0505_A_Brine_System_Flush+Replace_Valves_REV1.doc

DOC document 29 KB Posted

Attached to
USNS CHARLES DREW MTA Federal contract opportunity
Solicitation number
N3220519R6007
Issued by
Department of the Navy Military Sealift Command

About this file

Revised WI 0505

View the file

Other files for this federal contract opportunity

Other files attached to USNS CHARLES DREW MTA, newest first.
File Type Posted
QUESTION_to_Extend_MTA_rev1.docx DOCX document
QUESTION_to_Extend_MTA.docx DOCX document
QUESTION_2.docx DOCX document
Simsite_Installation_Procedure.pdf PDF
0018_A_DELIVERY_AND_REDELIVERY,_REV_MAY_16_REV1.docx DOCX document
0514_A_SW_PIPE_AND_VALVE_REPLACEMENTS_REV1.doc DOC document
0512_A__OVERHAUL_LTFW_3_WAY_VALVES_Rev1.doc DOC document
7488756_F_Secondary_Cargo_Coolant_Flush.pdf PDF
J_-_2_CAT_A_Items_REV_1.xlsx XLSX spreadsheet
RFC_Questions_&_Answers.docx DOCX document
7488716_D.pdf PDF
0514_A_SW_PIPE_AND_VALVE_REPLACEMENTS.doc DOC document
J_Documents.zip ZIP file
J_&_A_USNS_DREW-Redacted.pdf PDF
CDRL'S.zip ZIP file
N3220519R6007_USNS_DREW_MTA.docx DOCX document
J_-_14_Blank.docx DOCX document
SYNOPSIS_N32205-19-R-6007.docx DOCX document
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS CHARLES DREW

(T-AKE 10)

PROPULSION MACHINERY

N32205-19-r-6007

21 December 2018

ITEM NO. 505`

CATEGORY “A”

MSFSC/N43C/SAlvey

CARGO REFERIGERATION SYSTEM FLUSH

1.0 ABSTRACT

1.1 This item describes the requirement to flush the Cargo Refrigeration System (Brine) and replace the brine system valves.

2.0 REFERENCES/ENCLOSURES

2.1 References:

2.1.1 NAVSEA Dwg No. 516-7488756, Cargo Refrigeration Secondary Coolant Circ System Diagram.

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location/Quantity:

3.1.1 The Cargo Refrigeration System (Brine) pumps are located in the AMR, frame 65. Brine capacity is approximately 3000 gallons.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 LUG Style Valve Quantity = (15), PN: ACRIS IL-31KF/S9, 6" Butterfly Valve Lug 150# DI FLGD; ACRIS A.

5.0 NOTES

5.1 Any and all hazardous waste must be disposed of following all local, state, and federal regulations.

6.0 QUALITY ASSURANCE REQUIREMENTS

6.1 All work shall be performed to the satisfaction of the Master, Chief Engineer, and the Port Engineer.

7.0 STATEMENT OF WORK REQUIRED

7.1 Fill the Brine System with potable water.

7.1.1 Using references 2.1.1 for guidance, the contractor shall accomplish a system flush of all piping surfaces. The system flush shall be accomplished using potable water to fill the system and circulating the water using Ships Pumps to flush through the system piping. Ships Force shall determine flush time and if additional flush is necessary by sampling flush water.

7.1.2 Unless otherwise identified by Ships Force, fill and drain location shall be the AMR at the Brine Pumps. Contractor is responsible for all connections to/from the fill/drain connections, hoses, tanks, and pumps for removal of flushing water.

7.1.3 Prior to flushing the contractor shall develop and submit a Process Control Procedure (PCP) that will state in detail the contractor’s procedure for accomplishing the required system flush, for approval by the MSCREP.

7.1.4 Contractor shall include the cost of removal and disposal of all hazardous waste products and solutions. All hazardous waste products shall be removed and disposed of in accordance with the guidelines set forth in the work item 023 within this work package.

7.1.5 Contractor shall be responsible for replacing any system components damaged by the accomplishment of the system flush.

7.2 Replace Total number of 15 valves, As an estimate, in the brine system at the discretion of the Ship Force Chief Engineer.

7.3 Inspection/Testing:

7.3.1 All work shall be completed to the satisfaction of the MSCREP and Chief Engineer.

8.0 GENERAL REQUIREMENTS: NONE

505 - 2