This document is an amendment to a solicitation for construction services to upgrade Building 894 at the Naval Undersea Warfare Center (NUWC) in Keyport, Washington. The project requires the contractor to provide security upgrades including adding security bars to ductwork, removing and infilling doors, capping skylights, and enhancing door security with locks, badge readers, and astragals. The scope also includes installing emergency eyewash stations and new compressed gas bottle racks and return lines. This is a 100% set-aside for small businesses, and an organized site visit is planned. The solicitation is issued under FAR Parts 15 and 36, with a single firm fixed-price construction contract anticipated. Key dates and details are provided, including submittal requirements, performance period, and references to applicable specifications and requirements. The document also addresses environmental compliance, waste management, and other contractor responsibilities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_12_Wage_Determination_07122024.pdf | ||
| N0025324R50020005.pdf | ||
| N0025324R50020004.pdf | ||
| N0025324R50020003.pdf | ||
| N0025324R50020001.pdf | ||
| Attachment_5_Bid_Form.docx | DOCX document | |
| Attachment_7_Past_Performance_References.docx | DOCX document | |
| Attachment_12_Safety_Requirements_for_Contractors_and_Subcontractors.pdf | ||
| Attachment_10_OPSEC_Guide_for_Defense_Contractors_2016.pdf | ||
| N0025324R5002.pdf | ||
| Attachment_4_Schedule_of_Values.xlsx | XLSX spreadsheet | |
| Attachment_8_Safety_Data_Sheet.docx | DOCX document | |
| Attachment_13_Wage_Determination.txt | TXT text file | |
| Attachment_6_PPI_Form.docx | DOCX document | |
| Attachment_1_MaterialEquipment_In-Place_List.xlsx | XLSX spreadsheet | |
| Attachment_9_OSHA_Calculating_Injury_and_Illness_Incident_Rate.pdf | ||
| Attachment_11_NAVSEA_Guide_to_Environmental_Compliance_Requirements.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is to provide responses to PPIs received for this procurement. The point of contact for this amendment is James Wasson at james.k.w asson.civ@us.navy.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 18
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Jul-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0025324R5002
X 9B. DATED (SEE ITEM 11)
28-Mar-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Jul-2024
CODE
NAVAL UNDERSEA WARFARE CENTER
ATTN: JAMES WASSON
JAMES.K.WASSON.CIV@US.NAVY.MIL
610 DOWELL STREET, BLDG 206
KEYPORT WA 98345
N00253 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0025324R5002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 00 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
The following have been added by full text:
PPI AND RESPONSES
Inquiry 1. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
See section 2.5 Management and Administration A full-time site Superintendent and a full-time Quality Control (QC) representative are required to be on site for the duration of the project. The Superintendent may serve as the Site Safety and Health Officer (SSHO) as long as all requirements in Section 5.4 (Governmental Safety Requirements) are met.
Inquiry 2. (If building is occupied) Are there any phasing requirements? How many people will be in the building? Are there any temporary heating/cooling requirements?
No phasing is required. No temporary heating/cooling provided by the contractor is required but outages to the AHUs feeding occupied spaces outside the construction zone will need to go through the outage process and duration will need to take into account those spaces being occupied.
Inquiry 3. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
Amendment 0001 clarified period of performance to 270 calendar days. Based on the scope of work and government market research, no long lead times are anticipated for material/equipment on this project. If something comes up after award, it would need to be negotiated through the changes clause with the KO.
Inquiry 4. Concerning the duct security bars, threaded steel bars are shown being installed in one direction. Is this the intent or are bars to be installed both horizontally and vertically?
Bars are only required in one direction.
If the bars are to be installed both horizontally and vertically, are they to be affixed to each other at the point that they intersect? NA
If these intersections are to be affixed. In which manner are they to be affixed? NA
Inquiry 5. Paragraph 4. Physical Security Upgrades, viii. Is not redlined, which discusses the card reader.
However, the card readers are redlined in Table VIII-1 Door Security Requirements. Can you confirm the card readers are removed from the scope?
Card readers are no longer part of the scope. Paragraph 4. Physical Security Upgrades, table note viii is no longer needed and is redlined.
SECTION 00 10 00 - SOLICITATION
The following have been modified:
Statement of Work:
Naval Undersea Warfare Center (NUWC) , Keyport has a requirement for upgrades to building 894 to create a secure building boundary for the new use of the building. The project will require the contractor to provide security upgrades including adding security bars to duct work, door removal and wall infill, capping tube skylights and other upgrades such as welding door hinge pins, adding security locks, badge readers, and astragals to enhance door security. In addition, the scope also includes installing emergency eyewash stations. and adding new compressed gas bottle racks and return lines.
The Contractor shall provide labor, materials, and equipment, as required, to accomplish the work.
All work must be coordinated through the Contracting Officer Representative (COR). A preconstruction meeting will take place two weeks prior to the start of construction, the COR, Customer, Contractor and all required subs will be in attendance at a minimum.
I. References:
1. References:
A. Naval Base Kitsap (NBK) Instruction 11300.1 Utilities and Facilities Outages B. EM-385-1-1 Safety and Heath Requirements Manual, March 15, 2024 C. Unified Facility Criteria (UFC) 1-200-01 DoD Building Code –With Change
3 Revision Date February 26, 2024.
D. NAVFAC P307 Weight Handling Program Management Manual, June 2016 E. NAVSEA Safety Requirements for Contractors and Subcontractors, August
2021, REV P.
F. NAVSEA Guide to Environmental Compliance Requirements for Contractors and Subcontractors, October 2019 G. Naval base Kitsap (NBK) Instruction 11210.1A Road Closure/Disruption
Coordination August 21, 2014.
H. Unified Facilities Guide Specifications - UFGS 22 00 00 Plumbing, General
Purpose, November 1, 2015 I. Unified Facilities Guide Specifications – UFGS 04 20 00 Unit Masonry
November 1, 2015.
J. Military Handbook 1013/1A. December 15, 1993.
K. Federal Specification Locks, Combination, Electromechanical FF-L-2740B, June 15, 2011.
L. Federal Specification Lock Extensions (Pedestrian Door Lock Assembly
Preassembled, Panic and Auxiliary Deadbolt) FF-L-2890C February 22, 2019.
M. Department of Defense Manual DoDM 5200.01 Volume 3, July 28, 2020.
II. Submittals:
1. Electronic copies of Product/Material Submittals & Construction/Project Schedule shall be submitted to the COR for approval 21 days (3 weeks) after award. See Deliverables and Performance Table under General Requirements for a list of required submittals. Allow minimum 10 working days for Government review of all submittals.
2. Proposed equipment specifications shall be submitted to the COR for review and written approval prior to commitment to purchase.
3. Required outages shall adhere to Ref (A) and routed through the COR for information on scheduling. The COR is not responsible for outage coordination, obtaining signatures, or vetting outage requests, including Hot Work permits or Fire Alarm outages. Contractor pricing shall include all Contractor support and associated costs in their proposal.
4. All submittals requiring NUWC Keyport Environmental signature shall be routed through the COR for review. The COR shall be copied on all correspondence with Environmental. No work shall begin until all required Environmental forms have been accepted by Environmental.
5. All contractors working this project are subject to labor interviews and shall provide the information requested per “Labor Standards Interview” form 1445 (Rev. 12-96). The COR will conduct these interviews randomly during the performance of the work.
6. The contractor may submit an invoice no more frequently than once a month for the amount of progress made on the project. Therefore, the schedule of values submitted with each invoice shall have a section for each area of the project listed separately on the invoice. The schedule of values will be submitted to the Government COR for approval prior to final submission of the invoice. Tracking the cost of each area separately is required to properly track the costs for each area as it is completed. Failure to submit an invoice which lists each area separately will result in rejection of the invoice until properly submitted according to these instructions. Questions may be directed to the contracting officer.
III. Products:
1. All materials and products provided by the Contractor in the performance of this contract shall be new and manufactured and assembled in the United States of America and shall meet or exceed the manufacturer’s specifications.
2. The materials and/or products listed here are required for the completion and operation of this project, but may not be all inclusive.
A. Physical Security Upgrades
½” threaded steel ductwork security bars with welded nuts and washers
10” x 10” hinged inspection doors CMU blocks for door infill and associated rebar pins to tie to existing wall and paint to match existing wall Four (4) PVC skylight caps One (1) GSA-approved combination lock meeting the most current version of FF-L-2740.
Two (2) Badge Readers. Readers shall be scramble pads that match style and function as existing readers installed on other doors such as door B. Conduit and wiring shall be install from card reader to alarm panel.
Six (6) Eight (8) GSA-approved pedestrian door egress devices with deadbolts meeting the most current version of FF-L-2890 for secondary door use.
Two (2) GSA-approved pedestrian door egress devices with deadbolts meeting the most current version of FF-L-2890 for exit only door use.
Opaque film for windows to obstruct visual observation through windows.
Astragal and flush bolts for double doors.
Dead-bolts to secure four (4) six (6) existing roll-up doors.
A. Emergency Eye Wash Stations
Three (3) ANSI Z358.1 compliant Eyewash Stations including all piping, tempering valves and plumbing necessary to hard pipe water supply and drain to existing adjacent restrooms.
B. Pre-Fabricated Nitrogen Cylinder Bottle Rack Single Row, Twelve (12) bottle capacity (200-300 cu.ft. tank).
Steel construction with exterior grade black powder-coated and end caps
C. Pre-Fabricated Sulfur Hexafluoride (SF-6) Cylinder Bottle Rack Single Row, Eight (8) bottle capacity (200-300 cu.ft. tank) Steel construction with exterior grade black powder-coated and end caps
D. SF-6 Return Lines 1” schedule 40 threaded steel pipe with all associated isolation ball vales, fittings, caps and hangers.
IV. Quality Control:
1. The Contractor shall be a licensed contractor in the state of Washington. All components and services are to be installed per manufacturer’s specifications by trained technicians with a minimum of five (5) years’ experience or Journeyman level certifications, who specialize in the proposed trade specified herein.
2. The Contractor shall perform all work according to accepted standards, safety procedures, and applicable laws, regulations, codes, and standards to include the Unified Facilities Guide Specifications (UFGS), Unified Facilities Criteria (UFC), International Building Code (IBC), International Mechanical Code (IMC), International Plumbing Code (IPC), National Electrical Code (NEC), National Electrical Safety Council (NESC), and National Fire Protection Association
(NFPA).
3. The Contractor shall be responsible for all quality control, inspections, and tests required in the completion of this project. The Contractor shall obtain all approvals except those required for field installations, field applications, and post-field tests, prior to delivery of materials and equipment to the project site unless otherwise specified. The Contractor shall arrange for tests and inspections where and when required as defined in the approved Quality Control Plan.
4. Contractor shall verify all dimensions of all equipment to ensure that all access clearances can be met.
5. The contractor is responsible for providing a complete and useable system including providing manufactures manuals, specifications, any field tests, wiring diagrams and as- built prints (red line drawings) as necessary.
V. Execution: (general)
1. All approved project packages shall be kept on the jobsite and all employees shall be aware of its contents. Current, up-to-date Site Specific Activity Hazard Analysis (AHA) forms shall be available for review, if applicable. The Contractor shall inform all employees how to contact Base Emergency Services as approved in the contract submittal approvals.
2. Scheduling: The Contractor shall schedule work to cause the least amount of interference with station operations. The government will attempt to provide the Contractor 24 hours’ notice prior to work interruptions due to unscheduled/emergent operational requirements.
3. Protection of Government Property: The Contractor shall use every means at their disposal to prevent damage to government owned property during the execution of work. If government property is damaged, the Contractor shall contact the COR immediately and stop work until the issue is resolved.
4. Delivery, handling, storage, and protection of products to, and at the project site:
Inspect for damages, store in a clean dry place, and protect from construction traffic. Handle carefully to avoid damage to components, enclosures, and finish.
5. Close Out: Upon completion of work, the site shall be left free of any and all debris, dust, and chips generated by work throughout the construction area.
6. Access to NUWC Keyport is limited to cleared personnel and vehicles.
7. Furnish the COR with a list identifying personnel and vehicles requiring access.
8. Disposal of any material resulting from demolition shall be per applicable Environmental regulations, including all documentation (Waste Designation Tables, WGRs, and documented in accordance with Ref (F)
9. Contractor shall locate all utilities prior to starting any excavation work.
10. Contractors performing a Weight Handling Evolution shall adhere to Ref (D) and
(D).
11. Contractors utilizing lifting and handling equipment shall adhere to Ref (D) and (D).
12. The COR shall be contacted to coordinate access for job walks, site visits, and scheduling of work.
13. Completion Time Frame: The project is to be completed within 120 days after award.
VI. NUWC Keyport General
1. Smoking A. Smoking is only permitted in designated smoking areas.
2. Delays
A. Contractor operations are subject to reasonable delays, suspensions, and/or restrictions because of emergencies, alerts, drills, equipment movements and other such activities.
3. Flame Producing Devices A. Matches, lighters, and other spark producing devices are not allowed without a Hot Work permit.
4. Portable Electronic Device(s) (PED) A. PED is defined as a portable electronic device having the capability to store, record, and/or transmit text, images/video, or audio data. Examples of PED include, but are not limited to pagers, laptops, cellular telephones, radios, compact disc and cassette players/recorders, portable digital assistants, audio devices, watches with input capability, reminder recorders, and mobile devices.
B. PEDs are not allowed inside of NUWC Keyport Buildings. PED use will be clarified and discussed at the site walk and pre-construction meeting
C. The Government COR will provide location of phone for emergency use.
D. For work inside the NUWC Keyport Annex, refer to the Keyport Annex Safety and Physical Access Security Brief.
5. Photography
A. Photography by the Contractor is prohibited. Construction progress photos, and all other necessary photo documentation, will be provided by authorized Government personnel only.
6. Schedule A. Before starting any work, the COR is to be provided with the project schedule for review and approval. Government has 5 working days to review and return schedule.
7. Coordination A. The COR must be contacted to coordinate access to the buildings for job walks, site visits, and scheduling of the work.
8. Lock out Tag Out A. Lock Out/Tag Out: Contractors must notify the COR five (5) working days before anything can be locked out. The notification should include: what is being locked out, the tag number, the person on the tag and phone number shall also be provided to the COR within 24 hours of removal.
9. Vehicle Access A. Only government and authorized company vehicles will be allowed access to
NBK. The contractor shall provide the COR a list identifying all vehicles which will require access to the work site a minimum of three (3) calendar days in advance. All vehicle pass requests will be submitted with: Area access that is needed, company name, vehicle year, make and model, and license plate number, state, and tab expiration date. NUWC Keyport Annex Vehicle Passes must be picked up at the Annex MFO. Vehicle registration must have the company's name as the owner. If the vehicle is leased or rented the lease or rental agreement must be in the company's name.
B. All vehicles will be subject to inspection and search prior to entering and within Naval Base Kitsap. Avoid transporting sealed containers into Naval Base Kitsap. If such containers must be introduced, prior coordination with the COR is required.
10. Parking
A. Parking at NUWC Keyport is assigned so the contractor will have to apply for area outage for lay down/vehicle parking unless area is made available by the building POC. The Annex is wide open for parking
11. Security A. Compliance with the security directions of NBK Security Force Personnel is mandatory.
VII. Deliverables:
1. The Contractor is responsible for providing a complete and useable system.
2. The Contractor shall prepare and submit two (2) hard copies (in 3-ring binders) and two (2) CD/DVDs of the Operations and Maintenance (O&M) Manuals to the COR. Each binder shall have the project contract number, Prime Contractor letterhead, project title, and building number on the spine and face of the binder.
Each binder shall include Attachment (1) Material/Equipment In-Place List, all product data, manufacturer’s manuals, warranty, specifications, field test results, wiring diagrams, and as-built prints (red line drawings), as necessary.
3. Submit all manufacturers' signed warranties to COR prior to final commissioning and acceptance.
4. Before final payment will be approved, the Contractor shall provide all necessary training required on any and all new systems.
5. This project will not be accepted as complete until all project documentation and punch list items have been submitted to, and approved by the COR in their entirety and the Customer provides their concurrence electronically to the COR that the project is complete.
VIII. Work Description:
1. Coordinate with COR prior to commencement of work.
2. Building 894 was constructed in 1984. No lead or asbestos is anticipated.
3. Refer to attachment (3) Floor Plan for work location of the below listed tasks.
4. Physical Security Upgrades A. All utility openings larger than man-passable (96 square inches) need to hardened per Military Handbook 1013/A. Provide and install ½” threaded steel security bars at 6” on center attached with welded washers and nuts on both sides to all ducts and openings greater than 96 square inches that pass through the secure border. Each location shall also have a 10” x 10” hinged inspection door installed in an accessible point within 3’ of bars.
See attached Ductwork Security Bar Drawings for locations of required duct security bars and security bar detail. All security bars shall be located on the inside of the secure space border.
B. There are four (4) existing tube skylights near columns D7 and D8. Cut each skylight off to within 1’ of ceiling line and 2’ of roofline. Provide and install permanently glued PVC caps on roof side of each skylight.
C. Doors into the secure space from restrooms 143 and 142 (Doors J and K) shall be completely removed including frames. Infill each opening with CMU block and paint to match existing surrounding walls. All newly installed concrete block must be pinned to and interlocking with existing concrete wall/block by rebar or other approved devices(s). All door hardware and security devices to be returned to the COR.
D. Door Security Requirements shall be installed per location and requirements specified in Table VIII-Door Security Requirements below.
Table VIII-1 Door Security Requirements
D oo r
R oo m
T yp e
S po t W el di ng
H in ge P in s
(i
X -1
L oc k i.)
ea db ol t a nd
E gr es s
D ev ic e ii db ol t a nd
E gr es s
D ev ic e
(i v.
B la ck ou t W in do w s (v
A st ra ga l a nd
P in
D ou bl e do or vi db ol t ( i)
C ar d R ea de rs ii)
R em ov e ex is tin g ha rd w ar e an d re tu rn to C
O R
A Hall
Secondary Entrance
X
B Hall
Main Entrance
X
C 159 Secondary Entrance
X X X X
D 151 Exit X X X E 107 Secondary
Entrance X X
F 107 Secondary Entrance
X X
G 107 Roll Up X H 144 Secondary
Entrance X X X X
I 144 Roll Up X J 143 Door To be Removed See VIII. 4.C. Above K 142 Door To be Removed See VIII. 4.C. Above L 141 Secondary
Entrance
X X X X
M 141 Roll Up X N 139 Roll Up X O 136 Roll Up X P 136 Secondary
Entrance X X
Q 136 A
Exit Only X X
R 101 A
Roll Up X
S 134 Secondary Entrance
T 134 Roll Up X X
i. Door hinge pins that are accessible from outside of the building shall be spot welded to prevent removal of the door.
ii. Provide and install a combination lock meeting the most current version of Federal Specification FF-L-2740.
iii. Provide and install a GSA-approved pedestrian door egress device with deadbolt meeting the most current version of Federal Specification FF-L2890 for secondary door use. An AO-Approved alternate device with similar functionality may be authorized.
iv. Provide and install a GSA-approved pedestrian door emergency egress device with deadbolt configuration meeting the most current version of Federal Specification FF-L-2890 for exit only door use.
v. Provide and install opaque film to windows to obstruct visual observation into secure space.
vi. Provide and install an astragal strip attached to either door to prevent observation of the interior space through the opening between the doors. Inactive leaf of the double door shall also have flush bolts installed on top and bottom to secure door.
vii. Provide and install deadbolts on both sides of the existing Roll-Up doors lockable from inside the secure space.
viii. Provide and install access control badge reader and associated materials. Install wiring from card reader to alarm panel. Leave enough wiring for the Government to connect to panel. Readers shall be scramble pads that match style and function as existing readers installed on other doors such as door B.
5. Provide and Install new single row Nitrogen Cylinder rack for twelve (12) high pressure nitrogen cylinders (200-300 cu.ft.) in existing striped area in room 141.
A. Rack shall be a pre-fabricated steel rack(s) capable of securing cylinders to prevent falling due to contact, vibration or seismic activity in accordance with OSHA and NFPA requirements. Rack(s) shall be exterior grade black powder-coat painted with end caps for longevity and durability. Nitrogen cylinders to be provided by Government and not part of this contract.
6. Provide and Install new single row SF-6 Cylinder Rack for eight (8) SF-6 cylinders (200-300 cu.ft.) in room 136A.
A. Rack shall be a pre-fabricated steel rack(s) capable of securing cylinders to prevent falling due to contact, vibration or seismic activity in accordance with OSHA and NFPA requirements. Rack(s) shall be exterior grade black powder-coat painted with end caps for longevity and durability. SF-6 Cylinders to be provided by Government and not part of this contract.
B. Provide and install new 1” schedule 40 steel pipe return line from location of SF-6 return manifold in room 136A through exterior wall to existing cage area.SF-6 return manifold will be provided and installed by the Government not part of this contract. Each end of new pipe shall be capped and have isolation ball valves.
C. New piping shall be labeled with system name and directional flow arrows.
D. Pipe, fittings, hangars and valves: All piping shall be properly supported, installed straight and uniform. All access panels and service valves shall be non-obstructed and easily accessible for maintenance purposes.
E. Where pipes pass through walls, furnish and install tested and listed fire stopping systems, combination of materials, or devices to form an effective barrier against the spread of flame, smoke and gases, and maintain the integrity of fire resistance rated walls. Through-penetrations include the annular space around pipes.
F. Exact location of new pipe shall be approved by the COR before installation.
7. Provide and Install three (3) new permanently plumbed ANSI Z358.1 rated emergency eyewash stations.
A. Emergency eyewash stations shall be hard piped with drain connected to existing adjacent restrooms/washrooms. All necessary tempering, mixing and isolation valves shall be located on the secure side of the wall near the eye wash station for ease of inspection and maintenance.
B. Pipe, fittings, hangars and valves: All piping shall be properly supported, installed straight and uniform. All access panels and service valves shall be non-obstructed and easily accessible for maintenance purposes.
C. Where pipes pass through walls, furnish and install tested and listed fire stopping systems, combination of materials, or devices to form an effective barrier against the spread of flame, smoke and gases, and maintain the integrity of fire resistance rated walls. Through-penetrations include the annular space around pipes.
8. All dimensions provided by the Government are only approximations, the Contractor is responsible for field verifying all existing site conditions, dimensions, elevations, clearances, and egress’s and finishes at jobsite prior to commencement of any work.
9. Upon completion of the work, the Contractor shall inform the COR, and customer to demonstrate operational tests.
IX. Title to Materials:
1. All excess and/or discarded materials shall become property of the Contractor and shall be removed from government property, unless specifically noted. Title to the materials resulting from demolition is vested in the Contractor upon authorization of the Contracting Officer to begin demolition.
2. Recycling is preferred and recommended. A WGR is required for disposal and recycling is required for metal.
X. Material/Equipment In-Place List:
1. The Contractor shall provide a list of significant equipment and materials removed, replaced, or installed under this contract with the required information below, including the warranty expiration date.
A. Types of equipment and materials:
Materials: Roofing products, floor coverings, windows, doors, lighting, and all material with a manufacturer’s warranty.
Equipment: Mechanical (pumps, backflow preventers, HVAC components, pressurized piping systems, panel boxes, emergency lights, street lighting, etc.); mechanized doors, elevators, conveying systems, all equipment with an O&M manual or manufacturer’s warranty.
2. Required format and information: The Contractor shall provide material and equipment data in the attached format (Attachment (1) – Material/Equipment In- Place List). All of the requested data shall be provided prior to final inspection or final acceptance.
XI. Cleanup:
1. Contractor shall not dispose of debris/rubble on NBK property or in NBK dumpsters.
XII. Safety
1. The contractor is responsible for the actions of their personnel on site and any person on the project site has the authority to stop work if an unsafe condition exists.
2. Read and sign NAVSEA Safety Requirements for Contractors and Subcontractors, August 2021, REV P. Ref (E)
3. Ensure all workers are wearing the proper PPE for the assigned task.
4. The Contractor is responsible for inspecting their worksite for any hazards at all times, no exceptions. If an unsafe condition exists, work to correct or mitigate the hazard and contact the COR to assist in determining how to proceed, if needed.
XIII. Environmental:
1. The Contractor shall comply with all federal, state, and local laws, codes, regulations, acts, ordinances, and rules for Environmental Protection and Hazardous Waste Management / Disposal, including facility instructions and facility permits for work taking place on government properties. Take actions to mitigate creation of hazardous waste by recycling and other available methods.
2. The Contractor shall perform all work according to accepted Industry Standards, Safety and Environmental Procedures, and regulations, including Ref (B & E) and the latest revision of OSHA regulations.
3. Prior to the start of work on site, the contractor shall provide an Environmental
Protection Plan (EPP) detailing specific methods of handling encountered wastes and refuse, project storm water management and control, and spill response procedures. If sampling and analysis services will be provided, the EPP shall include qualifications of sampling personnel and analytical services provider laboratory accreditation documentation. Include Refrigerant Handling License:
Documentation of 40 CFR 82 refrigerant technician certification for contractor service technicians if contract involves HVAC system work involving refrigerants.
4. Facility Environmental Permits:
A. Equipment and work performed under this contract shall be in compliance with federal, state, and local environmental regulations and existing facility permits.
B. NBK Keyport has facility permits that place requirements on certain types of work being performed at the facility. Obtain information on requirements from the Base Environmental Office (BEO).
C. Existing Facility Permits include but are not limited to:
5. Contractor Employee Required Environmental Training
A. Training must be completed and documented prior to commencing work under this contract at the government facilities. Contact the BEO for instructions on accessing required training.
Waste Originator Training for NBK Bangor (0.5 hr). Required prior to generation of waste at NBK Bangor facility, for personnel involved in managing hazardous waste generated during the performance of the contract. Available online or in person.
NBK EMS Awareness/General Environmental Awareness Training (0.5 hr). Available online or in person from the BEO.
Required for all personnel performing work NBK property.
B. NBK Keyport Required Environmental Training (required only for work taking place at NBK Keyport facility)
Hazardous Waste Site Manager/Alternate (Waste Generator) (1.0 hr). Required prior to generation of waste at NBK Keyport facility, for personnel involved in managing hazardous waste generated during the performance of the contract. Available online or in person from the BEO.NBK EMS Awareness/General Environmental Awareness Training (0.5 hr). Available online or in person from the BEO. Required for all personnel performing work NBK property.
NUWC EMS General Environmental Awareness Training (0.5 hr).
Available online or in person from the BEO. Required for all personnel performing work on NBK Keyport property.
Read and sign NAVSEA Warfare Centers Keyport Guide to Environmental Compliance for Contractors and Subcontractors.
6. The Contractor shall safely store and manage Hazardous Materials used in the performance of this contract in accordance with applicable federal, state, and local regulations. Submit Safety Data Sheets (SDS’s) and expected quantities of HM to be used and stored in performance of the project and receive approval from the Government prior to HM use in conjunction with this contract, and prior to bringing HM onto government property for the purposes of this contract. For approval to use any hazardous material, submit material SDS’s and Contractor Hazardous Material Inventory (CHMI) form detailing expected material use and storage information for government review and approval. Submit CHMI form prior to performing onsite work, and update monthly while actively working on government property.
7. Products prohibited by the Government, which will not be approved for use, include but are not limited to: leads, chromiums, mercury, phenols, trichloroethylene, halons, PCBs, asbestos, silica sand (for use as blasting agent), Class I ODS, radioactive materials or instruments capable of producing ionizing radiation, and chemicals listed in 40 CFR 355.50, Appendix A. This prohibition prevails over any other provision, specification, drawings, or referenced documents. The Contracting Officer may consider exceptions to the use of any of the above excluded materials upon written request by the Contractor, and with BEO approval.
8. Clean Air Act Compliance: Work performed shall be in compliance with the
Puget Sound Clean Air Agency (PSCAA) Regulations I, II, and III. Contractor shall identify and receive approved permit for any air pollution generating equipment or processes that may require a Notice of Construction (NOC) pursuant to PSCAA Regulation prior to bringing equipment on site including non-road engines meeting PSCAA Regulation I, Article 15 applicability. Equipment meeting requirements for use under existing government facility NOC permits shall be approved for use by the BEO prior to being brought onsite.
9. All work involving refrigerants shall comply with the requirements of 40CFR 82 and other applicable federal, state, and local regulations to include Section 608 of the Clean Air Act. Any new equipment provided shall not contain Class I or Class II ODS in pure or blended form. All new shore-based, HVAC&R equipment supplied by the contract must use an EPA-SNAP program approved refrigerant with an Ozone Depletion Potential (ODP) of zero. Excess Class I and Class II ODS removed from existing equipment as part of the contract shall be turned in to the government for recycling/disposal. The contractor is responsible for providing adequate cylinders/containers for Class I and Class II ODS. Provide Refrigerant Work Checklist submittal for work performed on equipment containing refrigerants in accordance with 40 CFR 82 requirements.
10. Hazardous (Dangerous) Waste Management: Naval Base Kitsap Keyport is designated as a Large Quantity Generator in accordance with WAC 173-303, and waste generated onsite must be managed under the facility Hazardous Waste management program. Hazardous (dangerous) waste generated at the facility must be shipped and disposed of under the government’s site EPA Waste ID#’s.
The contractor is required to meet the regulatory requirements for large quantity generators for any work conducted within the boundaries of the Naval Base Kitsap Keyport and shall comply with provisions of federal, state, and local regulatory requirements applicable to this generator status regarding training and storage, handling, and disposal of generated wastes.
11. The government shall be responsible for disposal costs for Hazardous (dangerous) waste generated during work performed on government property. The Contractor shall reimburse the Government for HW disposal costs associated with a) spent cleaning supplies, such as contaminated rags, cleaning absorbents, solvents from cleaning machines, and degreasers; and, b) HW from Contractor spills and the spent materials and supplies used to clean the spill. All unused or partially used regulated material ordered by the contractor is the property of the contractor and shall not be left at the facility or turned in to the government for disposal as Hazardous Waste.
12. Hazardous (Dangerous) Waste Profiling (Determination): The Government shall determine whether waste generated during the performance of the contract at government facilities is Hazardous (Dangerous) waste.
A. Naval Base Kitsap (NBK) Keyport: Information required for the control and disposal of Hazardous Waste at NBK Keyport is included in the "Hazardous Waste Site Manager/Alternate (Waste Generator)" training module and the NAVSEA Keyport Contractor's Guide to Environmental Compliance.
Complete Waste Generation Record forms for waste determination for each waste stream expected during work performed under the contract. Contractor personnel submitting Waste Generation Record (WGR) forms must have received facility Hazardous Waste Site Manager/Alternate (Waste Generator) Training and Certification for NBK Keyport.
13. Hazardous (Dangerous) Waste Management:
A. Identify, minimize, segregate, contain, package, label and turn in Hazardous
(dangerous) waste to the Government for disposal. Collect dangerous waste in Department of Transportation (DOT)-approved containers in accordance with 49 CFR 171, 49 CFR 172, and 49 CFR 178 properly labeled to identify the type of waste, hazard to personnel, and the start date. Containers and labels will be supplied by the Government.
B. Notify the Contracting Officer 14 calendar days in advance for request of bulk containers. Request is accomplished by submission of a Waste Profile including an estimated quantity of dangerous waste and the number of containers. Identify dangerous waste generated within the confines of the station by the use of the station's EPA generator identification (ID) number.
C. Accumulate waste in a satellite or 90-day accumulation area that meets the requirements set forth in WAC-173-303 and approved by the BEO. Contact the Government no more than 45 calendar days from the start date for 90-day accumulation areas to arrange for transport. Accumulate bulk dangerous waste in a less than 90-day area. Turn in non-bulk dangerous waste from a 90-day area within 45 days of the start date. Turn in dangerous waste from satellite accumulation areas to the Government prior to exceeding time and quantity limits. Onsite treatment of waste by the contractor is prohibited. Contractor shall not transport Dangerous Waste on or off Government facilities without BEO authorization.
14. Control of Waste Without Documented Waste Determination:
A. Collect waste for which the Waste Determination Documentation has not been completed; label "waste awaiting designation" or "WAD" to indicate that analysis is pending. Accumulate and manage in an area that meets the minimum criteria for satellite or 90 day accumulation in accordance with WAC-173-303 and the Contract specifications.
B. Submit Waste Determination Documentation for each undesignated waste type within one day of generation. Do not turn in or dispose of waste without prior to designation by the Government.
15. All contractors and personnel on the project site shall be the competent person and responsible for their own actions. All persons on the project site will have the right to stop work if for any reason that unsafe conditions exist.
(End of Summary of Changes)