This document outlines requirements for a regular overhaul and dry-docking of the USNS Richard Byrd. Key details include:

The solicitation is for preparation and accomplishment of work items for the USNS Richard Byrd's regular overhaul and dry-docking. Required work includes Category A work items such as furnishing services, project planning, fire protection, and preservation work. Optional Category B work items include physical security, vessel cleaning, and continuation of services. The period of performance is 75 calendar days from vessel arrival at the contractor's facility. Prices should be submitted using the provided forms, including itemized breakdowns for Category A and B work items. Technical and price proposals are due by July 20, 2020. Offerors must meet eligibility requirements including ship repair experience and certifications. The pre-proposal vessel inspection is currently not available.

View the file

Other files for this federal contract opportunity

Other files attached to USNS BYRD ROH/DD, newest first.
File Type Posted
BYRD AMENDMENT 0008.docx DOCX document
BYRD AMENDMENT 0007.docx DOCX document
J - 10 Interport Differential REV.doc DOC document
BYRD AMENDMENT 0006.doc DOC document
J - 2 Category A Items.xls XLS spreadsheet
BYRD AMENDMENT 0005.doc DOC document
BYRD AMENDMENT 0004.doc DOC document
BYRD AMENDMENT 0003.doc DOC document
J - 10 Interport Differential.doc DOC document
RFCs AMENDMENT 0002.docx DOCX document
J - 10 Interport Differential.doc DOC document
BYRD AMENDMENT 0001.doc DOC document
J - 3 Category B Items.xls XLS spreadsheet
J - 12 Past Performance Data.doc DOC document
J - 13 PAST PERFORMANCE QUESTIONNAIRE.docx DOCX document
J - 2 Category A Items.xls XLS spreadsheet
J - 7 MSC Ship Repair Facility Survey (002).doc DOC document
J - 8 Request for Spec Clarification.doc DOC document
USNS BYRD ROH-DD N3220520R4096.doc DOC document
J - 11 Dry Dock Evaluation Form.docx DOCX document
J-A - BYRD ROH-DD FY21 POSTING.docx DOCX document
J - 9 Disclosure of Lobbying Activities SF-LLL.doc DOC document
SYNOPSIS N3220520R4096.docx DOCX document
SYNOPSIS N3220520R4096.docx DOCX document
Sources Sought USNS BYRD.doc DOC document
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION / CONTRACT FORM

The required response date/time has changed from 13-Jul-2020 02:00 PM to 20-Jul-2020 02:00 PM.

The number of offeror copies required has decreased by 4 from 4 to 0.

SECTION B - SUPPLIES OR SERVICES AND PRICES

The following have been added by full text:

RFCS RESPONSES

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.:0519

PARAGRAPH / SECTION NO: 2.5

TITLE: VCHT Piping Replacement with CuNi (T-ALT 518)

QUESTION:

2.5 MSC Drawing No. 528-8613488, Replace VCHT Piping with Cu-Ni Material Piping Modifications is missing from the provided references and will be needed to estimate scope.

ANSWER:

Please see attached Reference Drawing MSC Drawing No. 528-8613488.

SPECIFICATION ITEM NO.: 090

PARAGRAPH / SECTION NO: 2.1.2, 2.1.3 & 2.1.4

TITLE: DAILY COVID-19 PREVENTION AND CONTROL SERVICES

References listed could not be found in provided documents.

ANSWER:

Please see attached Documents

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.:

PARAGRAPH / SECTION NO: 2.1.3 & 2.2

(enclosures 1, 2 & 3)

TITLE: FW STERN TUBE LUBRICATION SYSTEM

References & enclosures listed could not be found in provided documents.

ANSWER:

Please see attached Enclosures

REQUEST FOR SPECIFICATION CLARIFICATION

PARAGRAPH / SECTION NO: 7.1.19.3

TITLE: FURNISH GENERAL SERVICES

Paragraph 7.1.19.3 The contractor shall provide a bid price for bilge water disposal based on an estimated quantity of 3000,000 gallons.

Please confirm 3,000,000 Gallons of bilge water for disposal.

ANSWER:

confirm 300,000 Gallons of bilge water for disposal (not 3 million Gallons)

REQUEST FOR SPECIFICATION CLARIFICATION

PARAGRAPH / SECTION NO: All

TITLE: TELEPHONE SERVICES

WI 012 TELEPHONE SERVICES: This specification is for phone service only, MSC currently does not have a specification for computers and other office equipment.

Please confirm

ANSWER:

Please read and review WI 010. WI 010 describes furnishes for the office for the Overhaul Management Team.

In WI010, paragraph 7.1.4, it describes the administrative assistant’s desk. Also, 7.2, it describes the MSCREP offices and workstations.

As described in WI 010, there should be a total 10 workstations. (Add items in paragraph 7.1.4 and 7.2).

SPECIFICATION ITEM NO.: 615

PARAGRAPH / SECTION NO: All

TITLE: Exterior Hull Vent Screens Material Replacement (T-ALT 425)

WI 615 requires FRP Vent assemblies and louver blades. After speaking with the recommended vender the lead time for these items is over 20 weeks. Receipt of these items would occur after the period of performance.

Contractor requests these items be changed to Government Furnished Materials so they can be procured in time or the material to be used is changed from FRP to Stainless Steel allowing for lower lead times.

ANSWER:

I would keep it as FRP material. I have made an order for the Vent Assemblies, Hope this comes prior to the availability. (So this material will be GFM vice CFM due to lead times).

If this does not come on time, I will write an RFP to perform preservation around the current Louver assemblies instead, vice replacing (as described by the WI

SPECIFICATION ITEM NO.: 024

PARAGRAPH / SECTION NO: ALL

TITLE: Physical Security at Private Contractor's Facility

Pricing for this item is normally provided as CAT B WI 025. WI 024 is normally “NSP”.

Please confirm this work item 024 is NSP. (not separately priced)

ANSWER:

Confirm that WI 024 is NSP. Please see attached Rev 23.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 251

PARAGRAPH / SECTION NO: 3.3

TITLE: TAKE CCSI Woodward Governors (24K Hours)

QUESTION:

Please provide the model / part number and serial numbers of the Woodward Governors. The numbers given in the work item are not Woodward part numbers.

ANSWER:

TYPE; PGG-EG

PART #; F8575-779

SERIAL;

#1 MDG; 14246450

#2 MDG; 24462309

#3 MDG; 24462298

#4 MDG; 14441485

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0585

PARAGRAPH / SECTION NO:2.1.4

TITLE: Ballast Tank TLI

QUESTION:

Please provide reference 2.1.4.

ANSWER:

Please see attached Reference.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0562

PARAGRAPH / SECTION NO:____________________

TITLE: TAKE CCSI SCBA ANNUAL INSPECTION

QUESTION:

Are the cylinders 4500 PSI or are they 5000 PSI I see both state on RFQ

Part number for low pressure hoses?

Manufacture and hydro-test date?

Last years’ certificates for cylinder and packs if I can get a copy of this?

ANSWER:

Depending on which Cylinders you are describing, they are either or.

If you are describing the Interspiro cylinders, they are 4500PSI (total qty 98).

If you are describing the filling station airbank cylinders, they are 5000PSI (Qty 8).

Not sure what the low pressure hose part number. Need to discuss with the OEM, they would have those part number. Western Fire & Safety Company was OEM that perform the latest certification (actually, they have been certifying the system for consecutive multiple years).

Please see attached 2019 report for Manufacture and hydro date.

Please see attached 2019 report for test results on the packs.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0562

PARAGRAPH / SECTION NO:2.0 / 2.1.5

TITLE: TAKE CCSI SCBA Annual Inspection

QUESTION:

Please provide reference 2.1.5 SCBA Service Report.

ANSWER:

Please see attached 2019 Report from Western Fire & Safety Co.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0567

PARAGRAPH / SECTION NO:2.0 / 2.1.3 and 2.1.6 TITLE: TAKE CCSI Fixed Foam Firefighting System Inspection and Test

QUESTION:

Please provide reference 2.1.3 Tech Manual T9555-CL-MMC-010.

Please provide reference 2.1.6 MSFSC SWIRR No. 22, Miscellaneous Valve Repair

ANSWER:

Please see attached References.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0570

PARAGRAPH / SECTION NO:2.0 / 2.1.2

TITLE: TAKE CCSI Portable Fire Extinguisher Service

QUESTION:

Please provide reference 2.1.2 Last Portable Fire Extinguisher Service Record.

ANSWER:

Please see latest Service Report on the Portable fire extinguisher.

SPECIFICATION ITEM NO.: N3220520R4096

PARAGRAPH / SECTION NO: CLIN ITEM 0002

TITLE: ODC BASE $

ODC base dollar amount was not provided.

ANSWER:

$1,000,000.00

SPECIFICATION ITEM NO.: N3220520R4096

PARAGRAPH / SECTION NO: L. para. 2.a.

TITLE: REQUIREMENTS FOR SUBMISSION OF PROPOSALS

Due to current pandemic climate, our company has mandated a work from home policy within all administrative departments, which limits our ability to print and mail documents. In line with Centers for Disease Control (CDC) recommendations, contractor is practicing social distancing and is ceasing all non-essential social interactions in relation to our duties within the bid proposal process. This is to include courier services of any type.

We are requesting that the Solicitation Section L, paragraph 2.a. for the for USNS RICHARD BYRD ROH 2020 be amended to allow electronic submittal using the secured DoD SAFE (Secure Access File Exchange) website and/or Contractors ShareFile secure file sharing and transfer service.

ANSWER:

Electronic submittal of package will be acceptable via DOD Safe hard copies will not be required.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0202

PARAGRAPH / SECTION NO:2.0 / 2.1.1

TITLE: TAKE CSI Main Engine Flexible Connection Replacement

QUESTION:

Please provide reference 2.1.1 NAVSEA S6430-AE-TED-010, Technical Directive, Piping Devices, Flexible Hose Assemblies.

ANSWER:

Please attached Document.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0090

PARAGRAPH / SECTION NO: Various TITLE: Daily COVID-19 Prevention and Control Services

QUESTION:

Could the owners offer more direction as to what areas are to be cleaned and how often?

ANSWER:

Please re-read paragraph 7.4 of the WI. It has detailed information on your question.

Paragraph 7 states:

7.4.1 All the spaces where production work is ongoing or the space transited by the contractor shall be cleaned. “

7.4.3 “Clean and disinfect high traffic and frequently touched areas and objects every two hours including but not limited to tables, doorknobs, doorframes, light switches, chairs, tables, appliances, countertops, handles, desks, phones, keyboards, toilets, faucets, sinks, hand rails in stairways and hallways, lounges, vestibules into house, machine shops and gangways, portable toilet facilities, exterior handrails (including exterior/interior to the vessel and engine room), stair towers, vertical ladder rungs, doors, door knobs, quarterdeck and gangways using NAVSEA approved cleaning agents.”

These two paragraphs are just two examples of answering your question. Please re-read all of Paragraph 7 as it tells you when and where to be clean and how often.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0114

PARAGRAPH / SECTION NO:Various TITLE: Forepeak Tank Preservation

QUESTION:

1. Can the owner confirm that the complete Forepeak (100% of the internal area) is to be prepared and coated and that 11,800 square feet noted in 3.1.3 is the total area of this tank? Please note that unless this vessel is a different design for the other TAK-E’s this estimated surface area isn’t even close to correct.

2. Paragraph 7.3.4 directs a 48 hour cure time between coats, the manufactures data sheet doesn’t confirm this. With a standard MSC system (two (2) full coats, two (2) stripe coats and final touch up the cycle time (with the reinstallation and coating inserts) could be as long as three weeks. The 48 hour requirement could be a misprint.

3. Paragraph 7.2.3.6 Grey Water tank seems to be a misprint. Please clarify.

ANSWER:

Since the avail is only 45 days long and the Squarefootage is off by a lot, I will be cancelling this WI and postpone this WI to my 2023 ROH/DD.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0156

PARAGRAPH / SECTION NO:Various TITLE: TAKE CCSI Flight Deck Preservation

QUESTION:

1. Please provide direction on how we are to coordinate the tie down testing (7.7.10) with the surface preparation and coating of the deck. Maybe we should blast the items to be tested first and then after testing blast the entire deck?

ANSWER:

Go-no-go testing of the tie downs can be perform after 7.7.5 is complete “Vacuum blast the entire flight deck area including deck tie down fittings to a SSPC-SP-10 Near White Metal…”

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0585

PARAGRAPH / SECTION NO: Various TITLE: Ballast Tank TLI

QUESTION:

1. Please provide list of tanks to be worked.

ANSWER:

Please refer the tanks being work in 2.1.1, in Table 11.D. All Tanks listed will be worked on (Tube and Wire type). Total amount of tanks worked is 14.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0901

PARAGRAPH / SECTION NO: Various TITLE: Docking and Undocking

QUESTION:

1. We see that the hull is to be pressure washed immediately after docking; but we do not see an accompanying item for hull preparation and coating.

ANSWER:

This is correct. This pressure wash is to assure the removal of dirt, slime, marine growth & fouling and other foreign substances.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0567

PARAGRAPH / SECTION NO: Various TITLE: TAKE CCSI Fixed Foam Firefighting System Inspection and Test

QUESTION:

Please provide a copy of certificates for the foam systems.

Please provide manufacturer of the foam system, foam valves, proportioners and gasket types.

ANSWER:

Please see attached certificates for the Foam System.

Please refer to reference 2.1.3 (Tech Manual T9555-CL-MMC-010), for any detailed information on the components found on the system.)

SPECIFICATION ITEM NO.: 0569

PARAGRAPH / SECTION NO: Various TITLE: TAKE CCSI Fire and Smoke Detection Alarm System

QUESTION:

Please provide a copy of last year’s certificates.

Please provide name and model on the detection panel.

ANSWER:

Please see attached Service Report

Model number of the Detection Panel is Consilium CS3000

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0565

PARAGRAPH / SECTION NO: Various TITLE: TAKE CCSI Fixed Gas Firefighting System Inspection and Test

QUESTION:

Please provide a copy of last years Halon and CO2 system reports and cylinder specification reports.

ANSWER:

Please see attached Service Report.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0572

PARAGRAPH / SECTION NO: Various TITLE: TAKE CCSI Deep Fat Fryer and Range Fire Extinguishing System

QUESTION:

Please provide a copy of last year’s certificates.

Please provide number of links and number of system cylinders.

ANSWER:

Please see attached Service Report.

The number of links is 5. And the number of system cylinders is 2 (One each 6 gallons, One each 1.25 Gallons)

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0570

PARAGRAPH / SECTION NO: Various TITLE: TAKE CCSI Portable Fire Extinguisher Service

QUESTION:

Please provide a copy of last year’s certificates.

ANSWER:

Please see attached Report

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0571

PARAGRAPH / SECTION NO: Various TITLE: TAKE CCSI Fire and Smoke Damper Service

QUESTION:

Please provide a copy of last year’s certificates.

ANSWER:

Please see attached Service Report.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: 0575

PARAGRAPH / SECTION NO: Various TITLE: TAKE CSI Water Mist Firefighting System – Inspection and Test

QUESTION:

Please provide a copy of last year’s certificates.

ANSWER:

Please see attached report.

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: _0517A

PARAGRAPH / SECTION NO:_2.1

TITLE: _TAKE CSI LTFW COOLER CLEANING AND INSPECTION (2.5 YR)

QUESTION:

Will the Technical Manual T9235-AZ-MMC-010 be available for the bidding process?

ANSWER:

Your request for T9235-AZ-MMC-010 is not part of the WI. T9532-AZ-MMC-010 is listed in Ref 2.1.

Please see attached Reference 2.1

REQUEST FOR SPECIFICATION CLARIFICATION

SPECIFICATION ITEM NO.: _0201

PARAGRAPH / SECTION NO:_2.1 and 3.1.2 (b)

TITLE: _TAKE CSI PROPULSION MOTOR AND COOLER CLEANING, INSPECTION AND MAINTENANCE

QUESTION:

Are these coolers tube and shell?

Will the Technical Manual T9235-AG-MMC-010 be available for the bidding process?

ANSWER:

The coolers are of double tube type.

Please see attached Reference.

The following have been modified:

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "A" WIs

FFP

Prepare for and accomplish the ROH/DD of the USNS RICHARD BYRD (T-AKE 4)

Total Category "A" WIs

Proposed unit price per KWh of electrical shore power $_____ IAW WI 0011, 7.1.1.4

Proposed unit price per gallon of potable water $______ IAW WI 0011, 7.1.3.3

Proposed unit price per gallon of distilled water $______ IAW WI 0011, 7.1.4.2

Proposed unit price per gallon of bilge water removal $______ IAW WI 0011, 7.1.19.3

Proposed unit price per crane usage $______ IAW WI 0011, 7.10.1

Proposed Hazardous Waste handling fee rate IAW WI 0023, 7.4.3. ______%

CDRLs FOR CLINs INCLUDING OPTION CLINs, IF EXERCISED:

The data to be furnished hereunder shall be prepared and submitted IAW the CDRL, DD Form 1423, Exhibit A, attached hereto. The CDRLs form a part of the schedule of this solicitation.

SEE PARAGRAPH 1.

FOB: Destination

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

AGR and ODC

AGR

(10,000) man-hours @ $________ per man-hour =

ODC

Base $1,000,000

Proposed G&A Rate _______________%

Subtotal:

Proposed Profit Rate _______________%

Subtotal:

SEE PARAGRAPH 2, 3, AND 4.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0025

WI 0025 - Physical Security at Private Contractor's Facility in FPCON Charlie - Delta

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

SEE PARAGRAPH 5.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0026

WI 0026 - Vessel Fianl Cleaning Rev A

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Category "B" WI 0030

WI 0030 – Continuation of Services

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

NET AMT

ITEM NO

SUPPLIES/SERVICES

QUANTITY

UNIT

UNIT PRICE

AMOUNT

Category "B" WI 0902

FFP

WI 0902 - Dry Docking and Undocking Vessel

Category “B” WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The ACO may require the contractor to perform the requirements of the optional Category “B” WIs by exercising the option via written notice to the contractor.

SEE PARAGRAPH 5.

NET AMT

TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0006 $______________

The contractor shall enter the total proposed price of all CLINs.

Section B, Price Schedule, detailed information

1. Attachment J-2, Category “A” WIs, provides a WI breakdown of CLIN 0001 pricing.

2. AGR and ODC

a. This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions, etc.) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated during the contract. Changes are inherent to vessel repair contracts and should be expected by the Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:

Abrasive cleaning/blasting

Tank cleaning

Welding

Machinists (inside and outside)

Burning

Brazing

Carpentry

Electrical work

Electronic work

Shipfitting

Lagging

Painting

Boilermaking

Pipefitting

Sheetmetal work

Engineering

Rigging

Staging/scaffolding

General labor

Fire Watch

b. Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:

Testing

Quality Assurance

Planning

Cleaning (except tank cleaning)

Material handling & warehousing

Security

Surveying

Administration

Transportation

Purchasing staff

Lofting

Other indirect support

Supervision

c. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor's FBLR and not separately priced.

d. The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The ACO will apply these rates to the ODCs for each CCO when it is negotiated and settled.

e. The base cost stated in this CLIN does not include the profit or G&A rates.

f. This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.

3. AGR details.

a. The Government may utilize CLIN 0002 for and not limited to, man-hours generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. AGR does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 AGR man-hours, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with ODC, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders AGR pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the AGR and will permit the ACO to take any of the three (3) options set forth in subparagraph “d” below. AGR proposals shall be priced using the FBLR set forth in Section B, CLIN 0002. The rate established in CLIN 0002 will be used in evaluating the contractor's proposal and for negotiating changes. As part of the contractor’s proposal submission for AGR, the following shall be included:

- FBLR

- Proposed Labor Mix/Categories

- Proposed Man Hours

- Total Proposed AGR

c. Considering FBLRs have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of labor categories and associated man-hours to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) as a result of the mix of labor categories and man-hours, the subsequent AGR price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “d”, below.

d. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

e. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the AGR at the contractor's facility. Furthermore, in cases described in subparagraphs “d.1” and “d.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

f. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for AGR (CLIN 0002). Settlement of AGR (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The Contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0006 at contract completion shall be de-obligated.

4. ODC details.

a. The Government may utilize CLIN 0002 for and not limited to, material and equipment generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. ODC does not include work performed pursuant to DFARS 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 ODC, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with AGR, and therefore will be performed concurrently.

b. As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders ODC pursuant to this CLIN, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the ACO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the ODC and will permit the ACO to take any of the three options set forth in subparagraph “e” below. As part of the contractor’s proposal submission for ODCs, the following shall be included:

Material

Equipment -Part number

- Part number

-Order quantity

- Order quantity

-Unit price

- Unit price

-Total price

- Total price

Other Direct Costs not captured above

- Travel

- Per diem (lodging, M&IE daily rates)

- Subcontractor Proposal Breakdown shall include but not be limited to, Material (Part number, Order Quantity, Unit Price, and Total Price), equipment (Part Number, Order Quantity, Unit Price, and Total Price), labor (FBLR, Proposed Labor Mix/Categories, and Proposed Manhours), and ODC (Travel and Per Diem)

- Etc.

The G&A and profit rates proposed shall be the same as the rates provided under CLIN 0002.

c. The contractor shall demonstrate due diligence in the assessment, evaluation, and determination resulting in the proposed utilization of other than local specialized labor resources. Only with ACO approval to proceed will a contractor, technical representative, or subcontractor be reimbursed for reasonable per diem costs (transportation, travel expenses, lodging, meals, and incidental expenses) required in connection with the associated change order. Per diem costs are considered reasonable, allowable, and reimbursable only to the extent that they do not exceed the allowed per diem rate in effect at the time of travel as set forth in the JTR.

d. Considering, G&A and profit rates have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of ODCs proposed to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) the costs of the ODCs are fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the ACO reserves the right to procure these ODCs utilizing alternative means described in subparagraph “e”, below.

e. Upon receipt of the contractor's price proposal for the AGR the contractor and the ACO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the ACO, the ACO reserves the right to:

1) Have the work performed by the Government;

2) Issue a unilateral modification; or

3) Cancel the requirement.

f. The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the ODC at the contractor's facility. Furthermore, in cases described in subparagraphs “e.1” and “e.2” above, the contractor waives any right to claims of interference under the DFARS 252.217-7011 - Access to Vessels.

g. The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for the ODC (CLIN 0002). Settlement of ODC (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the ACO. The contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0006 at contract completion shall be de-obligated.

5. Attachment J-3, Category “B” WIs, provides a WI breakdown of CLIN 0003 through 0006 pricing.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

ACRONYM TABLE

ABIH
American Board of Industrial Hygiene
ABR
Agreement for Boat Repair
ABS
American Bureau of Shipping
ACO
Administrative Contracting Officer
AGR
Additional Government Requirements
AIHA
American Industrial Hygiene Association
ALT
Alternate
AMT
Amount
BLDG
Building
CCO
Contract Change Order
CD
Compact Disc
CDRL
Contract Data Requirements List
CD-ROM
Compact Disc Read-Only Memory
CFM
Contractor Furnished Material
CFP
Contractor Furnished Property
CFR
Condition Found Report
CHENG
Chief Engineer
CFR
Code of Federal Regulations
CIH
Certified Industrial Hygienist
CLIN
Contract Line Item Number

CONUS

CPARS

Contiguous United States

Contractor Performance Assessment Reporting System

DBIDS
Defense Biometric Identification Systems
DFARS
Defense Federal Acquisition Regulation Supplement
DOD
Department of Defense
DOD SAFE
Department of Defense Secure Access File Exchange
DON
Department of the Navy
EMAIL
Electronic Mail
ESRS
Electronic Subcontract Report System
FAPIIS
Federal Awardee Performance and Integrity Information System
FAR
Federal Acquisition Regulation
FBLR
Fully-Burdened Labor Rate
F/CC
Fibers Per Cubic Centimeter
FPCON
Force Protection Condition
FTR
Federal Travel Regulations
G&A
General and Administrative
GFI-TD
Government Furnished Information – Technical Data
GFM
Government Furnished Material
GFP
Government Furnished Property
GPE
Governmentwide Point of Entry
IAW
In Accordance With
ID
Identification
ISO
International Organization for Standardization
JTR
Joint Travel Regulations
KO
Contracting Officer
KWh
Kilowatt Hour
LLTM
Long Lead Time Material
LPTA
Lowest Price Technically Acceptable
M&IE
Meals and Incidental Expenses
MSC
Military Sealift Command
MSCREP
Military Sealift Command Representative
MM
Millimeter
MSRA
Master Ship Repair Agreement
MTA
Mid-Term Availability
N/A
Not Applicable
NCACS
Navy Commercial Access Control System
NDA
Non-Disclosure Agreement
NO
Number
NSP
Not Separately Priced
ODC
Other Direct Costs
PAT
Proficiency in Analytical Testing

PDF

PII

Portable Document Format

Personally Identifiable Information

PM
Program Manager
PPE
Principle Port Engineer
PRIME
Prime Contractor
QA
Quality Assurance
QC
Quality Control
REV
Revision
RFC
Request for Specification Clarification
RFP
Request for Proposal
ROH/DD
Regular Overhaul/Dry-Docking
SECNAV
Secretary of the Navy
SF
Standard Form
SUB
Subcontractor
TPSN
Time Phased Sequencing Network
TWA
Time-Weighted Average
USC
United States Code
USCG
United States Coast Guard
USNS
United States Naval Ship
VR
Voyage Repair
WAWF
Wide Area Workflow
WI
Work Item

SCOPE OF WORK

1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS RICHARD BYRD (T-AKE 4) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.

2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):

a. Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.

b. Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR 52.245-1 and DFARS 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.

c. Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.

d. Using management procedures and systems to identify behind schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.

e. Developing a performance milestone schedule/critical path chart to measure scheduled performance. Deviations from the milestone schedule/critical path chart dates in WI 0013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted IAW the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths. The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 0013.

f. Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.

g. Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.

h. Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.

i. Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.

j. Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.

k. Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.

3. Contract work shall be performed by an eligible contractor as defined below.

a. The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.

b. The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:

1) Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority. Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.

2) Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.

3) Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.

4) Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.

5) Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.

6) Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.

7) Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.

8) Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training. First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.

9) Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records, which indicate type of material, date, and place of disposal.

10) Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:

· Pier, with services in place, accessible to the CLASS size ship for birthing

· Structural Shop

· Machine Shop

· Pipe Shop

· Electrical/Electronic Shop

· Carpentry Shop

· Rigging Equipment

· Dry-dock – when required for docking of vessel in performance of the specification

11) Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.

c. The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.

4. Asbestos removal requirements.

a. During the performance of this contract the contractor and subcontractors may be required to perform work which involves the removal or disturbance of asbestos or asbestos-containing products. This requirement applies to each instance of asbestos removal or disturbance.

b. The contractor shall comply with the precautions required in 29 CFR 1910.1001, 29 CFR 1926.58 and 40 CFR Part 61 and all other applicable Federal, state, and local restrictions. The contractor shall forward a copy of all required notices, licenses and permits to the KO immediately upon issuance or receipt.

c. The latest change to the Federal, state, and local regulations in effect at the time of issuance of the contract shall govern. Compliance with these regulations is mandatory and is necessary to protect the employees of the contractor and Naval personnel from exposure to asbestos fibers in excess of the OSHA Action level airborne concentration (currently 0.1 f/cc of air).

d. During removal or disturbance, the contractor shall control airborne asbestos concentrations outside the removal boundary to less than 0.1 f/cc at all times.

e. After removal or disturbance is complete, the areas within the removal boundary shall not be released for re-occupancy until clearance air sampling demonstrates these spaces have concentrations of asbestos less than 0.1 f/cc.

f. In all respects, the performance of air sampling and analysis shall be performed IAW the OSHA Reference Method (Appendix A of 29 CFR 1910.1001), with the following additional specifications:

1) Aggressive clearance sampling shall be performed on 25 mm cassettes at 2.0 liters per minute for a minimum of four (4) hours.

2) In performing the clearance sampling, the pump shall be placed within the compartment where the removal or disturbance occurred. When this operation is conducted in a multilevel space, at least one pump shall be placed on each level.

3) Air sampling shall be performed by a person competent in sampling procedures and overseen by a CIH by the ABIH.

4) Laboratory analysis of samples shall be performed by a participant in the AIHA PAT Program rated proficient for asbestos and air.

g. Personal sampling shall be conducted using breathing zone air samples which are representative of the 8-hour TWA exposure of each individual. Samples shall be collected and analyzed using the OSHA Reference Method contained in either 29 CFR 1910.1001 (as amended) or 29 CFR 1926.58 (as amended).

h. The contractor agrees to indemnify MSC for any fines assessed by Federal, state, or local agencies, for the contractor's failure to properly follow applicable regulations.

i. The contractor shall insert this instruction in all subcontracts entered into under this contract.

5. Post-award substitution of any major subcontractor should not be effected unless the proposed substitution is submitted to the KO and official approval is obtained. The post-award substitution or insertion of a second-tier subcontractor will be treated in the same manner as the substitution of a major subcontractor and will require specific approval by the KO.

6. Substitution of key personnel.

a. The contractor agrees to assign to this contract those persons identified as key personnel whose resumes were submitted with the proposal and who are necessary to fulfill the requirements of this contract. No substitution of key personnel shall be made except IAW these instructions.

b. All proposed substitutions must be submitted, in writing, at least seven (7) days in advance of the proposed substitutions to the KO and must provide the information required by paragraph “c” below.

c. All requests for substitution must provide a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information as requested by the KO. All proposed substitutes must have qualifications equal to or higher than the qualifications of the person to be replaced. The KO or his authorized representative will evaluate such requests and promptly notify the contractor of the approval or disapproval thereof.

7. It is anticipated the ship will arrive at the contractor’s yard on or about 26 OCT 2020. All work shall be completed in no more than 75 calendar days from the actual start date designated by the Government at the time of contract award.

8. The place of performance for this contract shall be the contractor’s facility.

Table 1: List of WIs:

SECTION 000

General Requirements

NOT SEPERATELY PRICED (NSP) REQUIREMENTS

Intent, Scope, General Conditions and

Definitions 25 Apr 2020

Technincal & Manufacturer’s Representative 25 Apr 2020

Approach, Berth, and Mooring Reuirements 25 Apr 2020

Testing and Quality Assurance 25 Apr 2020

Eelctrical Safety Procedures 25 Apr 2020

Heavy Weather Plan

Cold Weather Plan 25 Apr 2020

CATEGORY “A” WORK ITEMS

Furnish Office for OMT 25 Apr 2020

Furnish General Services 25 Apr 2020

Telephone Services 25 Apr 2020

Project Planning and Production Status 25 Apr 2020

Preparation of Weight and Moment Report 25 Apr 2020

Integrated Logistics C& GFM Support

Requirements

Fire Protection and Ship's Safety Program 25 Apr 2020

Handling Ships Stores 25 Apr 2020

Delivery and Re-Delivery 25 Apr 2020

Shipboard Access and Security 25 Apr 2020

Gas Free Certificates 25 Apr 2020

Clean and Gas Free Tanks, Voids, Cofferdams and Spaces 25 Apr 2020

Dock Trials and Sea Trial 25 Apr 2020

Hazardous Waste Disposal 25 Apr 2020

Physical Security at Private Contractor's

Facility 25 Apr 2020

DAILY COVID-19 PREVENTION AND CONTROL

SERVICES

CATEGORY “B” WORK ITEMS

Physical Security at Private Contractor's

Facility

VESSEL FINAL CLEANING REV A

25 Apr 2020

Continutation of Service 25 Apr 2020

SECTION 100

Hull Structure

CATEGORY “A” WORK ITEMS

Flight Deck and Hanger Deck Nonskid Renewal 25 Apr 2020

SECTION 200 Propulsion Machinery & Systems

CATEGORY “A” WORK ITEMS

TAKE CSI PROPULSION MOTOR AND COOLER CLEANING, INSPECTION AND MAINTENANCE (2.5 YR) (SCSI)

202 TAKE MAIN ENGINE FLEXIBLE CONNECTION REPLACEMENT

(10YR) (CSI)

TAKE CSI MDE CONTROL SAFETY INSPECTION AND TEST (1 YR) (SCSI)

25 Apr 2020

TAKE CSI AUTOMATION AND PROPULSION CONTROL INSPECTION AND TEST (1 YR) (SCSI)

25 Apr 2020

TAKE CSI VULKAN COUPLING INSPECTIONS

(1 YR)(SCSI)

25 Apr 2020

212A

TAKE CSI MAIN ENGINE 8 CYLINDER SERVICE (42K HRS)

(SCSI)

212B

TAKE CSI MAIN ENGINE 9 CYLINDER SERVICE (42K HRS)

MDE Engine SACO UPS Power Supply Repair 25 Apr 2020

TAKE CCSI WOODWARD GOVERNORS (24K HRS)

25 Apr 2020

Engine Lube Oil Isolation Valves

Replacement

SECTION 300 Electrical

CATEGORY “A” WORK ITEMS

301A Cleaning Main Generators and Propulsion

Control System 25 Apr 2020

TAKE CSI HIGH VOLTAGE, SHIP'S SERVICE, AND EMERGENCY

SWITCHBOARD INSPECTION AND CLEANING (25 YR)

TAKE CSI PLC SURVEY (2 YR)

25 Apr 2020

TAKE CSI SERVICE HARMONIC FILTERS (25 YR)

Consilium CS3000 Control Panel

Upgrade (T-ALT 469)

TAKE CCSI THERMOGRAPHIC SURVEY (1 YR)

25 Apr 2020

SECTION 400 Communication and Navigation

CATEGORY “A” WORK ITEMS

TAKE CSI ANTENNA PREVENTATIVE MAINTENANCE

(5 YR)

PA/GA and Telephone System UPS (T-ALT 323) 25 Apr 2020

TAKE CSI WIND SPEED MEASURING AND INDICATION SYSTEM CERTIFICATION (3 YR)

25 Apr 2020

Hydra Radio Upgrade (T-ALT 472) 25 Apr 2020

TVDTS UPGRADE (TALT 452)

25 Apr 2020

TAKE CCSI ANNUAL RADAR SERVICE

25 Apr 2020

TAKE CCSI ANNUAL GYRO SYSTEM

25 Apr 2020

TAKE CCSI ANNUAL VDR RECERTIFICATION

25 Apr 2020

TAKE CCSI ANNUAL RADIO COMMUNICATION EQUIPMENT RECERTIFICATION (2)

25 Apr 2020

TAKE CCSI EPIRB SERVICE (5 YR)

25 Apr 2020

TAKE CCSI ANNUAL INSPECTION OF ALARMS

SECTION 500

Auxiliary Machinery Systems

CATEGORY “A” WORK ITEMS

Anchor Windlass Repair 25 Apr 2020

Cargo Crane Survey 25 Apr 2020

TAKE CSI EMERGENCY DIESEL GENERATOR -ANNUAL TESTING AND INSPECTION (1 YR) (SCSI)

25 Apr 2020

Replace Firemain Loop Valves 25 Apr 2020

TAKE CSI SEWAGE SYSTEM PIPING CLEANING

(2.5 YR)

517A

TAKE CSI LTFW COOLER CLEANING AND INSPECTION

(25 YR)

518A

TAKE CSI HTFW COOLER CLEANING AND INSPECTION

(2.5 YR)

VCHT pipe replacement with CUNI (T-ALT 518) 25 Apr 2020

Replace exterior weather deck drain piping

(TALT 520)