ILDOT 97894-086.pdf

PDF 6 MB Posted

Attached to
Resurfacing, Patching, Sidewalk Replacement, Curb and Gutter Replacement, and Pedestrian Signal installation
Solicitation number
97894
Issued by
St. Clair County, Illinois

About this file

This is a Notice to Bidders and Supplemental Specifications document issued by the Illinois Department of Transportation (IDOT) for Contract No. 97894 in St. Clair County, Section 22-00176-06-RS, located in Belleville, Illinois. The project involves resurfacing, patching, sidewalk replacement, curb and gutter replacement, and pedestrian signal installation on West Main Street from 28th Street to 49th Street, encompassing 8,179.4 feet (1.55 miles). The scope of work includes removals, class B pavement patches, sidewalk and curb work, driveway pavement, HMA surface removal and overlay, storm sewer inlets, pavement markings, traffic signal installation including conduit, signal heads, and pedestrian push-buttons, and seeding operations. Electronic bids must be submitted to the iCX system prior to 12:00 p.m. on September 18, 2026, at which time bids will be publicly opened. The contract will be awarded to the lowest responsive and responsible bidder. The contractor must conduct a pre-job conference with subcontractors and union representatives at least 14 calendar days prior to construction commencement and submit various shop drawings for approval, including detectable warnings, HMA mix design, PCC mix design, and pavement markings.

The contract includes strict construction sequencing requirements divided into ten stages to minimize traffic disruption, with lanes maintained open to traffic except for designated four-day closures per street for pavement patching. The contractor must maintain access to all affected properties and businesses throughout construction and coordinate with the City of Belleville regarding any road closures requiring 48-hour advance approval. Multiple utility adjustments are required, including water meters and valves by Illinois American Water, electrical and gas relocations by Ameren UE, and fiber optic adjustments by Windstream, AT&T, and Segra. Traffic control surveillance is limited to 10 calendar days maximum during concrete median construction. The project employs both Quality Control/Quality Assurance procedures for hot-mix asphalt and requires compliance with OSHA safety standards, prevailing wage requirements, and DBE participation documentation. No specific contract duration or renewal terms are identified in the specifications provided.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting September 18, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 97894 ST. CLAIR County Section 22-00176-06-RS (Belleville) Route FAU 9182 (West Main Street) Project IHZ7-687 () District 8 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

September 18, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 97894 ST. CLAIR County Section 22-00176-06-RS (Belleville) Project IHZ7-687 () Route FAU 9182 (West Main Street) District 8 Construction Funds

Resurfacing, patching, sidewalk replacement, curb and gutter replacement, and pedestrian signal installation on West Main Street from 28th Street to 49th Street in Belleville.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

CONTRACT 97894

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS

Table of Contents

CHECK SHEET # PAGE NO.

LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment

SPECIAL PROVISIONS

FAU ROUTE 9182 (WEST MAIN STREET)

SECTION: 22-00176-06-RS

PROJECT: IHZ7 (687)

BELLEVILLE, ILLINOIS

INDEX TO SPECIAL PROVISIONS

DESCRIPTION OF WORK

COORDINATION OF CONTRACT DOCUMENTS

SHOP DRAWINGS

SAFETY AND HEALTH

SAFETY AND PROTECTION

CONSTRUCTION CONTRACTS

SEQUENCE OF CONSTRUCTION OPERATIONS

TRAFFIC CONTROL PLAN

PUBLIC NOTICE

TRENCH BACKFILL

SEEDING, CLASS 1A

AGGREGATE BASE COURSE, TYPE B 4”

BITUMINOUS MATERIALS (TACK COAT)

HOT-MIX ASPHALT SURFACE REMOVAL, TEMPORARY RAMPS

INCIDENTAL HOT-MIX ASPHALT SURFACING

PORTLAND CEMENT CONCRETE PAVEMENT, THICKNESS SPECIFIED (JOINTED)

TIE BARS & REINFORCEMENT BARS

EXPANSION JOINTS

DETECTABLE WARNINGS

HOT-MIX ASPHALT SURFACE REMOVAL

CLASS B PATCHES (SPECIAL)

STORM SEWER REMOVAL 12”

WATER VALVES TO BE ADJUSTED

DOMESTIC METER VAULTS TO BE ADJUSTED

TYPE 3 FRAME AND GRATE

TRAFFIC CONTROL SURVEILLANCE

TRAFFIC SIGNAL POST

SIGNAL HEAD

PEDESTRIAN SIGNAL HEAD

DETECTOR LOOP, TYPE I

PEDESTRIAN PUSH-BUTTON

REMOVE EXISTING TRAFFIC SIGNAL EQUIPMENT

REMOVE EXISTING HANDHOLE

SEQUENCE OF TRAFFIC SIGNAL CONSTRUCTION

KEEPING EXISTING TRAFFIC SIGNALS IN OPERATION

CONTRACTOR ACCESS

HOT-MIX ASPHALT SURFACE REMOVAL, VARIABLE DEPTH

CURB & GUTTER (SPECIAL)

STAMPED COLORED PORTLAND CEMENT CONCRETE MEDIAN SURFACE 6 INCH

CONCRETE MEDIAN (SPECIAL)

TRAFFIC CONTROL AND PROTECTION, (SPECIAL)

HANDHOLE (SPECIAL)

HANDHOLE TO BE ADJUSTED

TRAFFIC SIGNAL TURN-ON AND FINAL INSPECTION

CONCRETE STEPS

CONSTRUCTION LAYOUT

GREEN METHYL METHACRYLATE (MMA) PAVEMENT MARKING

METHYL METHACRYLATE (MMA) PAVEMENT MARKING – LINE 24”

STATUS OF UTILITIES TO BE ADJUSTED

LR 107-4 INSURANCE

LR 702 CONSTRUCTION AND MAINTAINENCE SIGNS

LR 1030-2 LOCAL QUALITY ASSURANCE / QUALITY MANAGEMENT QC/QA

SUBMITTAL OF EEO/LABOR DOCUMENTATION

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING 37

BDE SPECIAL PROVISIONS

The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.

File Name Pg. Special Provision Title Effective Revised 80099 39 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009

5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022

80460 41 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 58 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 62 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026

* 80029 64 Disadvantaged Business Enterprise Participation Sept. 1, 2000 July 2, 2026 80467 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 68 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 Inlet Filters April 1, 2026

* 80477 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 72 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 73 Pavement Patching Aug. 1, 2025 80441 74 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 Raised Reflective Pavement Markers Nov. 1, 2025 80455 80 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025

* 80445 82 Seeding Nov. 1, 2022 July 1, 2026 80457 88 Short Term and Temporary Pavement Markings April 1, 2024 April 2, 2024 80462 92 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 94 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 Structural Repair of Concrete Jan. 1, 2026 80397 96 Subcontractor and DBE Payment Reporting April 2, 2018 80391 97 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019 80463 98 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025

File Name Pg. Special Provision Title Effective Revised 80482 99 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 101 Surveying Services April 1, 2025 80481 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025

* 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 102 Traffic Signal Backplate Aug. 1, 2025 20338 103 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022 80439 106 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2022 80458 Waterproofing Membrane System Aug. 1, 2024 80302 107 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 108 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026

* 80485 111 Work Zone Width Restriction July 1, 2026 80071 112 Working Days Jan. 1, 2002

SPECIAL PROVISIONS

FAU ROUTE 9812 (WEST MAIN STREET)

SECTION: 22-00176-06-RS

PROJECT: IHZ7 (687)

BELLEVILLE, ILLINOIS

The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction", Adopted January 1, 2022, the “Supplemental Specifications and Recurring Special Provisions, Adopted January 1, 2026, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways" and the “Manual of Test Procedures of Materials” in effect on the date of the invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein and the “Standard Specifications for Water and Sewer Construction in Illinois”, 8th Edition which apply to and govern the construction of FAU 9182 (WEST MAIN STREET), Section 22-00176-06-RS, Belleville, Illinois, and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.

DESCRIPTION OF WORK

The proposed resurfacing project is located on West Main Street from 29th Street to 49th Street. The project length is 8,179.4 feet (1.55 miles).

The work on this project consists of removals, class B pavement patch, sidewalk, curb and gutter, driveway pavement, HMA surface removal, HMA surface course, storm sewer inlets, pavement markings, traffic signal conduit, signal heads, pedestrian push-buttons, seeding and all incidental and collateral work necessary to complete the work in the above-described Section according to the plans, specifications and special provisions.

COORDINATION OF CONTRACT DOCUMENTS

If a conflict exists between the “Standard Specifications for Road and Bridge Construction” and the “Standard Specifications for Water and Sewer Construction in Illinois”, the “Standard Specifications for Road and Bridge Construction” shall govern.

SHOP DRAWINGS

The Contractor shall submit shop drawings of the following items according to Articles 1042.03(b) and 105.04 of the "Standard Specifications for Road and Bridge Construction":

Detectable Warnings Inlets, Type A, Type 3 Frame & Grate Type 1 Frame, Closed Lid Concrete Steps Sign Panels Topsoil Aggregate Gradation HMA Mix Design

PCC Mix Design Thermoplastic Pavement Marking Green Methyl Methacrylate Pavement Marking Methyl Methacrylate Pavement Marking – Line 24”

Submit shop drawings for review and approval to:

Mr. Scott Saeger, City Engineer City of Belleville 101 S Illinois Street Belleville, Illinois 62220

Concurrent with the required shop drawing submittals to the City, the Contractor shall also submit a copy of each submittal to the Department. A maximum of two reviews by the Engineer will be provided for each shop drawing submittal. If any additional reviews are required, the Contractor shall pay the Engineer for all costs incurred at an hourly rate of $150. Payment for additional reviews shall be made directly to the City.

SAFETY AND HEALTH

The Contractor shall be responsible for enforcing all O.S.H.A. Safety and Health Standards pertaining to the construction industry as established by the United States Department of Labor, Occupational Safety and Health Administration. Such standards include, but are not limited to, 29 CFR 1910 and 1926.

SAFETY AND PROTECTION

A. CONTRACTOR shall be responsible for initiating, maintaining and supervising all safety and precautions and programs in connection with the Work. CONTRACTOR shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:

1. All employees on the work and other persons and organizations who may be affected thereby;

2. All the Work and materials and equipment to be incorporated therein, whether in storage on or off the site; and

3. Other property at the site adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and underground facilities not designated for removal, relocation or replacement in the course of construction.

CONTRACTOR shall comply with all applicable laws and regulations of any public body having jurisdiction for the safety of persons and property or to protect them from damage, injury or loss; and shall erect and maintain all necessary safeguards for such safety and protection. CONTRACTOR shall notify owners of adjacent property and of underground facilities and utility owners when prosecution of the Work may affect them and shall cooperate with them in the protection, removal, relocation and replacement of their property. All damage, injury or loss to any property referred to in paragraph 2. or 3. caused, directly or indirectly, in whole or in part, by CONTRACTOR, any Subcontractor, Supplier or any other person or organization directly or indirectly employed by any of them to perform or furnish any of the Work or anyone for whose acts either of them may be liable, shall be remedied by CONTRACTOR (except damage or loss attributable to the fault of Drawings or Specifications or to the acts or omissions of OWNER or ENGINEER or anyone employed by either of them or anyone for acts either of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of CONTRACTOR). CONTRACTOR's duties and responsibilities for the safety and protection of the Work shall continue until all the Work is completed and ENGINEER has issued a notice to OWNER and CONTRACTOR that the Work is acceptable.

B. CONTRACTOR shall designate a responsible representative at the site whose duty shall be the prevention of accidents. This person shall be CONTRACTOR's superintendent, unless otherwise designated in writing by CONTRACTOR to

OWNER.

C. In EMERGENCIES affecting the safety or protection of persons or the Work or property at the site or adjacent thereto, CONTRACTOR, without special instructions or authorization from ENGINEER or OWNER, is obligated to act to prevent threatened damage, injury or loss. CONTRACTOR shall give ENGINEER prompt, written notice if CONTRACTOR believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby. If ENGINEER determines that a change in the Contract Documents is required because of the action taken in response to an emergency, a Work Directive Change or Change Order will be issued to document the consequences of the changes or variations.

CONSTRUCTION CONTRACTS

The successful bidder, as a condition of this contract, must submit evidence that he has conducted a pre-job conference with his Subcontractors and their employees, or the employees' duly recognized representatives and union officials, to determine employee jurisdiction, job assignment and work schedules. This requirement is to promote industrial harmony and to eliminate work stoppages and jurisdictional disputes. The pre-job conference shall be conducted at least 14 calendar days prior to the commencement of any construction.

SEQUENCE OF CONSTRUCTION OPERATIONS

The Contractor shall conduct his work within the approved Sequence of Construction Operations at all times. The work shall be done in a manner that will minimize the inconvenience to local traffic. If a winter shutdown is experienced, the contractor shall clean up the site, open all lanes, and ensure there is proper striping and roadway signs during this time.

The Contractor shall conduct his operations to ensure local access to all properties throughout the project limits according to Article 107.09 and Section 701 and 703 of the "Standard Specifications for Road and Bridge Construction". If required, Type I, Type II or vertical barricades shall be used to channel traffic from the following locations to the adjoining side streets or private entrances. The number required will be determined by the Engineer during construction.

No main line road closures are planned, but if operations require closures, all road closures must be approved by the City of Belleville at least 48 hours prior to enacting any road closures. The City of Belleville will notify the appropriate Fire and Police Departments.

SUGGESTED SEQUENCE

During construction, the Contractor will be required to maintain access to all properties affected by this work. AGGREGATE FOR TEMPORARY ACCESS according to Section 402 of the “Standard Specifications for Road and Bridge Construction” will be used for this purpose.

The Contractor will not be allowed to begin subsequent construction operations until the preceding work is substantially complete. The construction sequence shall be compressed as much as possible to minimize the inconvenience to local traffic.

Unless authorized by the Engineer, the Contractor shall complete the construction in the following suggested sequence:

STAGE 1:

Setup traffic control and erosion control

STAGE 2:

Close the northbound outside lane and complete ADA ramps, associated curb work, and sidewalk work, following traffic control in highway standard 701602 Case IV. It is the contractor’s responsibility to maintain access to all business and driveways during this stage of work. Any required over excavation for curb work shall be patched with concrete at no additional cost to the contract.

STAGE 3:

Close the southbound outside lane and complete ADA ramps, associated curb work, and sidewalk work, following traffic control in highway standard 701602 Case IV. It is the contractor’s responsibility to maintain access to all business and driveways during this stage of work. Any required over excavation for curb work shall be patched with concrete at no additional cost to the contract.

STAGE 4:

Complete pavement patching and curb replacement for the existing drive lanes, following traffic control detail in the plan set for closing the two travel lanes and center turn lane to allow 8’ of clearance between open excavation at live traffic. Traffic Control Surveillance will not be allowed during this stage. It is the contractor’s responsibility to maintain access to all business and driveways during this stage of work.

STAGE 5:

Close the center drive lanes and the center turn lane to allow 8’ of clearance between open excavation at live traffic. Traffic Control Surveillance will not be allowed during this stage. Complete the pavement patching in the Center Turn Lane and pedestrian refuge islands in the center turn lane following highway standard 7016002 Case I.

STAGE 6:

Complete mill and overlay. The milling operation shall not be more than 48 hours ahead of the hot-mix asphalt paving operations. The contractor shall only mill the amount of material that can be replaced with hot-mix asphalt surface course within 48 hours.

STAGE 7:

Complete permanent pavement markings on lane lines and buffer zone and crosswalks at intersections. Mid-block crosswalks may be striped if contractor guarantees no damage during median installation.

STAGE 8:

Cut in and construct CONCRETE MEDIAN (SPECIAL) in the buffer zone. Lanes at the buffer zone are to be narrowed to allow a minimum of 24 inches from the travel way to the edge of work. Follow traffic control in highway standard 701006. This stage can be completed with Stage 4 and 5 but not with Stage 2 if the contract can fit their milling and paving machines between the proposed CONCRETE MEDIAN (SPECIAL) and the existing curb.

STAGE 9:

Stripe crosswalks at mid-block crossings.

STAGE 10:

Clean up the site, remove traffic control and erosions control.

All pavement patches, entrances, and roads shall be constructed to minimize disruption to traffic. This can be done by constructing them half at a time or by high early strength concrete unless written approval is received from the City and property owner to allow full closure.

Side streets may have up to a 4-day closure per street for pavement patching. Two adjacent streets should not be closed at the same time to limit the inconvenience to local traffic. Dead end streets should be pavement patched half at a time to allow access to all properties.

Traffic signal work may be completed during any stage with suitable traffic control.

Seeding operations shall be completed as soon as possible to minimize erosion potential.

The Contractor may submit an alternate sequence of operations and traffic control plan that would expedite construction and still maintain traffic control. Any and all changes to these plans must be submitted in writing and approved in advance by the Engineer. No additional compensation will be allowed if alternate plans are approved.

TRAFFIC CONTROL PLAN

Traffic control shall be according to the applicable Sections of the "Standard Specifications for Road and Bridge Construction", the applicable guidelines contained in the "Illinois Manual on Uniform Traffic Control Devices for Streets and Highways", these special provisions, and all special details and Highway Standards contained herein and on the plans.

At the preconstruction meeting, the Contractor shall furnish the name of the individual in his/her direct employ who is responsible for the installation and maintenance of the traffic control for this project. If the actual installation and maintenance are to be accomplished by the Subcontractor, consent shall be requested of the Engineer at the time of the preconstruction meeting according to Article 108.01 of the "Standard Specifications for Road and Bridge Construction". This shall not relieve the Contractor of the foregoing requirement for a responsible individual in his direct employ. The Department will provide the Contractor the name of its representative who will be responsible for the observation of the Traffic Control Plan.

The Contractor shall furnish, erect, maintain and remove all warning signs, flags, barricades and lights according to Article 107.14 and Sections 701 and 703 of the "Standard Specifications for Road and Bridge Construction", the latest edition of the "Manual of Uniform Traffic Control Devices for Construction and Maintenance Operations", the Special Provisions, and/or as directed by the Engineer.

Articles 107.09 and 107.14 and Sections 701 and 703 of the "Standard Specifications for Road and Bridge Construction" and the following Highway Standards relating to traffic control apply to this contract:

701301 701501 701502 701602 701701 701801

701901 MODIFIED URBAN LANE CLOSURE, MULTILANE, 2W WITH

BIDIRECTIONAL LEFT TURN LANE.

29th through 49th Streets shall be kept open to traffic at all times with the exception of a 4 day closure per street for pavement patching. Two adjacent streets should not be closed at the same time to limit the inconvenience to local traffic. Dead end streets should be pavement patched half at a time to allow access to all properties. Short-term, daytime lane closures will be allowed on the roads and entrances listed when workers are present according to Highway Standard 701501.

In addition, the following special provision(s) will also govern traffic control for this project:

SEQUENCE OF CONSTRUCTION OPERATIONS

TRAFFIC CONTROL AND PROTECTION, (SPECIAL)

CONTRACTOR ACCESS

WORK ZONE TRAFFIC CONTROL DEVICES

VEHICLE AND EQUIPMENT WARNING LIGHTS

PUBLIC NOTICE

Each Wednesday, the Contractor shall furnish his schedule for the next week’s work and shall post signs at least 72 hours in advance of his work on each street requiring a lane closure. Handbill notices approved by the Engineer shall be delivered to each residence located within the work zone, at least 72 hours prior to commencing work. Notices shall explain the proposed work and request the resident’s forbearance of the inconvenience. All complaints should be directed to the Contractor. Residents may contact the City if their concerns are not resolved satisfactorily by the Contractor.

This work will not be paid for separately, and the cost shall be considered as included in the contract unit prices bid for the various items of work involved.

TRENCH BACKFILL

This work shall be constructed according to Section 208 of the "Standard Specifications for Road and Bridge Construction", except as modified herein:

Fine aggregate according to Article 1003.04 may be used for bedding only, except as follows: Fine aggregate will be required for trench backfill within 2 ft. of all gas mains and gas service lines that are exposed during trenching operations.

Material for trench backfill shall be coarse aggregate gradation CA 6, CA 10 or CA 18 as specified in Article 1004.05.

Trench backfill material shall be compacted according to Method 1, as specified in Article 550.07(a) of the "Standard Specifications for Road and Bridge Construction".

This work will not be paid for separately but shall be included in the contract unit price of the various storm sewer items for which the trench backfill is required.

SEEDING, CLASS 1A

This work shall consist of preparing the seed bed, and furnishing, transporting and placing the seed required to restore all disturbed earth surfaces according to Sections 250 and 251 of the “Standard Specifications for Road and Bridge Construction”.

The Contractor shall guarantee a minimum of 90 percent uniform growth over the entire seeded area(s). Areas sustaining less than 90 percent uniform growth shall be interseeded or reseeded, as determined by the Engineer, at no additional cost.

This work will be paid for at the contract unit price per acre for SEEDING, CLASS 1A.

AGGREGATE BASE COURSE, TYPE B 4”

This work shall consist of furnishing and placing aggregate base according to Section 351 of the “Standard Specifications for Road and Bridge Construction.”

The moisture content of the aggregate shall be sufficient to prevent segregation of the aggregate. Water shall be added as required by the Engineer to obtain compaction satisfactory to the Engineer.

The cost of this work shall be included in the contract unit price per square yard for

AGGREAGATE BASE COURSE. TYPE B 4”.

BITUMINOUS MATERIALS (TACK COAT)

This work shall consist of applying bituminous materials (tack coat) on a prepared base according to Section 406 of the “Standard Specifications for Road and Bridge Construction.”

Bituminous tack coat application rate of 0.05 lb per sq ft was assumed in the quantities following the milling process.

Aggregate for covering the tack coat will not be paid for separately but shall be reported in the unit price for bituminous material tack coat.

If aggregate for covering the tack coat is not needed to maintain local traffic it may be eliminated at the engineer’s direction.

This work will not be paid for separately but shall be included in the reported price for BITUMINOUS MATERIALS (TACK COAT) in the unit price.

HOT-MIX ASPHALT SURFACE REMOVAL, TEMPORARY RAMPS

This work shall consist of constructing, maintaining and removing temporary ramps at butt joints and at structures in the pavement, according to Article 406.08 of the "Standard Specifications for Road and Bridge Construction" and BDE special provision “Drainage and Inlet Protection Under Traffic”.

Construction, maintenance and removal of temporary ramps will not be measured separately for payment.

The cost of this work shall be paid for at the contract unit price per square yard for TEMPORARY RAMPS, which price shall include constructing, maintaining and removing all temporary ramps.

INCIDENTAL HOT-MIX ASPHALT SURFACING

This work shall consist of the preparation of the base, the application of bituminous priming material and aggregate, and the construction of a hot-mix asphalt (HMA) surface on a prepared base at the locations shown on the plans according to Section 408 the "Standard Specifications for Road and Bridge Construction."

Bituminous prime coat and prime coat aggregate are required, but will not be measured separately for payment.

This work will be paid for at the contract unit price per ton for INCIDENTAL HOT-MIX ASPHALT SURFACING, which price shall include the bituminous priming material and aggregate for covering the prime coat.

PORTLAND CEMENT CONCRETE PAVEMENT, THICKNESS SPECIFIED (JOINTED)

This work shall consist of constructing a Portland cement concrete pavement according to Section 420 of the "Standard Specifications for Road and Bridge Construction,” except as modified herein.

All tie bars and reinforcement bars used in Portland cement concrete pavement shall be epoxy coated.

Tie bars and reinforcement bars will not be paid for separately but shall be included in the contract unit price of the various concrete pavement items for which tie bars and reinforcement bars are required.

All references to Sections or Articles in this specification shall be understood to mean a specified Section or Article of the "Standard Specifications for Road and Bridge Construction".

Article 420.03(b). A formless paver will not be required.

Article 420.03(c). A mechanical concrete spreader will not be required.

Article 420.03(d). A finishing machine will not be required.

Article 420.03(e). A mechanical longitudinal float will not be required.

Article 420.03(f). A concrete finisher float will not be required.

Article 420.03(h). Power driven finishing machines, including vibratory screeds and truss-type vibratory screeds, which are specifically designed for finishing concrete pavement and meet the approval of the Engineer, will be allowed.

Hand held fogging equipment capable of spraying a uniform application of membrane curing compound and maintaining constant pressure meeting the approval of the Engineer, will be allowed.

Article 420.09(a) (1).Revise this Article as follows:

After the concrete has been struck off, it shall be given the required consolidation by the vibratory method or by other means which will obtain a uniform and satisfactory density throughout the pavement.

If the vibratory method is used, the vibrating impulses shall be applied directly to the concrete through an apparatus especially designed for this purpose in a manner that the vibratory impulses are transmitted through the concrete mass with sufficient intensity to consolidate it throughout its entire depth and width. Not more than one pass of the vibratory equipment shall be made through the pavement.

Article 420.09(a) (3).Revise the first sentence of this Article to read as follows:

Vibrating screed. An approved vibrating screed may be used to strike off, consolidate and finish pavement.

Article 420.09(b). Longitudinal Float Hand Method will be permitted if approved by the

Engineer.

Article 420.09(e). Type B final finish shall be used throughout the project unless directed otherwise by the Engineer.

Article 420.20. Revise the first paragraph of this Article to read as follows:

Basis of Payment. This work will be paid for at the contract unit price per square yard for PORTLAND CEMENT CONCRETE PAVEMENT, of the thickness specified (JOINTED).

TIE BARS & REINFORCEMENT BARS

This work shall consist of furnishing and placing tie bars and reinforcement bars in concrete pavement, concrete curb, and concrete curb and gutter according to Sections 420, and 606 of the “Standard Specifications for Road and Bridge Construction”, except as modified herein:

All tie bars and reinforcement bars used in Portland cement concrete pavement, concrete curb, and concrete curb and gutter shall be epoxy coated.

This work will not be paid for separately but shall be included in the contract unit price of the various concrete pavement, concrete curb, and concrete curb and gutter items for which the tie bars and reinforcement bars are required.

EXPANSION JOINTS

This work shall consist of constructing expansion joints in concrete driveway pavement and sidewalk according to Articles 423.07 and 424.07 of the “Standard Specifications for Road and Bridge Construction” and Highway Standard 424001 except as modified herein:

Expansion joints required under Article 423.07 and 424.07(b) shall be preformed fiber joint filler according to Article 1051.04 of the “Standard Specifications for Road and Bridge Construction” and shall have a perforated tear off wood or plastic strip to provide a uniform 3/4 in. reservoir/channel for the required sealant.

Expansion joints required under Article 424.07(a) shall consist of preformed flexible foam expansion joint filler according to Article 1051.09 of the “Standard Specifications for Road and Bridge Construction” and shall have a pre-scored removable strip to provide a uniform 1/2 in. reservoir/channel for the required sealant.

Expansion joint filler and backer rod materials shall be a non-impregnated type that will not bond with the sealant.

Expansion joints shall be sealed with self-leveling (pour grade), or nonsag (gun) grade urethane sealant. The color of the sealant shall be limestone, unless otherwise approved by the Engineer.

This work will not be paid separately, but shall be included in the contract unit price of the various concrete items for which the expansion joints are required.

DETECTABLE WARNINGS

This work shall consist of constructing detectable warning surfaces in curb ramps and other locations shown on the plans according to Articles 424.09 of the “Standard Specifications for Road and Bridge Construction” and Highway Standard 424001 and 424026, and as modified herein:

Materials shall be: Cast-in-place replaceable panels.

Color shall be red.

Paver units shall consist of a homogeneous glass and carbon-reinforced composite which is colorfast and UV stable, Panel sections shall be of equal size and dimensions with no fragments unless approved by the Engineer.

Detectable warning panels shall be protected when applying curing compound to the adjoining concrete sidewalk. Any overspray on the panels shall be cleaned immediately to the satisfaction of the Engineer.

Joints between panels and around the perimeter of the panels shall be caulked with a self-leveling (pour grade), or nonsag (gun) grade urethane sealant. The color of the sealant shall be limestone, unless otherwise approved by the Engineer.

The concrete thickness under the panels shall be increased 1 inch. The subgrade shall be well-drained and properly compacted. Forms shall be positioned for proper grade, slope, and uniform slab thickness.

Detectable warning panels shall be placed as shown in the drawings and shall have visual contrast with the adjoining concrete surface. Adequate drainage shall be provided to prevent the accumulation of water and debris at the bottom of the ramp.

Panels shall be installed immediately in fresh concrete and adjusted to grade to ensure 100% surface contact with square edges of panels butted tightly together. The base of the truncated domes shall be set flush with the adjoining concrete surface. The maximum tolerance between the panels and the adjoining surface is 1/16 inch. Immediately after placement, the panels shall be checked for slope, elevation and proper grade. The concrete around the panels shall be edged with 1/8 in. radius edger and finished according to the contract specifications.

This work will be paid for at the contract unit price per square foot for DETECTABLE WARNINGS as specified herein.

HOT-MIX ASPHALT SURFACE REMOVAL

This work shall consist of removing hot-mix asphalt (HMA) surfaces to the limits specified on the plans according to Section 440 of the “Standard Specifications for Road and Bridge Construction”, except as modified herein.

Materials resulting from the HMA surface removal process shall become the property of the Contractor unless otherwise noted in the General Notes and their salvage value shall be reflected in the contract unit price for HOT-MIX ASPHALT SURFACE REMOVAL, thickness specified.

Concrete patches which have to be partially removed will be paid for as HOT-MIX ASPHALT SURFACE REMOVAL, thickness specified.

Manholes and valve vaults which are exposed by the HMA surface removal and transverse cuts at the end of the day that are more than 1/2 in. deep shall be tamped with a cold-mix asphalt. The cost of this temporary taper shall be included in the cost of HOT- MIX ASPHALT SURFACE REMOVAL, thickness specified.

When the removal width of the machine is less than the width of the lane, the operations shall be planned such that after the asphalt surface for a portion of the lane has been removed, the remaining portion shall have been removed by the end of the day so that the two passes begin and terminate even with each other.

If the depth of removal is greater than 1/2 in., the removal shall be tapered at the terminating point at the end of each day’s operation when the lane is open to traffic.

All materials, equipment, and labor necessary to complete the work and maintenance of the tapers as specified above shall be included in the contract unit price for HOT-MIX ASPHALT SURFACE REMOVAL, thickness specified.

After any HMA surface removal operation has been completed, the Contractor shall erect special “ROUGH GROOVED SURFACE” signs, as shown on the attached sheet, in advance of the construction zone in both directions, if applicable. In addition, these signs shall also be erected along side streets in advance of the construction zone.

These signs shall remain in place until they are no longer applicable as determined by the Engineer. They shall then be removed by the Contractor and become his property.

The cost of furnishing, erecting, maintaining, and removing these signs will not be paid for separately, but shall be considered as included in the cost of the HOT-MIX ASPHALT SURFACE REMOVAL, thickness specified.

This work will be paid for at the contract unit price per square yard for HOT-MIX ASPHALT SURFACE REMOVAL, of the thickness specified.

CLASS B PATCHES (SPECIAL)

This work shall consist of the removal of the existing pavement, the necessary excavation and the replacement with Class B patches of the type and thickness specified at the designated locations, according to Section 442 of the “Standard Specifications for Road and Bridge Construction”.

The existing pavement thickness is estimated to be 13 in. The existing pavement thickness shall be field verified. The existing pavement shall be replaced with a full-depth patch. If necessary, the pavement patching quantity will be adjusted according to Article

442.10 of the “Standard Specifications for Road and Bridge Construction”.

Dowel bars and tie bars of the diameter specified on the plans will be required and will not be measured separately for payment.

All tie bars and reinforcement bars used in CLASS B PATCHES, type specified, depth specified, (SPECIAL) shall be epoxy coated.

High-early strength concrete shall be used. The accelerator shall be non-chloride type and shall be according to AASHTO M 194, Type C (accelerating). A compressive strength of 3,000 psi shall be achieved within 24-36 hours.

Pavement fabric will be required, but will not be measured separately for payment.

Mandatory saw cuts will also not be measured separately for payment. A minimum 12 in.

wide ledge of undisturbed material shall be maintained along the sides of all pavement patches where trenching is required.

13” thick patches on W Main Street should be poured to match the existing roadway elevation. The patches will be milled off with the HMA SURFACE REMOVAL, 2” OR HMA SURFACE REMOVAL, VARIABLE DEPTH, at the contractor’s option, they may be poured lower than the existing pavement if temporary ramps are provided and they will be overlaid within 30 calendar days. These temporary ramps will not be paid for separately but shall be included in the cost of CLASS B PATCHES 13 INCH.

8” patches will be constructed to the finished grade elevations as shown in the plans and have a broom finish. Temporary ramps shall be used as needed and will not be paid for separately but shall be included in the unit cost for CLASS B PATCHES 8 INCH (SPECIAL). The intent of the 8” CLASS B PATCHES (SPECIAL) is to provide ADA compliant crosswalks at side streets. These patches will not be milled off and overlaid.

This work will be paid for at the contract unit price per square yard for CLASS B PATCHES (SPECIAL), of the type and thickness specified, which price shall include the cost of performing the work as specified in Section 442, including sawing and removal and disposal of existing materials; furnishing and installing contraction joints, dowel bars, tie bars, and pavement fabric, as required.

STORM SEWER REMOVAL 12”

This work shall consist of the removal and satisfactory disposal of existing storm sewers according to Section 551 of the “Standard Specifications for Road and Bridge Construction.”

Trenches resulting from the removal of existing storm sewers shall be backfilled according to Article 550.07 of the “Standard Specifications for Road and Bridge Construction” and according to the special provision for TRENCH BACKFILL

This work will be paid for at the contract unit price per foot for STORM SEWER REMOVAL 12”.

WATER VALVES TO BE ADJUSTED

This work shall consist of adjusting domestic water valves and meters to grade plans according to Section 602 of the “Standard Specifications for Road and Bridge Construction,” except as modified herein.

Existing material shall be reused where possible as directed by the Engineer. If the Engineer determines that the existing material is not reusable, the City will pay for the material that needs to be replaced as an extra to the contract.

DOMESTIC METER VAULTS TO BE ADJUSTED

This work shall consist of adjusting domestic water vaults to grade plans according to Section 602 of the “Standard Specifications for Road and Bridge Construction,” except as modified herein.

Existing material shall be reused where possible as directed by the Engineer. If the Engineer determines that the existing material is not reusable, the City will pay for the material that needs to be replaced as an extra to the contract.

TYPE 3 FRAME AND GRATE

This work shall consist of furnishing and installing cast iron frames and grates, together with the necessary inlets and manholes as shown on the plans according to Section 602 of the “Standard Specifications for Road and Bridge Construction”, except as modified herein.

All Type 3 Frames and grates shall conform to Highway Standard 604006, except the curb box shall have a single opening extending across the full width of the casting. The Contractor shall submit a shop drawing of the proposed frame and grate to the Engineer for approval according to Article 505.03 of the “Standard Specifications for Road and Bridge Construction”.

This work will be included the contract unit price per each for INLETS, TYPE A, TYPE 3

FRAME AND GRATE.

TRAFFIC CONTROL SURVEILLANCE

This work shall consist of surveillance of traffic control devices according to Section 701 of the “Standard Specifications for Road and Bridge Construction”.

Surveillance of traffic control devices is intended only during the construction of

CONCRETE MEDIAN (SPECIAL).

The contractor shall stage their work so that no more than 10 calendar days of traffic control surveillance is needed. No additional days will be paid for.

This work will be paid for at contract unit price per calendar day for TRAFFIC

CONTROL SURVEILLANCE.

TRAFFIC SIGNAL POST

This work shall consist of furnishing metal traffic signal posts and poles of the length specified and installing them on concrete foundations according to Sections 875 and 877 of the “Standard Specifications for Road and Bridge Construction”.

This work shall also include all material and labor necessary to apply a paint topcoat to all signal poles and arms including bases, fixtures, bracket bars, and all appurtenances.

The backs of all signs and appurtenances (including mounting brackets, bolts, nuts, washers, and fasteners) shall also be painted.

Surface Preparation for Iron or Steel Prior to being incorporated into an assembled product, steel may require blast cleaning to remove rolled-in mill scale, impurities, and non-metallic foreign materials. After assembly, all weld flux shall be mechanically removed.

The iron or steel product shall be degreased by immersion in an agitated 4.5 percent - 6 percent concentrated caustic solution elevated to a temperature ranging from 150-180 °F. It is then pickled by immersion in a heated sulfuric acid solution of 6 percent – 13 percent concentration, controlling the temperature at 150 °F. It is next rinsed clean from all residual effects of the caustic or acid solutions by immersion in a circulating fresh water bath.

Final preparation is done by immersion in a concentrated zinc ammonium chloride flux solution heated to 130 °F. The solution’s acidity content is maintained between 4.5-5.0 pH. The assembly is air dried to remove all moisture remaining in the flux coat and/or trapped within the product.

Surface Preparation for Aluminum Prior to being incorporated into an assembled product, material may require blast cleaning to remove rolled-in mill scale, impurities, and non-metallic foreign materials.

After assembly, all weld flux shall be mechanically removed.

The product shall be degreased by immersion in an agitated 4.5 percent – 6 percent concentrated caustic solution elevated to a temperature ranging from 150-180 °F. It is then pickled by immersion in a heated sulfuric acid solution of 6 percent – 13 percent concentration, controlling the temperature at 150 °F. It is next rinsed clean from all residual effects of the caustic or acid solutions by immersion in a circulating fresh water bath.

Zinc Coating for Iron or Steel The product is hot-dip galvanized to the requirements of either ASTM A123 (fabricated products) or ASTM A153 (hardware items) by immersion in a molten bath of prime western grade zinc maintained between 810-850 °F. Maximum aluminum content of the bath is controlled to 0.01 percent.

This is the start of the file's text. The full file is on GovTribe.