About this file
This document contains questions and answers related to a solicitation for a vessel charter opportunity with the Military Sealift Command. The solicitation seeks a contractor to provide a vessel equipped with a 30-ton crane to transport government-furnished equipment and Navy divers between Monday and Friday. The vessel must have the ability to deploy bow and stern anchors for training events, but there are no special requirements for the three-point mooring system. The period of performance is unspecified beyond being required Monday through Friday. All equipment loaded aboard the vessel is government-furnished for use by Navy divers during training events.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20R4127 QA 0002.pdf | ||
| WD 201902884.pdf | ||
| 20R4127 RFP.pdf | ||
| SPECIALTIME PROFORMA 2020 .pdf | ||
| SPECIALTIME Fuel Consumption Temp.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-20-R-4127
QUESTIONS AND ANSWERS#1
24 July 2020
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
1. Is the contractor required to have a dedicated shoreside facility with a 30 ton crane, or is access to a public commercial berth acceptable?
ANSWER: Commercial facilities equipped with a 30 Ton crane for loading and offloading material from flatbed trucks to the vessel would be acceptable.
2. We would appreciate if you can confirm the period of charter and clarify if the following equipment are contractor or GFE. If they are contractor provided, do Navy divers utilize them for their mission?
ANSWER: Period of charter is Monday – Friday; all equipment listed is government furnished, Sponsor Mission Equipment to be loaded, secured for sea and unloaded at completion of training events.
3. Are there any special requirements regarding the 3 point mooring system?
ANSWER: No, there are not any special requirements; however, the vessel must have the ability to deploy a bow and stern anchor.