Amendment 003.docx
DOCX document 126 KB Posted
- Attached to
- Midterm Availability on USNS WASHINGTON CHAMBERS Federal contract opportunity
- Solicitation number
- N3220521R4221
About this file
This document is an amendment to a solicitation for a midterm availability on the USNS WASHINGTON CHAMBERS. The amendment provides clarification on work items and door counts in response to contractor requests for clarification. It extends the bid due date from September 28, 2021 to October 5, 2021 to allow additional time for subcontractor and OEM quotes due to labor issues caused by the pandemic and outstanding requests for clarification. The work includes 239 hinged fire doors, inspection of a deep fat fryer, and removal of a work item for kettle deck preservation. The solicitation is issued by the Department of the Navy Military Sealift Command for an unspecified period of availability on the USNS WASHINGTON CHAMBERS.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION J - LIST OF DOCUMENTS, EXHIBITS & OTHER ATTACHMENTS
The following have been added by full text:
RFC #3
MILITARY SEALIFT COMMAND
N3220521R4221
Request for Clarification
RFC 1:
SPECIFICATION ITEM NO.: _574
PARAGRAPH / SECTION NO: 3.1.2a
TITLE: TAKE_CCSI_FIRE DOORS AND SHUTTERS
QUESTION:
Paragraph 3.1.2a. Two hundred and five (305) hinged fire doors. Additionally, Enclosure 2.2.1 is showing a different count and duplication of door numbers.
Please confirm number of hinged fire doors and correct location/door number of each.
ANSWER:
Correct number for hinged doors is 239. Enclosure has been validated as correct. Duplicate doors, and accurate within the space.
RFC 2.
SPECIFICATION ITEM NO.: _662
PARAGRAPH / SECTION NO: Spec
TITLE: TAKE_CCSI_A_DEEP FAT FRYER INSPECTION (1YR
QUESTION:
WI 662 is shown on the J-2 for pricing, but WI specification was not provided. Should this be deleted from the J-2?
This should be included in the Work Package.
RFC 3.
SPECIFICATION ITEM NO.: _603
PARAGRAPH / SECTION NO: Spec
TITLE: Kettle Deck Preservation
QUESTION:
WI 603 is shown on the J-2 for pricing, but WI specification was not provided. Should this be deleted from the J-2?
This Work Item should be removed from the J-2.
RFC 4:
SPECIFICATION ITEM NO.: Solicitation pg.1 PARAGRAPH / SECTION NO: Block 9
TITLE: Offers due date
QUESTION:
Contractor respectfully request a bid due date extension to 10/05/2021. We are starting to receive feedback from multiple Sub-Contractors and OEM’s asking for additional time to provide their quotes. We believe this is partially due to labor issues related to the pandemic. Additionally there are a few outstanding RFC’s yet to be answered. We believe the time it will take to receive, evaluate and include in our proposal currently is not sufficient. This additional time is in the best interest of the Government
Bid due date extended to 10/05/2021.
(End of Summary of Changes) image1.emf