21R4160 Q and A 0003.pdf

PDF 92 KB Posted

Attached to
TUGCON: Open-Ocean Barge Tow Mission
Solicitation number
N32205-21-R-4160
Issued by

About this file

This document contains answers to questions from potential offerors regarding solicitation N32205-21-R-4160 issued by the Military Sealift Command. The solicitation seeks an open-ocean barge tow mission to transport a berthing barge from the load point to the offload point. Offerors do not need to include a comprehensive tow plan and checklist with their proposals as those will be required only after award for tow plan approval. The Navy asset being towed does not have a load line so offerors should plan to obtain any necessary permits for towing the barge. While the Navy does not require agents, offerors must provide point of contact information for representatives available at the load and offload points to discuss questions about the towed barge and tow vessel.

View the file

Other files

File Type Posted
A0005 Reopen and Change Laydays.pdf PDF
A0003 Reopen and add Jones Act Language.pdf PDF
COMPREHENSIVE TOW PACKAGE CHECK LIST.doc DOC document
A0002 Add Checklist and Amend Language.pdf PDF
21R4160 Q and A 0002.pdf PDF
21R4160 Q and A 0001.pdf PDF
Combined file.pdf PDF
YC 1633 Maximum Towing Speed for an Ocean Tow.pdf PDF
Orange Shipbuilding Weight Report.PDF PDF
Amend 0001 Add Shipyard Data Template.pdf PDF
Shipyard Data Template for Offeror.xlsx XLSX spreadsheet
RFP 21R4160.pdf PDF
201902885.txt TXT text file
TUGCON 2020 (08-2020).pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-21-R-4160

QUESTIONS AND ANSWERS

05 MARCH 2021

THE FOLLOWING ARE ANSWERS TO QUESTIONS RECEIVED FROM POTENTIAL

OFFERORS. THE ANSWERS PROVIDE CLARIFICATION ONLY AND DO NOT

CONSTITUTE AN AMENDMENT TO THE SOLICITATION.

1. CAN YOU CONFIRM THAT THE COMPREHENSIVE TOW PACKAGE CHECKLIST

(APPENDIX H) IS NOT TO BE INCLUDED WITH THE OFFERORS PROPOSALS AND

ONLY REQUIRED OF THE AWARDEE?

REVISED ANSWER: YES, OFFERORS DO NOT NEED TO PROVIDE A

COMPREHENSIVE TOW PLAN AND CHECKLIST WITH THEIR PROPOSAL. BOTH

ITEMS WILL BE REQUIRED AFTER AWARD FOR TOW PLAN APPROVAL.

2. DOES THE BARGE HAVE A LOAD LINE? OR WE WILL IT NEED TO GET A TRIP

PERMIT?

ANSWER: A LOAD LINE WAS NOT PROVIDED BY THE SPONSOR (U.S. NAVY

ASSET). RECOMMEND YOU PLAN TO GET PERMITS AND APPROVALS AS MAY

BE NEEDED IN ORDER TO TOW THE BERTHING BARGE.

3. DOES THE NAVY REQUIRE AN AGENT IN BOTH THE LOAD AND DISCHARGE

PORTS AND WILL THAT COST NEED TO BE INCORPORATED INTO OUR BID?

ANSWER: THE NAVY DOES NOT REQUIRE AGENTS BUT DOES NEED POC

INFORMATION FOR YOUR COMPANY REPRESENTATIVE WHO WILL BE

AVAILABLE TO DISCUSS BARGE AND TOW VESSEL QUESTIONS AT THE LOAD

AND OFFLOAD POINTS.