RFP-RFQ_Q_AND_A_-_6.docx
DOCX document 28 KB Posted
- Attached to
- USNS FALL RIVER PSA/DD Federal contract opportunity
- Solicitation number
- N32205-15-R-4000
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N32205-15-R-4000_0006.doc | DOC document | |
| N32205-15-R-4000_Att_1.docx | DOCX document | |
| J_-_2_Category_A_Items.xls | XLS spreadsheet | |
| N32205-15-R-4000_0005.doc | DOC document | |
| J_-_10_Interport_Differential.doc | DOC document | |
| RFP-RFQ_Q_AND_A_-_7.docx | DOCX document | |
| N32205-15-R-4000_0004.doc | DOC document | |
| N32205-15-R-4000_0003.doc | DOC document | |
| RFP-RFQ_Q_AND_A_-_5.docx | DOCX document | |
| J_-_2_Category_A_Items.xls | XLS spreadsheet | |
| N32205-15-R-4000_0002.doc | DOC document | |
| RFP-RFQ_Q_AND_A_-_1.docx | DOCX document | |
| RFP-RFQ_Q_AND_A_-_4.docx | DOCX document | |
| J_-_2_Category_A_Items.xls | XLS spreadsheet | |
| N32205-15-R-4000_0002.doc | DOC document | |
| RFP-RFQ_Q_AND_A_-_3.docx | DOCX document | |
| RFP-RFQ_Q_AND_A_-_2.docx | DOCX document | |
| N32205-15-R-4000_0001.doc | DOC document | |
| N32205-15-R-4000.doc | DOC document | |
| SWI_CDRLS.zip | ZIP file | |
| J_Attachments.zip | ZIP file | |
| JHSV_SWI_CDRLs.zip | ZIP file | |
| Fall_River_J A.PDF |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N32205-15-R-4000
QUESTIONS AND ANSWERS - 6
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
Question 1: WI 0905 Hull Markings to support UWILD Cert, Paragraph No. 7 Is this work item to install new UWILD markings or to paint existing UWILD markings?
Answer:
Work item is install new markings where none currently exists.
Question 2: Para 7.1.4 requires not painting marking above the waterline. What do you want the contractor to accomplish above the waterline?
Contractor shall install in markings IAW reference drawings.
Question 3: What is the waterline for this work item, the Lightship Waterline or the DWL?
Waterline reference is the DWL. Any markings beginning below this water line or centered on the water line shall extend above the water line in order to complete the marking IAW the referenced drawing.
Question 4: Para 7.3 What are the cover plates?
Work item and reference revised to remove confusion.