Attachment_4_GRSP_FY_15_CDRLs_.docx
DOCX document 244 KB Posted
- Attached to
- Ground Range Sustainment Program Federal contract opportunity
- Solicitation number
- M67854-15-R-7818
- Issued by
- United States Marine Corps
About this file
Attachment 4 GRSP FY 15_CDRLs_
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 15-R-7818_combined_solicitation_and_synopsis_amend_01.doc | DOC document | |
| Attachment_3_GRSP_QASP.doc | DOC document | |
| 15-R-7818_combined_solicitation_and_synopsis.doc | DOC document | |
| Attachment_5_Sole_Source_Justification_for_Simplified_Aquisition_redacted.doc | DOC document | |
| Attachment_6c_WD_05-2473_Rev-18_Beaufort_SC_7.8.2015.pdf | ||
| Attachment_6a_WD_05-2057_Rev-17_San_Diego_CA_CPCA_7.8.2015.pdf | ||
| Attachment_2_GRSP_SPEC_1.2.docx | DOCX document | |
| Attachment_6b_WD_05-2393_Rev-17_Onslow_NC_CLNC_7.8.2015.pdf | ||
| Attachment_1_GRSP_PWS.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST (CDRL)
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
NSP
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
GROUND RANGE SUSTAINMENT PROGRAM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
TBD
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
SITE SURVEY REPORT
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-81381
5. CONTRACT REFERENCE
PWS PARAGRAPH 3.5, 4.2, 9
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
SEE BLK 16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
AD
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Draft Final
| Reg |
| Repo |
16. REMARKS
1 BLK 9 - THE FOLLOWING INFORMATION SHALL BE INCLUDED ON THE DELIVERABLE:
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 –
THE CONTRACTOR SHALL SUBMIT THE SITE SURVEY REPORT NO LATER THAN 10 WORKING DAYS AFTER THE CONCLUSION OF THE SITE SURVEY THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. THE CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
4. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
5. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
ROBERT PLATT, SYSTEMS ENGINEER
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
22 Jun 15
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A002
2. TITLE OF DATA ITEM
TEST/INSPECTION REPORT
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-80809B
5. CONTRACT REFERENCE
PWS PARAGRAPH 5.7.4, 9
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 – TEST/INSPECTION REPORTS SHALL BE SUBMITTED FOR EACH TEST EVENT (INCLUDING GOVERNMENT FINAL INSPECTION).
THE FINAL TEST/INSPECTION REPORT SHALL BE SUBMITTED WITHIN TEN (10) WORKING DAYS OF THE CONCLUSION OF EACH TEST EVENT.
THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. THE CONTRACTOR SHALL SUBMIT CORRECTED SUBMISSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
3. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT. |
4. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A003
2. TITLE OF DATA ITEM
TECHNICAL REPORT/STUDY SERVICES - RTM
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
PWS PARAGRAPH 5.3, 9
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 – FOR EACH DELIVERY ORDER, THE CONTRACTOR SHALL SUBMIT THE DOCUMENT PRIOR TO THE FOLLOWING TECHNICAL REVIEWS: SYSTEM REQUIREMENTS REVIEW (SRR) (10 WORKING DAYS), CRITICAL DESIGN REVIEW (CDR) (15 WORKING DAYS), AND TEST READINESS REVIEW (TRR) (15 WORKING DAYS).
THE GOVERNMENT SHALL HAVE 15 WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. THE CONTRACTOR SHALL SUBMIT CORRECTED VERSION 5 WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
4. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
4. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A004
2. TITLE OF DATA ITEM
TEST PROCEDURE
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-80603A
5. CONTRACT REFERENCE
PWS PARAGRAPH 5.7.5
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 –
FOR EACH TEST EVENT, THE CONTRACTOR SHALL SUBMIT THE TEST PROCEDURES FIFTEEN (15) WORKING DAYS PRIOR TO THE FOLLOWING TECHNICAL REVIEWS:
| A. DRAFT VERSION SHALL BE SUBMITTED FOR THE CRITICAL DESIGN REVIEW | (CDR) |
| B. FINAL VERSION SHALL BE SUBMITTED FOR THE TEST READINESS REVIEW (TRR) |
THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. THE CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
4. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
5. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A005
2. TITLE OF DATA ITEM
TEST PLAN
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI-80566A
5. CONTRACT REFERENCE
SOW PARAGRAPH 5.7.5
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 – DRAFT SUBMISSION SHALL BE 15 WORKING DAYS PRIOR TO PDR. UPDATED SUBMISSION SHALL BE 15 WORKING DAYS PRIOR TO CDR. UPDATED SUBMISSION SHALL BE 15 WORKING DAYS PRIOR TO TRR. ADDITIONAL SUBMISSIONS AS DEEMED NECESSARY.
3. BLK 13 - THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
4. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
5. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A006
2. TITLE OF DATA ITEM
SAFETY ASSESSMENT REPORT
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-SAFT-80102B
5. CONTRACT REFERENCE
SOW PARAGRAPH 6.1.1.1
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. SHALL BE COMPLETED IN ACCORDANCE WITH MIL-STD-882E TASK #301.
3. SHALL INCLUDE RESULTS OF SAFETY AND HEALTH HAZARDS ANALYSES PER MIL-STD-882E TASKS #205, #206, #207, AND #210.
4. SHALL INCLUDE CONSIDERATIONS FOR HUMAN ENGINEERING PER MIL-STD-1472G.
5. BLKS 10 AND 12. FIRST SUBMISSION SHALL BE SUBMITTED 30 DAYS AFTER THE PAC. FINAL SUBMISSION SHALL BE 15 WORKING DAYS PRIOR TO CDR. ADDITIONAL SUBMISSIONS AS DEEMED NECESSARY.
6. BLK 13. THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION. IF REQUIRED, CONTRACTOR SHALL HAVE FIVE (5) WORKING DAYS TO RESUBMIT AFTER RECEIPT OF GOVERNMENT COMMENTS.
7. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
8. THE CONTRACTOR SHALL INCLUDE THE FOLLOWING ITEMS IN THE SAR: MCAS BEAUFORT PISTOL RANGE, BLEACHERS, LWNLFS, MPTS. SESAMS KITS, AND TARGET TURNING SYSTEM.
9. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A007
2. TITLE OF DATA ITEM
TECHNICAL REPORT/STUDY SERVICES – LITHIUM BATTERY SAFETY REPORT
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
SOW PARAGRAPH 5.5.1, 6.1.2
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 – FOR EACH DELIVERY ORDER, THE CONTRACTOR SHALL SUBMIT THE LITHIUM SAFETY REPORT PRIOR TO THE FOLLOWING TECHNICAL REVIEWS:
| A. DRAFT VERSION SHALL BE SUBMITTED 30 WORKING DAYS AFTER THE PAC. |
| B. FINAL VERSION SHALL BE SUBMITTED 15 WORKING DAYS PRIOR TO THE CRITICAL |
| DESIGN REVIEW (CDR) |
THE GOVERNMENT SHALL HAVE 15 WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
3. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
4. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A008
2. TITLE OF DATA ITEM
TECHNICAL REPORT/STUDY SERVICES - EL-CID
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
SOW PARAGRAPH 5.4.1, 5.5.1, 6.2.1
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 – FOR EACH DELIVERY ORDER, THE CONTRACTOR SHALL SUBMIT THE DOCUMENTS PRIOR TO THE FOLLOWING TECHNICAL REVIEWS:
| A. SYSTEMS REQUIREMENTS REVIEW (SRR) (10 WORKING DAYS) |
| B. PRELIMINARY DESIGN REVIEW (PDR) (15 WORKING DAYS) |
| C. FINAL VERSION SHALL BE SUBMITTED FOR THE CRITICAL DESIGN REVIEW (CDR) |
| (15 WORKING DAYS) |
THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
3. BLK 14. REPRODUCIBLE SHALL BE DELIVERED AS AN ELECTRONIC COPY, IN THE EL-CID TOOL DATABASE FORMAT
4. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER ENGINEERING DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
A009
2. TITLE OF DATA ITEM
TECHNICAL REPORT/STUDY SERVICES – CORROSION PREVENTION PLAN
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
SOW PARAGRAPH 5.5.1
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 – SUBMISSIONS SHALL OCCUR FOR EACH DELIVERY ORDER. DRAFT SUBMISSION SHALL BE DUE 15 WORKING DAYS PRIOR TO PDR. FINAL SUBMISSION SHALL BE 15 WORKING DAYS PRIOR TO CDR. ADDITIONAL SUBMISSIONS AS DEEMED NECESSARY.
THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
3. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
4. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
SCOTT SZURGOT, CHIEF ENGINEER, INSTR
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
B
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER PROGRAM MANAGEMENT |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
B001
2. TITLE OF DATA ITEM
AGENDA
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMN-81249A
5. CONTRACT REFERENCE
SOW PARAGRAPH 5
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 12&13 – CONTRACTOR SUBMISSIONS SHALL BE DUE TO THE GOVERNMENT 15 DAYS PRIOR TO ALL TECHNICAL REVIEWS (SRR, CDR, TRR) AND 10 DAYS PRIOR TO ALL OTHER SCHEDULED IPT MEETINGS, REVIEWS, AND CONFERENCES.
3. THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
4. BLK 14- REPRODUCIBLE SHALL BE DELIVERED ON AN ELECTRONIC FORMAT, IN MICROSOFT WORD COMPATIBLE FORMAT. GRAPHICS SUCH AS FIGURES, TABLES, CHARTS, DRAWINGS, ETC. SHALL BE COMPATIBLE WITH MICROSOFT OFFICE.
5. BLK 4 – PREPARATION INSTRUCTIONS PARA. H, DELETE: “CHAIRPERSON, CO-CHAIR, AND SUBCOMMITTEE CHAIRS” INSERT CHANGE: “PARTICIPANTS”.
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
JIM MURNAN, PJM
H. DATE
17 Jun 2015
I. APPROVED BY
JIM MURNAN, PJM
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
B
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER PROGRAM MANAGEMENT |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
B002
2. TITLE OF DATA ITEM
MINUTES
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMN-81250A
5. CONTRACT REFERENCE
SOW PARAGRAPH 5
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10 - CONTRACTOR SUBMISSIONS SHALL BE DUE TO THE GOVERNMENT 5 DAYS AFTER THE CONCLUSION OF ALL IPT MEETINGS, REVIEWS, AND CONFERENCES. CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
3. THE GOVERNMENT SHALL HAVE 5 DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION.
4. BLK 14- REPRODUCIBLE SHALL BE DELIVERED VIA EMAIL, IN MICROSOFT WORD COMPATIBLE FORMAT. GRAPHICS SUCH AS FIGURES, TABLES, CHARTS, DRAWINGS, ETC. SHALL BE COMPATIBLE WITH MICROSOFT WORD.
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
JIM MURNAN, PJM
J. DATE
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
B
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER PROGRAM MANAGEMENT |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
B003
2. TITLE OF DATA ITEM
INTEGRATED MASTER SCHEDULE (IMS)
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81650
5. CONTRACT REFERENCE
SOW PARAGRAPH 5.2
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ & MNTHLY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 12- 30 DAYS AFTER CONTRACT AWARD. THE GOVERNMENT WILL HAVE 15 DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION.
2. BLK 14- IMS SHALL BE DELIVERED VIA EMAIL TO PM TRASYS IN MICROSOFT PROJECT 2003 FORMAT. EMAIL SHOULD BE ADDRESSED TO GOVERNMENT PROJECT OFFICER AND THE PMTRASYS LTS SCHEDULER
3. THE GOVERNMENT HAS RESERVED MICROSOFT PROJECT 2003 TEXT FIELDS 1-9 AND 11-15
AND FLAG FIELD 1-5 FOR INTERNAL GOVERNMENT USE. THE CONTRACTOR SHALL LEAVE RESERVE FIELDS BLANK.
4. THE CONTRACTOR SHALL ASSIGN A SINGLE POINT OF CONTACT FOR EACH TASK IN THE SCHEDULE. THE POINT OF CONTACT'S FIRST AND LAST NAME SHALL BE ENTERED INTO THE MICROSOFT PROJECT 2003 TEXT FIELD 10 FOR EACH TASK.
6. BLK 13. SECOND SUBMISSION IS REQUIRED FIVE DAYS IF/OR AFTER FIRST SUBMISSION IS REJECTED.
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| PMTRASYS SCHEDULER |
| 1 |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 3 |
| 5 |
| 0 |
G. PREPARED BY
H. DATE
17 Jun 2015
I. APPROVED BY
JIM MURNAN, PJM
J. DATE
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| NSP |
| A |
| TDP ____ |
| TM _____ |
| OTHER LOGISTICS |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
| RANGE TRAINING SYSTEM |
| M67854-15-C-7818 |
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| C001 |
| Logistics Product Data |
| Logistics Product Data |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-ALSS-81529 |
| 7.2.4 |
| PM TRASYS |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| SEE BLK 16 |
| SEE BLK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| C |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
| Draft |
| Final |
AD
| N/A |
| SEE BLK 16 |
| Reg |
| Repro |
| 16. REMARKS |
| PM TRASYS PJM |
| 0 |
| 1 |
| 1 |
| 1. | THIS IS TIER 1 DELIVERY ORDER SPECIFIC DATA | |
| 2. | BLK 9 - THE FOLLOWING INFORMATION SHALL BE INCLUDED ON THE DELIVERABLE: |
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
| 3. | INITIAL DOCUMENT OUTLINE SHALL BE DELIVERED 7 WORKING DAYS AFTER CONTRACT AWARD |
| 4. | THE REVISION SHALL BE DUE 15 WORKING DAYS BEFORE CDR |
| 5. | NEXT SUBMISSION SHALL BE DUE 7 WORKING DAYS BEFORE TRR |
| 6. | FINAL SUBMISSION SHALL BE DUE AT GFI |
| 7. | THE GOVERNMENT SHALL HAVE 5 WORKING DAYS AFTER GFI FOR REVIEW AND ACCEPTANCE / REJECTION FINAL SUBMSSION |
| 8. | ALL DOCUMENTS AND ASSOCIATED SUPPLEMENTAL DATA SHALL BE DELIVERED IN ELECTRONIC MEDIA USING MICROSOFT OFFICE AND ADOBE PDF FORMAT |
| 9. | COMPLETE THE FOLLOWING GOVERNMENT PROVIDED LMI DATA FIELDS: |
PART NUMBER, CAGE, SERIAL NUMBER, NOMENCLATURE, UNIT OF MEASURE, UNIT PRICE, QUANTITY, QUANTITY PER END ITEM, WARRANTY, AND MEAN TIME BETWEEN FAILURE
10. PLEASE REFER TO APPENDIX B
PM TRASYS PCO
| 0 |
| 1 |
| 1 |
| PM TRASYS LOGISTICS |
| 1 |
| 1 |
| 1 |
| MCB DELIVERY LOCATION |
| 0 |
| 0 |
| 1 |
| PM TRASYS ENGINEERING |
| 0 |
| 1 |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 4 |
| 5 |
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
| JANIS BRIDGES, LOGISTICS |
| 23 Jun 2015 |
| JANIS BRIDGES |
Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| NSP |
| A |
| TDP ____ |
| TM _____ |
| OTHER LOGISTICS |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
| RANGE TRAINING SYSTEM |
| M67854-15-C-7818 |
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| C002 |
| COMMERCIAL OFF-THE-SHELF (COTS) MANUAL AND ASSOCIATED SUPPLEMENTAL DATA |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI TMSS 80527C |
| PWS Paragraph 7, 7.2 |
| PM TRASYS |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| SEE BLK 16 |
| SEE BLK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| C |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
| Draft |
| Final |
| N/A |
| SEE BLK 16 |
| Reg |
| Repro |
| 16. REMARKS |
| PM TRASYS PJM |
| 0 |
| 1 |
| 1 |
1. THIS IS TIER 1 DELIVERY ORDER SPECIFIC DATA
2. BLK 9 - THE FOLLOWING INFORMATION SHALL BE INCLUDED ON THE DELIVERABLE:
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
3. THE FIRST SUBMSSION SHALL BE DUE 5 WORKING DAYS BEFORE SRR
4. THE REVISION SUBMISSION SHALL BE DUE 10 WORKING DAYS BEFORE CDR
5. THE FINAL SUBMISSION SHALL BE DUE AT GFI
6. THE GOVERNMENT SHALL HAVE 10 WORKING DAYS AFTER GFI FOR REVIEW AND ACCEPTANCE/REJECTION
7. ALL DOCUMENTS AND ASSOCIATED SUPPLEMENTAL DATA SHALL BE DELIVERED TO THE SITES WITHIN 30 DAYS OF GOVERNMENT ACCEPTANCE
| PM TRASYS PCO |
| 0 |
| 1 |
| 1 |
| PM TRASYS LOGISTICS |
| 1 |
| 1 |
| 1 |
| MCB DELIVERY LOCATION |
| 0 |
| 0 |
| 1 |
| PM TRASYS ENGINEERING |
| 1 |
| 1 |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 5 |
| 5 |
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
| JANIS BRIDGES, LOGISTICS |
| 23 Jun 2015 |
| JANIS BRIDGES |
| 23 Jun 2015 |
CONTRACT DATA REQUIREMENTS LIST (CDRL)
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
F
| C. CATEGORY: | ||||
| TDP | TM | _ | OTHER LOGISTICS DATA |
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
M67854-15-C-7818
F. CONTRACTOR
1. DATA ITEM NO.
F001
2. TITLE OF DATA ITEM
TRAINING MATERIALS - NET
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-ILSS-80872
5. CONTRACT REFERENCE
SOW PARAGRAPH 7, 7.2.3
6. REQUIRING OFFICE
PM TRASYS
18. ESTIMATED TOTAL PRICE
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
b. COPIES
8. APP CODE
11. AS OF DATE
N/A
13. DATE IF SUBSEQUENT SUBM.
Final
| Reg |
| Repo |
16. REMARKS
1. 1 BLK 9 - THE FOLLOWING INFORMATION SHALL BE INCLUDED ON THE DELIVERABLE:
DISTRIBUTION STATEMENT C: DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT AGENCIES AND THEIR CONTRACTORS, CRITICAL TECHNOLOGY, 26JUL11. OTHER REQUESTS FOR THIS DOCUMENT SHALL BE REFERRED TO COMMANDER, MARINE CORPS SYSTEMS COMMAND (ATTN: PDM RANGE TRAINING SYSTEMS), 12211 SCIENCE DRIVE, ORLANDO, FL 32826
2. BLK 10, 12, 13 – SUBMISSIONS SHALL OCCUR FOR EACH DELIVERY ORDER. DRAFT SUBMISSION SHALL BE DUE 30 WORKING DAYS AFTER TO SRR. FINAL SUBMISSION SHALL BE 15 WORKING DAYS PRIOR TO CDR. ADDITIONAL SUBMISSIONS AS DEEMED NECESSARY.
THE GOVERNMENT SHALL HAVE FIFTEEN (15) WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION OF EACH SUBMISSION. CONTRACTOR SHALL SUBMIT CORRECTED VERSION FIVE (5) WORKING DAYS AFTER RECEIPT OF GOVERNMENT COMMENTS.
3. BLK 14. REPRODUCIBLE SHALL -
| A. BE DELIVERED ON A CD-ROM OR AS AN ELECTRONIC COPY. | |
| B. BE DELIVERED IN BOTH - | |
| I - MICROSOFT OFFICE 2007 OR EQUIVALENT FORMAT; AND | |
| II - PDF FORMAT |
4. AT THE TIME OF DELIVERY, THE CONTRACTOR SHALL NOTIFY THE GOVERNMENT OF THE DELIVERY VIA E-MAIL. THE NOTIFICATION E-MAIL SHALL BE ADDRESSED TO THE CONTRACTING OFFICER, THE PROJECT OFFICER, THE SYSTEMS ENGINEER AND OTHERS AS INDICATED IN BLOCK 14 (“DISTRIBUTION”).
| PMTRASYS ENGINEERING |
| 1 |
| 1 |
| PMTRASYS PCO |
| LTR |
| 1 |
| PMTRASYS ILSM |
| 1 |
| 1 |
| PMTRASYS PJM |
| LTR |
| 1 |
| 15. TOTAL ▬▬▬▬► |
| 2 |
| 4 |
| 0 |
G. PREPARED BY
JANIS BRIDGES, LOGISTICS
H. DATE
17 JUN 2015
I. APPROVED BY
JANIS BRIDGES
J. DATE
17 JUN 2015
File details come from the government source that posted it. Updated .