This is a solicitation for a mid-term availability for the USNS ZEUS (T-ARC-7). The solicitation requires ship repair and maintenance work items to be completed within 90 days of contract award. The response date for proposals is July 21, 2022, with award to be made to the lowest price technically acceptable offer. This is a total small business set-aside being conducted by the Department of the Navy Military Sealift Command. The work includes categories of items with attachments providing itemized pricing breakdowns and facility and personnel requirements.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0002 for USNS ZEUS MTA to provide the follow ing:
(1) Incorporate RFC Q and A No. 4, 5, 6 and 7 to the solicitation.
(2) Provide revised J-1, J-2 and J-3.
(3) Provide new CAT A WIs 305 and WI 615 and CAT B WI 699. Inserted WI 305 and 615 to CLIN 0001AA.
(4) Provide WI draw ings references for WI 305.
(5) Change the total number of CLINS from 0010 to 0011 in Section B, L, and M.
(6) Add WIs 305, 615 and 699 to Section C.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 29
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Jul-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N3220522R4066
X 9B. DATED (SEE ITEM 11)
06-Jun-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Jul-2022
CODE
MILITARY SEALIFT COMMAND NORFOLK
471 EAST C STREET, BLDG SP-64 NAVAL STATION N
NORFOLK VA 23511
N32205 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N3220522R4066
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
SUBCLIN 0001AA
The CLIN extended description has changed from:
USNS ZEUS (T-ARC-7) ROH/DD MSC GENERAL REQUIREMENTS FUNDED CAT A
WIsCAT A WORK ITEMS 010, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023, 090, 104, 105, 106, 107, 111, 113, 114, 162, 201, 202, 204, 301, 302, 303, 353, 401, 402, 403, 458, 501, 502, 503, 505, 506, 507, 508, 510, 516, 517, 523, 524, 525, 526, 527, 540, 551, 601, 602, 604, 605, 606, 607, 608, 609, 610, 611, 614, 655.
To:
USNS ZEUS (T-ARC-7) ROH/DD MSC GENERAL REQUIREMENTS FUNDED CAT A
WIsCAT A WORK ITEMS 010, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023, 090, 104, 105, 106, 107, 111, 113, 114, 162, 201, 202, 204, 301, 302, 303, 305, 353, 401, 402, 403, 458, 501, 502, 503, 505, 506, 507, 508, 510, 516, 517, 523, 524, 525, 526, 527, 540, 551, 601, 602, 604, 605, 606, 607, 608, 609, 610, 611, 614, 615, 655.
CLIN 0010
This CLIN has been renumbered to CLIN 0011.
CLIN 0010 is added as follows:
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
OPTION Category "B" WI 0699
FFP
WI 0699 - Forward Crane Replace Certification
Category "B" WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category "B" WIs by exercising the option via written notice to the contractor.
FOB: Destination J998
NET AMT
The following have been modified:
TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0011 $______________
The contractor shall enter the total proposed price of all CLINs.
Section B, Price Schedule, detailed information
1. Attachment J-2, Category “A” WIs, provides a WI breakdown of CLIN 0001 pricing.
2. AGR and ODC
a. This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated during the contract. Changes are inherent to vessel repair contracts and should be expected by Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:
Abrasive cleaning/blasting Tank cleaning Welding Machinists (inside and outside)
Burning Brazing Carpentry Electrical work Electronic work Shipfitting Lagging Painting Boilermaking Pipefitting Sheetmetal work Engineering Rigging Staging/scaffolding General labor Fire Watch
b. Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:
Testing Quality Assurance Planning Cleaning (except tank cleaning) Material handling & warehousing Security Surveying Administration Transportation Purchasing staff Lofting Other indirect support Supervision
c. Consumable materials are goods used in the ordinary course of work performance that do not become an integral part of the repaired vessel (e.g., office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, paint buckets, paint brushes, protective clothing). Consumable material shall be included in the contractor's FBLR and not separately priced.
d. The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The ACO will apply these rates to the ODCs for each CCO when it is negotiated and settled.
e. The base cost stated in this CLIN does not include profit or G&A rates.
f. This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.
3. AGR details.
a. The Government may utilize CLIN 0002 for, and not limited to, man-hours generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI.
This work may consist of supplemental, emergent, or new work. AGR does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 AGR man-hours, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with ODC, and therefore will be performed concurrently.
b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders AGR pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time as may be granted, may be considered a failure of the parties to negotiate a fair and reasonable price for the AGR and will permit the ACO to take any of the three (3) options set forth in subparagraph “d” below. AGR proposals shall be priced using the FBLR set forth in Section B, CLIN 0002. The rate established in CLIN 0002 will be used in evaluating the contractor's proposal and for negotiating changes. As part of the contractor’s proposal submission for AGR, the following shall be included:
- FBLR
- Proposed Labor Mix/Categories
- Proposed Man Hours
- Total Proposed AGR
c. Considering FBLRs have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of labor categories and associated man-hours to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) as a result of the mix of labor categories and man-hours, the subsequent AGR price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “d”, below.
d. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:
1) Have the work performed by the Government;
2) Issue a unilateral modification; or
3) Cancel the requirement.
e. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the AGR at the contractor's facility. Furthermore, in cases described in subparagraphs “d.1” and “d.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.
f. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for AGR (CLIN 0002). Settlement of AGR (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The Contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0011 at contract completion shall be de-obligated.
4. ODC details.
a. The Government may utilize CLIN 0002 for and not limited to, material and equipment generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. ODC does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 ODC, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government.
Work under this CLIN may coincide with AGR, and therefore will be performed concurrently.
b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders ODC pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the ODC and will permit the ACO to take any of the three options set forth in subparagraph “e” below. As part of the contractor’s proposal submission for ODCs, the following shall be included:
Material Equipment -Part number - Part number -Order quantity - Order quantity -Unit price - Unit price -Total price - Total price
Other Direct Costs not captured above
- Travel
- Per diem (lodging, M&IE daily rates)
- Subcontractor Proposal Breakdown shall include but not be limited to, Material (Part number, Order Quantity, Unit Price, and Total Price), equipment (Part Number, Order Quantity, Unit Price, and Total Price), labor (FBLR, Proposed Labor Mix/Categories, and Proposed Manhours), and ODC (Travel and Per Diem)
The G&A and profit rates proposed shall be the same as the rates provided under CLIN 0002.
c. The contractor shall demonstrate due diligence in the assessment, evaluation, and determination resulting in the proposed utilization of other than local specialized labor resources. Only with ACO approval to proceed will a contractor, technical representative, or subcontractor be reimbursed for reasonable per diem costs (transportation, travel expenses, lodging, meals, and incidental expenses) required in connection with the associated change order.
Per diem costs are considered reasonable, allowable, and reimbursable only to the extent that they do not exceed the allowed per diem rate in effect at the time of travel as set forth in the JTR.
d. Considering G&A and profit rates have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of ODCs proposed to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) the price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “e”, below.
e. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:
1) Have the work performed by the Government;
2) Issue a unilateral modification; or
3) Cancel the requirement.
f. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing this work at the contractor's facility. Furthermore, in cases described in subparagraphs “e.1” and “e.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.
g. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for the ODC (CLIN 0002). Settlement of ODC (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0011 at contract completion shall be de-obligated.
5. Attachment J-3, Category “B” WIs, provides a WI breakdown of CLIN 0003 through 0011 pricing.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
ACRONYM TABLE
ABIH American Board of Industrial Hygiene ABR Agreement for Boat Repair ABS American Bureau of Shipping ACO Administrative Contracting Officer AGR Additional Government Requirements AIHA American Industrial Hygiene Association ALT Alternate AMT Amount BLDG Building CCO Contract Change Order CD Compact Disc CDRL Contract Data Requirements List CD-ROM Compact Disc Read-Only Memory CFM Contractor Furnished Material CFP Contractor Furnished Property CFR Condition Found Report CHENG Chief Engineer CFR Code of Federal Regulations CIH Certified Industrial Hygienist CLIN Contract Line Item Number
CONUS
CPARS
Contiguous United States Contractor Performance Assessment Reporting System
DBIDS Defense Biometric Identification Systems DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense DOD SAFE Department of Defense Secure Access File Exchange DON Department of the Navy EMAIL Electronic Mail ESRS Electronic Subcontract Report System FAPIIS Federal Awardee Performance and Integrity Information System FAR Federal Acquisition Regulation FBLR Fully-Burdened Labor Rate F/CC Fibers Per Cubic Centimeter FPCON Force Protection Condition
FTR Federal Travel Regulations G&A General and Administrative GFI-TD Government Furnished Information – Technical Data GFM Government Furnished Material GFP Government Furnished Property GPE Governmentwide Point of Entry IAW In Accordance With ID Identification ISO International Organization for Standardization JTR Joint Travel Regulations KO Contracting Officer KWh Kilowatt Hour LLTM Long Lead Time Material LPTA Lowest Price Technically Acceptable M&IE Meals and Incidental Expenses MSC Military Sealift Command MSCREP Military Sealift Command Representative MM Millimeter MSRA Master Ship Repair Agreement MTA Mid-Term Availability N/A Not Applicable NCACS Navy Commercial Access Control System NDA Non-Disclosure Agreement NO Number NSP Not Separately Priced ODC Other Direct Costs PAT Proficiency in Analytical Testing
PII
Portable Document Format Personally Identifiable Information
PM Program Manager PPE Principle Port Engineer PRIME Prime Contractor QA Quality Assurance QC Quality Control REV Revision RFC Request for Specification Clarification RFP Request for Proposal ROH/DD Regular Overhaul/Dry-Docking SECNAV Secretary of the Navy SF Standard Form SUB Subcontractor TPSN Time Phased Sequencing Network TWA Time-Weighted Average USC United States Code USCG United States Coast Guard USNS United States Naval Ship VR Voyage Repair WAWF Wide Area Workflow WI Work Item
SCOPE OF WORK
1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS ZEUS (T-ARC 7) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.
2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):
a. Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.
b. Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR 52.245-1 and DFARS 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.
c. Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.
d. Using management procedures and systems to identify behind-schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.
e. Developing a performance milestone schedule/critical path chart to measure scheduled performance.
Deviations from the milestone schedule/critical path chart dates in WI 0013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted IAW the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths.
The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 0013.
f. Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.
g. Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.
h. Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.
i. Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.
j. Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.
k. Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.
3. Contract work shall be performed by an eligible contractor as defined below.
a. The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.
b. The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:
1) Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority.
Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.
2) Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.
3) Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.
4) Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.
5) Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.
6) Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.
7) Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.
8) Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training.
First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.
9) Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records which indicate type of material, date, and place of disposal.
10) Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:
o Pier, with services in place, accessible to the CLASS size ship for berthing o Structural Shop o Machine Shop o Pipe Shop o Electrical/Electronic Shop o Carpentry Shop o Rigging Equipment o Dry-dock – when required for docking of vessel in performance of the specification
11) Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.
c. The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.
4. Asbestos removal requirements.
a. During the performance of this contract the contractor and subcontractors may be required to perform work which involves the removal or disturbance of asbestos or asbestos-containing products. This requirement applies to each instance of asbestos removal or disturbance.
b. The contractor shall comply with the precautions required in 29 CFR 1910.1001, 29 CFR 1926.58 and 40 CFR Part 61 and all other applicable Federal, state, and local restrictions. The contractor shall forward a copy of all required notices, licenses and permits to the KO immediately upon issuance or receipt.
c. The latest change to the Federal, state, and local regulations in effect at the time of issuance of the contract shall govern. Compliance with these regulations is mandatory and is necessary to protect the employees of the contractor and Naval personnel from exposure to asbestos fibers in excess of the OSHA Action level airborne concentration (currently 0.1 f/cc of air).
d. During removal or disturbance, the contractor shall control airborne asbestos concentrations outside the removal boundary to less than 0.1 f/cc at all times.
e. After removal or disturbance is complete, the areas within the removal boundary shall not be released for re-occupancy until clearance air sampling demonstrates these spaces have concentrations of asbestos less than 0.1 f/cc.
f. In all respects, the performance of air sampling and analysis shall be performed IAW the OSHA Reference Method (Appendix A of 29 CFR 1910.1001), with the following additional specifications:
1) Aggressive clearance sampling shall be performed on 25 mm cassettes at 2.0 liters per minute for a minimum of four (4) hours.
2) In performing the clearance sampling, the pump shall be placed within the compartment where the removal or disturbance occurred. When this operation is conducted in a multilevel space, at least one pump shall be placed on each level.
3) Air sampling shall be performed by a person competent in sampling procedures and overseen by a CIH by the ABIH.
4) Laboratory analysis of samples shall be performed by a participant in the AIHA PAT Program rated proficient for asbestos and air.
g. Personal sampling shall be conducted using breathing zone air samples which are representative of the 8-hour TWA exposure of each individual. Samples shall be collected and analyzed using the OSHA Reference Method contained in either 29 CFR 1910.1001 (as amended) or 29 CFR 1926.58 (as amended).
h. The contractor agrees to indemnify MSC for any fines assessed by Federal, state, or local agencies, for the contractor's failure to properly follow applicable regulations.
i. The contractor shall insert this instruction in all subcontracts entered into under this contract.
5. Post-award substitution of any major subcontractor should not be effected unless the proposed substitution is submitted to the KO and official approval is obtained. The post-award substitution or insertion of a second-tier subcontractor will be treated in the same manner as the substitution of a major subcontractor and requires specific approval by the KO.
6. Substitution of key personnel.
a. The contractor agrees to assign to this contract those persons identified as key personnel who are necessary to fulfill the requirements of this contract and whose resumes were submitted with the proposal. No substitution of key personnel shall be made except IAW these instructions.
b. All proposed substitutions must be submitted, in writing, at least seven (7) days in advance of the proposed substitutions to the KO and must provide the information required by paragraph “c” below.
c. All requests for substitution must provide a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information as requested by the KO. All proposed substitutes must have qualifications equal to or higher than the qualifications of the person to be replaced.
The KO or his authorized representative will evaluate such requests and promptly notify the contractor of the approval or disapproval thereof.
7. It is anticipated the ship will arrive at the contractor’s yard on or about 03 JAN 2023. All work shall be completed in no more than 90 calendar days from the actual start date designated by the Government at the time of contract award.
8. The place of performance for this contract shall be the contractor’s facility. Due to operational and national security availability considerations, the location shall be East and Gulf Coast.
Table 1: List of WIs:
Work Item
Item Name
CAT
000 GENERAL REQUIREMENTS
0001 SCOPE, GENERAL REQUIREMENTS, AND DEFINITIONS NSP
0002 TECHNICAL AND MANUFACTURER'S REPRESENTATIVES NSP
0003 APPROACH, BERTH, AND MOORING REQUIREMENTS NSP
0004 TESTING AND QUALITY ASSURANCE NSP
0005 ELECTRICAL SAFETY PROCEDURE REQUIREMENTS NSP
0006 HEAVY WEATHER PLAN NSP
0007 COLD WEATHER PLAN NSP
0010 FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM A
0011 GENERAL SERVICES FOR THE SHIP A
0012 INFORMATION TECHNOLOGY SERVICES A
0013 PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS A
0014 WEIGHT AND MOMENT REPORT A
0015 ILS GFM A
0016 FIRE PROTECTION AND SHIP SAFETY PROGRAM A
0017 HANDLING OF SHIP STORES A
0018 DELIVERY AND REDELIVERY OF THE VESSEL A
0019 SHIPBOARD ACCESS AND SECURITY A
0020 GAS FREE CERTIFICATES A
0021 CLEAN AND GAS FREE TANKS, VOIDS AND COFFERDAMS A
0022 MACHINERY SPACE TURN-OVER, DOCK TRIAL AND SEA TRIALS A
0023 HAZARDOUS WASTE DISPOSAL AT CONTRACTOR'S FACILITY A
0024 PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY NSP
0025 PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITY B
0026 VESSEL FINAL CLEANING COVID B
0030 CONTINUATION OF SERVICES B
0090 DAILY COVID PREVENTAION AND CONTROL A
100 HULL AND STRUCTURAL
0104 SUPERSTRUCTURE A
0105 INSPECT AND CLEAN ENGINE ROOM BILGES (1 YR) A
0106 PREPARE, PRIME, PAINT ENGINE ROOM BILGE SECTIONS A
0107 PREP, PRIME, PAINT BUOY HOLD DECK AND BILGE SECTIONS A
0108 ULTRASONIC B
0111 NON-SLIP RENEWAL (2.5YR) A
0112 KICK PIPES B
0113 HOS STRUCTURAL REPAIRS A
0114 LADDER REPAIRS A
0162 WATERTIGHT CLOSURE INSPECTION (5 YR) (3) A
200 PROPULSION MACHINERY
0201 SSDG 1 REPAIR AND MAINTENANCE SUPPORT A
0202 INSPECT MAIN PROPULSION MOTORS A
0204 AUTOMATION AND PROPULSION CONTROL SYSTEM INSPECTION AND
TEST (1 YR) (SCSI)
A
300 ELECTRICAL
0301 SWITCHBOARD A
0302 TRANSFORMER CLEANING (2.5YR) A
0303 BOW AND STERN THRUSTER MOTOR INSPECTION AND CLEANING (1YR) A
0305 SERVICE 150 AND 500 KVA MG SETS A
0353 THERMOGRAPHIC SURVEY (1YR) A
0399 MISCELLANEOUS MOTOR OVERHAUL B
400 COMMUNICATION AND NAVIGATION
0401 GMDSS SAFETY RADIO ANNUAL CERTIFICATION A
0402 RADAR AND ECDIS ANNUAL INSPECTION A
0403 GYRO COMPASS AND STEERING SERVICE A
0458 ANTENNA MAINTENANCE (5 YR) A
500 AUXILIARY MACHINERY
0501 HALON AND CO2 EXTINGUISHING SYSTEMS ANNUAL A
0502 PORTABLE EXTINGUISHER TEST AND INSPECT A
0503 FIRE ALARM ANNUAL INSPECTIONS A
0505 FIRE DAMPER INSPECTION A
0506 GAUGE CALIBRATION A
0507 FWD & AFT CABLE HANDLING SYSTEMS A
0508 PORT AFT CABLE DRUM PRESERVATION - REV B A
0510 OWS A
0516 SIMS PUMPS REPAIRS A
0517 DISTILLING PLANT SERVICE (2.5YR) A
0520 MISC PIPE B
0523 INCINERATOR SERVICE (1YR) A
0524 HOS OVERHAUL AND PRESERVATION A
0525 HP AIR COMPRESSOR SERVICE (2.5 YR) A
0526 BOW & STERN SHEAVE BEARING FLUSH A
0527 SEWAGE SYSTEM PIPING CLEANING (5 YR) A
0540 BOW STERN FAIRING A
0551 OVERHAUL PLATE COOLERS (2.5 YR) A
600 HABITABILITY , OUTFITTING AND FURNISHINGS
0601 ANNUAL ACOMM LADDER INSPECTION A
0602 ANNUAL SCBA COMPRESSOR SERVICE A
0604 ANNUAL FIRE HOSE HYDRO A
0605 CARGO ELEVATOR INSPECTION AND CERTIFICATION A
0606 ANNUAL LIFE RAFT CERTIFICAITON A
0607 ANNUAL RESCUE BOAT AND DAVIT INSPECTION A
0608 ANNUAL LIFE BOAT AND DAVIT INSPECTION AND CERTIFICATION A
0609 FORWARD CRANE CERTIFICATION A
0610 AFT CRANE CERTIFICATION A
0611 FIRE DOOR INSPECT AND REPAIR A
0614 VENTILATION DIFUSSERS AT DESIGNATED LOCATIONS - REV B COPY A
0615 ELECTRICAL MATTING IN THE AFT DOHB RM A
0655 IMMERSION SUIT INSPECTION AND SERVICE A
0699 FORWARD CRANE REPLACE CERTIFICATION B
700 SPONSOR RELATED
0701 CCTV CAMERA UPGRADE REV. A A
0702 MISSION CONTROL IDS UPGRADE A
0710 CRANE LIFTS AND SCAFFOLDING SUPPORT REV A
900 DRYDOCKING AND UNDOCKING
0926 STEEL B
SECTION E - INSPECTION AND ACCEPTANCE
The following Acceptance/Inspection Schedule was added for CLIN 0010:
INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
Destination Government Origin Government
SECTION F - DELIVERY AND PERFORMANCE
The following Delivery Schedule for CLIN 0011 has been added:
DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
POP 03-JAN-2023 TO
02-APR-2023
N/A N/A
FOB: Destination
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICE TO BIDDERS
INSTRUCTIONS TO OFFERORS
1. To obtain access to attachment J-1 and GFI-TD, complete and return attachment J-14 to the contract specialist.
Indicate if data will be forwarded to subcontractors. Files will be available via DOD SAFE for download for up to seven (7) days. Alternatively and at the determination of the KO, attachment J-1 and GFI-TD may be distributed on
CD.
2. REQUIREMENTS FOR SUBMISSION OF PROPOSALS
a. Proposal Submittal and Inquiries.
1) Submit proposals by the closing date and time identified on SF 33 block 9 through the Solicitation Module of the Procurement Integrated Enterprise Environment at https://piee.eb.mil/.
2) Other submission methods will not be accepted. Offerors are responsible for ensuring that the Government receives the complete proposal by the due date and time for proposal submission. For assistance access and training, offerors may contact their Contractor Account Administrator or Vendor Customer Support. Go to https://piee.eb.mil/xhtml/unauth/home/login.xhtml to search for the Contractor Account Administrator. Go to https://piee.eb.mil/xhtml/unauth/web/homepage/vendorCustomerSupport.xhtml for Vendor Customer Support. Go to https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/solicitation/proposals.xhtml for proposal submission training.
3) All questions concerning the solicitation shall be addressed via email to samuel.n.queen2.civ@us.navy.mil
4) See paragraph 5, “Inspection of Vessel/Pre-Proposal Conference,” for instructions to participate in a pre-proposal inspection of the vessel.
b. General Instructions
1) The selection of a source for award purposes will be conducted utilizing source selection (negotiated) procedures as delineated in FAR Subpart 15.3. Offers will be evaluated using the criteria under Section M, “Evaluation Factors for Award.” Noncompliance with the RFP requirements may hamper the Government’s ability to properly evaluate the proposal and may result in elimination of the proposal from further consideration for contract award.
2) The offer. The submission of the documentation specified below will constitute the offeror’s acceptance of the terms and conditions of the solicitation.
3) It is the Government’s intention to award without discussions. Offerors are encouraged to submit their best technical proposal and prices in initial proposals. IAW FAR 15.306, should discussions become necessary, the Government reserves the right to hold them. If this occurs, a competitive range will be determined and offerors notified. The competitive range may be limited for purposes of efficiency IAW FAR 15.306(c)(2). Proposals containing unacceptable ratings may be included in the competitive range provided they can be made acceptable as a result of discussions.
4) Instructions outlined in paragraph “c” below prescribe the format for the proposal and describe the approach for the development and presentation of proposal data. These instructions are designed to ensure the submission of information needed to allow for evaluation of proposals.
5) The WI Package is only available upon a written request to the contract specialist. All other referenced documents for this solicitation are available on the GPE website at https://beta.sam.gov/.
6) Debriefings. The KO will promptly notify offerors of the decision to eliminate their proposals from the competitive range, whereupon an offeror can request and receive a debriefing IAW FAR 15.505. The KO will notify unsuccessful offerors in the competitive range of the source selection decision IAW FAR 15.506. Upon such notification, unsuccessful offerors may request and receive a debriefing. Any offeror requesting a debriefing must make the request IAW the requirements of FAR 15.506.
c. Proposal Preparation Instructions
1) Offeror’s proposal shall consist of two (2) separate volumes: (Volume I) General; and (Volume II) Technical Proposal.
2) Proposal Format
a) The proposals shall be organized into two (2) separate volumes.
b) Offerors shall provide digital files in Adobe PDF, Microsoft Word, PowerPoint, and/or Excel. Offerors shall ensure that proposal files are virus-free and free of password protection. The Government reserves the right to eliminate a proposal from consideration if access to proposal data is prohibited due to viruses, passwords, and/or wrong format.
c) The table below shows detailed page limits to be submitted. The proposal shall not exceed the stated limits. If the page limits are exceeded, the pages in excess of the limit shall be removed and remain unread.
Volume Title Page Limits I General N/A II Technical Proposal 50 pages, excluding appendices
d. Proposal Content. The offeror shall submit a technical and a price proposal that shall include, at a minimum:
1) Volume 1 – General. Offerors are required to submit: (TAB A) a completed SF 33 to include acknowledgment of amendments, if applicable; (TAB B) Section B – Supplies or Services and Prices/Costs and an itemized breakdown of price on the form(s) provided in Attachments J-2 and J-3; (TAB C) Subcontracting Plan (not applicable for small business concerns); (TAB D) Section K Representations, Certifications, and Other Statements of Offerors; and (TAB E) Past Performance.
TAB A, SF 33. The SF 33 shall be fully completed upon submission. The offeror shall acknowledge any amendments to the RFP IAW the instructions on the SF 33 and FAR 52.215-1(b).
TAB B, Price:
Offerors shall submit prices in the format specified on the Contractor Price Breakdown forms of this solicitation, Attachments J-2 and J-3. Each specification Item Number must be either priced or marked “NSP.”
Overall Price. Unit prices and extended prices must be submitted as indicated, except NSP items.
Offerors shall include any costs associated with third-party access to the contractor’s facility, including costs for badges, safety orientation instruction, and/or parking, in the price proposal under the Shipboard Access and Security Item. For estimating purposes, offerors shall assume that (1) the Government will require access, to include safety orientation instruction and parking at the shipyard facility, for thirty (30) individuals for the entire duration of the performance period;
and (2) 20% of the badges issued to the Government and third-party personnel will be lost/misplaced and will require replacement.
The contractor agrees that its man-hour rate for the 10,600 man-hours of the AGR includes the complete and full compensation to which it is entitled, including, but not limited to, compensation for all the direct labor costs (e.g., straight time, overtime, premium time, shift differential, holiday time, standby time) for performing the AGR, as well as compensation for acceleration, delay and disruption, and other impacts, if any, to the aforementioned WI, to work performed under any other Government contract, and to any work in progress for the Government. The contractor further agrees that it is not entitled to a time extension to the delivery date of any ship under a Government contract by reason of or as a result of the ordering of the 10,600 man-hours of AGR.
AGR does not include work performed pursuant to the clauses of this contract entitled “Inspection and Manner of Doing Work,” “Guarantees,” or other contract provisions relating to the correction of defects.
The contractor shall follow the instructions stated below when completing Section B:
CLIN 0001 – The contractor shall complete CLIN 0001 NET AMT, each of the fill-in items stated in the extended description, and complete Attachment J-2 – Category “A” WIs.
CLIN 0002 – Indicate the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions) and the ODC profit and G&A rate.
CLINs 0003 through 0011 – The offeror shall complete CLIN 0003 through 0011 NET AMT, each of the fill-in items, and complete Attachment J-3 – Category “B” WIs.
TAB C (not applicable to small business concerns), Subcontracting Plan. IAW FAR 52.219-9, 52.219-9 Alt II, and DFARS 252.219-7003, offerors shall submit a Small Business Subcontracting Plan with their proposal. Offerors shall ensure they submit a Small Business Subcontracting Plan with all of the information required. In preparing the Small Business Subcontracting Plan, offerors should note historical compliance with FAR 52.219-8, 52.219-9 Alt II, and DFARS 252.219-7003.
TAB D, Section K (Representations, Certifications, and Other Statements of Offerors). The offeror shall ensure that its Section K submission is thoroughly completed, with all blocks in each certification/representation executed in their entirety and truthfully.
TAB E, Past Performance:
The Past Performance evaluation will be accomplished by reviewing aspects of an offeror’s recent and relevant Past Performance. Offerors may provide information for up to three (3) previous Government contracts where the effort is/was recent and relevant to the effort required by this solicitation. If the offeror has not had three (3) Government contracts within the last three (3) years, information on recent and relevant subcontracts and/or recent and relevant commercial contracts may be submitted.
a. “Recent” is defined as a contract in progress or completed within the last three (3) years.
b. “Relevant” is defined as a contract that is of similar scope, magnitude, and complexity to the requirements of this solicitation.
i. Scope: Experience in the areas defined in the WI package.
ii. Magnitude: The measure of the similarity of the volume, dollar value and/or duration of the work actually performed under the offeror’s submitted contracts to the WI package.
iii. Complexity: The measure of the similarity of technical difficulty, managerial intricacy and/or required coordination of efforts and disciplines performed by the offeror in its submitted contracts to the WI package. For complexity, not only will the tasks performed by the offeror be considered, but also the offeror’s ability to coordinate tasks (e.g., concurrent performance requirements).
A Past Performance Data Sheet (Attachment J-12) shall be submitted for each contract to be considered as past performance. Offerors shall provide a detailed explanation demonstrating the similarity of the contracts to the requirements of this solicitation; a detailed description of the work performed for the contract; and the role performed, including whether the offeror acted as a prime contractor or a subcontractor. Offerors are responsible for the accuracy of all data provided.
Past performance information regarding predecessor companies, key personnel who have relevant experience, and subcontractors that will perform major or critical aspects of the requirement may be provided as past performance submissions.
For each of the contracts the offeror describes in a Past Performance Data Sheet (Attachment J- 12), the offeror is requested to provide a Past Performance Questionnaire (Attachment J-13) to a reference at the organization that awarded the contract.
This is the start of the file's text. The full file is on GovTribe.