Exhibit A001-Status Reporting Requirements.pdf

PDF 135 KB Posted

Attached to
Touch Labor Fire Watch Support
Solicitation number
N3904024R0147
Issued by

About this file

This document is an Attachment 1 - Status Report Requirements that outlines the reporting requirements for a federal contract. It specifies the information to be included in the status reports, such as contract number, funded amount, period of performance, mechanic and management time tracking, and graphical representations of actual vs. budgeted hours and funds expended.

The related federal contract opportunity is for providing production support trade labor services, including 20 experienced Marine Fire Watch personnel, 2 supervisors, and program management, to assist with the execution of non-nuclear production labor support modernization and repair work onboard a nuclear-powered submarine at the Portsmouth Naval Shipyard in Kittery, Maine. The period of performance is September 30, 2024 to September 26, 2025, with a total estimated level of effort of 45,144 straight time hours and 4,494 overtime hours for the fire watch personnel and supervisors.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1

Attachment 1 – Status Report Requirements

Status Reporting Requirements

Items to include in status report:

1. Contract number.

2. Contract number.

3. Data date for data being used.

4. Funded amount.

a. Funds expended to date.

b. Funds remaining.

c. Percentage of funds expended to date.

d. Percentage of funds remaining.

5. Period of performance.

a. PoP Start Date.

b. PoP End Date.

c. Days PoP elapsed.

d. Days PoP remaining.

e. Percentage PoP elapsed.

f. Percentage PoP remaining.

6. Mechanic Time Tracking.

a. Straight time hours expended in reporting period (week).

b. Straight time hours expended to date.

c. Straight time hours remaining.

d. Overtime hours expended in reporting period (week).

e. Overtime hours expended to date.

f. Overtime hours remaining.

Attachment 1

Attachment 1 – Status Report Requirements

7. Management Time Tracking.

a. Hours expended in reporting period (week).

b. Hours expended to date.

c. Hours remaining.

8. Projections.

a. Projected funded fully expended date.

b. Projected mechanic straight time hours expended date.

c. Projected mechanic overtime hours expended date.

9. Graphical Representations (Updated Weekly)

a. Graph #1: Actual Straight Time Hours, Budgeted Straight Time Hours, Forecasted Straight Time

Hours.

b. Graph #2: Actual OT Hours, Budgeted OT Hours, Forecasted OT Hours.

c. Graph #3: Actual Funds Expended, Budgeted Funds Expended, Forecasted Funds Expended.

Graphical Data Representation Example: