Lime Silo Refurbishment - Invitation to Bid Summary
This is an Invitation to Bid (ITB 26-26) issued by the City of Bartow, Florida for the refurbishment of the Lime Silo at the Water Department located at 2500 Highway 17N, Bartow, FL 33830. The project scope includes repairs to exterior metal panels, interior bands, metal doorframes and doors, along with all associated painting, delivered as a turnkey solution. The contractor must obtain all necessary materials, equipment, and building permits. The bid was released on July 28, 2026, with a question submission deadline of August 11, 2026 at 4:00 PM and bid submissions due on August 19, 2026 at 2:00 PM. Bids may be submitted in person at 450 N. Wilson Ave., Bartow, FL 33830 or via teleconference. The contract time is 120 calendar days total, consisting of 90 calendar days from Notice to Proceed to Substantial Completion and 30 calendar days from Substantial Completion to Final Completion. The City will conduct a pre-construction conference with the successful bidder, City representatives, the Professional, and other relevant parties prior to work commencement.
Bidders must meet minimum qualifications including two years of operation under the same name and TIN/FEIN number, a valid Florida Certified General Contractor license or equivalent authorization, current AWS D1.1-compliant welder certifications, OSHA-compliant confined-space training for applicable personnel, and employment of a Florida Licensed Structural Engineer. Contractors must maintain a corporate safety program and AMPP-certified coating applicators and inspectors, and provide three references documenting similar structural steel rehabilitation projects completed within five years. A Bid Bond is required for all bids exceeding $150,000 (not to exceed 5% of the preliminary estimate), and a Performance Bond and Payment Bond are required for contracts exceeding $250,000 in an amount equal to the awarded contract price. The City of Bartow is exempt from state and federal sales and use taxes; accordingly, no taxes shall be included in bid prices. All prices are firm for the contract duration, and the City retains the right to reject any and all bids or award based on the Base Bid, Base Bid plus selected alternates, or any combination deemed in the City's best interest. All contractors must comply with OSHA regulations, Florida Statute 553.60 (Trench Safety Act), and maintain specified insurance coverage including Workers' Compensation, Commercial General Liability, and Commercial Automobile Liability.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For more information, please visit our online supplier portal, located at https://procurement.opengov.com/portal/bartowfl
City of Bartow, FL
Invitation to Bid
Lime Silo Refurbishment Project ID: ITB 26-26
RELEASE DATE: July 28, 2026
RESPONSE DEADLINE: August 19, 2026, 2:00 pm
Please refer to the project timeline in this document for all important deadlines.
#ITB 26-26
Title: Lime Silo Refurbishment
Table Of Contents
1. INTRODUCTION AND BACKGROUND INFORMATION
2. INSTRUCTIONS TO BIDDERS - CONSTRUCTION
3. FOR SEALED HARD COPY SUBMISSION ONLY: ADDRESS LABELS
4. SCOPE OF WORK
5. STANDARD TERMS AND GENERAL CONDITIONS
6. PRICING TABLE
7. SPECIAL CONDITIONS
8. VENDOR SUBMITTAL FORMS
Attachments:
A - Appendix A - Specifications Lime Silo Refurbishment
B - Appendix B - Lime Silo Inspection Report
C - Appendix C- Divider
D - Appendix D - Lime Storage Silo (Leg Support Type) and Accesory Equipment
E - Appendix E- Lime Feed Facility Site Key Plan
SECTION 1: INTRODUCTION AND BACKGROUND INFORMATION
1.1. Purpose of Solicitation
The City of Bartow is seeking bids from qualified and experienced contractors to provide all necessary labor, materials, equipment, supplies, and supervision to complete the refurbishment of the Lime Silo at the Water Department located at 2500 Highway 17N, Bartow, FL 33830. The scope includes repairs to exterior metal panels, interior bands, metal doorframes and doors, along with all associated painting.
The project requires a contractor capable of delivering a turnkey solution that includes obtaining necessary materials, equipment, and building permits. The selected contractor must ensure timely and efficient completion while maintaining strict safety standards, adhering to all engineering specifications, and assuming full responsibility for site maintenance and restoration.
1.2. City Background Information
The Lime Silo is an essential component of the City’s water treatment processes, and its exterior and interior structural elements have reached a point where refurbishment is necessary. This project is intended to restore the silo’s integrity through repairs to metal panels, interior bands, doorframes, and doors, as well as protective painting and related improvements. The work will help maintain proper system performance, extend the lifespan of the structure, and ensure continued compliance with safety and operational standards.
SECTION 2: INSTRUCTIONS TO BIDDERS - CONSTRUCTION
2.1. Bid Schedule
ITB-CON Solicitation Issued: July 28, 2026
Question Submission Deadline: August 11, 2026, 4:00pm
Bids Due: August 19, 2026, 2:00pm
In person: 450 N. Wilson Ave., Bartow, FL 33830 or via Teleconference at +1 872-256-4257,,312519811#
2.2. Bid Opening
It is the responsibility of the bidder to assure that their bid is delivered or submitted at the proper time and place prior to the bid opening. All bid openings shall be public, following 2:00 pm, on the date specified in the solicitation. Bids which for any reason are not so delivered or submitted electronically through the City’s e-procurement system, will not be considered. Bid Submittals Using
Facsimile or Email Will Not Be Accepted.
Note: In accordance with Florida Statute 119.071, a listing of vendors that provided a bid submittal shall be posted to the City’s e-procurement platform OpenGov.
All bids shall remain exempt from disclosure, including bid amounts, until recommendation of award or 30 days after bid opening, whichever event occurs first. Should the City reject all bids, before the recommendation of award or 30 days after bid opening, and concurrently provide notice of the City’s intent to reissue the bid, the rejected bids will remain exempt from
Florida Statute 119.07 until such time as the City provides notice of recommendation of award of the reissued bid or until the
City withdraws the reissued bid. The bid is not exempt for longer than 12 months after the notice of rejection of all bids.
2.3. Recommendations of Award
A bid may be recommended for award by the Financial Services Manger to the lowest responsive and responsible Bidder, provided that Bidder’s bid submittal is considered (within the sole discretion of said Manager) reasonable, in the best interest of City to recommend, and no bid protest has been filed. Unless otherwise noted, the basis of recommendation will either be the Base Bid, the
Base Bid plus all alternates or any combination thereof, whichever is in the best interest of the City or may be determined by the availability of funds. Should the basis of award be the Base Bid plus selected alternates, the priority of the selection of those alternates will be set forth in the Supplementary Conditions, if applicable.
The successful Bidder to whom a bid is recommended for award will be so notified by City staff. The Financial Services Manager, however, at their sole discretion, reserves the right to reject any and all bid submittals or to waive any informality concerning the bid submittal whenever such rejection or waiver is in the best interest of the City. The Financial Services Manager, likewise, reserves the right to reject the bid submittal of any Bidder who has previously failed to perform properly or to complete on time, contracts of a similar nature; or who is not in a position to perform the contract; or who has habitually and without just cause neglected the payment of bills or otherwise disregarded its obligations to subcontractors, materialmen or employees.
2.4. Execution of Bid
Bid must contain an original signature of an authorized representative in the space provided on the signature page. Bid must be typed or printed in black ink. Erasable ink is not permitted. Corrections made by the bidder to any bid entry must be initialed by the person who signs the bid.
2.5. Bid Submittals
Submittal may be withdrawn by notifying the City, in writing, at any time prior to the deadline for bid submittal. After the deadline, the bids become a record of the City and will not be returned to the Contractor unless the bid is cancelled. It is the responsibility of the
Contractor to make a written request for return of the Bid Submittal after notification of cancellation. Absent this written request, the
City shall destroy the submittal. Negligence on the part of the Contractor in preparing their Bid Submittal confers no right of withdrawal or modification of their Bid Submittal after such Bid Submittal has been opened by City Staff at the appointed time and place. Bid Submittals and any bid security shall be in force for a period of not less than ninety (90) calendar days after the bid opening time.
At the time and place specified for the opening of Bid Submittals (see above), every Bid Submittal properly delivered within the time specified for receiving Bid Submittals will be opened and publicly read aloud, irrespective of any irregularities found therein. Bidders and other people interested may be present or represented.
2.6. Bid Submittal -Exhibits & Forms
Supplementary Conditions, Special Conditions, Plans, Drawings, Instructions to Bidders, the Conditions of the Contract, Exhibits, the
Bid Submittal, Technical Specifications, any resulting addenda issued, and the Contract together therein identified constitute the entire
“bid package” and upon award shall constitute the Contract Documents concerning this present bid matter.
The following documents, collectively, comprise the “Bid Submittal” which, when tendered, on or before the Bid due date and time, must include:
• Bid Sheet(s) o Bid pricing must be submitted through the City’s e-procurement system, OpenGov. A printed copy may also be included with the physical bid submission, if applicable. Contractors shall not deviate from the Pricing Table unless expressly authorized by the City of Bartow Procurement Contact. Any unauthorized deviation from the provided Pricing Table may result in the bid being deemed non-responsive.
• With the signature of an authorized representative of the company or their designee, all information requested below shall be uploaded and submitted with your bid in accordance with the requirements of this bid/project (Contractors are to
Refer to Section 8: Vendor Submittal Forms):
o Bidder Incorporation Information o Reference Form o Acknowledgement Form o Exhibit I – Bid Bond, when applicable o Exhibit IV – Non-Collusion Affidavit of Prime Bidder.
o Exhibit VI – Affidavit of Percentage of Work (this requirement does not include o Exhibit VI-A – Subcontractor List o Exhibit VI-B – Good Faith Effort Documentation).
o Exhibit VII – Trench Safety Act Compliance o Exhibit VIII – Equal Employment Opportunity o Exhibit IX – Drug-Free Workplace Form o Exhibit X – Safety Requirements/Regulations o Exhibit XVIII – Certificate of Compliance o Exhibit XIX – Affidavit Certification Immigration Laws o Exhibit XX – Contractor Certification regarding Scrutinized Companies List o Exhibit XXI – Certification Regarding Debarment, Suspension, Proposed Debarment, and other Responsibility Matters o Exhibit XXII – Appendix A, 44 C.F.R. Part 18 – Certification Regarding Lobbying o Exhibit XXIII – Employment Eligibility Verification (E-Verify) Certification o Exhibit XXIV – Sworn Statement of Public Entity Crimes o Exhibit XXV – Affidavit Regarding the Use of Coercion for Labor or Services o All additional information requested as a “must” item in any Addendum.
o All corrections made by the Bidder to the Bid Sheets and Acknowledgement Form should be acknowledged by written initials of the authorized representative signing the Bid Submittal or their designee. Should a price correction not be acknowledged, the lowest price will prevail.
2.7. Requested Information by the City (Post Submittal/ Pre-Award)
All additional requested information and Exhibits must be submitted within a reasonable period of time if chosen as the apparent low, responsive and responsible bidder during the Bid Analysis phase. These items include:
• Exhibit II, Public Performance Bond
• Exhibit III, Payment of Bond
• Exhibit V, Non-Collusion Affidavit of Subcontractor
Upon Execution of a Contract (Post Notice to Proceed Forms, when or if applicable):
• Exhibit XI, Application for Payment
• Exhibit XII, Contractor Certification of Disbursement
• Exhibit XIII, Certification of Substantial Completion
• Exhibit XIV, Certification of Final Completion
• Exhibit XV, Materials & Equipment Stored On-site
• Exhibit XVI, Allowance Authorization Release (AAR)
• Exhibit XVII, Change Order
• Sales Tax Saving Form
2.8. F.O.B Destination
All prices covered by this bid/contract will be inclusive of all cost to the jobsite within the City of Bartow, Florida.
2.9. Packaging
All containers shall be suitable for storage or shipment, and all prices should include standard commercial packaging.
2.10. Taxes
No taxes shall be included in any bid price. The City of Bartow is exempt from state and federal sales use and excise tax. If sales taxes are applicable due to third party purchasing, nothing herein shall prohibit the City from deleting line items and purchasing said items directly from a supplier if it is determined that there are sufficient sales tax savings to make purchasing by the City practical.
2.11. Prices
Unless otherwise specified, all prices and/or discounts shall be firm for the duration of the original contract/purchase order. In the event of price decreases the City of Bartow shall be given full proportionate benefits immediately at any time during the contract period.
2.12. Invoices
Any invoices at higher prices than the contract price shall be held until proper credit memorandums have been received. Any applicable cash discounts that apply as the result of this contract shall be taken even though the allowable time has elapsed due to the time awaiting credit memorandums. All original invoices shall be mailed to the City of Bartow, Finance Department at 450 N.
Wilson Ave., Bartow, FL 33830 or they may be emailed to: cbrown.finance@cityofbartow.net. The bidder shall include the bid number and/or the purchase order number on all invoices. By submitting an invoice, Bidder’s Project Manager or any authorized officer is attesting to the correctness and accuracy of all charges. Invoices will be processed for payment when approved by the appropriate User Division/ Department. The City’s payment of an invoice shall not constitute evidence of the City’s acceptance of the
Bidders performance of the Service or the City’s acceptance of any work
2.13. Discounts
Bidders may offer a cash discount for prompt payment (within 30 days); however, such discounts shall not be considered in determining the lowest net cost for bid evaluation purposes. Bidders are encouraged to reflect cash discounts in the prices quoted.
2.14. Manufacturer's Name
Any manufacturer’s name, trade name, brand name, information and catalog numbers used herein are for proposes of description and establishing general quality levels. References are not intended to be restrictive of any products that manufacturer may offer. The determination as to whether any alternate product or service is equal shall be made by the city of Bartow and such determination shall be final and binding among all bidders.
2.15. Safety Requirements / Regulations
All Bidders are required to submit with their Bid Submittal, Exhibit X, Safety Requirements/Regulations which states that if the firm falls under the Occupational Health and Safety Administration (OSHA) Regulations, as interpreted by OSHA, the successful contractor will be able to provide, at the request of the City, a copy of their OSHA 300 Log for the past three (3) years, a copy of the
Workers Compensation Modification Rate; a copy of the Contractor’s Safety and Health Program, and a copy of the Contractor’s
Drug Free Workplace Program. Any questions regarding compliance with this provision shall be directed to The City of Bartow.
The Bidder is hereby notified that if awarded the bid and it involves work such as maintenance, repair, turnaround, renovation, construction or engineering on chlorine disinfection facilities or other covered process(es) must be able to provide, at the request of the City, the following items for review: OSHA 300 Log for past five (5) years, current safety program, training program and experience with other related processes. Documented evidence showing compliance with confined space entry, lockout/tagout, emergency response and safe work is required. All contract workers must comply with the facility’s safe work practices and controls outlined in the facility safety manual and operating procedures.
The Bidder is hereby notified that if awarded the bid they shall be responsible for maintenance of traffic within the limits of the project for the duration of the construction period, including any temporary suspensions of the Work. The Contractor shall construct and maintain detours and provide facilities for access to residences, businesses, etc., along the project. The contractor shall furnish, install and maintain traffic control and safety devices during construction, furnish and install work zone pavement markings for maintenance of traffic in construction areas, and provide any other special requirements for safe and expeditious movement of traffic specified on the plans. Maintenance of Traffic includes all facilities, devices and operations as required for safety and convenience of the public within the work zone. Refer to Florida Department of Transportation’s (FDOT) latest edition of the Standard Specifications for Road and Bridge Construction and the latest version of the Manual on Uniform Traffic Control Devices (MUTCD) for the minimum national standard for traffic control for highway construction, maintenance, and utility operation.
2.16. Toxic Substances
Chapter 442 of the Florida Statue states that manufacturers, importers or distributors of any toxic substance shall prepare and provide each direct purchaser of such toxic substance with Material Safety Data Sheet(s), herein referred to as MSDS, which to the best of the manufacturer’s, importer’s or distributor’s knowledge, is current, accurate and complete based on information then reasonably mailto:cbrown.finance@cityofbartow.net available to the manufacturer, importer or distributor. Upon notification of a new or revised MSDS the manufacturer, importer or distributor, on a timely basis not to exceed three (3) months after notification, shall provide the City with the revised information as it becomes available to the manufacturer, importer or distributor.
Failure to provide the MSDS, when applicable, shall be cause for rejection of bid.
2.17. Liquidated Damages
Bidders are hereby advised that if the Contract documents so indicate, a reasonable amount for liquidated damages may be assessed for Contractor’s failure to meet stated specifications, schedule, or other relevant issues as determined by the City. Information regarding the composition of liquidated damages can be found in the Supplementary Conditions. Liquidated damages are not intended as a penalty.
2.18. Specifications
Any deviations from bid specifications indicated herein shall be clearly stated, otherwise it shall be considered that items offered are in strict compliance with specifications, and the successful bidder shall be held responsible. Deviations shall be explained in detail.
2.19. Standard Basis for Bidding
Where a particular system, product or material is specified by name, it shall be considered as a standard basis for bidding and as the most satisfactory for its particular purpose. Where two or more products, materials or manufacturers are specified by name, each shall be considered as a predetermined equal and acceptable for its particular purpose; and the bidder may use any of the listed items within their bid.
2.20. Approval of Contract
The recommended Bidder will be required to execute the contract documents as outlined in the bid package including, the Public
Construction Bond, all signed exhibits and other required information stated in the supplemental conditions or any addendums. The executed documents should be returned to Procurement within 10 working days of the documents being sent by Procurement to the
Bidder for execution. After the executed documents are received back by Procurement, they will be given to the City Legal
Department for approval to be added to a Board agenda for Board approval and execution by the City Commission for contracts over
100,000.00, if the project was not specifically listed in the approved fiscal year’s budget. If the project was listed it shall be executed by the City Manager.
All contracts are subject to final approval of the City of Bartow Board of City Commissioners or City Manager. Persons or firms which incur expenses or change positions in anticipation of a contract prior to the City’s approval do so at their own risk.
2.21. Security Forfeiture
If after Bidder’s receipt of a notice of recommendation for award the successful Bidder refuses or otherwise neglects to execute and deliver the required Contract documents, including the Public Construction Bond, all signed exhibits, required insurance documents and other required information stated in the supplemental conditions or addendums within a reasonable time, the amount of the
Bidder’s bid security (Bid Bond) may be forfeited and the award rescinded if such action is deemed to be in the best interests of the
City. The Financial Services Manager will make the determination of “a reasonable time”. It is recommended that the executed contract documents be returned to Procurement within 10 working days of the documents being sent by Procurement to the recommended Bidder for execution. No plea of mistake in the bid or misunderstanding of the conditions of forfeiture shall be available to the Bidder for the recovery of their bid security or as a defense to any action based upon the neglect or refusal to execute the required agreement or furnish the required bonds and insurance certification.
2.22. Performance
Efficient service is essential to this contract. Therefore, if determined that the holder of the bid is unable to meet delivery within a reasonable amount of time it may become necessary to make procurement from other bidders or suppliers. This shall be determined by the City of Bartow.
2.23. Conflict of Interest
All bidders must disclose, with their bid, the name of any officer, department head or agent who is also an employee of the City or any of their agencies. Furthermore, all bidders must disclose the name of any City employee who owns, directly or indirectly, any interest of any amount in the bidder’s firms or any of their branches. Award of this bid shall be subject to the provisions of Chapter 112, Florida Statutes.
2.24. Samples
Samples of items, when called for, must be furnished free of expense and may, upon request, be returned at the bidder’s expense. Each individual sample must be labeled with bidder’s name, manufacturer’s brand name and number, bid number and item reference.
Samples of successful bidder’s items may remain on file with the Procurement Department for the term of the contract. Request for return of samples shall be accompanied by instructions, which include shipping authorization and name of carrier, and must be received within ninety (90) days after bid opening date. If instructions are not received within this time, the Procurement Department shall dispose of the samples.
2.25. Inspection, Acceptance and Title
Inspection and acceptance will be at the designated facility unless otherwise indicated. Title and risk of loss or damage to all items shall be the responsibility of the contract supplier until accepted by the City, unless loss or damage results from negligence by the
City.
2.26. Drug-free Workplace
This form shall be included with your bid.
2.27. Bid Protest
Any bidder desiring to file a bid protest, with respect to a recommended award of any bid, shall do so by filing a written protest. The written protest must be in possession of the Procurement Department within three (3) working days of the Notice of Recommended
Award posting date. All bidders who bid will be sent a Notice of Recommended Award, unless only one bid is received. A copy of the bid protest procedures may be obtained from the City of Bartow’s website: https://www.cityofbartow.net/431/Protest-Procedures.
“Failure to Follow Bid Protest Procedure Requirements Within the Time Frames Prescribed Herein as Established by the City of Bartow, Florida Shall Constitute a Waiver of Your Protest and Any Resulting Claim.”
2.28. Code of Ethics
If any bidder violates or is a party to a violation of the code of ethics of the City of Bartow or the State of Florida, with respect to this bid, such bidder may be disqualified from performing the work described in this bid or from furnishing the goods or services for which the bid is submitted and shall be further disqualified from bidding on any future bids for work, goods, or services for the City.
2.29. Attorney's-in-fact
Attorneys-in-fact who sign bonds or other surety instruments must attach with each bond or surety instrument an effective and certified power of attorney.
2.30. Bonds
The Bid Bond and Public Construction or Performance Bond & Payment Bond shall be executed by a surety authorized to do business in the State of Florida and as named in the current list of “Companies Holding Certificates of Authority as Acceptable Sureties on
Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Audit Staff, Bureau of
Government Financial Operations, U.S. Treasury Department and A.M. Best rated A VIII or better. All bonds signed by an agent must be accompanied by a certified copy of authority to act and indicate that they are licensed to do business in the State of Florida.
• Bid Bond: A Bid Bond is required to be submitted with all construction bids in excess of $150,000.00 in an amount not exceed five percent (5%) of the preliminary estimate of the cost of the work (amount bid). Unsuccessful bidders will be entitled to return of surety. A successful bidder may forfeit any surety required upon failure on their part to enter into a contract within the specified time after the award.
https://www.cityofbartow.net/431/Protest-Procedures
• Performance Bond & Payment Bond: A Public Construction or Performance and Payment Bond will be required on all construction contracts when the price exceeds $250,000. A surety bond shall be required of the successful bidder in an amount equal to the awarded contract price and, if called out in the contract, the allowance amount; and shall be submitted to Procurement along with the executed contract documents as outlined under Instructions to Bidders, Approval of Contract.
The City may choose, in its discretion and applicable only to multiyear maintenance contracts, to allow for incremental annual contract bonds that cumulatively total the full, awarded, multiyear contract price.
2.31. Coordination
The Contractor shall notify all utilities, transportation department, etc., in writing, with a copy to the Public Works Department before construction is started and shall coordinate his Work with them. The Contractor shall cooperate with the owners of any underground or overhead utility lines in their removal, construction and rearrangement operations in order that services rendered by these parties will not be unnecessarily interrupted.
The Contractor shall arrange his Work and dispose of his materials so as to not interfere with the operation of other Contractors engaged upon adjacent work and to join his Work to that of others in a proper manner and to perform his Work in the proper sequence in relation to that of other Contractors all as may be directed by the Public Works Department Head. Each Contractor shall be responsible for any damage done by him or his agents to the work performed by another Contractor.
The Contractor shall contact the City of Bartow Public Works and the Florida Department of Transportation, as applicable, to verify and obtain the location of any and all traffic conduits, loops, and street light underground services.
2.32. Compliance with Federal Laws, Regulations and Executive Orders
Bidders are required to comply with all provisions of federal, state, county and city local laws, ordinances, rules and regulations that are applicable to the services being offered in the bid. Lack of knowledge of the Bidder shall in no way be a cause for relief from responsibility.
The Bidder shall familiarize itself and comply with all Federal, State, County and City laws, codes, ordinances or regulations controlling the action or operation of those engaged in the Work, or affecting materials or methods used, and govern itself in accordance with them. If the Bidder observes that there are conflicts between the Drawings and Specifications or between any other documents, they shall promptly notify the City in writing. Failure of the Bidder to notify the City of these variances shall not provide relief for compliance to the document as may be interpreted by the City. The Bidder shall hold harmless, to the fullest extent permitted by Florida Law, the City and all of its officers, agents or servants against any claims or liability arising from, or based upon the violations of any such laws, by-laws, ordinances, regulations, orders or decrees, whether by itself or their employees.
2.33. Debarred or Suspended
The bidder or proposer certifies, by submission of a response to this solicitation, that neither it nor its principals and subcontractors are presently debarred or suspended by any Federal department or agency.
2.34. Employees of Contractor
Employees of the Contractor shall at all times be under its sole direction and not be an employee or agent of the City. The Contractor shall supply competent employees. The City may require the Contractor to remove an employee or subcontractor it deems careless, incompetent, insubordinate or otherwise objectionable without any cost to the City or without any increase in Contract Price.
Contractor shall be responsible to the City for the acts and omissions of all employees working under its directions whether or not the actions taken go beyond the normal scope of employment.
2.35. Examination of Bid Documents and Site
The Contractor assumes responsibility to examine the site of the Work and become familiar with the form of Submittal, Drawings, Specifications, any Addenda issued thereto and all other forms of Contractual Documents pertaining to the proposed Work. The submission of the bid shall be sufficient to establish the presumption that the Contractor has investigated the site of the Work and is satisfied as to all conditions to be encountered, the character, quantity and quality of the work to be performed and materials furnished in the completion thereof. No pleas of ignorance of conditions or difficulties that may be encountered in the execution of the Work pursuant to this bid package as a result of failure to make necessary and reasonable examinations and investigations will be accepted as an excuse for any failure or omission on the part of the successful Bidder to fulfill, in every detail, all of the requirements of the
Contract Documents; nor will they be accepted as a basis for any claims whatsoever for extra compensation or for any extension of time. Prior to the time specified for receiving bid submittals any interpretation or modifications of the proposed Contract documents will be made only by Addendum. The City will send a courtesy notification when addenda are issued to each person to whom attended a mandatory or non-mandatory pre-bid meeting, if applicable; and/or submitted Bidder Registration. It is the sole responsibility of the
Bidders to check the City’s website at https://www.cityofbartow.net/bids.aspx and/or OpenGov to ensure that all available information, addenda, has been received prior to submitting a bid. The City shall not be responsible for oral instructions.
2.36. Expenses
Neither the City nor its representatives shall be liable for any expenses incurred in connection with the preparation of a response to this bid. All expenses in the preparation of this bid are the sole responsibility of the Proposer. All Submittals should be prepared to provide a straightforward and concise description of the respondents’ qualifications and ability to meet the requirements of the bid.
2.37. Materials and Construction
All material, equipment and construction furnished shall be new and shall be of good quality, workmanship and material. If silent in specifications, then the most acceptable industry-standard product shall be furnished and installed.
2.38. Florida Trench Safety Act Compliance
In the event this contract requires trench excavation, the requirement of Fla. Stat. 553.60, et seq., shall be adhered to by all
Contractors. Every Contractor shall provide a certification on the form provided and other required documentation.
2.39. Women/Minority Business Enterprises Outreach (W/MBEs)
The City hereby notifies all Bidders that W/MBE’s are to be afforded a full opportunity to participate in any bid by the City and will not be subject to discrimination on the basis of race, color, sex or national origin. The City asks that Bidders make good faith efforts to use qualified W/MBE subcontractors in preparing their bid. The W/MBE’s must be identified as such on the subcontractors list. If a
Bidder makes a good faith effort to find and utilize qualified W/MBE subcontractors, but is not successful, they have fulfilled the
Good Faith Effort required. Good Faith Effort shall be described as the effort put forth by bidders on construction bids to solicit prices from women/ minority contractors.
2.40. Non-Exclusivity Contract
Contractor agrees and understands that the contract shall not be construed as an exclusive arrangement and further agrees that the City may, at any time, secure similar or identical services from another vendor at the City’s sole option.
2.41. Unit Prices
Unless otherwise stated in this document unit prices will be utilized to adjust the total compensation due the successful Bidder based on actual quantities provided as part of the Work and verified by the City. Significant changes in quantities, including deletion of any particular item are possible. Negotiation of unit prices shall not be allowed except under conditions of Force Majeure, where those conditions are sufficiently documented to the full satisfaction of the City. No other claim to negotiate unit prices will be considered.
2.42. Substitution of Personnel
It is the intention of the City that the Contractor’s personnel proposed for the contract will be available for the contract term. In the event the Contractor wishes to substitute personnel, he shall propose personnel of equal or higher qualifications and all replacement personnel are subject to City approval. In the event substitute personnel are not satisfactory to the City and the matter cannot be resolved to the satisfaction of the City, the City reserves the right to cancel the Contract for cause.
2.43. Use of Florida Lumber, Timber and Other Forest Products
In accordance with Florida Statute 255.20 (3), the City specifies that lumber, timber, and other forest products used for this project shall be produced and manufactured in the state of Florida if such products are available and their price, fitness, and quality are equal.
This requirement does not apply to plywood specified for monolithic concrete forms, if the structural or service requirements for timber for a particular job cannot be supplied by native species, or if the construction is financed in whole or in part from federal funds https://www.cityofbartow.net/bids.aspx with the requirement that there be no restrictions as to species or place of manufacture. The Bidder affirms by submitting a bid response to this solicitation that they will comply with section 255.20 (3) Florida Statutes.
2.44. Preconstruction Conference
After the Commission Board and/or City Manager has approved the Bidder’s executed contract and prior to the start of construction, a joint meeting may be held with representatives of the successful Bidder, the City and other invited parties or government agencies which may be affected by or have jurisdiction over the Work.
2.45. Placing of Orders
The award of this bid does not constitute an order. Before shipments or service is provided, the contractor shall receive a signed
Purchase Order or Purchase Order number. In some cases, contractors shall be issued blanket orders. In this case shipments shall be specified on the order.
SECTION 3: FOR SEALED HARD COPY SUBMISSION ONLY: ADDRESS LABELS
All bids shall be securely sealed in an envelope and clearly marked on the outside with:
• Company/ Bidder’s Name,
• Company Address,
• The Bid Number & Title,
• Due Date & Time, and
• Attention: Procurement Department
“An address label has been provided for your use below. The City of Bartow will not be responsible for bids opened prior to the specified time due to envelopes that are improperly addressed or not marked as instructed in this notice.”
NAME OF COMPANY: ___________________________________________________
COMPANY ADDRESS: _______________________________________________
CITY: _____________________________ STATE: ____________ ZIP CODE: _____________
BID NUMBER & TITLE: ITB 26-26, Lime Silo Refurbishment
BIDS ARE DUE PRIOR BY 2:00 PM (EDT) ON, Wednesday, August 19, 2026
DELIVER TO: CITY OF BARTOW, PROCUREMENT DEPARTMENT
450 N. WILSON AVE.
BARTOW, FL 33830
It is recommended that the above label is taped onto the outside of the envelope that contains the bid documents.
Note: Be sure to label the envelope containing the bid documents or if the envelope is placed inside another envelope or shipping container (e.g., UPS envelope/box or FedEx envelope/box), then the label shall be affixed to the outside of that outer envelope or box.
SECTION 4: SCOPE OF WORK
4.1. Overview
The City of Bartow is seeking bids from qualified and experienced contractors to provide all necessary labor, materials, equipment, supplies, and supervision to complete the refurbishment of the Lime Silo at the Water Department located at 2500 Highway 17N, Bartow, FL 33830. The scope includes repairs to exterior metal panels, interior bands, metal doorframes and doors, along with all associated painting.
The project requires a contractor capable of delivering a turnkey solution that includes obtaining necessary materials, equipment, and building permits. The selected contractor must ensure timely and efficient completion while maintaining strict safety standards, adhering to all engineering specifications, and assuming full responsibility for site maintenance and restoration.
4.2. Project Timeline
The Contract Time is as follows: 120 CALENDAR DAYS
The contract time for this project is 90 calendar days from Notice to Proceed to reach Substantial Completion and 30 calendar days from Substantial Completion for Final Completion.
Completion of the contract will have been achieved once Final Completion has been reached and all final documentation, including final application for payment, has been received and processed.
4.3. Minimum Required Services
The Work to be done consists of the furnishing of all labor, materials, and equipment, and the performance of all Work included in this solicitation and further detailed in attachments - Appendix A through Appendix E.
The Contractor shall comply with the following Scope of Work requirements (Appendix A):
Work Included:
A. The Contractor shall furnish all labor, superintendence, materials, plant power, light, heat, fuel, water, tools, appliances, equipment, supplies, and means of construction necessary for proper performance and completion of the Work. The
Contractor shall obtain and pay for all necessary local building permits. The Contractor shall perform and complete the Work in the manner best calculated to promote rapid construction consistent with safety of life and property and to the satisfaction of the Engineer, and in strict accordance with the Contract Documents. The Contractor shall clean up the Work and maintain it during and after construction, until accepted, and shall do all Work and pay all costs incidental thereto. He shall repair or restore all structures and property that may be damaged or disturbed during performance of the Work.
B. The cost of incidental work described in these Project Requirements, for which there are no specific Contract Items, shall be considered as part of the general cost of doing the Work and shall be included in the prices for the various Contract Items. No additional payment will be made, therefore.
C. The Contractor shall provide and maintain such modern plant, tools, and equipment as may be necessary, in the opinion of the Engineer, to perform in a satisfactory and acceptable manner all the Work required by this Contract. Only equipment of established reputation and proven efficiency shall be used. The Contractor shall be solely responsible for the adequacy of his workmanship, materials, and equipment, prior approval of the Engineer notwithstanding.
Lime Storage Silo (Leg Supported Type) – Scope of Work (Appendix D):
A. Furnish all labor, materials, equipment, and incidentals required, and install and field test complete and ready for operation, one (1) lime storage silo suitable for storage of pebble quicklime with accessories as shown on the Drawings and as specified herein.
B. Furnish the lime storage silo system, including silo, level indicators, bin vibrators, dust control systems, ladders, bulk pneumatic truck unloading equipment, controls, and all piping and other appurtenances necessary for a complete system.
4.4. Detailed Scope of Services
The detailed Scope of Work is provided in the Attachments section and includes the following documents:
A. Specifications – Lime Silo Refurbishment
B. Lime Silo Inspection Report
C. Divider
D. Lime Storage Silo (Leg Support Type) and Accessory Equipment
E. Lime Feed Facility Site Key Plan
**Please note, if there is any conflict between the main solicitation document and any Appendix - Supplemental Information, the main solicitation document will control. This includes, but is not limited to, bid submission instructions, required forms, contract terms, insurance requirements, bonds, pricing table requirements, procurement procedures, and communications with the City.
4.5. Qualifications
Bidders must meet the following minimum qualifications to be considered responsive and responsible:
• The Contractor submitting a bid must have been in business under the same name & TIN/FEIN number for the past two (2) years.
• The Contractor shall hold valid Florida Certified General Contractor license or a valid Certified Structural Steel Work
Specialty Contractor license or otherwise be legally authorized under Florida law to perform the scope of work.
▪ All welders shall hold current AWS D1.1-compliant welder performance qualifications for the processes, positions, and joint details used on the project.
▪ All personnel assigned confined-space duties shall have current OSHA compliant training and documented employer certification for their specific roles.
▪ Employ a Florida Licensed Structural Engineer for all structural member calculations, temporary support, and repair designs.
▪ Maintain a verifiable corporate safety program and formal Quality Assurance/Quality Control (QA/QC) protocols.
▪ Employ AMPP (formerly NACE/SSPC) certified coating applicators and inspectors for all surface preparation and lining work
• The Contractor shall provide three (3) references that successfully completed at least (3) similar structural steel rehabilitation project within the last five (5) years including project summaries. Please refer to the Reference Form provided under the Vendor Submittal Forms.
• The Contractor shall not be permitted to use alternative materials or supplies for this Project unless expressly authorized in writing by the Project Manager.
Appendix D – Additional Manufacturer/Supplier Qualifications
• The equipment shall be produced by manufacturers who are experienced, reputable, and qualified in manufacturing the equipment required. All system components shall be designed, constructed, delivered, and installed in accordance with industry best practices.
• The supplier/manufacturer shall have sufficient financial capability to produce and deliver the specified equipment and shall maintain a minimum of $500,000 in product liability insurance for all products furnished.
• The system shall be furnished by a single supplier responsible for coordinating the system design and for ensuring proper system operation. Equipment shall be as specified and manufactured by Nosun Engineering Sales, Daco, or an equal approved by the Engineer.
• The equipment design, layout, sizes, configuration, and electrical wiring shown in the Drawings are based on equipment furnished through Nosun Engineering Sales. If equipment is supplied by another manufacturer, the
Contractor is responsible for confirming or revising all required equipment and wiring interfaces.
• The supplier/manufacturer shall have successfully provided a minimum of ten (10) installations of similar design or scope over at least five (5) years. The supplier/manufacturer shall provide at least five (5) references including location, contact name, phone number, and cost of equipment furnished.
Note: Contractors are to review, complete and upload Qualifications Statement of the Bid Document as it relates to this section.
SECTION 5: STANDARD TERMS AND GENERAL CONDITIONS
5.1. Contract Documents & Definitions
1.1 Contract Documents
1.1.1 The Contract Documents comprise the entire contract between the City and the Contractor.
1.2 Definitions
Whenever used in any of the Contract Documents, the following meaning shall be given to the terms herein:
1.2.1 The term “Addendum” or “Addenda” means any changes, revisions or clarifications of the Contract Documents which have been duly issued by the City to prospective Bidders prior to the time of receiving Bids.
1.2.2 The term “Allowance Authorization Release” means the written pre-approval forms signed by the City Manager or their designee for all allowance work.
1.2.3 The term “Allowance Work” means work that may not have been in the specifications and is deemed by the City to be necessary.
1.2.4 The term “Application for Payment” means the pay request accepted by the Professional and the City which is to be used by the Contractor in requesting progress or final payments that is accompanied by such supporting documentation as is required by the
Contract Documents.
1.2.5 The term “Bid Submittal” means the offer or submittal of the Bidder submitted on the prescribed form setting forth the price(s) for the Work to be performed.
1.2.6 The term “Bonds” means the Bid and Public Construction Bond and other instruments of security furnished by the Contractor and its Surety in accordance with the Contract Documents.
1.2.7 The term “Change Order” means any change that requires the City’s approval and either includes a change in the work or a change in the Contract Time.
1.2.8 The term “Construction Change Directive” means any change initiated by the City where a change order has not been agreed to between the City and the Contractor.
1.2.9 The term “Contract” means the Contract executed by the City and the Contractor.
1.2.10 The term “Contractor” means the person, firm or corporation entering into the Contract with the City to construct and install the improvements embraced in this Contract.
1.2.11 The term “Contractor Certification of Disbursement of Previous Progress Payments to Subcontractors and Suppliers” means the form that the Contractor must execute and submit with each Application for Payment certifying that the Contractor has paid all Subcontractors and Suppliers their respective pro rata share of all previous payments (to include payments of retainage) that the
City has made to Contractor for Work that has been satisfactorily completed.
1.2.12 The term “Contract Documents” means and shall include the following: Special Conditions, Plans, Drawings, Relocation
Schedule Permits, Instruction to Bidders, General Conditions, Exhibits, Supplementary Conditions, Technical Reports, Technical
Specifications, Bid Submittal, Bid and Public Construction Bonds, all Addenda issued by the City, Certificates of Insurance, Permits, Notice of Award, Allowance Authorization Release Form, Change Order Form, Substantial Completion Form and Final Completion
Form duly delivered after execution of Contract.
1.2.13 The term “Contract Time”, unless otherwise provided, means the period of time including adjustments by Change Order, allotted in the Contract Documents for substantial completion of the work.
1.2.14 The term “City” means the City of Bartow, FL, and its authorized designees, agents or employees.
1.2.15 The term “Day” may be either a working day or a calendar day as defined in the bid documents. When the Contract Time is specified as calendar days, workdays will be established in the supplementary conditions. Workdays are defined as those days of the week and hours of the day that the Contractor may perform the scope of work defined in the Bid Document. If a workday day shall fall on a City Holiday that day shall be omitted from the computation of days for Contract Time. City Holidays are: New Year’s Day, Martin Luther King Day, Memorial Day, Fourth of July, Labor Day, Veterans Day, Thanksgiving Day, the Friday following
Thanksgiving Day, Christmas Eve and Christmas Day, all as adopted by the Board of City of Bartow Commissioners.
1.2.16 The term “Drawings” means the Drawings or plans listed in Part F.
1.2.17 The term “Effective Date of the Contract” means the date on which the contract has been approved by the Board and executed by the Chairman of the Board.
1.2.18 The term “Field Order” means a written direction to the Contractor from the Professional that modifies Drawings and
Specifications without changing Contract Price or Contract Time.
1.2.19 The term “Free on Board” (FOB) means the cost of the goods including the shipment to the job site.
1.2.20 The term “Good Faith Efforts” means documented efforts to secure the participation of women and/or minority-owned subcontractors utilizing available resources to assist Bidder.
1.2.21 The term “Lump Sum” means that portion of the total contract amount that is fixed as a result of the amount of the bid submitted by the Contractor. If there is no “Allowance for Work” this amount is the total Contract amount. If there is an “Allowance for Work” then the bid price and the amount of the “Allowance for Work” becomes the total Contract amount.
1.2.22 The term “Not to Exceed” means that portion of the total Contract amount described as “Allowance for Work” that along with the amount of the bid submitted by the Contractor becomes the total Contract amount. Changes in the Work submitted by the
Contractor that are eligible and approved for funding from the “Allowance for Work” shall not exceed the amount provided a
“Allowance for Work” either in a single request or cumulative during the performance of the Work.
1.2.23 The term “Notice of Award” means the written notice issued by the City to the successful bidder.
1.2.24 The term “Notice to Proceed” means a written notice issued by the Purchasing Department to the Contractor fixing the date on which the Contract Time will commence, and the Contractor shall start to perform the obligations under the Contract Documents, unless otherwise specified in the Notice to Proceed. The actual Start Date shall be within ten (10) days of Notice to Proceed date or when all applicable permits have been secured, unless otherwise stated.
1.2.25 The term “Professional” means the architectural/engineering firm or individual retained by the City or in-house designated person designated to perform the design and/or resident engineering services for the Work. The Professional can also serve as the
Project Manager.
1.2.26 The term “Project Area” means the area within which are the specified…