This is a Request for Proposals (RFP) for restroom door replacement at the Naval Undersea Warfare Center (NUWC) Division in Keyport, Washington. The solicitation (N0025325Q0009) requires the replacement of two existing interior doors and frames in Building 1, specifically for rooms 131 and 132, with new 18-gauge steel doors and 12-gauge welded frames. The contractor will be responsible for removing existing doors and hardware, installing new left and right swing doors, repairing any drywall damage, and painting the doors, frames, and affected wall sections to match existing colors.

The solicitation is a 100% small business set-aside with a government estimate between $15,000 and $50,000. Key requirements include coordinating with the Contracting Officer's Representative, completing work within 60 calendar days, performing a pre-construction meeting, and submitting required documentation such as product submittals, O&M manuals, and warranties. The target award date is June 10, 2025, with offers due by May 22, 2025. Offerors must be registered in the System for Award Management (SAM) and comply with environmental, safety, and quality control standards specified in the comprehensive statement of work.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Restroom Doors, newest first.
File Type Posted
C24_N0025325Q00090001.pdf PDF
C26_ SOW_REV1.pdf PDF
C12_Att_04_Kpt_EV_Guide_for_Contractors_Jan_2025.pdf PDF
C12_Att_03_Safety_Requirements_for_Contractors_and_Subcontractors.pdf PDF
C12_Att_05_OPSEC_Guide_for_Defense_Contractors.pdf PDF
C12_Att_11_OSHA_Calculating_Injury_and_Illness_Incident_Rate.pdf PDF
C11d_Att_07_Past_Performance_References.docx DOCX document
C12_Att_06_Schedule_of_Values.xlsx XLSX spreadsheet
C12_Att_01_Material_Equipment_In_Place_List.xlsx XLSX spreadsheet
C11b_Att_02_WD_WA20250109_03072025.pdf PDF
C12_Att_09_PPI_Form.docx DOCX document
C12_Att_10_Safety_Data_Sheet.docx DOCX document
C12_Att_08_Bid_Form.xlsx XLSX spreadsheet
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Title: Restroom Door Repair

The point of contact for this action is James Wasson at james.k.w asson.civ@us.navy.mil and Kimberly Hammit at kimberly.s.hammit.civ@us.navy.mil.

JAMES K WASSON (360) 396-2935

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

23-Apr-2025

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________60 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________22 May 2025 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

NAVAL UNDERSEA WARFARE CENTER

ATTN: JAMES WASSON

JAMES.K.WASSON.CIV@US.NAVY.MIL

610 DOWELL STREET, BLDG 206

KEYPORT WA 98345

N00253

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: 360-396-2935 TEL: FAX:

N0025325Q0009 104

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

N0025325Q0009

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Project

RESTROOM DOOR REPAIRS

FFP

Provide restroom door repairs in accordance with the statement of work. Wage Determination WA20250109 applies to this CLIN.

FOB: Destination

PSC CD: Z2AA

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

I. Statement of Work:

Naval Undersea Warfare Center (NUWC) Division, Keyport has a requirement for the replacement of two interior doors in Bldg. 1.

The Contractor shall provide labor, materials, and equipment, as required, to accomplish the following work in accordance with the statements herein:

Replace two existing restroom doors and frame with two new steel doors and frames on rooms 131 and 132.

All work must be coordinated through the Contracting Officer’s Representative (COR). A preconstruction meeting will take place two weeks prior to the start of construction, the COR, Customer, Contractor and all required subs will be in attendance at a minimum.

II. References:

A. Naval Base Kitsap (NBK) Instruction 11300.1B (July 2021) Utilities and Facilities Outages (available upon request)

B. EM-385-1-1 Safety and Heath Requirements Manual (March 15, 2024), available at https://www.usace.army.mil/Missions/Safety-and-Occupational-Health/Safety-and-Health- Requirements-Manual/.

C. NAVFAC P307 Weight Handling Program Management Manual, June 2016, (available upon request)

D. Naval base Kitsap (NBK) Instruction 11210.1A Road Closure/Disruption Coordination, August 21, 2014 (available upon request)

E. Unified Facility Criteria (UFC) 1-200-01 DoD Building Code – General Requirements-With Change 3 Revision Date February 26, 2024, available at https://www.wbdg.org/dod/ufc

III. Submittals:

1. Electronic copies of Product/Material Submittals & Construction/Project Schedule shall be submitted to the COR for acceptance. See Deliverables and Performance Table under General requirements for a list of required submittals. Allow a minimum of ten (10) working days for Government review of all submittals.

2. Proposed equipment specifications shall be submitted to the COR for review and written approval prior to commitment to purchase.

3. Required outages shall adhere to Ref (A) and routed through the COR for information on scheduling. The COR is not responsible for outage coordination, obtaining signatures, or vetting outage requests, including Hot Work permits or Fire Alarm outages. Contractor pricing shall include all Contractor support and associated costs in their proposal.

4. All submittals requiring NBK Bangor and NUWC Keyport Environmental signature shall be routed through the COR for review. The COR shall be copied on all correspondence sent to Environmental. No work shall begin until all required Environmental forms have been accepted by Environmental.

5. The contractor may submit an invoice no more frequently than once a month for progress made on the project. Therefore, the Schedule of Values (attachment 06) submitted with each invoice shall have a section for each area of the project listed separately on the invoice. The Schedule of Values will be submitted to the Government COR for acceptance prior to final submission of the invoice.

Failure to submit an invoice, which lists each area separately, will result in rejection of the invoice until properly submitted according to these instructions. Questions may be directed to the Contracting Officer.

6. All contractors working this project are subject to labor interviews and shall provide the information requested per “Labor Standards Interview” Standard Form 1445. The COR/Contracting Officer will conduct these interviews randomly during the performance of the work.

IV. Products:

1. All materials and products provided by the Contractor in the performance of this contract shall be new and manufactured and assembled in the United States of America and shall meet or exceed the manufacturer’s specifications.

2. The materials and/or products listed here are a description of the minimum specifications or characteristics of the noted items, and not intended to be an all-inclusive list of materials required for the project.

A. Steel doors with frame

18-gauge door and 12 gauge welded frame.

B. Latex paint

Low volatile organic compounds (VOC) interior latex paint matching the existing color and sheen.

V. Quality Control:

1. The Contractor shall comply with all applicable Washington State licensing requirements, from the time of proposal submission through the entire performance period. All components and services are to be installed per manufacturer’s specifications by trained technicians with a minimum of five (5) years’ recent experience or have journeyman certification, who specialize in the type of work indicated herein.

2. The Contractor shall perform all work according to accepted standards, safety procedures, and applicable laws, regulations, codes, and standards to include the Unified Facilities Guide Specifications (UFGS), Unified Facilities Criteria (UFC), International Building Code (IBC), International Mechanical Code (IMC), International Plumbing Code (IPC), National Electrical Code (NEC), National Electrical Safety Council (NESC), and National Fire Protection Association

(NFPA).

3. The Contractor shall be responsible for all quality control, inspections, and tests required in the completion of this project. The Contractor shall obtain all approvals except those required for field installations, field applications, and post-field tests, prior to delivery of materials and equipment to the project site unless otherwise specified. The Contractor shall arrange for tests and inspections where and when required as defined in the approved Quality Control Plan.

4. Contractor shall verify all dimensions of all equipment to ensure that all access clearances can be met.

5. The contractor is responsible for providing a complete and useable system including providing manufactures manuals, specifications, any field tests, wiring diagrams and as- built prints (red line drawings) as necessary.

VI. Execution: (general)

1. All accepted project packages shall be kept on the jobsite and all employees shall be aware of its contents. Current, up-to-date Site-Specific Activity Hazard Analysis (AHA) forms shall be available for review, if applicable. The Contractor shall inform all employees how to contact Base Emergency Services in the event of an emergency.

2. Scheduling: The Contractor shall schedule work to cause the least amount of interference with station operations. The government will attempt to provide the Contractor 24 hours’ notice prior to work interruptions due to unscheduled/emergent operational requirements.

3. Delivery, handling, storage, and protection of products to, and at the project site: Inspect for damages, store in a clean dry place, and protect from construction traffic. Handle carefully to avoid damage to components, enclosures, and finish.

4. Disposal of any material resulting from demolition shall be per applicable Environmental regulations, including all documentation Waste Designation Tables, WGRs and documented in accordance with Attachment 04.

5. Contractors performing a Weight Handling Evolution shall adhere to Ref (C) and Attachment 03.

6. Contractors utilizing lifting and handling equipment shall adhere to Ref (C) and Attachment 03.

7. The COR shall be contacted to coordinate access for job walks and scheduling of work.

VII. NUWC Bldg. 1 General

1. Safety and Security Brief

A. A Safety and Security brief is required for the contractor’s complete crew before any work can begin. The brief is conducted at the Pre-Construction meeting and periodically throughout the execution of the Contract.

B. Compliance with the security directions of NBK Security Force Personnel is mandatory.

C. Performance under this contract requires the contractor to adhere to Attachment 05, Operations Security (OPSEC) requirements, which are attached to this solicitation and will be incorporated into the subsequent award and are also available online at:

http://www.navsea.navy.mil/Home/Warfare-Centers/NUWC-Keyport/Resources;

search for OPSEC Guide for Defense Contractors.

2. Smoking

A. Smoking is only permitted in designated smoking areas.

3. Delays

A. Contractor operations are subject to reasonable delays, suspensions, and/or restrictions because of emergencies, alerts, drills, equipment movements and other such activities.

4. Flame Producing Devices

A. Matches, lighters, and other spark producing devices are not allowed without a Hot Work permit.

5. Portable Electronic Device(s) (PED)

A. PED is defined as a portable electronic device having the capability to store, record, and/or transmit text, images/video, or audio data. Examples of PED include, but are not limited to pagers, laptops, cellular telephones, radios, compact disc and cassette players/recorders, portable digital assistants, audio devices, watches with input capability, reminder recorders, and mobile devices.

B. PEDs are not allowed inside of NUWC Keyport Buildings. PED use will be clarified and discussed at the site walk and pre-construction meeting

C. The COR or Building POC will provide location of phone for emergency use.

6. Photography

A. Photography by the Contractor is prohibited. Construction progress photos, and all other necessary photo documentation, will be provided by authorized Government personnel only.

7. Lock out Tag Out

A. Lock Out/Tag Out: Contractors must notify the COR five (5) working days before anything can be locked out. The notification should include what is being locked out, the tag number, the person on the tag and phone number shall also be provided to the COR within 24 hours of removal.

8. Vehicle Access

A. Only government and authorized company vehicles will be allowed access to NBK. Vehicle registration must have the company's name as the owner. If the vehicle is leased or rented the lease or rental agreement must be in the company's name.

B. All vehicles will be subject to inspection and search prior to entering and within Naval Base Kitsap. Avoid transporting sealed containers into Naval Base Kitsap. If such containers must be introduced, prior coordination with the COR is required.

9. Parking

A. Parking at NUWC Keyport sites is generally unreserved unless otherwise explicitly marked with specific signage or common markings such as (but not limited to) handicap markings, “government vehicle”, and red & yellow marked zones. Numeric marked spaces are no longer indicators of reserved parking. However, this means parking availability is generally in order of arrival and conventional parking stalls cannot necessarily be guaranteed to the contractor.

1. For small projects with very limited number of work vehicles and little to no outdoor laydown, company-marked contractor vehicles may generally utilize yellow-marked “loading” zones for parking, so long as this does not block building doorways nor marked personnel egress paths, nor intrudes into vehicle traffic lanes, nor causes other safety problems.

VIII. Deliverables:

1. The Contractor is responsible for providing a complete and useable system.

2. The Contractor shall prepare and submit Operations and Maintenance (O&M) Manuals to the

COR.

3. Submit all manufacturers' signed warranties to Contracting Officer prior to final commissioning and acceptance.

4. Before final payment will be approved, the Contractor shall provide all necessary training required on any and all new systems.

5. This project will not be accepted as complete until all project documentation and punch list items have been submitted to, and approved by the COR in their entirety and the Customer provides their concurrence electronically to the COR that the project is complete.

IX. Work Description:

1. Coordinate with COR prior to commencement of work.

2. Remove the existing restroom doors and frames on rooms 131 & 132. Install a new left swing steel door on room 132 (men’s restroom) and a right swing steel door on room 131 (women’s restroom) Remove all existing door hardware, closing devices and reinstall on new doors.

3. Repair any drywall damaged during door replacement. The finish shall match the surrounding area.

4. Paint doors and frames to match existing color and finish. Paint interior and exterior walls of men’s and women’s restrooms corner to corner on disturbed wall section to match existing color and finish.

5. All field verification will be the contractor’s responsibility. Including but not limited load requirements and sizing.

6. After becoming familiar with all details of the work, perform Verification of Dimensions in the field, and advise the Contracting Officer of any discrepancy before performing any work.

7. Upon completion of the work, the Contractor shall inform the COR, and customer to demonstrate operational tests.

X. Title to Materials:

1. All excess and/or discarded materials shall become property of the Contractor and shall be removed from government property, unless specifically noted.

2. Recycling is preferred and recommended. A WGR or Waste Identification Tracking Numbers (WITS) is required for disposal and recycling is required for metal.

XI. Material/Equipment In-Place List:

1. The Contractor shall provide a list of significant equipment and materials removed, replaced, or installed under this contract with the required information below, including the warranty expiration date.

A. Examples of equipment and materials to report.

Materials: Roofing products, floor coverings, windows, doors, lighting, and all material with a manufacturer’s warranty.

Equipment: Mechanical (pumps, backflow preventers, HVAC components, pressurized piping systems, panel boxes, emergency lights, street lighting, etc.); mechanized doors, elevators, conveying systems, all equipment with an O&M manual or manufacturer’s warranty.

2. Required format and information: The Contractor shall provide material and equipment data in the attached format (Attachment 01 Material/Equipment In-Place List). All of the requested data shall be provided prior to final inspection or final acceptance.

XII. Cleanup:

1. Contractor shall not dispose of debris/rubble on NBK property or in NBK dumpsters.

XIII. Safety

1. The contractor is responsible for the actions of their personnel on site and any person on the project site has the authority to stop work if an unsafe condition exists.

2. Read and sign Attachment 03 NAVSEA Safety Requirements for Contractors and Subcontractors.

3. Ensure all workers are wearing the proper PPE for the assigned task.

4. The Contractor is responsible for inspecting their worksite for any hazards at all times, no exceptions. If an unsafe condition exists, work to correct or mitigate the hazard and contact the COR to assist in determining how to proceed, if needed.

XIV. Environmental:

1. The Contractor shall comply with all federal, state, and local laws, codes, regulations, acts, ordinances, and rules for Environmental Protection and Hazardous Waste Management / Disposal, including facility instructions and facility permits for work taking place on government properties.

Take actions to mitigate creation of hazardous waste by recycling and other available methods.

2. The Contractor shall perform all work according to accepted Industry Standards, Safety and Environmental Procedures, and regulations, including Attachment 03 NAVSEA Safety Requirements for Contractors and Subcontractors and the latest revision of Occupational Safety and Health Administration (OSHA) regulations.

3. Prior to the start of work on site, the contractor shall provide an Environmental Protection Plan (EPP) detailing specific methods of handling encountered wastes and refuse, project storm water management and control, and spill response procedures.

4. Facility Environmental Permits:

A. Equipment and work performed under this contract shall be in compliance with federal, state, and local environmental regulations and existing facility permits.

5. Contractor Employee Required Environmental Training

A. Training must be completed and documented prior to commencing work under this contract at the government facilities. Contact the BEO for instructions on accessing required training.

NBK EMS Awareness/General Environmental Awareness Training (0.5 hr).

Available online or in person from the BEO. Required for all personnel performing work NBK property.

NAVSEA Keyport Manager / Alternate Training Read and sign NUWC Keyport Guide to Environmental Compliance

Requirements for Contractors and Subcontractors.

6. The Contractor shall safely store and manage Hazardous Materials (HM) used in the performance of this contract in accordance with applicable federal, state, and local regulations. Submit Safety Data Sheets (SDS’s) and expected quantities of HM to be used and stored in performance of the project and receive approval from the Government prior to HM use in conjunction with this contract, and prior to bringing HM onto government property for the purposes of this contract.

For approval to use any hazardous material, submit material SDS’s and Contractor Hazardous Material Inventory (CHMI) form detailing expected material use and storage information for government review and approval. Submit CHMI form prior to performing onsite work and update monthly while actively working on government property.

7. Products prohibited by the Government, which will not be approved for use, include but are not limited to: leads, chromium, mercury, phenols, trichloroethylene, halons, PCBs, asbestos, silica sand (for use as blasting agent), Class I ODS, radioactive materials or instruments capable of producing ionizing radiation, and chemicals listed in 40 CFR 355.50, Appendix A. This prohibition prevails over any other provision, specification, drawings, or referenced documents.

The Contracting Officer may consider exceptions to the use of any of the above excluded materials upon written request by the Contractor, and with BEO approval.

8. Hazardous (Dangerous) Waste Management: Naval Base Kitsap Keyport is designated as a Large Quantity Generator in accordance with WAC 173-303, and waste generated onsite must be managed under the facility Hazardous Waste management program. Hazardous (dangerous) waste generated at the facility must be shipped and disposed of under the government’s site EPA Waste ID#’s. The contractor is required to meet the regulatory requirements for large quantity generators for any work conducted within the boundaries of the Naval Base Kitsap Keyport and shall comply with provisions of federal, state, and local regulatory requirements applicable to this generator status regarding training and storage, handling, and disposal of generated wastes.

9. The government shall be responsible for disposal costs for Hazardous (dangerous) waste generated during work performed on government property. The Contractor shall reimburse the Government for HW disposal costs associated with a) spent cleaning supplies, such as contaminated rags, cleaning absorbents, solvents from cleaning machines, and degreasers; and, b) HW from Contractor spills and the spent materials and supplies used to clean the spill. All unused or partially used regulated material ordered by the contractor is the property of the contractor and shall not be left at the facility or turned in to the government for disposal as Hazardous Waste.

10. Hazardous (Dangerous) Waste Profiling (Determination): The Government shall determine whether waste generated during the performance of the contract at government facilities is Hazardous (Dangerous) waste.

A. Naval Base Kitsap (NBK) Keyport: Information required for the control and disposal of

Hazardous Waste at NBK Keyport is included in the "Hazardous Waste Site Manager/Alternate (Waste Generator)" training module and the NAVSEA Keyport Contractor's Guide to Environmental Compliance. Complete Waste Generation Record forms for waste determination for each waste stream expected during work performed under the contract. Contractor personnel submitting Waste Generation Record (WGR) forms must have received facility Hazardous Waste Site Manager/Alternate (Waste Generator) Training and Certification for NBK Keyport.

11. Laboratory Analysis: When, at the sole discretion of the Government, laboratory analytical information is necessary to designate waste, the contractor shall provide sampling and analysis services in accordance with WAC-173-303 and EPA SW-846. Sampling personnel shall be trained and proficient in environmental sampling and laboratory must meet applicable accreditation for the analysis conducted. Submit sampling personnel qualifications and laboratory accreditation as part of the Environmental Protection Plan (EPP)

12. Submit analytical results and reports to the Government as part of the Waste Determination Documentation. If the government determines that a waste is not a hazardous (dangerous) waste, the contractor may dispose of the waste in accordance with federal, state, and local regulations and per guidance in Waste Determination Documentation form.

13. Discharge of any industrial wastewater, including paint wash water, to the sanitary sewer or storm water system is prohibited without prior written acceptance from the cognizant Government Environmental Division.

14. Hazardous (Dangerous) Waste Management:

A. Identify, minimize, segregate, contain, package, label and turn in Hazardous (dangerous) waste to the Government for disposal. Collect dangerous waste in Department of Transportation (DOT)-approved containers in accordance with 49 CFR 171, 49 CFR 172, and 49 CFR 178 properly labeled to identify the type of waste, hazard to personnel, and the start date. Containers and labels will be supplied by the Government for waste that has been designated as Hazardous/Dangerous. Containers and disposal for waste designated as non-hazardous is the responsibility of the Contractor.

B. Notify the Contracting Officer fourteen (14) calendar days in advance for request of bulk containers that have been designated as Hazardous/Dangerous waste. Bulk containers and disposal of non-hazardous waste is the responsibility of the contractor.

C. Accumulate waste in a satellite or 90-day accumulation area that meets the requirements set forth in WAC-173-303 and approved by the BEO. Contact the Government no more than 45 calendar days from the start date for 90-day accumulation areas to arrange for transport.

Accumulate bulk dangerous waste in a less than 90-day area. Turn in non-bulk dangerous waste from a 90-day area within 45 days of the start date. Turn in dangerous waste from satellite accumulation areas to the Government prior to exceeding time and quantity limits.

Onsite treatment of waste by the contractor is prohibited. Contractor shall not transport Dangerous Waste on or off Government facilities without BEO authorization.

15. All contractors and personnel on the project site shall be the competent person and responsible for their own actions. All persons on the project site will have the right to stop work if for any reason that unsafe conditions exist.

GENERAL REQUIREMENTS

1. GENERAL INFORMATION

1.1 Construction Work Categories

Category III construction services are primarily composed of minor renovation or repair. Local environmental or usage permits are required; state or federal permits are not required unless specifically requested in the contract.

Building and/or site approvals are not required. There are no plans and specifications; work is developed from a scope of work supplemented by professional engineering staff as needed with sketches, catalog cuts, and/or narrative descriptions. Examples of typical Category III work include fire protection alarm relocation; pre-engineering buildings (>120 sf) with no utilities; installation of pre-fabricated carports; replacement of conveyors; non-structural demolition; overhead door repair/replacement (>100 sf); replacement of non-load bearing wall; exterior insulation finish system; HVAC package units (<5 tons, ground level); paving, asphalt overlay, large repair; sprinkler head, fire protection relocation/replacement (<21); roof replacement, structural repair in-kind; stairs, interior or exterior, single flight pre-engineering; utilities -connecting to existing with provider consultation; walls partition, no ingress/egress issues, no utilities; and window installation on non-load bearing walls.

1.2 The Unified Facility Guide Specifications

The Unified Facility Guide Specifications are mandatory for all work required under this contract. The contractor is responsible for obtaining the Unified Facility Guide Specifications and for maintaining updates to the specifications. The specifications whether referenced or not (in whole or part), shall be considered to be a part of this contract. Where two specifications are listed for a certain item of work the Navy section as denoted by an “N” shall be used. In the absence of specifications use an industry standard specifications or others listed in the Construction Criteria Identified in the Scope of Work. A complete listing of the UFGS Division 01 - General Requirements can be obtained at https://wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

1.3 Proposal Preparation Costs

The costs for preparation of contract proposals shall be the responsibility of the Contractor and not directly reimbursable. The Contractor shall furnish all project management, planning, estimating, labor, transportation, mobilization, materials, equipment, tools, supervision, design if applicable, and all other associated costs necessary to fulfill the requirements of the contract.

1.4 Joint Venture (JV), Limited Liability Companies (LLC), Limited Partnerships (LTD), and ETC.:

Joint Ventures and Limited Liability Companies and Limited Partnerships shall submit the following additional documentation regarding their business entities with the bid:

a. A copy of the JV, LLC or LTD agreement.

b. A detailed statement outlining the following in terms of percentages where appropriate:

1) The relationship of the team/partners/parties in terms of business ownership, capital contribution, profit distribution or loss sharing.

2) The management approach in terms of who will conduct, direct supervise, and control.

3) The structure and decision-making responsibilities of the partners/parties in terms of who will control the manner and method of performance of work.

4) Identify (by name and title) the personnel having the authority to legally bind the partners/parties (including authority to executed the contract documents and bonds).

c. A list of partners/parties, to include company name, DUNS and CAGE numbers, address, point of contact, e-mail address, phone number and facsimile number

NOTE: A bid may be rejected if the company name identified on the bonds is different from the JV, LLC or LTD name identified on the agreement.

1.5 EPAYROLL

SPECIAL CONTRACT REQUIREMENT FOR CONTRACTOR TO SUPPLY AND USE AN

ELECTRONIC SOFTWARE FOR PROCESSING WAGE RATE REQUIREMENTS (CONSTRUCTION)

ACT CERTIFIED PAYROLLS IN COMPLIANCE WITH FAR 52.222-8, PAYROLLS AND BASIC

RECORDS AND FAR 52.222-13, COMPLIANCE WITH WAGE RATE REQUIREMENTS

(CONSTRUCTION) AND RELATED ACT REGULATIONS.

The US Department of Labor accepts the electronic submission of certified payrolls and the “electronic signature” is accepted for the purposes of “certifying the payroll”. There are several electronic systems currently commercially available to contractors for payroll processing in compliance with the Wage Rate Requirements (Construction) and Related Acts.

The contractor may use a supplemental electronic Wage Rate Requirements (Construction) Act payroll processing system to process and submit certified payrolls electronically to the Government that are compliant with appropriate Wage Rate Requirements (Construction) Act payroll provisions in the FAR. The contractor shall be responsible for obtaining and providing all access, licenses, and other services required for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Wage Rate Requirements (Construction) and Related Act Regulations. The electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion, and providing a durable record copy of all payrolls and other documentation to the government at contract closeout.

The contractor shall obtain and provide access to the Government via the internet with login authorization, as required to comply with the Wage Rate Requirements (Construction) and Related Act Regulations over the duration of this construction contract. The access shall include electronic review access via the internet by the Government contract administrative office to the electronic payroll processing system used by the contractor.

The supplemental electronic payroll processing service shall meet the following basic functional criteria:

commercially available;

compliant with appropriate Wage Rate Requirements (Construction) Act payroll provisions in the FAR;

able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract;

demonstrated security of data and data entry rights;

ability to produce contractor-certified electronic versions of weekly payroll data;

ability to identify erroneous entries and track the data/time of all versions of the certified Wage Rate requirements (Construction) payrolls submitted to the government over the life of the contract;

capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout.

This durable record copy of data from the electronic Wage Rate Requirements (Construction) payroll processing system shall be provided to the Government during contract closeout.

All contractor-incurred costs related to the contractor’s provision and use of an electronic payroll processing service shall be included in the contractor’s price for the overall work under the contract. The costs for Wage Rate Requirements (Construction) Act compliance using electronic payroll processing services shall not be a separately bid or reimbursed item under this contract.

1.6 Project Plans and Specifications

This solicitation identifies all available project plans, drawings and specifications that are applicable to the requirement in the Scope of Work.

1.7 Pre-award Site Inspections

Upon receipt of the scope of work, including applicable drawings, and following a brief time period for reviewing the documents, the Contractor shall inspect the job site per the site visit instructions scheduled in Provision L-237- W001 Any deficiencies, conflicts, or other areas of concern existing in the scope of work and applicable drawings should be brought to the attention of the Contracting Officer through the PPI process. The Contractor shall also notify the Contracting Officer upon observing any features in the work required to be performed that appear to be ambiguous, confusing, conflicting or erroneous.

1.8 Subcontracting Responsibilities

The contractor shall be responsible for the management and performance of all subcontractors. The contractor shall ensure subcontractors are competent and capable of handling all assigned work. The contractor shall ensure subcontractor work is completed within the stated requirements.

1.9 Notice of Constructive Changes

No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether or not acting within the limits of his authority, or any other representative of the Government, shall contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting Officer.

1.10 Construction Schedule

Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final (substantially complete) and final (entirely complete) inspection dates, and other major milestones. Provide updates to baseline schedule as needed or as requested (when there is a change to the critical path). Requirements of this deliverable are in Section C – General Requirements under Deliverables and Performance

1.11 Schedule of Values (SOV)

Submit a schedule of values, Attachment 06, with a breakdown of component work activities for which progress payments will be requested seven (7) days after award. The total costs for the component work activities shall equal the total contract price. Requirements of this deliverable are posted in Deliverables and Performance.

Monthly Work-Hour Reports: Monthly work-hour reporting to the Contracting Officer is required to be attached to the monthly billing request. Requirements of this deliverable are posted in Deliverables and Performance. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor.

The Contracting Officer will provide copies of any special forms at the contract Pre-Performance meeting.

1.12 Weekly and Daily Progress Reports

Reports are to be prepared, signed and dated by the Contractor Project Manager assigned to the project. The contractor shall provide a weekly report that addresses the progress made and how issues identified in Daily Progress Reports were mitigated, to the Government Project Manager through electronic mail. The Contracting Officer will have five (5) business days to address any concerns raised in the weekly Progress Reports that are outstanding. At a minimum, the following information shall be included in each daily report:

Progress this period Status of all tasks developed in the project management plan (with attachment copies of meeting notes, point and working papers).

Indication that the Contract Completion Date (CCD) is being met or if not, a description of new CCD. It must include the reasons for a change in the date and identify the impact of the change on the project.

What is needed from Government in order to meet the CCD.

Activity planned for the next reporting period; planned supporting activities, as well as the status of all products/working papers, including planned CCD and actual and/or anticipated CCD.

Problems encountered; identification of any problems, issues or delays and recommendations as to their resolution concerning the problems submitted during the interim, and any corrective action that was taken to correct identified problems.

Pictures of construction progress of key milestones or events on the project.

1.13 As-Built Drawings

1. When required to be provided as a project close-out submittal, revise identified existing facility record drawings as specified to show all variations between the work performed under this contract and the features shown on the existing facility record drawings.

2. Hard copies of the existing facility drawings will be provided for use after the contract is awarded as requested.

3. Requests for partial payment will not be approved if the marked prints are not kept current. Final payment will not be processed until complete and accurate marked prints are submitted and approved.

CONTRACT ADMINISTRATION DATA

2. MANAGEMENT AND ADMINISTRATION

2.1 Identification of Procuring Contracting Officer

The Procuring Contracting Officer (PCO) is located at: NUWC Division, Facilities Contracting Service, 610 Dowell Street, Keyport WA 98345. Overall administration of the basic contract will be the responsibility of this office. The PCO is responsible for the contract in its entirety and possesses complete authority to modify the terms of the basic contract to include contract interpretation, claims avoidance and resolution, negotiated change orders (as applied to the contract in its entirety), award of option periods, and direction authority.

All correspondence for the basic contract shall be addressed to the NUWC Division, Facilities Contracting Service, PCO and shall include the contract number assigned.

2.2 Contracting Officer Authority

In no event shall any understanding or agreement between the Contractor and any Government employee other than the Contracting Officer on any contract, modification, change order, letter or verbal direction to the Contractor be effective or binding upon the Government. All such actions must be formalized by a proper contractual document executed by an appointed Contracting Officer. The Contractor is hereby put on notice that in the event a Government employee other than the Contracting Officer directs a change in the work to be performed or increases the scope of the work to be performed, it is the Contractor's responsibility to make inquiry of the Contracting Officer before making the deviation. Payments will not be made without being authorized by an appointed Contracting Officer with the legal authority to bind the Government.

2.3 Management and Administration

The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, certified payroll generation, establishing and maintaining records, and quality control. The Contractor shall provide a staff with the necessary management expertise to assure performance objectives and standards are met.

A full-time site Superintendent and a full-time Quality Control (QC) representative are required to be on site for the duration of the project. The Superintendent may serve as the Site Safety and Health Officer (SSHO) as long as all requirements in Section 5.4 (Governmental Safety Requirements) are met.

Employment Eligibility Verification (E-Verify)

Statutes and Executive orders require employers to abide by the immigration laws of the United States and to employ in the United States only individuals who are eligible to work in the United States. In accordance with FAR Clause 52.222-54, Employment Eligibility Verification, this contract requires the use of E-Verify which provides an Internet-based means of verifying employment eligibility of workers employed in the United States, but is not a substitute for any other employment eligibility verification requirements.

2.4 List of Proposed Subcontractors

Provide the Contracting Officer a list of all proposed subcontractors including address, telephone number, name of point of contact (POC), their qualifications, and description of work that will be performed under this SOW. Provide alternate POCs for each company.

2.5 Organizational Chart, List of Personnel and Their Qualifications

The Contractor shall provide their organizational chart, list of personnel and their (Program Manager, Project Manager, Quality Assurance Manager, and Site Safety & Health Officer) qualifications and experience. Identify any special certifications they may carry (Section 5, Health and Safety).

2.6 Employee Requirements

The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract.

Personnel shall be fully knowledgeable of all safety and environmental requirements associated with the work they perform.

2.7 Employee Appearance

The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.

2.8 Employee Conduct

Contractor employees and Subcontractor employees shall conduct themselves in a proper, efficient, courteous and business-like manner.

2.9 Removal of Employee

The Contractor shall remove from the site any individual whose continued employment is deemed by the Government to be contrary to the public interest or inconsistent with the best interests of National Security.

2.10 Registered Historic Buildings and Facilities

Not included in this solicitation/award.

3. CONTRACTOR ACCESS AND USE OF PREMISES

3.1 Activity Regulations

The contractor shall ensure that contractor personnel employed on the Activity become familiar with and obey Activity regulations. The Pre-Construction Meeting will proactively include customers to address special requirements ahead of performance. The contractor personnel shall limit operations and physical proximity to the established work area and agreed upon access and egress avenues. All personnel shall wear hard hats and other required PPE as applicable in designated areas. No contractor personnel shall enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

3.2 Occupied Buildings

The contract may require the Contractor to work in or around existing building(s), which are occupied. Entry into the building shall be in accordance with the approved production schedule or accompanied by a government representative. If entry outside the approved production schedule is necessary, permission must be requested in advance so that building management may be notified. When required by the contract, the existing buildings and their contents shall be kept secure at all times. The contractor shall provide temporary closures as required to maintain security as directed by the Contracting Officer. Provide dust covers or protective enclosures to protect existing work that remains and Government material located in existing facilities during the construction period.

3.3 Jobsite Lay-Down Area

Materials and equipment may be stored at the jobsite lay down area which must be approved in advance through submission of a Universal Outage Request. Requirements of this deliverable are posted in Deliverables and Performance. There will not be office space available at any location. All job site lay down areas are dependent upon contract size and location of the work.

3.4 Hazardous Areas

The contractor shall not enter into work areas where personnel are using protective equipment such as respirator and masks, areas marked for High Voltage Electricity, or marked boundary areas without prior approval from authority designated in the contract. Contractor personnel shall not, under any circumstances, enter a radiologically controlled area, or cross any posted radiological boundary. This paragraph applies to all phases of contract work. Radiation areas are posted with signs consistent with OSHA requirements. Ensure that employees are familiar with the radiation signs and symbols. All personnel entering the shipyard for the first time are required to receive radiological indoctrination training. Should contract workers encounter radiological postings and/or boundaries that appear to limit their ability to access or carry out their intended work, they shall notify their contract administrator for resolution of the problem.

3.5 Protection of Natural Resources

Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work. Confine construction activities to within the limits of the work indicated or specified. If the work is near streams, lakes, or other waterways, conform to the national permitting requirements of the Clean Water Act. Do not disturb fish and wildlife. Do not alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as indicated or specified. Except in areas to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer. Where such use of attached ropes, cables, or guys is authorized, the Contractor will be responsible for any resultant damage. Protect existing trees which are to remain and which may be injured, bruised, defaced, or otherwise damaged by construction operations.

Remove displaced rocks from uncleared areas. By approved excavation, remove trees with 30 percent or more of their root systems destroyed. Remove trees and other landscape features scarred or damaged by equipment operations, and replace with equivalent, undamaged trees and landscape features. Obtain Contracting Officer's approval before replacement. The Contracting Officer's approval is required before any equipment will be permitted to ford live streams. In areas where frequent crossings are required, install temporary culverts or bridges.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .