N0025318Q0079 Amendment 0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N0025318Q0079-0006.pdf | ||
| N0025318Q0079-0005.pdf | ||
| N0025318Q0079-0004.pdf | ||
| N0025318Q0079-0003.pdf | ||
| N0025318Q0079-0002.pdf | ||
| N0025318Q0079.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to provide answ ers to vendor questions, update the Statement of Work (SOW), update Notes to Offerors, provide Site Visit information and extend the closing date.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Mar-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0025318Q0079
X 9B. DATED (SEE ITEM 11)
12-Feb-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Mar-2018
CODE
NAVAL UNDERSEA WARFARE CENTER
ATTN: KIRSTEN NEWHARD
KIRSTEN.NEWHARD@NAVY.MIL
610 DOWELL STREET, BLDG 206
KEYPORT WA 98345
N00253 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0025318Q0079
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 15-Mar-2018 10:00 AM to 03-Apr-2018 10:00 AM.
The following have been added by full text:
VENDOR QUESTIONS AND ANSWERS
Question 1: Will there be a site survey prior to award?
Answer 1: Yes – Please see updated Notes to Offerors for details.
Question 2: How many users need to control the content of the video wall simultaneously?
Answer 2: One.
Question 3: Will the government provide PCs which to load software to control the video wall and video wall software?
Answer 3: No.
Question 4: Will the video wall be left on 24/7/365?
Answer 4: No.
Question 5: Do you require the ability to turn off the video wall?
Answer 5: Yes.
Question 6: Is a freestanding structure required for the video wall?
Answer 6: See Answer 7.
Question 7: Will the video wall be installed on a wall?
Answer 7: The current rear projection screen opening is 271" x 68". These three screens will be removed to expose the opening during installation. This opening will provide the medium with which to install the video wall to. At a minimum, the existing screen opening will be covered by the new video wall just on the outside of the hardwood trim that wraps the opening. The opening shall be used to facilitate a contractor provided “free standing” video wall support structure using vertical/horizontal poles/steel tubes etc. members that will attach the monitors just outside the opening of the wall, and shall be securely fastened to the existing framing/trim located around the perimeter of the existing projection screen opening.
Question 8: The requirements state to interface with a 5.1 surround sound with inputs from a Polycom vortex.
Please provide a detailed explanation of exactly what is required?
a. Are you asking that each of the 15 inputs be connected to the Polycom Vortex?
b. Are you asking that the video wall processor have an audio output to feed the Polycom Vortex?
c. How are you controlling volume of the surround sound system?
d. Do you require reconfiguration of the Polycom vortex?
Answer 8:
a. Not if the Video wall processor can handle this, but audio is necessary to be controlled from inputs.
b. If it does not then a separate controlling interface would be required.
c. Extron control.
d. Currently microphones in the control room and Master Presentation Room (MPR), as well as Computers are controlled by switchbox interface and can be adjusted or muted independently of each other. This ability to adjust the microphone volume is necessary, PC’s can be controlled by the PC volume (Operating System) if necessary.
Reconfiguration of the Vortex would not be required if the videowall processor can provide the same audio control over PC’s, VTC, etc as is currently used (PC, Microphone, Aux, etc).
Question 9: Is the rest of the audio system already in place, such as an amplifier and speakers?
Answer 9: Yes
Question 10: Is there an existing control system?
Answer 10: Yes, it is outdated and will be replaced by this requirement.
Question 11: What is the existing control system?
Answer 11: Extron CrossPoint.
Question 12: Do you have the source code for the existing control system?
Answer 12: No.
Question 13: Do you require modification of the existing control interface?
Answer 13: The existing control interface will be replaced.
Question 14: Do you require a rack for the video wall processor or is there an existing rack that can be repurposed?
Answer 14: There are 2 available racks, the third contains the audio processors and amplifiers, all are side by side.
Question 15: How far is the video wall from the location where the video wall processor will be installed?
Answer 15: 50 Ft. line of sight
Question 16: Do you require the ability to drag and drop content across the video wall pixel space?
Answer 16: Yes, currently we have this ability to drag content across from one projector to another so that 3 items can be displayed simultaneously.
Question 17: Do you require the ability for a source to be partially in one display and partially in another?
Answer 17: Yes. Example: Extremely wide spreadsheets are currently run across two projectors and displayed as one.
Question 18: Will you consider making this a Small Business Set Aside under the same NAICS code?
Answer 18: No. Based on our market research, we will not be setting this requirement aside.
Question 19: Will electrical be provided as necessary to support the video wall and video wall processor?
Answer 19: Yes. Existing electrical power is available.
Question 20: How far are the 15 inputs from where the video wall processor will be installed?
Answer 20: Only 8 inputs required per updated SOW, approximately 3-15 ft away.
Question 21: Is it required to provide signal extension from the location of the 15 inputs to the location of the video wall processor?
Answer 21: No.
Question 22: Is there an existing video wall in place?
Answer 22: No, 3 rear projectors are in place.
Question 23: If there is an existing video wall in place do you require the existing video wall and supporting equipment to be disassembled and decommissioned, and left on site for the government to dispose of?
Answer 23: There is no existing video wall. Projector screens are in place and the Government will remove prior to installation.
Question 24: Is the room or rooms on a raised floor?
Answer 24: Yes.
Question 25: What is the ceiling height?
Answer 25: 12 Feet in height.
Question 26: The requirements state that the gaps between monitors should be no greater than a ¼".This is very large distance, they typical industry standard is about 1-2mm.
Answer 26: The Statement of Work has been updated to 1-2mm for gap.
Question 27: Do you require that each monitor be 1080P or the entire video wall have an aggregate resolution of 1080P?
Answer 27: Each monitor shall be a minimum resolution of 1080p.
Question 28: Do you require each 1080P monitor that makes up the video wall to be driven at 1080P (1920x1080) resolution?
Answer 28: Yes.
Question 29: What are the dimensions of the overall room?
Answer 29: 29.4 feet x 43.3 feet x 12 feet in height.
Question 30: Can you provide a general floor plan of the room?
Answer 30: Yes. Attachment will be posted to FBO.
Question 31: Is there a location to stage equipment when it is delivered?
Answer 31: Yes
Question 32: Is there a clear pathway from a loading dock to the room where the equipment will be installed?
Answer 32: There is no loading dock.
Question 33: The SOW states that the video wall shall be a minimum of 271” x 68”. What is the maximum?
Answer 33: The maximum size the video wall can support is 307” wide x 80” tall.
Question 34: What will the video wall be mounted to?
Answer 34: Video wall should be built onto a contractor provided structure/mounting surface (vertical and/or horizontal) mounted within the inside or on the front of the existing 271” x 68” opening.
Question 35: Will the Navy provide carpentry and other construction to insure a proper fit of the video wall?
Answer 35: The Navy will not provide carpentry or other construction service, although we can work with the installation team to resolve connection issues with respect to contractor supplied mounting structures.
Question 36: The SOW states that there will be 15 digital inputs and 8 digital outputs. How will this be displayed on the overall wall?
Answer 36: Please refer to the updated SOW. .
Question 37: The SOW does not specify a video wall processor which is a costly item. Please clarify.
Answer 37: The SOW has been updated to include a video wall processor – this drives the video wall and shall be a replacement for the 15 input/8 output switch box.
Question 38: What type of ceiling is currently employed at this installation site? If drop ceiling, are cable trays already provided?
Answer 38: There is currently a dropped ceiling in place, however all cabling will be routed via a raised floor system. No aerial cabling will be required to support subject video wall Question 39: What is the ceiling height at the installation location?
Answer 39: See answer 25 above.
Question 40: Does the CTEC employ a raised floor with access/cable trays underneath?
Answer 40: Yes.
Question 41: What are the dimensions of the room where the installation is required?
Answer 41: See answer 29 above.
Question 42: Is there space for an equipment rack in the Video Wall room, or is there a GFE Equipment Rack where all rack mounted equipment is to be installed?
Answer 42: Yes. See answer 14 above.
Question 43: Are all the mixer inputs for microphones, are they paired to make stereo for workstations or a combination of the two?
Answer 43: Yes.
Question 44: What type of Audio encoding is being supplied from GFE Workstations that will supply input audio into the Video Wall Audio Processor?
Answer 44: Line level audio from PC output.
Question 45: Would mixer channels need to be live mix, pre-emptive mix, gated or selectable?
Answer 45: Live Mix.
Question 46: Is control of the existing Polycom EF2280s required?
Answer 46: Yes.
Question 47: are there any existing systems (exception of the five Polycom EF2280s) that need to be integrated into this video wall? If yes, please identify the make and model of the equipment.
Answer 47: No.
Question 48: Are there any existing systems that need to be controlled by the control processor? If yes, please identify make and model of the equipment.
Answer 48: No.
Question 49: Is the purpose of the site survey after award to determine the materials necessary to install the video wall?
Answer 49: Yes.
Question 50: Is the price to be bid for the video wall equipment and training only?
Answer 50: The price should include all costs, please refer to SOW Section 1 Scope.
Question 51: Will the installation cost be added to the award after site survey?
Answer 51: No.
Question 52: 3.4.c (page 4) – Please define what is meant by output, what is the purpose of the outputs? Our understanding of outputs are connections from the video processor to the displays in the video wall, for example a 6 wide by 3 tall video wall would have 18 outputs.
Answer 52: Your understanding is correct. Please see revised SOW.
C. 107 INSTRUCTIONS FOR OBTAINING EXPORT-CONTROLLED TECHNICAL DATA
An offeror may not receive export-controlled technical data, which are specified in this solicitation, unless it is a qualified U.S. contractor as defined in clause C.106. See clause C.106 for instructions on becoming a qualified U.S.
contractor. Questions about this program or DD Form 2345 should be addressed to U.S./Canada Joint Certification Office, Defense Logistics Information Services (DLIS), Federal Center, 74 Washington Avenue North, Battle Creek, MI 49017-3084; or telephone (616) 961-4358, toll free (800) 352-3572; or email jcp-admin@dlis.dla.mil.
If a contractor is requesting qualification, they must submit the request to DLIS within @@ days after the solicitation issue date with an email to @@@@ stating they have requested qualification. If it is determined necessary (and if time permits), an additional @@ days will be added to the closing date if any requests are received. An amendment to this effect will be issued, and if not issued, offerors shall assume no requests were received and the original closing date applies.
If an offeror is a qualified U.S. contractor and needs a copy of the restricted technical data, its appointed Data Custodian must be registered with DLIS (Defense Logistics Info Svc Joint Certification Program (JCP).
Registration instructions and Vendor Guide book can be found on the FedBizOpps homepage https://www.fbo.gov.
C.121 CONTROLLED UNCLASSIFIED INFORMATION (INCLUDES FOR OFFICIAL USE ONLY
INFORMATION)
Ref: (a) DoD Regulation 5200.01, DoD Information Security Program
(b) SECNAV M-5510.36, DON Information Security Program Manual
Contractor may be required to handle Controlled Unclassified Information (CUI). There are numerous types of CUI, e.g. documents with limited distribution statements, documents marked as For Official Use Only (FOUO), etc.
The minimum level of protection for all CUI is adherence to FOUO protection standards. Distribution Statements (DS) and warning labels, such as the Arms Export Control Act Warning, identify additional protection requirements for a given document. Minimum FOUO protection requirements/controls applicable to the performance of this contract for CUI are listed below. Additional protection requirements, as marked on a given CUI document, are in addition to the standards listed.
1. Handling/Storage: Access to FOUO is limited to those needing it to conduct official business for the Department of Defense (DoD). FOUO information is not classified information, but requires extra precautions to ensure it is not released to the public. During business hours, reasonable steps shall be taken to minimize risk of access by unauthorized personnel. After business hours, FOUO information shall be stored in unlocked containers, desks, or cabinets if Government or Government-contracted building security is provided. If it is not, store in locked desks, file cabinets, bookcases, locked rooms, or similar items.
2. Transportinq/Transmitting/Release/Destruction: FOUO information shall be transported in a manner that prevents disclosure of the contents. FOUO information may be sent via USPS first-class mail, parcel post, or - for bulk shipments – 4th class mail. Electronic transmission of FOUO information (voice, data, or facsimile) shall be by approved secure communications systems. Transmission via unsecure fax is acceptable if an authorized person is standing by on the receiving end to take custody. All emails containing FOUO or attachments with FOUO must be digitally signed and encrypted when transmitted within a Navy network or to an approved contractor email address.
Transmission of FOUO (i.e. any CUI) to personal email accounts (e.g. AOL, Yahoo, Hotmail, Comcast, etc.) is strictly prohibited. FOUO sent out of the contractor's facility electronically must be encrypted (DoD FIPS 140-2 standard). FOUO material shall not be released outside the contractor's facility except to representatives of DoD.
When no longer needed, destroy FOUO by a method that precludes its disclosure to unauthorized individuals.
3. Markings: Unclassified documents (paper or electronic) generated in support of this contract which contain FOUO are to be marked "For Official Use Only'' at the bottom on the outside of the front cover (if any), on each page containing FOUO information, and on the outside of the back cover (if any). Each paragraph containing FOUO information shall be marked as such. Within a classified document, an individual page with both FOUO and classified information shall be marked at the top and bottom with the highest security classification of information appearing on the page. Individual paragraphs shall be marked at the appropriate classification level, as well as unclassified or FOUO, as appropriate. Within a classified document, an individual page that contains FOUO information but no classified information shall be marked "For Official Use Only'' at the top and bottom of the page, as well as each paragraph that contains FOUO information. Other records, such as photographs, films, tapes, or slides, shall be marked "For Official Use Only'' or "FOUO" in a manner that ensures that a recipient or viewer is aware of the status of the information therein. DS on technical documents identify access restrictions. DS "B" through "D" preclude public release and while not marked as FOUO, are subject to all FOUO protection requirements, including the prohibition on unencrypted transmission over the public Internet.
The following have been modified:
NOTES TO OFFERORS
NOTE 1: Government Point of Contact for this Solicitation/Request for Quote (RFQ) is: Kirsten Newhard Contract Specialist, Phone: 360-396-1915, Fax: 360-396-7036, Email: kirsten.newhard@navy.mil
NOTE 2: All questions regarding this solicitation should be submitted in writing via e-mail within seven (7) days of solicitation closing date. Email questions to kirsten.newhard@navy.mil. Questions received after this time may not be entertained. (DO NOT include government drawings or government protected information in your reply emails unless they are digitally signed and encrypted per Federal Information Processing Standard (FIPS) Publication 140- 2.)
NOTE 3: A site visit is scheduled for 10:00 AM on 20 March 2018 at Naval Undersea Warfare Center Division Keyport (NUWC Keyport). Prospective offerors shall notify David Manning at (360) 396-2148 or email at david.h.manning@navy.mil by 3:00 PM on Wednesday 14 March 2018 in order to reserve time and submit the names of employees who will attend. Pre-registration is mandatory to meet security and access requirements prior to arrival at NUWC Keyport. Offerors shall include the company name, CAGE code, and solicitation number in subject line of the email. Upon receipt of this information, a Government POC will confirm receipt and provide any final instructions required to attend. Offerors are encouraged to provide cellular contact numbers for company officials attending to allow for last minute changes if necessary. Pre-registration is mandatory to guarantee adequate time for security and access requirements prior to arrival: pre-registration after 3:00 PM on 14 March 2018 could result in the offeror not being able to attend the site visit.
NOTE 4: All offerors must submit a Technical Statement which states that they are able to comply with all specifications called out in the Performance Working Specifications. Technical compliance is evaluated by the offeror’s statement that all items meet the required specifications. See 52.212-2 herein.
NOTE 5: Utilize the pages in this solicitation to list all unit prices, extended prices. Each Item No. or CLIN must be filled out. Company quote forms may be used but not substituted for completed solicitation/amendment pages.
NOTE 6: If you cannot meet the requested delivery date / Period of Performance (POP), line through and replace with your availability. All line items must state the unit price and extended price. Quote quantities as stated in this
RFQ.
NOTE 7: Company quote forms may be provided but not substituted for completed solicitation/amendment pages.
The Government terms and conditions (T&C’s) listed in this solicitation are required by law through the Federal Acquisition Regulations (FAR) and the Department of Defense FAR Supplement (DFARS). It is preferred that company T&C’s not be included with your quote submittal as many company T&C’s are inconsistent with federal law and unenforceable.
NOTE 8: Offers shall be FOB Destination pricing to Keyport, WA 98345.
NOTE 9: Due to the size of this RFQ the Government prefers that submission be electronically by email.
NOTE 10: Failure to provide all required information from this solicitation and any subsequent amendment(s) may deem your company to be considered non-responsive.
NOTE 11: COMPLIANCE WITH SPECIFICATIONS
In order to ensure compliance with all the specification requirements, the contractor shall indicate in its offer and notify the Government in a cover letter, what specifications, if any; the offeror does not intend to meet. The offeror shall explain, in detail, how any proposed deviation/exception will nonetheless meet the Government's functional requirements. Should descriptive literature be supplied by the offeror, it will be presumed that the offeror intends to meet all of the specifications, regardless of the descriptive literature, unless the offeror specifically notes its exceptions.
It shall be the obligation of the contractor to exercise due diligence to discover and to bring to the attention of the contracting officer at the earliest possible time, in writing, any ambiguities, discrepancies, inconsistencies, or conflicts in or between the specifications and the applicable drawings or other documents incorporated by reference herein. Failure to comply with such obligation shall be deemed a waiver and release of any and all claims for extra costs or delays arising out of such ambiguities, discrepancies, inconsistencies, and conflicts.
NOTE 12: Performance under this contract requires the contractor to adhere to Operations Security (OPSEC) requirements. Explanation of these requirements is detailed in Section I of the Operations Security Guide for Defense Contractors available online at:
http://www.navses.navy.mil/Home?WarfareCenters/NUWCKeyport/Resources.aspx; click on OPSEC Guide for Defense Contractors on the right-hand side.
NOTE 13: On-site contractors must comply with NUWC Division, Keyport publication “Safety Requirements for Contractors and Subcontractors” and NUWC Division, Keyport publication “Contractor’s Guide to Environmental Compliance”. Both documents are incorporated in full by reference and are available at:
http://www.navsea.navy.mil/Home/WarfareCenters/NUWCKeyport/Resources.aspx; click on Environmental Policy & Documents.
NOTE 14: ARMS EXPORT CONTROL DRAWINGS
Restricted Drawings and Technical Information are only available by accessing Federal Business Opportunities (FBO). Registration instructions and Vendor Guide books can be found on the FBO homepage https://www.fbo.gov.
Drawings referenced in this solicitation are restricted by the Arms Export Control Act and are ONLY available to vendors/contractors appointed Data Custodians that are registered with Defense Logistics Information Service (DLIS) Joint Certification Program (JCP). Vendor’s/Contractor’s Data Custodian’s that are not registered with DLIS JCP can obtain registration information at http://www.dla.mil/HQ/InformationOperations/Offers/Products/LogisticsApplications/JCP.aspx or by phone at 888- 352-9333.
Drawings for this solicitation have been posted to the FBO website: https://www.fbo.gov. Bidders who have registered with FBO and have registered in DLIS JCP can access this data under solicitation number:
STATEMENT OF WORK
STATEMENT OF WORK
Subject: Collaborative Test and Evaluation Center (CTEC) Video Wall
Background:
CTEC supports a variety of missions for Naval Undersea Warfare Center and requires a video display and distribution system to more effectively manage operations. Upgrades to CTEC are necessary to allow real-time analysis of operations.
Installation Location:
Installation of LAN systems will be performed in the CTEC at Naval Undersea Warfare Center (NUWC) Division Keyport, Keyport, WA.
1. SCOPE:
This work requirement includes: Site Survey, system design, material purchase, installation, operational tests, desired one (1) year warranty of workmanship and materials, and to provide "as built" drawings for system installation.
2. REFERENCES:
2.1 Operations Security (OPSEC) Guide for Defense Contractors (Rev-B 5/1/2016)
3. REQUIREMENTS:
3.1 The Contractor has the option to perform a site survey of CTEC, BLDG 1074 to determine the necessary effort and materials needed for installation.
3.2 The contract shall provide design and material list to the Technical Point of Contact within two weeks of contract award for review and approval.
3.3 The Contractor shall provide all supplies and materials needed for video wall installation to include trim.
3.4 The Contractor shall perform the installation of video wall per agreed upon design with the following characteristics:
a. Video Wall of minimum 271" x 68"
b. Video Wall shall include rack mountable video processor capable of support a minimum of 8 digital (each input consists of an HDMI & DVI port) and 2 analog video inputs
c. Removed
d. Interface with 5.1 Surround Sound system with inputs from 5 Polycom Vortex EF2280 Digital signal processors utilizing Phoenix-type connectors.
e. Flat screen
f. Gaps between monitors shall not exceed 2 mm
g. No wireless capability or permanently disable wireless capability
h. No "SMART" technology or permanently disabled "SMART" technology
i. The video wall shall incorporate multiple display arrays with the capability to display computer signals at a minimum of up to 1920 X 1200 and High Definition 1080p (HD) per monitor and Must be LED or OLED with an aspect ratio of 16:9
j. Must run natively on WIN10, 64 bit.
k. The video wall and processor shall be capable of dynamically balancing color and brightness between all the display units.
l. The video wall components shall be configured for easily accessible from access for maintenance and troubleshooting.
3.5 The Contractor shall perform all work necessary to ensure system operates per design and integrates with current systems.
3.6 The Contractor shall adhere to OPSEC requirements in accordance with reference 2.1.
3.7 The Contractor shall generate one set of “As-Built” drawings of installed video wall system.
3.8 The Contractor shall provide one-time training for up to 8 primary Government operators.
3.9 The Contractor shall provide a desired one (1) year warranty of workmanship and materials to include technical assistance.
4. ACCEPTANCE
4.1 Post installation government acceptance will occur after the Contractor demonstrates that each system is functioning properly per design.
(End of Summary of Changes)