J -2 FS SPECS_GAOA 0805 120-2.095_Black Creek Bridge Repair Const.pdf

PDF 481 KB Posted

Attached to
Black Creek Bridge Repair Construction
Solicitation number
12445221B0003
Issued by

About this file

This solicitation is for construction services to repair one bridge on the Apalachicola Ranger District in the National Forests in Florida. The project includes timber pile splicing repairs, guardrail repairs, and concrete pile cap and superstructure repairs. A pre-bid conference will be held on June 3, 2021 at 11:30 am at the specified coordinates. Questions must be submitted in writing at least five days prior to the conference. The award will be made to the lowest priced, responsible offeror who is responsive to the solicitation. Responsibility will be determined in accordance with FAR Subpart 9.104-1. The solicitation is being conducted by the Department of Agriculture Forest Service.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revision #1 CJG 02/19/21 Added times to 156.03 & 156.05

Table of Contents Preface

101 - Terms¸ Format¸ and Definitions

101.01 Meaning of Terms

101.03 Abbreviations

101.04 Definitions

102 - Bid¸ Award¸ and Execution of Contract

Delete Section 102

103 - Scope of Work

Delete Subsections 103.02, 103.03, 103.04, 103.05

104 - Control of Work

Delete Subsections 104.01, 104.02, 104.04

104.06 Use of Roads by Contractor

105 - Control of Material

105.05 Use of Material Found in the Work

106 - Acceptance of Work

106.01 Conformity with Contract Requirements

106.02 Visual Inspection

107 - Legal Relations and Responsibility to the Public

Delete Subsection 107.05

108 - Prosecution and Progress

Delete Section 108

109 - Measurement and Payment

Delete Subsections 109.06, 109.07, 109.08, 109.09

109.01 Measurement of Work

109.02 Measurement Terms and Definitions

153 - Contractor Quality Control

153.02 Qualifications

153.03 Quality Control Plan

155 - Schedules for Construction Contracts

Delete Section 155

156 - Public Traffic

Section 156. – PUBLIC TRAFFIC

551 - Driven Piles

Delete Section 551.11(d)

557 - Timber Structures

Delete and Replace 557.19

716 -Material for Timber Structures

Add Sections 716.05 and 716.06

SP-930 Materials for Concrete Repair

SP-973 Fiber Reinforced Polymer (FRP) Composite Structural Shapes

Preface Preface_wo_07_28_2020

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-14 for construction of National Forest System Roads.

101 - Terms¸ Format¸ and Definitions 101.01_National_11_9_2016

Add the following paragraph to Subsection 101.01:

101.01 Meaning of Terms.

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_National_11_9_2016

Add the following to Subsection 101.03:

101.03 Abbreviations.

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations

AFPA — American Forest and Paper Association

FSAR — Forest Service Acquisition Regulations

MSHA — Mine Safety and Health Administration

NESC — National Electrical Safety Code

WCLIB — West Coast Lumber Inspection Bureau

(f) Miscellaneous unit abbreviations.

MP — milepost location ppm — parts per million volume

STA station location

101.04_National_1_22_2020

Make the following changes to Subsection 101.04:

101.04 Definitions.

Delete these definitions and replace the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings — (Public Works Contracts) Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor according to FAR Clause 52.236-21 Specifications and Drawings for Construction. Also refers to submissions and submittals.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Solicitation—(Public Works Contracts) The complete assembly of documents (whether attached or incorporated by reference) furnished to prospective bidders.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Shop Drawings — (Timber and Stewardship Contracts) Referred to as “Drawings” in FP-14, include drawings, diagrams, layouts, schematics, descriptive literature, illustrations, lists or tables, performance and test data, and similar materials furnished by Purchaser to explain in detail specific portions of the work required by the contract.

Utilization Standards —

The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and IRTC contract provisions to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid¸ Award¸ and Execution of Contract 102.00_National_11_9_2016

Delete Section 102 in its entirety.

Delete Section 102.

103 - Scope of Work 103.00_National_11_9_2016

Delete all of Section 103 except Subsection 103.01 Intent of Contract.

Delete Subsections 103.02, 103.03, 103.04, 103.05.

104 - Control of Work 104.00_National_11_9_2016

Delete Subsections 104.01, 104.02, and 104.04.

Delete Subsections 104.01, 104.02, 104.04.

104.06_National_11_9_2016

Add the following to Subsection 104.06:

104.06 Use of Roads by Contractor.

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.02_National_11_1_2016

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material safely at government-approved location, at no additional cost to government.

106 - Acceptance of Work 106.01_National_7_18_2017

Delete Subsection 106.01 and replace with the following:

106.01 Conformity with Contract Requirements.

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project.

When the Government tests work, copies of test reports are furnished to the Contractor upon request.

Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive.

The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove, repair, or replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted. Removing, repairing, or replacing work;

providing temporary traffic control; and any other related work to accomplish conformity will be at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

1. Sampling method;

2. Number of samples;

3. Sample transport;

4. Test procedures;

5. Testing laboratories;

6. Reporting;

7. Estimated time and costs; and

8. Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

1. Have the work accepted at a reduced price; or

2. Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.02_National_11_9_2016

Delete Subsection 106.02 and replace with the following:

106.02 Visual Inspection.

Acceptance is based on visual inspection of the work for compliance with the specific contract requirements. Use prevailing industry standards in the absence of specific contract requirements or tolerances.

107 - Legal Relations and Responsibility to the Public

107.05_National_7_18_2017

Delete Subsection 107.05.

Delete Subsection 107.05.

108 - Prosecution and Progress 108.00_National_11_9_2016

Delete Section 108 in its entirety.

Delete Section 108.

109 - Measurement and Payment 109.00_National_11_9_2016

Delete Subsections 109.06, 109.07, 109.08, and 109.09:

Delete Subsections 109.06, 109.07, 109.08, 109.09.

109.01_National_2_22_2019

Delete the third paragraph and Table 109-1 of Subsection 109.01 and replace with the following:

109.01 Measurement of Work.

Take measurements as described in Subsection 109.02 unless otherwise modified by the Measurement Subsection of the section controlling the work being performed. Table 109-1 indicates the accuracy required for quantities of the various pay units used in the Schedule of Items. Use this guide to determine the decimal placement in the final payment.

Table 109-1

Decimal Accuracy of Quantities for Final Payment

Pay Item Level of Precision Linear Foot 1

Exception--Timber, Steel, and concrete Piles 0.1 Station 0.1 Mile 0.01 Square Foot 0.1 Square Yard 0.1 Each 1 Acre 0.01 Gallon 1 M-Gals. 0.1 Cubic Yard 1

Exception--Structure Excavation; Sheathing Materials; Bedding, Bed Course, and Backfill Materials; Gabions;

0.1

Exception--Concrete; Masonry 0.01 Pound 1 Ton 0.1

Exception--Calcium Chloride;

Sodium Chloride; Hydrated Lime;

Bituminous Materials; Pavements;

Bed Course Materials

0.01

Hour 0.1

MFBM 0.01

Station Yard 1 Cubic Yard Mile 1 Ton Mile 1

109.02_National_11_9_2016

Add the following sentence to Subsection 109.02(b):

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

109.03_National_11_1_2016

153 - Contractor Quality Control 153.02_National_11_1_2016

Delete Subsection 153.02 and replace with the following:

153.02 Qualifications.

Submit the following for approval with the quality control plan:

(a) Quality control manager (QCM). Furnish a QCM who has at least 2 years’ experience in construction, inspector, quality control and material testing on construction projects of similar type and scope.

(b) Testers. Provide testers with at least one year experience in the type of sampling and testing required, and with one of the following for the type of sampling and testing performed:

(1) NICET Level II certification in highway material or equivalent state or industry certification;

(2) Certification by a regional certification program (such as Western Alliance for Quality Transportation Construction (WAQTC), Northeast Transportation Technician Certification Program (NETTCP), Southeast Task Force for Technician Training and Qualification (STFTTQ), or Multi Regional Training and Certification (M-TRAC)); or

(3) At least one year employment by an AASHTO accredited laboratory performing equivalent sampling and testing.

153.03_National_11_1_2016

Add the following paragraph to the end of Subsection 153.03(b):

153.03 Quality Control Plan.

(b) Quality Control Procedures.

Submit written proposals for approval of alternate AASHTO or State approved test methods. Alternate methods may be allowed based on documented equivalence to the specified method.

155 - Schedules for Construction Contracts 155.00_National_11_9_2016

Delete Section 155 in its entirety.

Delete Section 155.

156 - Public Traffic 156.00_National_2_5_2019

Delete Section 156 in its entirety and replace with the following:

Section 156. – PUBLIC TRAFFIC Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Permanent Traffic Control 633

Traffic Signing and Marking Material 718

Concrete Barriers and Precast Guardwalls 618

Temporary plastic fence 710.11

Construction Requirements

156.03 General. Accommodate traffic according to MUTCD, approved traffic control plan and this section. Perform work in a manner that ensures safety and convenience of the public. Unless otherwise provided for in Table 156‐1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 120 minutes at any one time followed by an open period of no less than 15 minutes. Accommodate public traffic on roads adjacent to and within the project until the project is accepted according to Subsection

106.07(b).

Submit traffic control plan at least 30 days prior to intended use. Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved.

Post construction signs and traffic control devices in conformance with MUTCD and Forest Service EM

7100‐15. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the

National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156‐1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

Table 156-1 Temporary Road Closures

Road

Number From Terminus To Terminus

Maximum Consecutive

Days of Closure

Minimum

Consecutive Days

Open

<number>

<MP or description>

<MP or description> <number> <number>

120 BOP EOP 90 0

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Payment for contract work is provided indirectly. See Subsection 109.05.

551– Driven Piles 716.05_Regional_03_28_2018

Delete Subsection 551.11(d) in its entirety:

Delete Subsection 551.11 (d)

557– Timber Structures

Delete Subsection 557.19 and replace with the following:

557.19 Epoxy Repair of Timber Structures.

Furnish epoxy resin meeting requirement of 716.05 of FSSS.

557.19 (a) Preparation for all epoxy repairs.

Action must be taken to remove the damaged wood, arrest the infections, and prevent renewed damage.

Remove all of the decayed sections of timber until sound, unaffected wood fiber is reached. If moisture content of 20 percent or greater is detected the member should be dried before repairs are made. All bonding surfaces must be thoroughly cleaned of all dirt, debris, and excess oil and preservatives.

557.19 (b) Epoxy Structural Adhesion For application and structural bonding of different materials, such as Kevlar wrap, woven E-glass, carbon fabrics or timber hardware. Rollers, brushes, syringes, notched spreaders or caulking tubes may be used to apply epoxy. Apply coats per manufacturers written instructions.

557.19 (c) Epoxy Injection and Consolidation of Decayed Wood For saturation and encapsulation of wood decay, priming damaged areas, and sealing the end grain of new and old wood to prevent future decay. The repair area must be completely sealed prior to epoxy placement. Drill 1/4” to 3/8” port holes close together in the decay zone to provide for better penetration. Ports must be set to allow the injection of epoxy and the displacement of air. Additional ports may be set to monitor the complete filling of the void. Porous and/or checked timbers may require sealing with thick epoxy paint to prevent leakage upon injection.

Injection pressure must be sufficient to completely fill the void without breaking joint seals. Maximum recommended pressure is 40 psi. As epoxy fills the voids in the joint, venting ports begin to leak an even flow of epoxy and are progressively sealed. Apply consolidant repeatedly until the wood glosses over and accepts no more epoxy. The objective is fiber saturation to encapsulate and stabilize any remaining decay.

557.19 (d) Epoxy Structural Gap-Filling of Decayed Wood.

For filling larger cavities and voids in decayed wood and providing structural support. Install size #5 fiberglass reinforced polymer (FRP) rebar a minimum of 18 inches into sound wood and thru the full length of area to be filled. A minimum of two rebar per square foot of area shall be installed. Porous areas to be filled should be primed with epoxy consolidant so repair will adhere to stabilized wood.

Fill large voids (over 1½” deep) in layers to prevent excessive exothermic heat from epoxy reaction. Use adhesive (high-density) fillers or graded siliceous aggregates for structural gap filling. Protect treated areas with clear polyethylene or another type of cover to keep the repair zone warm in cold weather.

716 – Material for Timber Structures

Add the following to Section 716:

716.05 Epoxy Resin Adhesives

Furnish epoxy resin adhesives for epoxy adhesion, injection and reinforcement of decayed wood. Epoxy is used for timber repair as a bonding agent (adhesive) and/or grout (filler) in both structural and semi-structural repairs.

Epoxy resin shall be primarily liquid epoxy resin, or DGEBA (Diglycidyl Ether of Bisphenol A), used for wood conservation. Submittals of epoxy resin adhesives shall contain the following information:

PROPERTIES TEST METHOD

Resin Density ASTM D1475 Hardener Density ASTM D1475 Resin Viscosity ASTM D2196 Hardener Viscosity ASTM D2196 Epoxy Content of Epoxy Resins ASTM D1652 Pot Life ASTM D1338 Tensile Strength ASTM D638 Shear Strength ASTM D732 Cure Time (hours)

716.06 Aramid Fiber Wrap

Furnish aramid fiber wrap for external reinforcement of timber repairs. Wrap is to be bonded to timber using epoxy resin adhesive and shall be impregnated with epoxy prior to application.

Submittals of epoxy resin adhesives shall contain the following information:

PROPERTIES TEST METHOD

Tensile Strength ASTM D3039/3039M Ultimate Tensile Strength ASTM D7269 Elongation ASTM D7269

SP-930 (Taken from FDOT Specifications)

MATERIALS FOR CONCRETE

REPAIR

930-1 Description.

This Section covers cementitious materials used to repair concrete including defects or purposely placed openings in concrete elements. Materials containing organic compounds, such as bitumen and epoxy resin as the principal binder are not included. The requirements for epoxy resin materials are covered in Section 926. Any depth larger than the manufacturer’s recommendation for the specific material shall be repaired with portland cement concrete meeting the requirements of Section 346.

930-2 Product Acceptance on the Project.

930-2.1 Product Acceptance: Use only products listed on the Department’s Approved

Product List (APL). Manufacturers seeking evaluation of products must submit an application in accordance with Section 6 and include independently certified test reports that the material meets the requirements of this Section. The application package must describe detailed quality control requirements for installation including, but not limited to: maximum water to cementitious material ratio, formulation for two or more component systems, special materials and/or equipment, recommendations for all surface preparation, and curing requirements.

Provide the Engineer certification conforming to the requirements of Section 6 from the manufacturer confirming that the materials used meets the requirements of this Section and is the appropriate product for the intended use.

When specified in the Contract Documents, submit a report of test results from an independent laboratory on samples taken from material shipped. Ensure the test was performed within 45 days prior to the shipping date of the material.

930-2.2 Material Supply, Storage, and Marking: The material shall be pre-proportioned including aggregate. Deliver products in original, unopened containers with manufacturer’s name, date of manufacture, and clearly marked with all information described below. Store the material in an elevated dry and weather protected enclosure in full compliance with the manufacturer’s recommendations. Material must be used within manufacturer’s recommended shelf life.

The material from which the containers are made shall have water vapor transmission not greater than 100 g/m2 in 24 hours as determined in accordance with Procedure B of

ASTM E96.

All containers shall be marked with the following information:

1. LOT identification number and material expiration date

2. Directions for use shall include but are not limited to the following:

a. The type and kind of adhesive recommended (if any) to bond fresh repair material to the concrete or mortar being repaired.

b. The recommended amount of resin, other liquid component, or both, to be mixed with the package contents.

c. The recommended length of mixing time or sequence of mixing and resting times in minutes.

3. Date the material was packaged.

4. The yield in cubic feet or yield in ft2/in. thickness when mixed with the recommended amount of liquid.

5. The net weight in each container. The contents of any container shall not vary by more than 2% from the weight stated in the declarations. The average weight of filled containers in a LOT shall be not less than the individual weight stated in the declarations.

6. Instructions for the maximum and minimum water (or solutions) to cementitious material ratio.

7. State the approximate working time.

930-2.3 Sampling, Mixing, and Additional Testing: A LOT is the packaged repair material normally placed on a pallet. A unit sample is a single container or package of material randomly selected from the LOT. Mix and install the materials in accordance with the manufacturer’s recommendations. Manufacturers will be required to provide field representation upon request by the Engineer. The Department reserves the right to conduct further field testing on any approved material.

930-2.4 Rejection: All broken containers will be rejected. Material that fails to meet any of the requirements of this Specification will be rejected. Report all materials failing to meet this specification and state the reasons for rejection in writing to the Engineer and the producer or supplier. Material in local storage in the hands of a vendor for more than six months after testing will be retested before use, except for the scaling resistance test and length change immersed in sulfate solution test for magnesium ammonium phosphate concrete. Retested material will be rejected if it fails to conform to any of the requirements of this Specification.

930-3 Laboratory Specimen Preparation:

930-3.1 Mixing and Fabrication: Mechanically mix the dry packaged materials with liquid components in accordance with the manufacturer’s recommendations.

930-3.2 Length Change: Make and cure the test specimens in accordance with ASTM C157, except omit the curing period in Section 10.3; however both 11.1.1 and 11.1.2 shall apply for 28 day curing period.

930-3.3 Manifestly Faulty Specimens: Visually examine each group of specimens representing a given test or a given age of test, including tests of freshly mixed concrete, before or during the test, or both, whichever is appropriate. Discard any specimen found to be manifestly faulty by such examination without testing. Visually examine all specimens representing a given test at a given age after testing, and should any specimen be found to be manifestly faulty the test results thereof shall be disregarded. Should more than one specimen representing a given test at a given age be found manifestly faulty either before or after testing, the entire test shall be disregarded and repeated. The test result reported shall be the average of the individual test results of the specimens tested or, in the event that one specimen or one result has been discarded, it shall be the average of the test results of the remaining specimens.

930-4 Materials for Repair of Predominately Horizontal Surfaces.

930-4.1 General: This material is intended to be used to repair concrete where the area to be treated will be on a horizontal surface. Examples of the type of locations for these materials are bridge decks, portland cement concrete pavements and other locations required by the Contract Documents. Follow the manufacturer’s recommendations for preparing the surfaces, mixing, placing, and curing the repair material unless otherwise directed in the Contract Documents.

930-4.2 Classification: The materials to be considered under this classification shall meet the following requirements:

930-4.2.1 Rapid Hardening: Moderate compressive strength for repairing concrete with an in-place compressive strength less than or equal to 4,000 psi.

Table 930-1 - Physical Properties of Repair Materials for Horizontal Surfaces

Requirement Test Method Rapid Hardening

Very Rapid Hardening

Minimum Compressive Strength, psi

3 hours

ASTM C39* or

ASTM C109*

N/A 2,000

24 hours 2,000 4,000 7 days 4,000 6,000

28 days Greater than or equal to strength at 7 days.

Maximum Length Change, % Allowable expansion at 28 days when water cured compared to length at one day

ASTM C157**

0.12

0.12

Allowable shrinkage at 28 days when air cured compared to length at one day -0.12 -0.12

Allowable difference between increase in water and decrease in air 0.20 0.20

Minimum Slump (Concrete), inches ASTM C143*** 3 3

Minimum Flow (Mortar), % ASTM C1437*** 100 80

Time of Setting (Initial), minutes ASTM C191* or

ASTM C403*

Minimum

10 to 29

Coefficient of Thermal Expansion, in/in/°F

ASTM C531* or

AASHTO T336

3.0x 10-6 to

9.0 x 10-6

3.0 x 10-6 to

9.0 x 10-6

Minimum Bond Strength by Slant Shear, psi 24 hours

7 days

FM 5-587

400 450 Greater than or equal to strength at 24 hours.

Maximum Allowable Total Chlorides lb/yd3

FM 5-516 0.40

* as applicable ** Make and cure the test specimens in accordance with ASTM C-157, except omit the curing period in Section 10.3; however both 11.1.1 and 11.1.2 shall apply for 28 day curing period.

*** Testing for flow/slump will be completed in 15 plus or minus 1/2 minute after the start of mixing liquid with the rapid hardening materials or 5 plus or minus 1/2 minute after mixing the liquid with the very rapid hardening materials.

930-4.2.2 Very Rapid Hardening: High compressive strength for repairing concrete with an in-place compressive strength greater than 4,000 psi. This material may be used in lieu of rapid hardening materials.

930-4.3 Physical Properties: The repair material shall meet or exceed the physical properties stated in Table 930-1 as determined by the specified test methods.

930-4.4 Specimen Preparation:

930-4.4.1 Flow/Slump: Testing for flow/slump will be completed in 15 minutes, plus or minus 1/2 minute, after the start of mixing liquid with the rapid hardening materials or

5 minutes, plus or minus 1/2 minute, after mixing the liquid with the very rapid hardening materials.

930-5 Materials for Repair of Predominately Vertical Surfaces.

930-5.1 General: This material is intended to be used to repair concrete where the area exposed in the field to be treated will be on a vertical surface. If an element has both horizontal and vertical surfaces, then the repair used will be for vertical surfaces. If it is not apparent which material is to be used, the vertical application will prevail. Examples of the type of locations for these materials are columns, caps, beams, piles, incidental concrete products, drainage structures and other locations required by the Contract Documents. Follow the manufacturer’s recommendations for preparing the surfaces and for mixing, placing and curing the repair material.

930-5.2 Classification: The materials to be considered under this classification shall meet the following requirements:

930-5.2.1 High Performance: Moderate compressive strength for repairing concrete with a designed compressive strength greater than or equal to 5,000 psi.

930-5.2.2 Ultra-high Performance: High compressive strength for repairing concrete with a designed compressive strength greater than 5,000 psi. These materials may be used in lieu of high performance vertical materials.

930-5.3 Physical Properties: The repair material shall meet or exceed the physical properties stated in Table 930-2 as determined by the specified test methods.

SP – 973 (Taken from FDOT Specifications)

FIBER REINFORCED POLYMER (FRP) COMPOSITE STRUCTURAL SHAPES

973-1 Description.

This Section covers material and fabrication requirements for fiber reinforced polymer

(FRP) composite structural shapes.

973-2 Product Acceptance.

Obtain FRP composites from a producer that is currently on the Department’s Production

Facility Listing. Producers seeking inclusion on the list shall meet the requirements of Section 105.

973-3 Thermoset Pultruded Structural Shapes.

Thermoset pultruded structural shapes must meet the requirements in the materials section of the ASCE, Pre-Standard for Load & Resistance Factor Design (LRFD) of Pultruded Fiber Reinforced Polymer (FRP) Structures.

Manufactured components shall be inspected according to ASTM D3917 for dimensional tolerances and ASTM D4385 for visual defects.

Pultruded profiles located on bridge and overhead sign structures shall meet a flame spread index of Class B in accordance with ASTM E84 and meet the requirements of UL94 with a rating of V-1.

973-4 Vacuum Infusion Processed (VIP) Structural Shapes: 973-4.1 Materials:

973-4.1.1 Fibers: Use commercial grade glass fibers that conform to

ASTM D578. Glass fibers may be in any form such as rovings, woven fabrics, braided fabrics, stitched fabrics, continuous fiber mats, continuous strand mats, continuous filament mats (CFM), and chopped strand mats (CSM) of any size or weight.

Each structural element shall contain a minimum of 40% (by weight) of glass fibers oriented in a minimum of two directions in accordance with the manufacturer’s requirements.

Tensile strength of glass fiber strands, yarns and rovings shall not be less than 290 ksi in accordance with ASTM D7290, determined by a tension test in accordance with ASTM D2343.

973-4.1.2 Resin: Use a commercial grade thermoset resin for fabricating shapes.

973-4.1.3 Additives: Additives such as fillers, promoters, accelerators, inhibitors, UV agents, and pigments, used in the processing or curing shall be compatible with the fiber and resin.

973-4.2 Physical and Mechanical Properties: The physical properties of VIP FRP products shall conform to the requirements of Table 973-1. The characteristic mechanical properties of VIP FRP composite structural members, determined in accordance with

ASTM D7290, shall equal or exceed the minimum requirements in Table 973-2 for shapes and Table 973-3 for plates.

Table 973-1 Required Physical Properties - VIP FRP

Physical Property Requirement Test Method Barcol Hardness > 40 ASTM D2583

Glass Transition Temperature > 180 F ASTM D4065 Coefficient of Thermal Expansion < 7.5 x 10-6 in/in/ F (longitudinal) ASTM D696

Moisture Equilibrium Content < 2% ASTM D570, Section 7.4

Table 973-2 Required Mechanical Properties - VIP FRP Shapes

Property Minimum Requirement Test Method Longitudinal Tensile Strength 30,000 psi

ASTM D3039

Transverse Tensile Strength 7,000 psi

Longitudinal Tensile Modulus 3 x 106 psi Transverse Tensile Modulus 0.8 x 106 psi

Longitudinal Compressive Strength 30,000 psi ASTM D6641 Longitudinal Compressive Modulus 3 x 106 psi

Transverse Compressive Modulus 1 x 106 psi In-Plane Shear Strength 8,000 psi ASTM D5379 In-Plane Shear Modulus 0.4 x 106 psi ASTM D5379

Interlaminar Shear Strength 3,500 psi ASTM D2344

Table 973-3 Required Mechanical Properties -VIP FRP Plates

Property Minimum Requirement Test Method Longitudinal Tensile Strength 20,000 psi

ASTM D3039

Transverse Tensile Strength 7,000 psi

Longitudinal Tensile Modulus 1.8 x 106 psi Transverse Tensile Modulus 0.7 x 106 psi

Longitudinal Compressive Strength 24,000 psi

ASTM D6641

Transverse Compressive Strength 15,500 psi

Longitudinal Compressive Modulus 1.8 x 106 psi Transverse Compressive Modulus 1 x 106 psi

Longitudinal Flexural Strength 30,000 psi

ASTM D790

Transverse Flexural Strength 13,000 psi

Longitudinal Flexural Modulus 1.6 x 106 psi Transverse Flexural Modulus 0.9 x 106 psi

In-Plane Shear Strength 6,000 psi ASTM D5379 In-Plane Shear Modulus 0.4 x 106 psi

Interlaminar Shear Strength 3,500 psi ASTM D2344

973-4.3 Fire, Smoke and Toxicity: VIP profiles located on bridge and overhead sign structures shall meet a flame spread index of Class B in accordance with ASTM E84 and meet the requirements of UL94 with a rating of V-1.

973-4.4 Impact Tolerance: Where impact resistance is stipulated, impact resistance shall be determined in accordance with ASTM D7136.

973-5 Thermoplastic Structural Shapes.

973-5.1 General: For the purpose of this specification, use the following definitions:

a. Thermoplastic Structural Shapes (TSS) includes a thermoplastic matrix reinforced with chopped fiberglass filaments.

b. Reinforced Thermoplastic Structural Shapes (RTSS) includes a thermoplastic matrix reinforced with chopped fiberglass filaments and continuous FRP reinforcing bars meeting the requirements of this Section. Steel reinforcing bars are not permitted.

973-5.2 Materials: Use polyethylene made from recycled post consumer or post industrial thermoplastics. Mix the polyethylene with appropriate colorants, UV inhibitors, hindered amine light stabilizers, antioxidants, and chopped fiberglass reinforcement so that the resulting product meets the requirements specified in Table 973-4 for RTSS and Table 973-5 for TSS. Use a minimum of 15% (by weight) chopped fiberglass reinforcement for both TSS and RTSS. The thermoplastic matrix must not corrode, rot, warp, splinter or crack. Meet the requirements of 932- 3 for FRP reinforcing bar materials.

For RTSS members, the use of separate materials for skin and core is at the discretion of each manufacturer; however, both materials must meet the requirements in Table 973-4. The material surrounding the rebar within 1 inch from the rebar surface shall not contain voids greater than 3/4 inch diameter and extend no further than 2 inches along the length of the member. The cross section of the product shall not contain voids exceeding 1-1/4 inches in diameter and the sum of all voids greater than 3/8 inches in diameter shall not exceed 5% of the cross sectional area.

Extrude final product as one continuous piece with no joints or splices to the dimensions and tolerances in accordance with Table 973-6.

Reject any sections containing cracks or splits.

Table 973-4 RTSS Matrix

Property Test Method Requirement Density ASTM D792 48–63 pcf

Water Absorption ASTMD570 2 hrs: <1.0% weight increase 24 hrs: <3.0% weight increase

Brittleness ASTM D746 Brittleness temperature < minus 40°C

Impact Resistance ASTM D256, Method A (Izod) >0.55 ft-lbs/in

Hardness ASTM D2240 44-75 (Shore D)

Ultraviolet ASTM D4329

UVA

500 hours <10% change in Shore D Durometer Hardness

Abrasion ASTM D 4060 Weight Loss: <0.02 oz Cycles = 10,000

Table 973-4 RTSS Matrix

Wheel = CS17 Load = 2.2 lb

Chemical Resistance

ASTM D543

Sea Water: <1.5% weight increase Gasoline: <9.5% weight increase

No. 2 Diesel: <6.0% weight increase Tensile Properties ASTM D638 2,200 psi at break min.

Compressive Modulus ASTM D695 40 ksi min.

Static Coefficient of Friction ASTM D1894 0.25, wet max.

Screw Withdrawal ASTM D6117 400 lb (screw) min.

Table 973-5 TSS Matrix

Property Test Method Requirement Density ASTM D792 50-65 pcf

Impact Resistance ASTM D256 Method A (Izod) > 2.0 ft-lbs/in

Hardness ASTM D2240 44-75 (Shore D)

Ultraviolet ASTM D4329 (UVA) 500 hours <10% change in Shore D Durometer Hardness

Chemical Resistance

ASTM D756 or

ASTM D543

Sea Water: <1.5% weight increase Gasoline: <7.5% weight increase

No. 2 Diesel: <6.0% weight increase Tensile Properties ASTM D638 3,000 psi at break min.

Static Coeffecient of Friction ASTM D2394 0.25, wet or dry min.

Nail Withdrawal or Screw Withdrawal ASTM D6117 250 lb (nail) min.

400 lb (screw) min.

Secant Modulus at 1% Strain ASTM D6109 150,000 psi min.

Flexural Strength ASTM D6109 2,500 psi min.

Compressive Strength ASTM D6108 2,200 psi min.

Compressive Strength Perpendicular to grain ASTM D6108 700 psi min.

Table 973-6 Tolerances

Dimension Tolerance Length 0/+6 inch

Width – RTSS Width – TSS

±1/2 inch ±1/4 inch

Height – RTSS Width – TSS

±1/2 inch ±1/4 inch

Clear cover from outer surface to rebar elements (RTSS)

≤3/4 inch (wales) ±1/2 inch (other)

Straightness (while lying on a flat surface) <1-1/2 inches per 10 feet

Preface
101 - Terms¸ Format¸ and Definitions
101.01 Meaning of Terms.
101.03 Abbreviations.
101.04 Definitions.
102 - Bid¸ Award¸ and Execution of Contract
Delete Section 102.
103 - Scope of Work
Delete Subsections 103.02, 103.03, 103.04, 103.05.
104 - Control of Work
Delete Subsections 104.01, 104.02, 104.04.
104.06 Use of Roads by Contractor.
105 - Control of Material
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.01 Conformity with Contract Requirements.
106.02 Visual Inspection.
107 - Legal Relations and Responsibility to the Public
Delete Subsection 107.05.
108 - Prosecution and Progress
Delete Section 108.
109 - Measurement and Payment
Delete Subsections 109.06, 109.07, 109.08, 109.09.
109.01 Measurement of Work.
109.02 Measurement Terms and Definitions.
153 - Contractor Quality Control
153.02 Qualifications.
153.03 Quality Control Plan.
155 - Schedules for Construction Contracts
Delete Section 155.
156 - Public Traffic
Section 156. – PUBLIC TRAFFIC
551– Driven Piles
Delete Subsection 551.11 (d)
557– Timber Structures
557.19 Epoxy Repair of Timber Structures.
716 – Material for Timber Structures
716.05 Epoxy Resin Adhesives
716.06 Aramid Fiber Wrap
SP-930 (Taken from FDOT Specifications)
MATERIALS FOR CONCRETE REPAIR
930-2 Product Acceptance on the Project.
930-3 Laboratory Specimen Preparation:
930-4 Materials for Repair of Predominately Horizontal Surfaces.
930-4.4 Specimen Preparation:
930-5 Materials for Repair of Predominately Vertical Surfaces.
SP – 973 (Taken from FDOT Specifications)
973-2 Product Acceptance.
973-3 Thermoset Pultruded Structural Shapes.
973-4 Vacuum Infusion Processed (VIP) Structural Shapes: 973-4.1 Materials:
973-5 Thermoplastic Structural Shapes.

File details come from the government source that posted it. Updated .