20RJM40_SOL_0001_att1.pdf
PDF 394 KB Posted
- Attached to
- REGENERATIVE BATTERY TEST SYSTEM
- Solicitation number
- N0016420RJM40
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20RJM40_SOL_0003.pdf | ||
| 20RJM40_sol_0002_att1.pdf | ||
| 20RJM40_sol_0002.pdf | ||
| 20RJM40_SOL_0001.pdf | ||
| 20RJM40_SOL_att1.zip | ZIP file | |
| 20RJM40_SOL.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 3
1. Question:
In regards to the technical requirement of paragraph 1.1 of the SOW in solicitation N0016420RJM40, is the battery to be tested going to be a single battery pack made up of 40-48 cells, or is it 40-48 individual battery cells that will need to be tested simultaneously? In other words, will the test system need to consist of just a single test channel or 48 separate test channels?
Answer:
The battery to be tested is going to be a single battery pack made up of 40-48 cells. The Battery Test System needs to consist of just a single test channel.
2. Question:
The pre-solicitation (back in May timeframe) stated 270 Calendar days after receipt of funded order.
I now see 154 days in the more recent solicitation.
Can you confirm if this change was made appropriately, and if so, for what reason this deadline has been changed?
Answer:
The solicitation has been changed from 154 days to 270 Calender days after receipt of funded order to be in accordance with the synopsis.