N3220520R4136 Amendment 0004.docx

DOCX document 33 KB Posted

Attached to
USNS MATTHEW PERRY MTA Federal contract opportunity
Solicitation number
N3220520R4136
Issued by
Department of the Navy Military Sealift Command

About this file

This document contains clarification questions and answers regarding a solicitation for maintenance work on the USNS MATTHEW PERRY. The solicitation number is N3220520R4136 from the Department of the Navy Military Sealift Command. Clarification questions were asked about work items including scheduled maintenance on main diesel engines requiring overhaul of one cylinder head, an emergency fire pump overhaul which will include separating the casing and removing the rotating assembly to replace bearings, seals and wear rings, and cleaning and gas freeing applicable fuel and void tanks as identified on the tank list enclosure. The answers provided clarification on the scope of work, materials to be provided, and tasks required for each work item.

View the file

Other files for this federal contract opportunity

Other files attached to USNS MATTHEW PERRY MTA, newest first.
File Type Posted
N3220520R4136 Amendment 0005.docx DOCX document
N3220520R4136 Amendment 0003.docx DOCX document
N3220520R4136 Amendment 0002.docx DOCX document
J - 10 Interport Differential.doc DOC document
N3220520R4136 Amendment 0001.docx DOCX document
J - 2 Category A Items PERRY 20R4136.xls XLS spreadsheet
MPR MTA 1QTR FY21 CDRLs.zip ZIP file
J-4 USNS MATTHEW PERRY.xlsx XLSX spreadsheet
J Attachments.zip ZIP file
N3220520R4136 USNS MATTHEW PERRY.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220520R4136

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION J - LIST OF DOCUMENTS, EXHIBITS & OTHER ATTACHMENTS

The following have been added by full text:

REQUEST FOR CLARIFICATION 0004

MILITARY SEALIFT COMMAND

N3220520R4136

Request for Clarification

SPECIFICATION ITEM NO.: 216

PARAGRAPH / SECTION NO: 4.1.1

TITLE: 8 CYLINDER MAIN DIESEL ENGINE 36,000 HOUR SCHEDULED MAINTENANCE REV-

QUESTION #16:

1.Par 3.1 list the items to be worked but no total surface area for these items is provided. Please provide a total surface area for these items.
2.Par 7.10 direct to abrade all other surfaces; would hand sanding satisfy this requirement or would grit sweep blasting be required?
3.Can the coatings in Par 7.12.3 through 7.12.7 be applied via brush and roll as long as the proper DFT is obtained?

ANSWER:

1. The Work Item Reads Correctly. The 36K OH only removes 1 Head. Only One Head will be shipped. You will use that head in its place and overhaul the removed and send back to Norfolk W143 Warehouse once OEM is done. See Table for Work Cards on Page 12. Task 172.

172
Cylinder Head
Remove, clean and check one cylinder head. Check bolt loosening pressure.
055.01

055.02

SPECIFICATION ITEM NO.: 541

PARAGRAPH / SECTION NO: 4.2, 7

TITLE: EMERGENCY FIRE PUMP NO 2 OVERHAUL

QUESTION #17:

Statement of Work paragraphs do not direct contractor to remove or reinstall pump.

Also paragraph 7.1.3 directs contractor to replace the rotating assembly with the material listed in 4.2, but 4.2 does list any rotating assembly.

Please confirm scope is to shop overhaul the pump only. No removal or reinstallation.

Please also advise if rotating assembly will be provided or required.

ANSWER:

1. The WI is correct. The pump is a spare. We will provide the pump, Contractor OH, return to ship’s force. Spare Pump.

2. What is meant by the Rotating Assembly, you will have to separate the casing, remove the rotating assembly, take out the Bearing, seals and wear rings, clean the assembly and ready for newly provided Bearings, Seals and Wear Rings. There is not a new or separate rotating assembly. Just replacing the provided material on the Rotating assembly

SPECIFICATION ITEM NO.: 0021

PARAGRAPH / SECTION NO: 2.2.1

TITLE: Clean and Gas Free Tanks, Voids, Cofferdams, and Spaces

QUESTION #18:

Para. 2.2.1, USNS Matthew Perry (T-AKE 9) List of Applicable Tanks, Voids and Cofferdams – Please clarify what the “X” indicates on the tank list enclosure. Should we assume all tanks are being cleaned?

ANSWER:

1. WI 0021 Table – only the items with an “X” are to be done. For Example. The Fuel Oil Storage is required to be Clean and Gas Free and Safe for Hot Work. The Fuel Oil Overflow Tank is not to be touched. SO whatever box is checked for whatever tank, that action is to be taken.

Description
Tank Location
95% Capacity

(gals) Arrival Condition (gals)

Clean and Gas Free
Safe for Hot Work
Fuel Oil Storage
3-81.5-2
70,270
2000
X
X
Fuel Oil Overflow Tank
3-82-1
64,640
0

(End of Summary of Changes) image1.wmf