Intersection Improvements Moonspinner St at West Preserve Loop.pdf
PDF 619 KB Posted
- Solicitation number
- 2026-0024, TR271
- Issued by
- San Bernardino County, California
About this file
Summary
This is a Special Provisions and Contract Documents package for the City of Chino, California for the construction of intersection improvements at Moonspinner Street and West Preserve Loop (Project No. TR271). The work includes sawcutting, removal and replacement of concrete improvements, installation of ADA-compliant curb ramps, removal and replacement of landscaping and irrigation, asphalt pavement reconstruction, asphalt cold mill and overlay, furnishing and installing Rectangular Rapid Flashing Beacons (RRFBs) and audible pedestrian push button assemblies, striping installation, and thermoplastic crosswalk markings per Caltrans specifications, and traffic control. Bids will be received electronically via the City of Chino's PlanetBids portal until 10:00 a.m. on October 22, 2026 (IFB# 2026-0024). No pre-bid meeting will be held. The project work is anticipated to begin in January 2027 and must be completed within 30 working days after the Notice to Proceed is issued. All bids are valid for 60 days after the bid due date. Questions or requests for interpretation must be submitted through PlanetBids before 10:00 a.m. on October 8, 2026.
The successful bidder must possess a valid California Class A contractor's license and must be registered with the State Department of Industrial Relations. This is a prevailing wage public works project subject to California Labor Code requirements, with prevailing wage rates available through the Department of Industrial Relations website or from the City. The contractor is required to furnish a 10% bid bond, 100% Labor and Materials Bond, 100% Faithful Performance Bond, and 10% Warranty Bond. All bonds must be secured by surety companies satisfactory to the City Council. The City reserves the right to reject any or all bids and award to the lowest responsive, responsible bidder. Bidders must submit all required documents including the Non-Collusion Declaration, Certification of Non-Discrimination, Workers' Compensation Insurance Certificate, Site Examination Certificate, Labor Code Section 2810 information, Iran Contracting Act Compliance Affidavit, and a Qualification and Experience Statement documenting three similar projects completed within the past two years.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF CHINO
CALIFORNIA
SPECIAL PROVISIONS AND CONTRACT DOCUMENTS
FOR
THE CONSTRUCTION OF
INTERSECTION IMPROVEMENTS
MOONSPINNER ST AT WEST PRESERVE LOOP
PROJECT NO.:TR271
Bids will be received electronically (online only) via the City of Chino’s PlanetBids portal at https://www.planetbids.com/portal/portal.cfm?CompanyID=26384 until 10:00 a.m., October 22, 2026
Prepared under the supervision of:
Alberto Espinoza, P.E., T.E
Deputy Director of Public Works/City Engineer R.C.E. 71374
Expiration Date : 12/31/2027
09/25/2026 Date
Authorized for Construction:
Hye Jin Lee, P.E.
Director of Public Works R.C.E. 57407
Expiration Date : 12/31/2027
TABLE OF CONTENTS
BID DOCUMENTS
PAGE
Notice Inviting Bids Instruction to Bidders Bid Proposal Documents and Certification Bid Schedule Addenda Acknowledgement List of Subcontractors Bid Bond Non-Collusion Declaration Certification of Nondiscrimination by Contractors Worker’s Compensation Insurance Certificate Certificate of Site Examination Information to Comply with Labor Code 2810 Iran Contracting Act of 2010 Compliance Affidavit Statement of Bidder: Qualification and Experience Statement Compliance with Applicable Laws, Rules, Regulations and Ordinances
AGREEMENT AND CONTRACT DOCUMENTS
List of Documents Required Prior to Award Agreement Faithful Performance Bond Labor and Materials Bond Warranty Bond Notice of Award Notice to Proceed with Construction
SPECIAL PROVISIONS
PROJECT PLANS .............................................................................................................. (5 SHEETS)
APPENDIX
City of Chino Truck Routes Business License Permit Applications Insurance Documents General Liability Special Endorsement Contractor’s Affidavit of Release of Liens Sub-contractor’s Affidavit and Final Waiver of Lien and Final Release W-9 Miscellaneous Forms City of Chino Standard Drawings – obtain from the City’s Website
NOTICE INVITING BIDS
THE CITY OF CHINO
STATE OF CALIFORNIA
PROJECT NO.: TR271
RECEIPT OF BIDS: Bids will be received electronically (online only) via the City of Chino’s PlanetBids portal at http://www.planetbids.com/portal/portal.cfm?CompanyID=26384 until 10:00 a.m., October 22, 2026.
Reference IFB# 2026-0024. All bids received for this project will be publicly opened via the City of Chino’s PlanetBids portal immediately following the close of the bidding period. Late bids will be rejected.
The City reserves the right to reject any or all Bids, to waive any irregularity, and award contracts in the best interest of the City.
PRE-BID MEETING: No Pre-Bid Meeting will be held.
DESCRIPTION OF WORK: The Contractor shall supply all labor, materials, and equipment to perform the work. Work shall include but is not limited to the following: Sawcutting, removal and replacement of existing concrete improvements, installation of ADA compliant curb ramps, removal and replacement of existing landscaping and irrigation in conflict with improvements, asphalt pavement reconstruction, asphalt cold mill and overlay, furnishing and installing Rectangular Rapid Flashing Beacons (RRFBs) and audible pedestrian push button assemblies, re-installation of striping and placement of thermoplastic crosswalk markings per Caltrans current specifications, and traffic control.
WORK SCHEDULE: The Project Work is anticipated to begin January 2027. All work shall be completed within 30 working days after the date set forth in the Notice to Proceed.
OBTAINING CONTRACT DOCUMENTS: Plans, Specifications, and Contact Documents may be obtained via City of Chino PlanetBids portal at:
https://www.planetbids.com/portal/portal.cfm?CompanyID=26384
Refer to invitation to Bid Number IFB #2026-0024
CONTRACTOR'S LICENSE: The Contractor shall possess a valid California Class A contractor’s license from the time bids are due and throughout the entire term of the contract. City will not award this Contract to a Bidder who fails to possess the required license and certifications.
PREVAILING WAGE REQUIREMENTS: This is a public works project in the state of California. Therefore, prevailing wage rates will be enforced.
Pursuant to Division 2, Part 7, Chapter 1 of the Labor Code of the State of California (including sections 1771 and 1773.2), the City has obtained from the Department of Industrial Relations of the State of California the general prevailing rate of per diem wages, and the general prevailing rate of holiday and overtime work in the locality in which the public work is to be performed for each craft, classification or type of workers needed to perform the Work, and they are on file in the office of the City Clerk, 2nd Floor, City Hall, 13220 Central Avenue, Chino, CA 91710. The Contractor to whom the Contract is awarded, and its subcontractors, shall pay to all workers in the performance of the Work not less than the prevailing rate of wages needed to execute the contract. Copies of schedules of prevailing wage rates may be obtained on the California Department of Industrial Relations website http://www.dir.ca.gov/dlsr and will be made available by the City upon request.
DEPARTMENT OF INDUSTRIAL RELATIONS (DIR) COMPLIANCE: This is a public works project and is subject to compliance monitoring and enforcement by the Department of Industrial Relations (DIR). In bidding on this work, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance requirements under this contract and applicable law in its bid.
REGISTRATION WITH THE DEPARTMENT OF INDUSTRIAL RELATIONS: Pursuant to Labor Code sections 1725.5, 1771.1, and SB 854, Public Works Contractor Registration Program, all contractors and subcontractors who bid or work on Public Works projects must be registered with, and pay an annual fee to, the State Department of Industrial Relations (DIR), subject to the limited exceptions set forth in Labor Code Section 1771.1(a) (regarding the submission of a bid as authorized by Business & Professions Code Section
7029.1 or Public Contract Code Section 10164 or 20103.5), provided that contractors and subcontractors subject to such exceptions shall be registered with the DIR at the time the contract is awarded. No bid will be accepted, except as provided above, nor any contract entered into, without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a contract, the Bidder and its subcontractor, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project.
REQUIRED BONDS: The successful bidder is required to furnish a Bid Bond in the amount of 10% of the contract amount, Labor and Materials Bond in an amount of 100% of the contract amount, Faithful Performance Bond in an amount equal to 100% of the contract amount, and a Warranty Bond in the amount of 10% of the contract amount; the bonds to be secured by a surety company or surety companies satisfactory to the City Council of the City of Chino.
DATED: 09/25/2026
ALBERTO ESPINOZA, P.E., T.E.
DEPUTY DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
Authorized to advertise by:
DATED: 09/25/2026
HYE JIN LEE, P.E.
DIRECTOR OF PUBLIC WORKS
INSTRUCTION TO BIDDERS
Please read these instructions carefully. If you do not submit a complete Bid, the City may determine that your Bid is non-responsive, in which case the City will reject your Bid.
SUBMISSION OF BID & RECEIPT OF BIDS: Bids will be received electronically (online only) via the City of Chino’s PlanetBids portal at http://www.planetbids.com/portal/portal.cfm?CompanyID=26384 until 10:00 a.m., October 22, 2026. All bids received for this project will be publicly opened via the City of Chino’s PlanetBids portal immediately following the close of the bidding period. Late bids will be rejected.
Any bid form submitted other than specified in this bid solicitation will be rejected. Bidders must be registered on the City’s PlanetBids portal to access and download the bid documents and plans and specifications. All documents to be completed and submitted are contained in Bid Proposal Documents - Pages 8 through 24. The bidder must complete and submit all parts of the Bid Proposal Documents to be considered a responsive bidder. The Bid Proposal form shall be signed in longhand by the bidder (if an individual), by a member of a partnership, or by an officer of a corporation authorized to sign contracts on its behalf. If made by a corporation, the bid proposal shall show the name of the state under the laws of which the corporation is chartered or organized.
Bidders are warned against making erasures or alterations of any kind on their bid proposal. Bid proposals which contain omissions, erasures, alterations, conditions, or additions not called for may be rejected.
BID SECURITY: All Bids shall be accompanied by cash, a certified bank draft, or a bond from an accredited surety company payable to the City of Chino for an amount not less than ten percent (10%) of the bid submitted. The bid security will be declared forfeited if the successful bidder refuses or fails to enter into a contract within ten (10) days following receipt of the Notice of Award with the contract documents, in accordance with California Public Contract Code Sections 20170 through 20174.
DISQUALIFICATION OF BIDDERS: More than one bid from an individual, firm partnership, corporation, or association under the same or different names will not be considered. Reasonable grounds for believing that any bidder is interested in more than one bid for the work contemplated will cause the rejection of all bids in which such bidder is interested. If there is reason for believing that collusion exists among the bidders, all bids will be rejected and none of the participants in such collusion will be considered in future bids.
SUBSTITUTION OF SECURITIES: In conformance with Public Contract Code 22300, the Contractor may substitute securities for any monies withheld by the City to ensure performance under the contract. At the request and expense of the Contractor, securities withheld shall be deposited with the City or with a State or Federally chartered bank as the escrow agent, who shall pay such monies to the Contractor upon notification by the city of Contractor’s satisfactory completion of the contract. The type of securities deposited and the method of release shall be approved by the City Attorney’s office.
VALIDITY OF BIDS: The Bidder shall guarantee that the Total Bid Price shall be valid for 60 days after the bid due date.
ADDENDA: The correction of any discrepancies or omissions from the specifications or other contract documents or any interpretation thereof during the bidding period will be made only by written addendum via PlanetBids. A completed and signed Addendum Acknowledgement Form shall be returned to the City with the bid proposal. Failure to do so may result in bid rejection. Any other interpretation or explanation of such documents other than posted to PlanetBids will not be considered binding.
QUESTIONS OR REQUESTS FOR INTERPRETATION: All questions or requests for interpretation regarding this bid solicitation must be submitted online through PlanetBids before 10:00 a.m. on October 8, 2026. Bidders submitting such requests are responsible for their timely delivery. City will interpret or correct the Contract Documents only by a written Addendum, and such Addendum will be posted to PlanetBids. The City is not bound by any oral interpretation of the Contract Documents made by any City employee. If Bidder fails to raise any issue regarding such interpretation or correction or if the City fails to respond to a request, Bidder will be deemed to have accepted all risks associated with that issue. Bidder specifically waives the right to request a Change Order, equitable adjustment, or to request additional time, or to seek recovery in quantum meruit in conjunction with any such issue. Bidder further waives the right to assert arguments of estoppel or implied or express warranty of design with regard to any such issue.
Bidders are not to directly contact City personnel with any questions or clarifications concerning this bid other than through PlanetBids. Any City response for this bid that is not posted through PlanetBids is unauthorized and will be considered invalid.
BID MISTAKES: Attention is directed to the provisions of Public Contract Code Sections 5100 to 5107, inclusive, concerning relief of bidders and in particular to the requirement therein, that if the bidder claims a mistake was made in his bid, the bidder shall give the City written notice within five (5) working days, excluding Saturdays, Sundays, and state holidays, after the opening of the bids of the alleged mistake, specifying in the notice in detail how the mistake occurred
DISCREPANCIES IN BIDS: In case of discrepancy between numeric and spelled-out amounts, the spelled-out amount shall prevail. In case of discrepancy between the Unit Price and the Item Total set forth for that item, the Unit Price shall prevail; provided however, if the amount set forth as a Unit Price is ambiguous, unintelligible, or uncertain for any cause, or if it is omitted, or in the case of unit basis items, is the same amount as the entry in the Item Total column, then the amount set forth in the Item Total column for the item shall prevail in accordance with the following:
(1) As to lump sum items, the amount set forth in the Item Total column shall be the item price.
(2) As to unit basis items, the amount set forth in the Item Total column shall be divided by the estimated quantity for the item and the price thus obtained shall be the unit cost.
If the Total Bid Price does not equal the sum of the Item Totals, then the Engineer, after resolving any discrepancy in the Item Totals, shall sum the Item Total column and the resultant amount shall be considered the Total Bid Price.
WITHDRAWAL OF BIDS: Bidders may withdraw their bids via PlanetBids before the bids are due as specified in the Notice Inviting Bids. Bidders may not withdraw their bids after the bids are due without forfeiture of their bid security. Withdrawal of the bid will not prejudice any bidder’s right to submit a new bid, if there is time to do so.
BID PROTEST: Only a bidder who has actually submitted a bid proposal to the City is eligible to protest a bid. The City will not accept or entertain bid protests from anyone who did not submit a bid for the project or work being protested.
Bidders may file a protest of a bid proposal with the Finance Department – Purchasing Division, City of Chino - 13220 Central Avenue, Chino, CA 91710, no later than 4:00 p.m. on the fifth (5th) business day from the day in which the bids are opened.
At the time of the filing, the bid protest shall be:
a. Submitted on the bidder’s formal letterhead and include the bidder’s company name, address, phone number and the name and title of the individual filing the protest; and
b. List the reasons for the protest including the specific section of the documents or technical specifications being disputed and shall site any statutes or case law supporting or serving as the basis for the protest and describe how they support the item(s) being disputed.
If the protest does not meet these requirements, the City will reject it without further review. If the protest is submitted on time and complies with all the above requirements, the Director of Finance or their designee, shall review the protest and all relevant information submitted by the protesting bidder. The City will provide a written response to the protesting bidder. The City has the right to respond to any protest until the date on which the contract is awarded by the Chino City Council.
The procedure and time limits set forth in this paragraph are mandatory and are the sole and exclusive remedy in the event of a bid protest. Failure to comply with these procedures shall constitute a failure to exhaust administrative remedies and a waiver of any right to further pursue the bid protest, including filing a Government Code Claim or legal proceedings.
If the City determines that the protest is frivolous, the party originating the protest may be determined irresponsible and that party may be determined to be ineligible for future contract awards.
PROPRIETARY INFORMATION: Responses to the Notice Inviting Bids become the exclusive property of the City of Chino. All bids submitted in response to the Notice Inviting Bids are a matter of public record and shall be regarded as public records. Exceptions will be those elements in each bid that are defined by the bidder as business or trade secrets and are marked as “Trade Secrets,” “Confidential,” or “Proprietary.”
The City shall not be liable or responsible in any way for disclosure of any records not marked as “Trade Secrets,” “Confidential,” or “Proprietary.” The City shall not be liable or responsible in any way for disclosure of any records so marked if disclosure is deemed to be required by law or by a court order.
IRAN CONTRACTING ACT: In accordance with California Public Contracting Code Section 2200-2208, all bidders submitting proposals for, entering into, or renewing contracts with the City and estimated at $1,000,000 or more are required to complete, sign and submit the “Iran Contracting Act of 2010 Compliance Affidavit” contained in the Bid Documents below.
TAXES: Bidders shall not mention Sales Tax, Use Tax, or any other tax in their bids. All bid amounts shall include all applicable taxes.
LISTING SUBCONTRACTORS: Bidders shall submit the list of subcontractors on this Project that is required by the Subletting and Subcontracting Fair Practices Act (Public Contract Code Section 4100 et seq.).
LATE BIDS: The City will reject any Bid submitted after the bid due time and date set forth in the Notice Inviting Bids. No exceptions.
AWARD OF CONTRACT AND OWNER’S RIGHTS RESERVED: If the City awards the Contract, it will award the Contract to the lowest, responsive, responsible bidder as determined solely by the City. The City reserves the right to cancel this bid solicitation, reject any or all bids, and, to the extent not prohibited by law, to waive any minor irregularity or informality in any bid that does not give the bidder a competitive advantage over other bidders and to take the bids under advisement for the bid guarantee period shown above, as may be necessary in the best interests of the City. The City is not required to provide a reason should it choose to cancel this bid.
ESTIMATED QUANTITIES: The quantities given in the bid proposal and contract form are approximate, being given as a basis for the comparison of bids only, and the City does not, expressly or by implication, agree that the actual amount of work will correspond therewith, but reserves the right to increase or decrease the amount of any class or portion of the work, or to omit any portion of the work, as may be deemed advisable or necessary by the Engineer.
BID PROPOSAL DOCUMENTS
All documents provided in Section C, including this page, must be completed. Unless otherwise specified, all Bid Proposal documents must be submitted to be considered for award for this bid solicitation.
1. Bid Proposal Documents and Certification
2. Bid Schedule
3. Addenda Acknowledgement
4. List of Subcontractors
5. Bid Bond
6. Non-Collusion Declaration
7. Certification of Non-Discrimination by Contractors
8. Worker’s Compensation Insurance Certificate
9. Certificate of Site Examination
10. Information to Comply with Labor Code 2810
11. Iran Contracting Act of 2010 Compliance Affidavit
12. Statement of Bidder: Qualification and Experience Statement
13. Compliance with Applicable Laws, Rules, Regulations and Ordinances
I, _______________________________ (Bidder), certify that all of the above required documents have been completed. I also understand that failure to submit a completed bid package (fully completed and executed) will result in rejection of bid.
BIDDER INFORMATION
The following information will be used for statistical analysis only:
Is the Bidder a Disadvantaged Business (DBE)? _____ If yes, Certification No. __________
Is the Bidder a Minority-Owned Business? _____ Which racial minority? __________
Is the Bidder a Women-Owned Business? _____
Is the Bidder a certified Small Business? _____ If yes, Certification No._________
Dated (Bidder)
(Signature)
(Printed Name)
(Title)
BIDDER’S NAME: ___________________________
In accordance with the Notice Inviting Bids for this Work in the City of Chino, California, Bidder offers to furnish all necessary labor, tools, materials, appliances and equipment for and to perform all Work mentioned in the Notice Inviting Bids, in full compliance with all documents, including plans, specifications, attachments and exhibits at the prices listed below. If night work is approved by the Engineer, the Contractor shall not receive any additional compensation.
Unit prices shall prevail over extended prices in the event of a discrepancy between extended prices and unit prices.
Bidder understands that these quantities are estimates only and are given solely for the purpose of facilitating the comparison of Bids, and that the Contractor’s compensation will be computed on the basis of the actual quantities in the completed Work.
BID SCHEDULE
TR271 - INTERSECTION IMPROVEMENTS
BID SCHEDULE
ITEM DESCRIPTION
REFERENCE
SPEC
QTY UNIT
UNIT
PRICE
TOTAL COST
Mobilization And Demobilization;
Clearing & Grubbing. This Bid Item Also Includes All Items Necessary to Complete the Project Work Per the General Provisions Not Contained Within the Itemized Bid Schedule Below (Not to Exceed 5% of Bid).
No Temporary Laydown Yard Will Be Provided.
7-3.4,300-1 1 LS $ $
Project Information Sign. (4' x 6') per City of Chino Standard Drawing 165A.
7-1, 7-3, 600-2.1, Std Dwg 165A & C
1 EA $ $
Construction Notices and Door Hangers: Preparation and Distribution of Construction Letters and 72-Hour Notice Door Hangers.
302-4.8, 600- 2.2
1 LS $ $
Erosion Control & BMP Implementation
3-12, 3- 12.6.2, 3-
12.6.5
1 LS $ $
BID SCHEDULE (CONTINUED)
REFERENCE
SPEC
QTY UNIT
UNIT
PRICE
TOTAL COST
Construction Surveying.
Construction Staking, Re-establishment of Centerline Ties, and Monument Perpetuation.
3-10, 3-10.3, 400-2
1 LS $ $
Traffic Control and Pedestrian Detour Plan. Layout of Traffic Control Devices Per WATCH Book.
Approval by the City of Chino Traffic Division is Required for Each Layout Proposed, Prior to Placement.
Implement and Maintain the Traffic Control Devices for the Duration of the Project.
3-8.8, 302- 4.8, 600-
7.1.2, Part 6
1 LS $ $
Unclassified Excavation.
Including Hauling and Disposal Complete.
300-2, 300- 2.8, 300-2.9
100 CY $ $
8 Remove existing 8” Curb.
201, 301, 303-5
125 LF $ $
Remove and Construct 8” Curb per City of Chino Std. Drawing No.
200.
Std Dwg 200, 201, 301, 303-5
200 LF $ $
Remove and Construct 8” Type B Curb and Gutter per City of Chino Std. Drawing No. 205 Including Asphalt Pavement Slot Patch
Std Dwg
205, 201, 301, 303-5
275 LF $ $
Remove and Construct 4” Thick PCC Sidewalk per City of Chino Std. Drawing No. 230
Std Dwg
230, 201, 301, 303-5
1,175 SF $ $
Remove Existing Improvements and Construct Curb Ramp Including Asphalt Pavement Slot Patch and Cast-in-Place Detectable Warning Surface.
201, 301, 303-5, 303- 5.5.6, 303-
5.9
4 EA $ $
Cold Mill 2” Depth of Existing AC Pavement and Dispose of Excess Grinding.
404, 404-11, 404-12
765 SY $ $
14 Asphalt Concrete Pavement
302-5, 302- 5.13, 302- 5.14., Std Dwg 100
(Secondary Arterial)
220 TN $ $
REFERENCE
SPEC
QTY UNIT
UNIT
PRICE
TOTAL COST
Furnish and Install New Water Valve Can and Cover to Finish Grade. Remove and Dispose of Existing and Paint New Cover Blue
Std Dwg 455, 206-
3.3.2
3 EA $ $
Furnish and Install Polara Audible Pedestrian Push Button Assembly Including Post and Conduit Run Per City of Chino Std Plan 815A & B.
Std Dwg
815A, B, C, 700-5.9
2 EA $ $
Furnish and Install Rectangular Rapid Flashing Beacon Per City of Chino Std Plan 810 A, B, and C.
Including Conduit and Pull Box per Std Plan 803
Std Dwg
810A, B, C, 803, 701-11, 701-11.1.2.1
2 EA $ $
Relocate Existing Sign on New Post Furnish and install new post, per City of Chino Std. Dwg. No. 805
Std Dwg 805 2 EA $ $
Install R9-3 Sign Furnish and install new sign and post, per City of Chino Std. Dwg. No. 805
Std Dwg 805 2 EA $ $
Install R1-5 Sign, See Detail A on Plans; Furnish and install new sign and post per City of Chino Std. Dwg.
No. 805
Std Dwg 805 2 EA $ $
Striping, Pavement Legends, and Raised Pavement Markers Install Thermoplastic for all Striping, Legends, Crosswalks, and Symbols.
Includes Temporary Striping in Paint In-Lieu of Tabs and Cat-Tracking
214-5, 302- 15.1, 314,314-2.2, 314-2.3, 314-
4.4.5, 314- 4.4.6, 601-4, 602-5
1 LS $ $
Remove Existing Landscape and Irrigation in Conflict with Improvements and Re-Establish In-Kind Including Adjusting Existing Irrigation Heads, Landscape Lights, and Lines Impacted by Improvements.
7-1, 7-3, PART 8, Std
Dwg 605, 403-1
1 LS
REFERENCE
SPEC
QTY UNIT
UNIT
PRICE
TOTAL COST
Relocate Existing Irrigation Pull Box
403-1, 701-
1 EA $ $
TOTAL BID PRICE (ITEMS 1 – 23) $
TOTAL BID (SCHEDULE) PRICE IN WORDS:
TOTAL BID (SCHEDULE) IN NUMBERS:
ADDENDA ACKNOWLEDGEMENT/SIGNATURE
This Bid is submitted with respect to the changes to the Plans & Specifications included in the following addenda numbers:
1 2 3 4 5 6 7
(Initial above all appropriate numbers)
Bidder certifies that Bidder has examined the site and that the Bid is complete. By signing below, Bidder certifies that the Contractor will not submit a claim based on failure to examine the site thoroughly.
Respectfully submitted, Bidder Signature Date
Print Name / Title
Legal Name of Company Business Address (PO Box)
Telephone Number Email Address
Contractor’s License Number DIR Registration Number
PROJECT NO,: TR271
LIST OF SUBCONTRACTORS
In accordance with the requirements provided in the "Subletting and Subcontracting Fair Practices Act" Division 2 Part 1, Chapter 4 of the California Public Contract Code, the Bidder shall set forth hereon the name, the location of the place of business, Department of Industrial Relations registration number, and the California contractor license number of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvement, or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to plans and specifications, in an amount in excess of one‐half of 1 percent of the prime contractor's total bid or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one‐half of 1 percent of the prime contractor's total bid or ten thousand dollars ($10,000), whichever is greater. The prime contractor shall also set forth hereon the portion of the work (type and dollar value) that will be done by each subcontractor. The prime contractor shall list only one subcontractor for each portion as defined by the prime contractor in his or her bid. Information requested, other than the subcontractor's name, location of business, Department of Industrial Relations registration number, contractor license number, and the portion of work that will be done by each subcontractor, may be submitted by the prime contractor within 24 hours after the deadline for submission of bids.
Name: Type of Work:
Address: Email Address:
Phone No.: Dollar Value of Subcontract: $
License No.: DIR Registration No.:
Name: Type of Work:
Address: Email Address:
BOND NO. __________________
BID BOND
KNOW ALL MEN BY THESE PRESENTS that we _________________________________ as Principal, hereinafter referred to as “Contractor” and _________________________________ as Surety, are held and firmly bound unto the City of Chino, hereinafter called the “City,” in the sum of _________________________________________________________________________Dollars ($______________), for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally, firmly by these presents. The conditions of this obligation are such that whereas the Contractor submitted to the City a certain Bid, attached hereto and hereby made a part hereof, to enter into a contract in writing for the INTERESECTION IMPROVEMENTS - MOONSPINNER ST AT WEST PRESERVE LOOP, and will furnish all required certificates of insurance and bonds as required by the Contract.
NOW, THEREFORE, if said Bid shall be rejected; or in the alternate, if said Bid is accepted, and the Contractor (i) executes and delivers a contract in the prescribed form of the Agreement, (ii) delivers certificates evidencing that the required insurance is in effect, (iii) executes and delivers bonds in the forms prescribed, and (iv) in all other respects performs the agreement created by the acceptance of said Bid, then this obligation shall be void; otherwise this obligation shall remain in full force and effect, it being expressly understood and agreed that the liability of the Surety for any and all default of the Contractor hereunder shall be the amount of this obligation as herein stated. In the event suit is brought upon this bond by City and judgment is recovered, Surety shall pay all costs incurred by City in said suit, including a reasonable attorney's fee to be fixed by the court.
The Surety, for the value received, hereby stipulates and agrees that the obligations of said Surety and its bond shall in no way be impaired or affected by an extension of the time within which the City may accept such a bid; and said Surety does hereby waive notice of any such extension.
SIGNED AND SEALED, this ________day of ______________________, 20______
________________________________(Seal) ________________________________(Seal) (Principal) (Surety)
By: ____________________________ By: _________________________________ (Signature) (Signature)
(SEAL AND NOTARIAL ACKNOWLEDGMENT OF SURETY)
NON-COLLUSION DECLARATION
(TO BE EXECUTED BY BIDDER AND SUBMITTED WITH BID)
The undersigned declares:
I am the _______________ of __________________, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding.
The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on ________________________ [Date], at ________________________ [City], ___________________ [State].
CONTRACTOR
Subscribed and sworn to before me this day of _________________, 20 ______ by _________________
Notary Public in and for the County of ________________________________________, State of California.
My Commission Expires ____________________________, 20__
CERTIFICATION OF NON-DISCRIMINATION BY CONTRACTORS
As suppliers of goods and services to the City of Chino, the company listed below certifies that, except as permitted in Government Code section 12940, it does not discriminate in its employment on the basis of the race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender identity, gender expression, age, sexual orientation, or military and veteran status of any person; that it is in compliance with all federal, state, and local laws regarding non-discrimination in employment; and that it agrees to positively and aggressively pursue the principle of equal opportunity in employment.
We agree specifically:
1. To establish or observe employment policies which affirmatively promote opportunities for minority persons at all job levels.
2. To communicate this policy to all persons concerned, including all company employees, outside recruiting services, especially those serving minority communities, and to the minority communities at large.
3. To take affirmative steps to hire minority employees within the company.
COMPANY NAME:
NAME OF PERSON SIGNING:
TITLE OF PERSON SIGNING:
SIGNATURE:
DATE:
Please include any additional information available regarding equal opportunity employment programs now in effect within your company.
MOONSPRINNER ST AT WEST PRESERVE LOOP
WORKERS’ COMPENSATION INSURANCE CERTIFICATE
The Contractor shall execute the following form as required by the California Labor Code, Section 1860 and 1861:
I am aware of the provisions of Section 3700 of the State Labor Code which require every employer to be insured against liability for worker’s compensation or to undertake self-insurance in accordance with the provisions of that Code, and I will comply with such provisions before commencing the performance of this contract.
DATE: ____________________
CONTRACTOR
MOONSPRINNER ST AT WEST PRESERVE LOOP
CERTIFICATION OF SITE EXAMINATION
Each bidder shall be fully informed of the conditions relating to the construction of the work and the employment of labor thereon. Failure to do so will not relieve Contractor of the obligation to furnish all material and labor necessary to carry out the provisions of the Contract Documents. Each bidder shall examine the site for the work described herein. Bidders shall attend a mandatory pre-bid meeting of the site conducted by the City. Failure to attend the mandatory pre-bid meeting shall be cause for rejection of the bid.
This is to certify that I have examined the site and the bid is complete and there will be no additional payment for failure to examine the site thoroughly.
Date of Site Examination
Bidder
Printed Name of Bidder Representative
Signature of Representative
INFORMATION TO COMPLY WITH LABOR CODE SEC. 2810
To comply with Labor Code Sec. 2810, Contractor shall complete and submit this Information Sheet which shall be incorporated into and be a part of the Contract:
1) Workers’ Compensation Insurance:
a. Policy Number:
b. Name of Insurer (NOT Broker):
c. Address of Insurer:
d. Telephone Number of Insurer:
2) For vehicles owned by Contractor and used in performing work under this Contract:
a. VIN (Vehicle Identification Number):
b. Automobile Liability Insurance Policy Number:
c. Name of Insurer (NOT Broker):
d. Address of Insurer:
e. Telephone Number of Insurer:
3) Address of Property used to house workers on this Contract, if any:
4) Estimated total number of workers to be employed on this Contract:
5) Estimated total wages to be paid those workers:
6) Dates (or schedule) when those wages will be paid (Describe schedule: For example, weekly or every other week or monthly):
7) Estimated total number of independent contractors to be used on this Contract:
8) Contractor’s Taxpayer’s Identification Number:
IRAN CONTRACTING ACT of 2010 COMPLIANCE AFFIDAVIT (Public Contract Code Sections 2202-2208)
The California Legislature adopted the Iran Contracting Act of 2010 to respond to policies of Iran in a uniform fashion (PCC §2201(q)). The Iran Contracting Act prohibits bidders engaged in investment activities in Iran from bidding on, submitting proposals for, or entering into or renewing contracts with public entities for goods and services of one million dollars ($1,000,000) or more (PCC § 2203(a)). A bidder who “engages in investment activities in Iran” is defined as either:
1. A bidder providing goods or services of twenty million dollars ($20,000,000) or more in the energy sector of Iran, including provision of oil or liquefied natural gas tankers, or products used to construct or maintain pipelines used to transport oil or liquefied natural gas, for the energy sector of Iran; or
2. A bidder that is a financial institution (as that term is defined in 50 U.S.C. § 1701) that extends twenty million dollars ($20,000,000) or more in credit to another person, for 45 days or more, if that person will use the credit to provide goods or services in the energy sector in Iran and is identified on a list created by the California Department of General Services (DGS) pursuant to PCC § 2203(b) as a person engaging in the investment activities in Iran.
The bidder shall certify that at the time of submitting a bid for new contract or renewal of an existing contract, the bidder is not identified on the DGS list of ineligible businesses or persons and that the bidder is not engaged in investment activities in Iran in violation of the Iran Contracting Act of 2010.
California law establishes penalties for providing false certifications, including civil penalties equal to the greater of $250,000 or twice the amount of the contract for which the false certification was made; contract termination; and three-year ineligibility to bid on contracts (PCC § 2205).
To comply with the Iran Contracting Act of 2010, the bidder shall provide its vendor or financial institution information below:
OPTION #1 - CERTIFICATION
I, the official named below, certify I am duly authorized to execute this certification on behalf of the vendor/financial institution identified below, and the vendor/financial institution identified below is not on the current list of persons engaged in investment activities in Iran created by DGS and is not a financial institution extending twenty million dollars ($20,000,000) or more in credit to another person/vendor, for 45 days or more, if that other person/vendor will use the credit to provide goods or services in the energy sector in Iran and is identified on the current list of persons engaged in investment activities in Iran created by DGS.
Vendor Name/Financial Institution (Printed) Federal ID Number (or n/a)
By (Authorized Signature)
Printed Name and Title of Person Signing
Date Executed Executed in
OPTION #2 – EXEMPTION
Pursuant to Public Contract Code sections 2203(c) and (d), a public entity may permit a vendor/financial institution engaged in investment activities in Iran, on a case-by-case basis, to be eligible for, or to bid on, submit a proposal for, or enters into or renews, a contract for goods and services.
If you have obtained an exemption from the certification requirement under the Iran Contracting Act, please fill out the information below, and attach documentation demonstrating the exemption approval.
Vendor Name/Financial Institution (Printed) Federal ID Number (or n/a)
By (Authorized Signature)
Printed Name and Title of Person Signing Date Executed
STATEMENT BY BIDDER: QUALIFICATION AND EXPERIENCE STATEMENT
The following outline is a record of the undersigned Bidder's experience in construction of three (3) projects of a type similar in magnitude and character to that contemplated under Project No: TR271 INTERSECTION IMPROVEMENTS - MOONSPINNER ST AT WEST PRESERVE LOOP within the past two years. Include the location of each project as well as the name, address, and phone number of the owner, and name of individual to contact.
Subcontractors performing in excess of one half of one percent of the prime Contractor’s total bid, or in the construction of streets or highways, one half of one percent of the prime contractor’s total bid or ten thousand dollars ($10,000), whichever is greater shall provide a similar outline. Additional pages outlining this portion of the Bid may be attached. Failure to provide this statement may result in rejection of the bid by the City of Chino.
1. Owner’s Name:
Contact Person: Phone:
Address of Owner:
Project Description:
Amount of Contract: Completion Date:
2. Owner’s Name:
3. Owner’s Name:
Contractor agrees to comply with all federal, state, and local laws, rules, regulations, and ordinances, as applicable. It is further acknowledged that contractor certified compliance with all provisions, laws, acts, regulations, etc. as specifically noted above.
Contractor’s Name/Company Name:
Address:
Phone Number:
Email:
Name of Authorized Representative:
Title of Authorized Representative:
Signature of Authorized Representative:
Date:
CONTENTS OF DOCUMENTS
REQUIRING COMPLETION, SIGNATURE OR CERTIFICATION
PRIOR TO AWARD OF CONTRACT
Agreement
Performance Bond
Labor and Material Bond
Warranty Bond
Contract No.:
Approved:
AGREEMENT
THIS AGREEMENT is made and entered into this xTH day of Month, 2026 by and between THE CITY OF CHINO, a municipal corporation, hereinafter called “City”, and Contractor Name, hereinafter called “Contractor”.
WITNESSETH, that the parties hereto mutually agree as follows:
ARTICLE I: For and in consideration of the payments and agreements hereinafter mentioned to be made and performed by City, Contractor agrees to perform and complete all of the work for the project Intersection Improvements - Moonspinner St at West Preserve Loop in a good and workmanlike manner in accordance with all plans and specifications therefor, to furnish at Contractor’s sole cost and expense all tools, equipment, labor, and materials necessary therefor, except such materials and equipment as are expressly stipulated to be furnished by City, and to do everything required by the Contract Documents.
ARTICLE II: Contractor shall be responsible for furnishing all labor, materials, equipment, tools, and services, furnishing and removing all plants, temporary structures, tools, and equipment, and doing everything required by this Agreement and by the Contract Documents. Contractor shall also be responsible for all losses and damages arising out of the performance of the Work, from the action of the elements, or from any unforeseen difficulties that may arise during the prosecution of the Work until its acceptance by City; for all risks of every description associated with the Work; and for all expenses resulting from the suspension or discontinuance of the Work. City shall pay Contractor, and Contractor shall receive, for completing the Work in accordance with the requirements of the Contract Documents and in full compensation therefor, the price named in the Bid Proposal. Subject to any additions or deductions that may be made by change order or amendment, and any penalties or damages that may be assessed against Contractor, Contractor shall receive a total contract amount of xxxxx Dollars and ($ xxxxx) for completion of the contract work.
ARTICLE III: The City hereby employs said Contractor to perform the work according to the terms of this Agreement for the above-mentioned price(s), and agrees to pay the same at the time, in the manner, and upon the conditions stipulated in the Contract Documents; and the said parties for themselves, their heirs, executors, administrators, successors and assignees, do hereby agree to the full performance of the covenants herein contained.
ARTICLE IV: Contractor shall begin work after receiving a Notice to Proceed from the City and the work shall be completed within Thirty (30) working days. If the work is not completed within said time period, liquidated damages shall apply.
ARTICLE V: The Notice Inviting Bids, the Summary of Work, the Instructions to Bidders, the Bid Documents, the Required Post-Bid Documents, the General Provisions, the Special Provisions, the Technical Specifications, and all other drawing, plans, or specifications for the Work (collectively, “Contract Documents”) are hereby incorporated into and made part of this Agreement.
ARTICLE VI: Contractor shall indemnify, defend with legal counsel approved by City, and hold harmless City, its officers, officials, employees and volunteers from and against all liability, loss, damage, expense, cost (including without limitation reasonable legal counsel fees, expert fees and all other costs and fees of litigation) of every nature arising out of or in connection with Contractor's negligence, recklessness or willful misconduct in the performance of work hereunder or its failure to comply with any of its obligations contained in this Agreement, except such loss or damage which is caused by the sole or active negligence or willful misconduct of the City. In instances where City is shown to have been actively negligent and where City’s active negligence accounts for only a percentage of the liability involved, the obligation of Contractor will be for that entire portion or percentage of liability not attributable to the active negligence of City. Should conflict of interest principles preclude a single legal counsel from representing both City and Contractor, or should City otherwise find Contractor’s legal counsel unacceptable, then Contractor shall reimburse the City its costs of defense, including without limitation reasonable attorneys’ fees, expert fees and all other costs and fees of litigation. The Contractor shall promptly pay any final judgment rendered against the City (and its officers, officials, employees and volunteers) with respect to claims determined by a trier of fact to have been the result of the Contractor’s negligent, reckless or wrongful performance. It is expressly understood and agreed that the foregoing provisions are intended to be as broad and inclusive as is permitted by the law of the State of California and will survive termination of this Agreement.
ARTICLE VII: No officer or employee of the City shall have any financial interest in this Agreement nor shall any such officer or employee participate in any decision relating to the Agreement which affects his financial interest or the financial interest of any corporation, partnership or association in which he is interested, in violation of any State statute or regulation. Similarly, Contractor warrants that it has not paid or given and will not pay or give any third party any money or other consideration for obtaining this Agreement.
ARTICLE VIII: This Agreement shall be interpreted, construed and governed both as to validity and to performance of the parties in accordance with the laws of the State of California. Legal actions concerning any dispute, claim or matter arising out of or in relation to this Agreement shall be instituted in the Superior Court of the County of San Bernardino, State of California, or any other appropriate court in such county, and Consultant covenants and agrees to submit to the personal jurisdiction of such court in the event of such action. In the event of litigation in a U.S. District Court, venue shall lie exclusively in the Central District of California, in the County of San Bernardino, State of California.
ARTICLE IX: Waiver by any party to this Agreement of any term, condition, or covenant of this Agreement shall not constitute a waiver of any other term, condition, or covenant. Waiver by any party of any breach of the provisions of this Agreement shall not constitute a waiver of any other provision or a waiver of any subsequent breach or violation of any provision of this Agreement. Acceptance by City of any work or services by Contractor shall not constitute a waiver of any of the provisions of this Agreement. No delay or omission in the exercise of any right or remedy by a non-defaulting party on any default shall impair such right or remedy or be construed as a waiver. Any waiver by either party of any default must be in writing and shall not be a waiver of any other default concerning the same or any other provision of this Agreement.
ARTICLE X: No officer or employee of the City shall be personally liable to the Contractor, or any successor in interest, in the event of any default or breach by the City or for any amount which may become due to the Contractor or to its successor, or for breach of any obligation of the terms of this Agreement.
ARTICLE XI: The terms of this Agreement shall be construed in accordance with the meaning of the language used and shall not be construed for or against either party by reason of the authorship of this Agreement or any other rule of construction which might otherwise apply.
ARTICLE XII: In the course of its work under this Agreement, the Contractor, its agents and employees shall be bound by and comply with all applicable federal, state and local laws and requirements.
ARTICLE XIII: The persons executing this Agreement on behalf of the parties hereto warrant that (i) such party is duly organized and existing, (ii) they are duly authorized to execute and deliver this Agreement on behalf of said party, (iii) by so executing this Agreement, such party is formally bound to the provisions of this Agreement, and (iv) the entering into this Agreement does not violate any provision of any other Agreement to which said party is bound.
IN WITNESS WHEREOF, the parties hereto have caused this contract to be executed on the day and year first above written.
Approved as to Form: Approved as to Content:
City Attorney Hye Jin Lee, P. E.
Director of Public Works
CONTRACTOR COMPANY NAME:
Dated: By:
Name:
(Please Type or Print Name)
(Signature must be notarized) Title:
(Please Type or Print Title)
CITY OF CHINO
Dated:
Dr. Linda Reich, City Manager
ATTEST:
Natalie…
This is the start of the file's text. The full file is on GovTribe.