Specification_Clarifications_response_1-5.docx
DOCX document 17 KB Posted
- Solicitation number
- N32205-15-R-5001
About this file
This document is a detailed response for the specification clarifications 1-5.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JA_for_USNS_COMFORT_MTA_Growth_1.doc | DOC document | |
| 0003.pdf | ||
| Specification_Clarifications_Response_6-15.docx | DOCX document | |
| 0002.pdf | ||
| Attachment_4 _Government_Furnished_Property.pdf | ||
| 0001.pdf | ||
| N32205-15-R-5001.doc | DOC document | |
| J A _N104-15-R-5001_Redacted.pdf | ||
| Attachments_2-14.zip | ZIP file | |
| Exhibits_A-W.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR SPECIFICATION CLARIFICATION #1
SPECIFICATION ITEM NO.: Solicitation No. N32205-15-R-5001
PARAGRAPH / SECTION NO:____________________
TITLE: Proposal Due Date
QUESTION:
The due date for proposal submission on the SF 33 is 30 October 2015, yet the solicitation was only posted on FEDBIZOPPS on 6 October 2015. We would like to request a full 30 days to prepare our proposal.
ANSWER:
Amendment 0001 extends the solicitation close date from 30 Oct 2015 to 6 Nov 2015.
REQUEST FOR SPECIFICATION CLARIFICATION #2
SPECIFICATION ITEM NO.: _703_________________
PARAGRAPH / SECTION NO:_2.0 and 4.0__________
TITLE: _MTF Berthing Space Head Overhaul_________
QUESTION: 1.) Paragraph 2.0 does not include drawings for space equipment configuration plans, elevation arrangement specifics, piping, electrical, or material list(s). Please provide applicable references/guidance.
2.) Paragraph 4.0 states there is no GFM. Please confirm.
1) The contractor is encouraged to shipcheck the item as required for further detail with regards to this item. The following additional references are provided for the convenience of the contractor 5981347 Shower Area Joiner outfitting, 5980552 for lighting, 5980735 for plumbing.
2) Confirmed, no GFM will be provided for this work item.
REQUEST FOR SPECIFICATION CLARIFICATION #3
SPECIFICATION ITEM NO.: _701_________________
PARAGRAPH / SECTION NO:_7.6.6_______________
TITLE: _Refurbish MTF Spaces ___________________
QUESTION: Paragraph states to relocate the 3 items; What specific bulkhead, and distance from deck or overhead that these equipments will be relocated to?
Exact locations to be determined with the MSCREP once furniture has been installed.
REQUEST FOR SPECIFICATION CLARIFICATION #4
SPECIFICATION ITEM NO.: 701__________________
PARAGRAPH / SECTION NO:__7.5.3______________
TITLE: _Refurbish MTF Spaces ____________________
QUESTION: 1.) For estimating purposes; Please provide existing overhead lighting fixture(s) manufacture(s)/style(s)/brands and their existing lumen output.
2.) For estimating purposes; Please state the symbol #/ style/ type of new LED fixtures that are recommended to be installed.
1) The contractor is encouraged to ship check this item to determine installed quantities, location and types and validate technical information provided. The existing fixtures are a mixture of Pauluhn fixtures found in Drawings 5980558, 5980549, 5980560, 5980563 with 20W and 40W fluorescent bulb fixtures with varying numbers of bulbs. Assume the lumen output of a 20W bulb is 1000 lumens and 40W bulb is 2000 lumens. For example; For a 60W fixture (with 3 20W bulbs), assume a lumen output of 3000 lumens. The drawings provide details on wattage and number of bulbs in each fixture as well as the emergency lighting capabilities where applicable.
2) Examples of new LED fixtures are from Phoenix (LFSB and HDL-LED), Pauluhn (DLL Series) and LC Doane (300LED and 303LED) and other commercially available sources. Quantity of fixtures will be determined by fixture lumen output for the space it serves. The new fixture must meet all required statutory and regulatory requirements.
REQUEST FOR SPECIFICATION CLARIFICATION #5
SPECIFICATION ITEM NO.: __701___________________
PARAGRAPH / SECTION NO:_4.0___________________
TITLE: __Refurbish MTF Spaces _____________________
QUESTION: Paragrph 4.0 states that there is no GFM associated with work item. Please confirm.
GFM will be provided for this work item. GFM section has been updated to reflect furniture provided by MSC and installed by the contractor in sections 7.6 and below.