC FAR EAST
INSPECTOR OF RECORD
FEAD ATSUGI
PSC 477 BOX 15
FPO AP 96306-0001
N40084
Section 00 70 00 - Conditions of the Contract
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 000101 N/A N/A N/A N/A 0002 Destination Government Destination Government
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions JUN 2020 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government JUN 2020 52.203-7 Anti-Kickback Procedures JUN 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
JUN 2020
52.203-13 Contractor Code of Business Ethics and Conduct NOV 2021 52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
JUN 2020
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018 52.204-23 Prohibition on Contracting for Hardware, Software, and
Services Developed or Provided by Kaspersky Lab and Other Covered Entities
NOV 2021
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
NOV 2021
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
NOV 2021
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research NOV 2021 52.211-13 Time Extensions SEP 2000 52.222-50 Combating Trafficking in Persons NOV 2021 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-15 Energy Efficiency in Energy-Consuming Products MAY 2020
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
JUN 2020
52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.225-14 Inconsistency Between English Version And Translation Of
Contract
FEB 2000
52.228-2 Additional Bond Security OCT 1997 52.228-4 Workers' Compensation and War-Hazard Insurance Overseas APR 1984 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-15 Performance and Payment Bonds--Construction JUN 2020 52.229-6 Taxes--Foreign Fixed-Price Contracts FEB 2013 52.229-12 Tax on Certain Foreign Procurements FEB 2021 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Products and Commercial
Services
JAN 2022
52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2020 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019 252.204-7006 Billing Instructions OCT 2005 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7009 Limitations on the Use or Disclosure of Third-Party Contractor Reported Cyber Incident Information
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
MAY 2016
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2021
252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism
MAY 2019
252.222-7002 Compliance With Local Labor Laws (Overseas) JUN 1997 252.223-7001 Hazard Warning Labels DEC 1991 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7030 Restriction On Acquisition Of Carbon, Alloy, And Armor
Steel Plate
DEC 2006
252.225-7031 Secondary Arab Boycott Of Israel JUN 2005 252.225-7041 Correspondence in English JUN 1997 252.225-7042 Authorization to Perform APR 2003 252.225-7048 Export-Controlled Items JUN 2013 252.227-7032 Rights In Technical Data And Computer Software (Foreign) JUN 1975 252.227-7033 Rights in Shop Drawings APR 1966 252.231-7000 Supplemental Cost Principles DEC 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7008 Assignment of Claims (Overseas) JUN 1997 252.232-7010 Levies on Contract Payments DEC 2006 252.233-7001 Choice of Law (Overseas) JUN 1997 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.239-7098 (Dev) Prohibition on Contracting to Maintain or Establish a
Computer Network Unless Such Network is Designed to Block Access to Certain Websites - Representation.
(Deviation 2021-O0003)
APR 2021
252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012
CLAUSES INCORPORATED BY FULL TEXT
52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV 2021)
(a) Definitions. As used in this clause--
Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
(End of clause)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 652 calendar days after contract award for the base item and 245 calendar days after option exercise for the option item. The time stated for completion shall include final cleanup of the premises.
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of ¥50,000 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)