RFC_0015-0016.doc

DOC document 41 KB Posted

Attached to
USNS CHARLES DREW T-AKE 10 ROH/DD
Solicitation number
N32205-15-R-3002
Issued by

View the file

Other files

File Type Posted
J A_mod_4_Redacted.pdf PDF
J A_REDACTED.pdf PDF
DD254_USNS_CHARLES_DREW.pdf PDF
ADDING_ATTACHMENT_J-15_DD254.docx DOCX document
RFC_0017-0021.doc DOC document
CHARLES_DREW_ROH-DD_JA_3_9_15_MOD_1.docx DOCX document
Amendment_0002.docx DOCX document
RFC_0007-0014.doc DOC document
RFC_0006.doc DOC document
RFC_0004.doc DOC document
RFC_J_8_Request_for_Spec_.doc DOC document
RFC__002_-_Extension_request_adr_20Feb2015.doc DOC document
RFC_0001_J_-_13_PAST_PERFORMANCE_QUESTIONNAIRE_FBO.doc DOC document
J_-_13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
N32205-15-R-3002_REV_1.docx DOCX document
J_-_8_Request_for_Spec_Clarification.doc DOC document
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
J_-_9_Disclosure_of_Lobbying_Activities_SF-LLL.doc DOC document
DREW_J A_1_REDACTED.PDF PDF
J_-_6_WI_015_CDRL.pdf PDF
J_-_12_Past_Performance_Data.doc DOC document
J_-_2_Category_A_Items.xls XLS spreadsheet
J_-_4_GFP.xlsx XLSX spreadsheet
J_-_3_Category_B_Items.xlsx XLSX spreadsheet
J_-_10_Interport_Differential_West_Coast.doc DOC document
J_-_11_Dry_Dock_Evaluation_Form.docx DOCX document
N32205-15-R-3002_FINAL.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR SPECIFICATION CLARIFICATION 0015

NAME OF CONTRACTOR:

SPECIFICATION ITEM NO.: 0204

PARAGRAPH / SECTION NO: 3.0 & 4.0

TITLE:

Analog Shaft RPM and Rudder Monitoring system

QUESTION:

It is unclear from review of the work item requirements and J-4 GFM list what is government furnished and what is contractor furnished. Also, materials for this work item on the J-4 are listed as item 0101.

Please clarify what materials are contractor furnished.

ANSWER:

The PPE has ordered material as GFM and the J-4 just listed the Work item incorrectly. The GFM report should reflect this material under Work Item 204. Paragraph 3.3.1 should be considered to be provided by the Government vice the Contractor.

REQUEST FOR SPECIFICATION CLARIFICATION 0016

SPECIFICATION ITEM NO.: 0525

PARAGRAPH / SECTION NO: 3 & 4

TITLE:

Chloropac Installation

QUESTION:

The materials listed in reference 2.1.1 are all CFM, but there are additional materials listed on the J-4 as GFM.

Please clarify.

ANSWER:

Contractor shall provide all material as CFM from reference 2.1.1. If the same material is listed on the GFM J-4 then the contractor should not provide it.

ATTACHMENT J – 8