M6700419R0007_Questions_and_Answers.docx

DOCX document 29 KB Posted

Attached to
Intermediate Depot Level Maintenance Services (IDLMS)
Solicitation number
M6700419R0007
Issued by

About this file

Revision 1 Q&A

View the file

Other files

File Type Posted
M6700419R0007_Questions_and_Answers.docx DOCX document
Wage_Determination_15-4539.txt TXT text file
M6700419R0007_Questions_and_Answers.docx DOCX document
M6700419R0007_Site_Vist_12-17-18_MFR.pdf PDF
M6700419R0007_RFP.doc.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M6700419R0007

GOVERNMENT RESPONSES TO VENDOR SUBMITTED QUESTIONS

1. Question: Paragraph 3.1.6.1.20 states, "…remove blast grit from Void #1." Paragraph 3.1.6.1.23 states, "Remove blast grit from Void #4." However, there is no interior blasting requirement specified for that module or any of the modules throughout the SOW.

Please clarify the removal of blast grit from Void #1 and #4.

Likewise please address the similar reference to blast grit removal in paragraphs;

4.1.7.1.21 4.2.5.1.20 5.1.5.1.23

Government Response: The requirement to remove blast grit from the identified spaces is for Blast grit contamination from a previous overhaul that was not removed. In some cases the blast grit is loose and can be swept out and in other cases the blast grit has gotten wet and has solidified and must be scraped out prior to touch up painting/cleaning. The wet blast grit has caused staining to the coating system.