ILDOT 80D51-016.pdf
PDF 867 KB Posted
- Attached to
- Full Expressway Cleaning Cycle & Supplemental Sweeping - Various State Maintained Expressway Routes
- Solicitation number
- 80D51
- Issued by
- Cook County, Illinois
About this file
This is a Letting Notice and Special Provisions document issued by the Illinois Department of Transportation (IDOT) for Contract No. 80D51, a full expressway cleaning cycle and supplemental sweeping project on various state-maintained expressway routes within Cook, DuPage, Lake, and Will counties in District 1. The work consists of pickup, removal, and disposal of debris including limbs, sticks, leaves, sand, stones, dirt, weeds, deceased animal carcasses, refuse, and litter accumulated on expressway areas. The contract covers ten expressways: Eisenhower, Edens, Dan Ryan, Bishop Ford/Kingery, Kennedy, Stevenson, I-290 Extension, I-55, I-57, and I-80. The full expressway cleaning cycle encompasses approximately 1,131.2 total shoulder and curb miles and must be completed within 80 calendar days per work order. Supplemental sweeping work orders must be completed within 2 calendar days and are measured in miles of expressway shoulder cleaned. Electronic bids were due by 12:00 p.m. on September 18, 2026, through the iCX-Integrated Contractors Exchange system. The overall contract completion date is December 31, 2027. The contractor must obtain daily work authorization from the Engineer by 6:30 a.m. each workday and provide at least 72 hours advance notice for weekend or holiday work.
The contractor shall be liable for liquidated damages of $2,300 per calendar day for failure to complete interim cleaning cycles on time. Failure to maintain open traffic lanes results in damages of $2,000 per 15-minute interval or portion thereof. The contract is subject to federal-aid requirements and prevailing wage obligations under Illinois law. The contractor must maintain 10 two-way communication devices, provide high-intensity amber strobes on all vehicles, and ensure all personnel wear approved OSHA-standard flagger vests when not in vehicles. Equipment must include truck-mounted impact attenuators and comply with diesel retrofit emission control requirements for equipment rated 50 hp and above used more than seven days. The contract includes a 0.00% Disadvantaged Business Enterprise (DBE) participation goal. Contractors with awarded contract values of $500,000 or more must comply with the Illinois Works Apprenticeship Initiative, targeting 10% of total labor hours performed by apprentices, with at least 50% of apprentice hours performed by program graduates. The contract requires comprehensive traffic control in accordance with Illinois Department of Transportation standards and the Manual on Uniform Traffic Control Devices, with specific restrictions on lane closures, speed display trailers, and work zone protections.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
September 18, 2026 Letting
Notice to Bidders, Specifications and Proposal
Contract No. 80D51 Various Counties Section 2026-2190-I Various Routes District 1 Construction Funds
Prepared by S
Checked by (Printed by authority of the State of Illinois)
NOTICE TO BIDDERS
1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.
September 18, 2026 prevailing time at which time the bids will be publicly opened from the iCX SecureVault.
2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the
Invitation for Bids as:
Section 2026-2190-I Various Routes District 1 Construction Funds
Full Expressway Cleaning Cycle & Supplemental Sweeping shall consist of the pickup, removal and satisfactory disposal of limbs, sticks, leaves, sand, stones, dirt, weeds, debris, deceased animal carcasses, refuse, Litter and any other rubbish which has accumulated on the highway areas located on various State maintained expressway routes located within the counties of Cook, DuPage, Lake and Will.
3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.
(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.
4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to readvertise the proposed improvement, and to waive technicalities.
By Order of the Illinois Department of Transportation
Gia Biagi, Secretary
Section 2026-2190-I
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS
AND RECURRING SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
RECURRING SPECIAL PROVISIONS
The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:
CHECK SHEET # PAGE NO.
1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)
3 X EEO
4 X Specific EEO Responsibilities Nonfederal-Aid Contracts 5 X Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos Hot-Mix Asphalt Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes
10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays i
TABLE OF CONTENTS
LOCATION OF IMPROVEMENT
DESCRIPTION OF IMPROVEMENT
INTERIM COMPLETION DATE (VIA CALENDAR DAYS)
MAINTENANCE OF ROADWAYS (D1)
CONTRACT COMPLETION DATE
FAILURE TO COMPLETE THE WORK ON TIME
GENERAL REQUIREMENTS
FULL CYCLE EXPRESSWAY CLEANING (DAYTIME)
SUPPLEMENTAL SWEEPING
TRAFFIC CONTROL PLAN
PUBLIC CONVENIENCE AND SAFETY (D1)
TRAFFIC CONTROL FOR WORK ZONE AREAS
KEEPING THE EXPRESSWAY OPEN TO TRAFFIC
FAILURE TO OPEN TRAFFIC LANES TO TRAFFIC
TRAFFIC CONTROL AND PROTECTION (EXPRESSWAYS)(MAINTENANCE)
SPEED DISPLAY TRAILER (D1)
COMPENSABLE DELAY COSTS (BDE)
CONSTRUCTION AIR QUALITY – DIESEL RETROFIT (BDE)
DISADVANTAGED BUSINESS ENTERPRISE PARTICIPATION (BDE)
ILLINOIS WORKS APPRENTICESHIP INITIATIVE – STATE FUNDED CONTRACTS (BDE)
REMOVAL AND DISPOSAL OF REGULATED SUBSTANCES (BDE)
SUBCONTRACTOR AND DBE PAYMENT REPORTING (BDE)
SUBCONTRACTOR MOBILIZATION PAYMENTS (BDE)
SUBMISSION OF BIDDERS LIST INFORMATION (BDE)
SUBMISSION OF PAYROLL RECORDS – STATE CONTRACT (BDE)
SURVEYING SERVICES (BDE)
VEHICLE AND EQUIPMENT WARNING LIGHTS (BDE)
WEEKLY DBE TRUCKING REPORTS (BDE)
WORK ZONE TRAFFIC CONTROL DEVICES (BDE)
WORK ZONE WIDTH RESTRICTION (BDE)
PROJECT LABOR AGREEMENT
STATE OF ILLINOIS
SPECIAL PROVISIONS
The following Special Provisions supplement the "Standard Specifications for Road and Bridge Construction," adopted January 1 2022, the latest edition of the "Manual on Uniform Traffic Control Devices for Streets and Highways," and the "Manual of Test Procedures for Materials" in effect on the date of invitation for bids, and the Supplemental Specifications and Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction of Various Routes, Section 2026-2190-I, Various Counties, Contract No. 80D51 and in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take precedence and shall govern.
LOCATION OF IMPROVEMENT
This work is located on various State maintained expressway routes located within the counties of Cook, DuPage, Lake and Will.
DESCRIPTION OF IMPROVEMENT
The work to be done under Full Expressway Cleaning Cycle & Supplemental Sweeping shall consist of the pickup, removal and satisfactory disposal of limbs, sticks, leaves, sand, stones, dirt, weeds, debris, deceased animal carcasses, refuse, Litter and any other rubbish which has accumulated on the highway areas hereinafter described as the areas to be cleaned. After each cleaning cycle all areas must present an appearance which is completely satisfactory to the Engineer. Adequate equipment and hand labor shall be provided to accomplish the work to the satisfaction of the Engineer. Specific provisions for the two (2) categories of work will be described in subsequent pages of these Special Provisions.
INTERIM COMPLETION DATE (VIA CALENDAR DAYS)
The Contractor shall complete each Full Expressway Cleaning Cycles on or before the completion date as stated in the Work Order which will be based upon 80 calendar days regardless of over lapping cycles.
The Contractor shall complete each Supplemental Sweeping Work Order on or before the completion date as stated in the Work Order which will be based upon 2 calendar days regardless of over lapping work orders.
The completion date will be determined by the issuance date of the work Order adding the specified number of calendar days to the date the Work Order has been issued, unless a delayed start is granted by the Engineer. Failure to complete the Expressway Cleaning Cycles or Supplemental Sweeping in the required calendar days will result in liquidated damages as stated in Failure to Complete Work on Time section.
MAINTENANCE OF ROADWAYS (D1)
Effective: September 30, 1985 Revised: November 1, 1996
Beginning on the date that work begins on this project, the Contractor shall assume responsibility for normal maintenance of all existing roadways within the limits of the improvement. This normal maintenance shall include all repair work deemed necessary by the Engineer, but shall not include snow removal operations. Traffic control and protection for maintenance of roadways will be provided by the Contractor as required by the Engineer.
If items of work have not been provided in the contract, or otherwise specified for payment, such items, including the accompanying traffic control and protection required by the Engineer, will be paid for in accordance with Article 109.04 of the Standard Specifications.
CONTRACT COMPLETION DATE
The Contractor shall schedule his/her operations in order to complete all work and open all expressways to traffic on or before December 31, 2027.
The Provisions of Article 108.09 of the Standard Specification shall apply to the contract completion date.
FAILURE TO COMPLETE THE WORK ON TIME
Should the Contractor fail to complete the work on or before the completion date as specified in the Special Provision for “Interim Completion Date (via Calendar days) ”, or within such extended time as may have been allowed by the Department, the Contractor shall be liable to the Department in the amount of $2,300.00, not as a penalty but as liquidated damages, for each calendar day or a portion thereof of overrun in the contract time or such extended time as may have been allowed.
In fixing the damages as set out herein, the desire is to establish a certain mode of calculation for the work since the Department’s actual loss, in the event of delay, cannot be predetermined, would be difficult of ascertainment, and a matter of argument and unprofitable litigation. This said mode is an equitable rule for measurement of the Department’s actual loss and fairly takes into account the loss of use of the roadway if the project is delayed in completion. The Department shall not be required to provide any actual loss in order to recover these liquidated damages provided herein, as said damages are very difficult to ascertain. Furthermore, no provision of this clause shall be construed as a penalty, as such is not the intention of the parties.
A calendar day is every day shown on the calendar and starts at 12:00 midnight and ends at the following 12:00 midnight, twenty-four hours later.
GENERAL REQUIREMENTS
1. WORK AUTHORIZATION AND APPROVAL: The Engineer will verbally instruct the contractor on the type and the location of work to be performed (Expressway Cleaning and Supplemental Sweeping). The Contractor shall contact the Engineer by telephone, no later than 6:30 AM, each workday (excluding Saturdays, Sundays, and holidays observed by the Illinois Department of Transportation), to coordinate and obtain approval for daily work. At least 72 hours in advance of work on Saturdays, Sundays or holidays (including holidays observed by the Illinois Department of Transportation). Verbal work authorization instructions will be followed by written confirmation by the Engineer. The Contractor shall not revise the sequence of daily planned work without the Engineer's approval.
No Daily Contractor Work Requests / Scheduling shall be authorized or approved to start when it is determined by the Engineer that weather conditions will be unfavorable.
Approval of all Daily Contractor Work Schedule Requests shall be solely determined by the Engineer.
Because sweeping operations need water to work effectively, sweeping will NOT be allowed when temperatures or wind chill factors are forecasted by the departments certified consulting meteorologists to be and or drop below freezing. TEMPERATURE MUST BE ABOVE THIRTY TWO (32) DEGREES FARENHEIT. All shoulders and curb lines must be free of any existing snow and or ice. Dry sweeping shall be allowed only if it is considered an emergency, immediate hazard, or any work as designated by the Department that requires first priority corrective action.
The Contractor shall repeat work that is not satisfactory. If after inspection the Engineer determines the work is to be repeated, the Engineer will verbally instruct the Contractor on the type and the location of the work to be repeated by the later of the following: 11:30 AM of the 3rd day (excluding Saturdays, Sundays, and holidays observed by the Illinois Department of Transportation) following the day the work was performed or 55 hours after receipt of the completed Report of Contractor’s Daily Work.
After satisfactory completion of the work, the Contractor will be furnished a written document of acceptance. Written authorization and/or acceptance of work will be made via email.
If a section of roadway scheduled to be cleaned cannot be completed due to unforeseen highway operational reasons; including, but not limited to, areas of roadway under construction during the period of the contract and emergency conditions resulting in closures or restrictions for safety purposes, that portion(s) of a cleaning cycle shall be deleted from the contract. The section of roadway deleted may be returned to the contract, at the direction of the Engineer, when highway operational reasons no longer require the section of roadway to be deleted. When a section of roadway is returned to the contract the work will be paid at the same percentage of the cycle that was deleted and no additional compensation will be allowed. The Contractor shall indicate all sections of roadway deleted from the cleaning cycle, including mileage and the reason for deletion, on the Report of Contractor’s Daily Work.
NO work shall be allowed Day or Night on the following dates unless it is considered an emergency, immediate hazard or any work as designated by the Department that requires first priority corrective action:
2025: April 18 – April 21 Easter Holiday May 23 – May 27 Memorial Day Holiday July 3 – July 7 Independence Day Holiday November 26 – December 1 Thanksgiving Holiday December 22 to January 1 Christmas/New Year’s Holiday
2026: April 3 – April 6 Easter Holiday May 23 – May 27 Memorial Day Holiday July 3 – July 7 Independence Day Holiday November 25 – December 1 Thanksgiving Holiday December 21 to January 1 Christmas/New Year’s Holiday
2. PERFORMANCE OF WORK:
A. Work Direction: Cleaning equipment and workers will move in the same direction as traffic.
B. Damage to State Property: The Contractor must perform the work in a manner that will not disturb or damage State Property. Curbs, guardrails, fences, railings, light poles, delineators, semi-permanent cones and barricades, signs and the like must not be damaged or disturbed. If State property is damaged or disturbed, the cost of repairs or replacement will be borne by the Contractor.
C. Inconvenience: The Contractor will prosecute the work in a manner that will minimize the inconvenience to the motoring public. The Contractor shall create neither air pollution with dust nor hazardous conditions with water on the pavement.
D. Traffic Obstruction: Should the operations of the Contractor be performed in a manner that causes traffic to congest to a degree which is unsatisfactory to the Engineer, the Contractor will, at the discretion of the Engineer, cease work until the Engineer decides work can resume without undue traffic congestion.
E. Disposal of Waste: Removal and disposal of all waste and deceased animal carcasses collected during the prosecution of this work will be the responsibility of the Contractor and will be disposed of by the Contractor at his expense. If the deceased animal carcasses are of nominal size the contractor shall contact the Engineer and request that it be disposed of in another approved manor. All applicable laws and ordinances related to the hauling, handling and disposition of such material shall be complied with by the Contractor. This applies especially to spillage, covered loads in trucks and legal dumping depots such as a commercial land fill operation.
F. Flushing: Flushing shall not be done without receiving written approval from the
Engineer. If approved, care shall be taken to prevent flushing waste into traffic or creating a hazard to traffic in areas being flushed. Flushing shall not be used for cleaning under and behind guardrail or to clean the shoulders. Waste shall not be flushed outside of the area to be cleaned. All water Truck should have down facing nozzles as to not move debris outside of the cleaning area. Vehicles without the proper nozzle will be removed for the project until they are in good working order and meet the requirements.
G. Solid Waste Management Site: The Contractor will not be allowed to use any State right-of-way or any existing Department solid waste management site as part of this contract.
The Contractor may procure an Illinois Environmental Protection Agency, Bureau of Land permit to develop and operate a private solid waste management site to transfer non-hazardous waste generated from street sweeping. The cost of developing and operating a private solid waste management site shall be considered as included in the contract unit prices bid for the work, and no additional compensation will be allowed.
H. Sweeper Speed Limit: At no time shall the sweeping unit and any related vehicles in the sweeping train exceed 15 miles per hour in speed while performing any work.
3. EQUIPMENT AND LABOR: The Contractor is hereby informed and shall understand that sufficient equipment and labor force shall be provided and maintained so that the various cleaning cycles and work orders are satisfactorily completed within the allotted time and that cleaning cycles are started in close conformance with the determined during the preconstruction meeeting regardless of overlapping.
The Contractor, taking into consideration lost work days due to weather, will be expected to provide the necessary number of sweeping units and labor force to satisfactorily complete the Full Expressway Cleaning Cycle and Supplemental sweeping, and other cleaning cycles on time. The Contractor shall provide adequate and sufficient supervision, equipment and labor to ensure a satisfactory, safe completion of all work to meet the cleaning schedules determined in the preconstruction meeting.
Due to heavy accumulation of dirt and rubbish during the winter months, the First Full Expressway Cleaning Cycle and Supplemental Sweeping will require a concentrated effort of equipment and manpower to satisfactorily complete the work on time. Multiple cleanings of the same areas may be required before obtaining satisfactory results and acceptance by the Engineer.
Personnel shall be made available, with hand tools, to clean areas not accessible to sweeping units, such as on top of raised medians, aggregate/ stone shoulders regardless of width, under and 10 feet behind all guardrail regardless of surface type, and drainage swales, roadway runoffs; also to loosen tightly compacted dirt in curb lines. Hand work will also be required for the removal of all rubbish, debris and litter including but not limited to sand, rocks, gravel, concrete, wood, limbs, leaves, weeds, garbage and animal carcasses from all surfaces on expressways.
Labor, material and equipment will remain on State right-of-way only for such time as is necessary to successfully prosecute the cleaning work required by the contract.
Maintenance or over-night parking of equipment will not be permitted on State right-of-way.
The Contractor shall furnish a total of ten (10) two-way mobile communication devices meeting the approval of the Engineer as a means of expediting and maintaining communication with the Engineers. The Contractor shall provide and maintain two-way mobile communication devices in State and Consultant vehicles designated by the Engineer.
The communication devices shall be operated on the same frequency as the Contractor's supervisor's vehicles. The communication devices shall remain in the State and Consultant vehicles until completion of the contract.
Follow vehicles are to be equipped with a truck mounted impact attenuator at all times per cleaning train basis, in accordance with the plan sheets District One details for typical application of traffic control devices for highway and sign cleaning operations.
All vehicles are to be equipped with working two-way radios at all times when work is performed.
All vehicles are to be equipped with high intensity amber strobes. Strobes, headlights and flashers shall be displayed at all times when work is performed.
All personnel working under this contract will be required to wear an approved State OSHA Standard that IDOT adheres to flagger vest when not in a vehicle.
4. DRAINAGE STRUCTURES: Particular care shall be taken to prevent dirt and rubbish from being pushed into roadway drainage structures. All bridges located within the specified limits of the Expressways that have drainage structures (scuppers, inlets, floor drains etc.) shall be cleaned by utilizing vacuum type sweepers or other approved equipment and methods that will prevent dirt and rubbish from being deposited into the drainage structures. Material removed from these areas must be removed from the site and not disposed of in an unsatisfactory manner. This work shall be included in the price of the Full Expressway Cleaning Cycles.
5. EXTRA WORK: If the Contractor is required by the Engineer to perform cleaning work other than that delineated in these Special Provisions, payment for such work will be in accordance with Article 109.04 of the Standard Specifications.
6. METHOD OF MEASUREMENT: The satisfactory completion of a Full Expressway Cleaning
Cycle and Supplemental Sweeping will be the standard measurement for payment.
It shall be the Contractor's responsibility to notify the Engineer when each cycle and/ or work order is completed on any designated routes.
Full Expressway Cleaning Cycle includes complete cleaning of all contract areas within the limits of all the expressways specified in Quantities, including debris, rubbish and litter which has accumulated over the seasons. Mechanical and/or hand sweeping will be required to remove debris and litter that has accumulated.
If a cleaning cycle cannot be completed due to unforeseen highway operational reasons;
including, but not limited to, areas of roadway under construction during the period of the contract and emergency conditions resulting in closures or restrictions for safety purposes, payment will be made for the percentage of the cycle completed and will be calculated by shoulder and curb mileage basis. The Contractor will not be compensated for parts of cycles that are not complete. The Engineer shall determine to what extent work is not completed.
Any work that cannot be completed shall be stated by the contractor on the report of contractor’s daily work. The contractor shall include limits, mileage and reasons.
Supplemental Sweeping will be measured for payment in miles of expressway shoulder cleaned rounded down to the tenth of a mile. A standard automobile odometer shall be used by the Engineer to make the measurements. Supplemental sweeping not authorized in writing by the Engineer will not be measured for payment.
It shall be the Contractor's responsibility to notify the Engineer when supplemental sweeping is completed on any authorized sweeping routes.
7. BASIS OF PAYMENT: Expressway cleaning will be paid for at the contract unit price per each for FULL EXPRESSWAY CLEANING CYCLE and at the contract unit price per each for
Supplemental sweeping will be paid for at the contract unit price per mile for
SUPPLEMENTAL SWEEPING.
Laboring will not be paid for as a separate item, but the cost shall be considered as included in the contract unit prices for the cleaning cycles involved and no additional compensation will be allowed.
8. QUANTITIES: The quantities of cleaning cycles and curb miles specified in this contract are estimated amounts and are intended as approximations to be used for bidding purposes only. The contractor shall understand before bidding that all individual estimated shoulder and curb mile limits shown for each expressway will stand as shown regardless of whether the mileage is low or high. No additional mileage compensation will be allowed. It shall be understood that the unit prices of this contract will prevail throughout the period of this contract.
FULL CYCLE EXPRESSWAY CLEANING (DAYTIME)
LOCATION: Full cleaning cycles shall be performed on the following expressways:
EISENHOWER EXPRESSWAY
EDENS EXPRESSWAY
DAN RYAN EXPRESSWAY
BISHOP FORD/KINGERY EXPRESSWAY
KENNEDY EXPRESSWAY
STEVENSON EXPRESSWAY
I 290 EXTENSION
I 55 EXPRESSWAY
I 57 EXPRESSWAY
I 80 EXPRESSWAY
The areas of work on each expressway are all parts of the expressway. Areas to be cleaned are those with various surfaces, ramps, curbs, gutters, medians (striped, raised, corrugated, barrier), gores, stabilized shoulders, wheel guards, bridge decks, bridge medians, bridge sidewalks, walkways underneath bridges and traveled lanes as required. Rubbish and Litter shall be removed from all surface areas. Located in the plans are typical cross sections of the expressways showing, in general, the areas which are to be cleaned. All cleaning shall be considered incidental to the Full Expressway Cleaning Cycle.
LIMITS OF CLEANING: The limits of each expressway to be cleaned with the Full Cleaning Cycle, of the expressway specified, shall include all entrance and exit ramps up to the nearest intersection and all accident investigation sites and are specified as follows:
Bishop Ford/Kingery Expressway Interstate 94 from Cottage Grove Avenue to the Indiana State line excluding northbound and southbound left hand side from Cottage Grove Avenue to 171st St., Illinois 394 from Interstate 94 to Goodenow Rd., the entire Stony Island Avenue - 103rd Street Interchange. Interstate 80 from Interstate 94 to Interstate 294 and all accident investigation sites.
Stevenson Expressway Interstate 55 (Stevenson Expressway) from Lake Shore Dr. to the Cook – DuPage County Line (County Line Rd.), including First Avenue, from 43rd Street to Archer Avenue, the ramps to and from Joliet Rd from Interstate 55 to Wolf Rd, the ramps from northbound Interstate 55 to northbound Interstate 294 Tollway and from southbound Interstate 294 Tollway to northbound Interstate 55 (Limits of cleaning on these ramps are from Interstate 55 to the first painted gore south of the bridge over Joliet Rd), and all accident investigation sites, excluding the entire Stevenson – Dan Ryan Interchange.
Eisenhower Expressway Interstate 290 and its appurtenances from Wells St. to Austin Blvd. in its entirety, from Austin Blvd. to IL-83 right hand side and all ramps, the eastbound collector-distributor lane and ramps at the U.S. 12/20/45 (Mannheim Rd.) interchange and westbound to Roosevelt Rd.
on its extension.
I-290 Extension I-290 extension from Illinois 83 to Interstate 90 Jane Addams Tollway, Illinois 53 from Interstate 90 Jane Addams Tollway to Lake Cook Road including I-355 from I-290 to Army Trail Road, All Ramps onto IL 390.
I-55 Expressway Interstate 55 from Cook - DuPage county line (County Line Rd.) to I-355, I & M Canal to Will
– Grundy county line (Reed Rd.) in its entirety, including all ramps and the entire I-55 - I-80 interchange, all accident investigation sites, Blodgett Rd. from Kelly Rd. to West Frontage Rd., Arsenal Rd. from the East Frontage Rd. to Elwood International Port Rd. (Baseline Rd.), and the West Frontage Rd. Connector from Arsenal Rd. to the southbound entrance ramp.
I-57 Expressway Interstate 57 from Halsted Street to The Will-Kankakee County Line, in its entirety including the entire I-57 – I-80 Interchange and all accident investigation sites, and from Interstate 57 to Interstate 94 Day Ryan right hand side only.
I-80 Expressway Interstate 80 from Interstate 294 Tri-State Tollway/Interstate I-294 to US 30 and all ramps, including the ramp from eastbound Interstate 80 to northbound Interstate 294 and from southbound Interstate 294 to westbound Interstate 80.
Kennedy Expressway All Ramps on Interstate 90/94 from Ogden Ave to Interstate 90/94 Junction at Edens Expressway, Interstate 90 from Interstate 90/94 Junction at Edens Expressway to Interstate 90/190 Junction, and Interstate 190 from Interstate 90/190 Junction to the East Limits of O’Hare International Airport (Bessie Coleman Rd) unless ramps are too narrow to allow traffic to pass sweeping crew.
Dan Ryan Expressway Interstate 94 from Cottage Grove Ave to 31st St right hand side of both local and express lanes and all ramps except slip ramps between local and express lanes and any ramps too narrow to allow traffic to pass sweeping crew.
Edens Expressway Interstate 94 from Montrose to Dundee Road and US 41 from Dundee Road to Route 22, including two ramps at Clavey Road, two ramps at West Park Avenue, four ramps at Deerpath Road and the entire US 41/Deerfield Road interchange. Also included is Tower Road from Edens Expressway to Forestway Drive.
CLEANING CYCLE ADJUSTMENT BASIS:
The total shoulder and curb miles for a complete Full Expressway Cleaning Cycle and is estimated to be approximately 1131.2 miles and is the basis to be used in computations when a cleaning cycle cannot be completed due to unforeseen highway operational reasons.
The total shoulder and curb miles for each individual Expressway Cleaning Cycle is estimated as follows:
Eisenhower Expressway approximately 88.8 miles Edens Expressway approximately 101.2 miles Dan Ryan Expressway approximately 58.5 miles Bishop Ford/Kingery Expressway approximately 142.2 miles Kennedy Expressway approximately 26.2 miles Stevenson Expressway approximately 110.2 miles I-290 Extension approximately 129.4 miles I-55 Expressway approximately 197.9 miles I-57 Expressway approximately 176.9 miles I-80 Expressway approximately 99.9 miles
9. SCHEDULE OF CLEANING: The Full Expressway Cleaning Cycle shall be completed on or before 80 calendar days regardless of overlap. Full Expressway Cleaning Cycles shall start in close conformity with the schedule stated in the Work Order.
ADDITIONAL DEBRIS AND ADJUSTED CLEANING SCHEDULE: The Department acknowledges that, due to the absence of a sweeping contract for several years, there is an increased amount of debris behind the guardrails. As a result, Engineering judgment will be used to allow for an extended timeframe to complete the first sweeping cycle. To ensure a thorough cleaning, the Department plans to allow the Contractor three full sweeping cycles to fully remove all accumulated debris behind the guardrails. This phased approach is intended to restore and maintain the area according to established standards. Following the three Adjusted Cleaning Schedule, the Contractor shall adhere to the standard Schedule of Cleaning.
10. SEQUENCE OF WORK: The Contractor shall submit at the preconstruction meeting, a sequence of work (by expressway) for the Full Expressway Cleaning Cycle. The sequence of work shall be approved by the Engineer prior to commencing operations. It is required that the Full Expressway Cleaning Cycle be completed to the satisfaction of the Engineer.
The Contractor may be required to alter the sequence of work at any time throughout the duration of the contract upon instruction from the Engineer.
SUPPLEMENTAL SWEEPING
1. LOCATION AND LIMITS OF CLEANING: The intent of this work is to provide additional cleaning of the gutters of existing curb and gutter and stabilized surfaces during the term of this contract. The intent of this work is also to provide cleaning of the gutters and stabilized surfaces of additional curb and gutter and stabilized surfaces constructed during the term of this contract which is not specified for cleaning in these Special Provisions. Supplemental Sweeping shall not be limited to the various expressways routes within the limits of specified in these Special Provisions but shall include all expressways routes located within District One.
The work to be done under Supplemental Sweeping shall consist of the pickup, removal and satisfactory disposal of all sand, stones, debris, refuse, dead animal carcasses, grease, oil, and other rubbish, which has accumulated on the highways and right of ways due to unforeseen events that are not in sequence with the regularly scheduled cleaning categories of this contract.
2. DEFINITION:
Supplemental Sweeping is work that is required to correct a condition which is an immediate hazard to the public or any work as designated by the Department that requires first priority corrective action. The contractor shall be available on a 7 days per week, 24-hours per day basis to accomplish this work. The Contractor shall have sufficient resources at the location specified by the Engineer within three (3) hours of notification or within a time specified by the Engineer to accomplish the work. The location of work shall be as determined by the Engineer and may be required at any time.
The use of this item shall not in any way mitigate any liquidation damages associated with noncompliance to the Full Expressway Cleaning Cycle guarantee working days specified, or any other cleaning cycles.
TRAFFIC CONTROL PLAN
Effective: September 30, 1985 Revised: January 1, 2007
Traffic Control shall be according to the applicable sections of the Standard Specifications, the Supplemental Specifications, the "Illinois Manual on Uniform Traffic Control Devices for Streets and Highways", any special details and Highway Standards contained in the plans, and the Special Provisions contained herein.
Special attention is called to Article 107.09 of the Standard Specifications and the following Highway Standards, Details, Quality Standard for Work Zone Traffic Control Devices, Recurring Special Provisions and Special Provisions contained herein, relating to traffic control.
The Contractor shall contact the District One Bureau of Traffic at least 72 hours in advance of beginning work.
STANDARDS: 701400, 701401, 701411, 701426, 701428 and 701901
DETAILS: Single Lane Weave and Multi Lane Weave (TC-09) Traffic Control Details for Freeway Shoulder Closures and Partial Ramp Closures
(TC-17)
SPECIAL PROVISIONS: Keeping Expressways Open to Traffic Failure to Open Traffic Lanes to Traffic Traffic Control and Protection (Expressways) Speed Display Trailer (D-1) Nighttime Work Zone Lighting (D-1) Public Convenience and Safety (D-1) Equipment Parking and Storage (BDE) Work Zone Traffic Control Devices (BDE) Work Zone Width Restriction (BDE)
PUBLIC CONVENIENCE AND SAFETY (D1)
Effective: May 1, 2012 Revised: July 15, 2012
Add the following to the end of the fourth paragraph of Article 107.09:
“If the holiday is on a Saturday or Sunday, and is legally observed on a Friday or Monday, the length of Holiday Period for Monday or Friday shall apply.”
Add the following sentence after the Holiday Period table in the fourth paragraph of Article 107.09:
“The Length of Holiday Period for Thanksgiving shall be from 5:00 AM the Wednesday prior to 11:59 PM the Sunday After”
Delete the fifth paragraph of Article 107.09 of the Standard Specifications:
“On weekends, excluding holidays, roadways with Average Daily Traffic of 25,000 or greater, all lanes shall be open to traffic from 3:00 P.M. Friday to midnight Sunday except where structure construction or major rehabilitation makes it impractical.”
TRAFFIC CONTROL FOR WORK ZONE AREAS
Effective: September 14, 1995 Revised: January 1, 2007
Work zone entry and exit openings shall be established daily by the Contractor with the approval of the Engineer. All vehicles including cars and pickup trucks shall exit the work zone at the exit openings. All trucks shall enter the work zone at the entry openings. These openings shall be signed in accordance with the details shown elsewhere in the plans and shall be under flagger control during working hours.
The Contractor shall plan his trucking operations into and out of the work zone as well as on to and off the expressway to maintain adequate merging distance. Merging distances to cross all lanes of traffic shall be no less than 1/2 mile. This distance is the length from where the trucks enter the expressway to where the trucks enter the work zone. It is also the length from where the trucks exit the work zone to where the trucks exit the expressway. The stopping of expressway traffic to allow trucks to change lanes and/or cross the expressway is prohibited.
Failure to comply with the above requirements will result in a Traffic Control Deficiency charge.
The deficiency charge will be calculated as outlined in Article 105.03 of the Standard Specifications. The Contractor will be assessed this daily charge for each day a deficiency is documented by the Engineer.
KEEPING THE EXPRESSWAY OPEN TO TRAFFIC
Effective: March 22, 1996 Revised: October 9, 2020
Whenever work is in progress on or adjacent to an expressway, the Contractor shall provide the necessary traffic control devices to warn the public and to delineate the work zone as required in these Special Provisions, the Standard Specifications, the State Standards and the District Freeway details. All Contractors’ personnel shall be limited to these barricaded work zones and shall not cross the expressway.
The Contractor shall request and gain approval from the Illinois Department of Transportation's Expressway Traffic Operations Engineer at www.idotlcs.com twenty-four (24) hours in advance of all daily lane, ramp and shoulder closures and 7 days in advance of all permanent and weekend closures on all Freeways and/or Expressways in District One. This advance notification is calculated based on workweek of Monday through Friday and shall not include weekends or Holidays.
Temporary shoulder and non-system interchange partial ramp closures are allowed weekdays between 9:00 A.M. and 3:00 P.M. and between 7:00 P.M. and 5:00 A.M or as approved by the Expressway Traffic Operations Engineer. Lane closures are normally not permitted during the day.
Exact hours will be determined by the Expressway Traffic Operations Engineer.
The following expressway limits will permit temporary moving closures on shoulders from 8:30 A.M. to 3:30 P.M.:
I-290 Extension: Inbound and Outbound from IL 83 (including all ramps to/from IL. 83) to US 20 (Lake Street) Exit/Entrance Ramp. This includes NB Route 53 towards EB I-290 and WB I-290 towards SB 53 but does not include the WB I-290 to NB Route 53 and SB Route 53 towards EB I-290.
I-57: Inbound and outbound from the county line up to 183rd Street all ramps included.
NB and SB 394 from Thornton-Lansing to the southern limits.
I-80: Eastbound and westbound from 183rd to US 30 including all ramps.
I-55: Northbound and southbound from southernmost limit to US 6 including all ramps.
I-94 (Edens Expressway): Inbound and outbound from Dundee to Skokie Blvd including all ramps.
I-94 (Edens Expressway): Inbound only from Dempster to Cicero Exit.
Narrow Lanes and permanent shoulder closures will not be allowed between Dec. 1st and April 1st. Permanent shoulder closures per District Detail TC-17 will only be permitted if called for in the plans or as approved by the Expressway Traffic Operations Engineer.
All daily lane closures shall be removed during adverse weather conditions such as rain, snow, and/or fog and as determined by the Engineer. Also, the contractor shall promptly remove their lane closures when Maintenance forces are out for snow and ice removal.
Additional lane closure hour restrictions may have to be imposed to facilitate the flow of traffic to and from major sporting events and/or other events.
Private vehicles shall not be parked in the work zone. Contractor's equipment and/or vehicles shall not be parked on the shoulders or in the median during non-working hours. The parking of equipment and/or vehicles on State right-of-way will only be permitted at the locations approved by the Engineer.
FAILURE TO OPEN TRAFFIC LANES TO TRAFFIC
Effective: March 22, 1996 Revised: February 9, 2005
Should the Contractor fail to completely open and keep open all the traffic lanes to traffic in accordance with the limitations specified under the Special Provisions for "Keeping the Expressway Open to Traffic", the Contractor shall be liable to the Department for the amount of:
One lane or ramp blocked = $ 2000/15 minutes
Not as a penalty but as liquidated and ascertained damages for each and every 15 minute interval or a portion thereof that a lane is blocked outside the allowable time limitations. Such damages may be deducted by the Department from any monies due the Contractor. These damages shall apply during the contract time and during any extensions of the contract time.
TRAFFIC CONTROL AND PROTECTION (EXPRESSWAYS)(MAINTENANCE)
Effective: March 8, 1996 Revised: April 1, 2019
Description. This work shall include furnishing, installing, maintaining, replacing, relocating, and removing all traffic control devices used for the purpose of regulating, warning, or directing traffic.
Traffic control and protection shall be provided as called for in the plans, applicable Highway Standards, District One Expressway details, Standards and Supplemental Specifications, these Special Provisions, or as directed by the Engineer.
General. The governing factor in the execution and staging of work for this project is to provide the motoring public with the safest possible travel conditions on the expressway through the construction zone. The Contractor shall arrange his operations to keep the closing of lanes and/or ramps to a minimum.
The Contractor shall be responsible for the proper location, installation, and arrangement of all traffic control devices. Special attention shall be given to existing warning signs and overhead guide signs during all construction operations. Warning signs and existing guide signs with down arrows shall be kept consistent with the barricade placement at all times. The Contractor shall immediately remove, completely cover, or turn from the motorist's view all signs which are inconsistent with lane assignment patterns.
The Contractor shall coordinate all traffic control work on this project with adjoining or overlapping projects, including barricade placement necessary to provide a uniform traffic detour pattern.
When directed by the Engineer, the Contractor shall remove all traffic control devices that were furnished, installed, or maintained by him under this contract, and such devices shall remain the property of the Contractor. All traffic control devices shall remain in place until specific authorization for relocation or removal is received from the Engineer.
Additional requirements for traffic control devices shall be as follows.
(a) Traffic Control Setup and Removal. The setting and removal of barricades for the taper portion of a lane closure shall be done under the protection of a vehicle with a truck/trailer mounted attenuator and arrow board per State Standard 701428 and Section 701 of the Standard Specifications. Failure to meet this requirement will be subject to a Traffic Control Deficiency. The deficiency will be calculated as outlined in Article 105.03 of the Standard Specifications. Truck/trailer mounted attenuators shall comply with Article 1106.02(g) or shall meet the requirements of NCHRP 350 Test Level 3 with vehicles used in accordance with manufacturer’s recommendations and requirements.
(b) Sign Requirements
(1) Sign Maintenance. Prior to the beginning of construction operations, the Contractor will be provided a sign log of all existing signs within the limits of the construction zone.
The Contractor is responsible for verifying the accuracy of the sign log. Throughout the duration of this project, all existing traffic signs shall be maintained by the Contractor. All provisions of Article 107.25 of the Standard Specifications shall apply.
(2) Work Zone Speed Limit Signs. Work zone speed limit signs shall be installed as required in Article 701.14(b) and as shown in the plans and Highway Standards.
Based upon the exiting posted speed limit, work zone speed limits shall be established and signed as follows.
a. Existing Speed Limit of 55mph or higher. The initial work zone speed limit assembly, located approximately 4200’ before the closure, and shall be 55mph as shown in 701400. Additional work zone 45mph assemblies shall be used as required according to Article 701.14(b) and as shown in the Highway Standards and plans. WORK ZONE SPEED LIMIT 55 PHOTO ENFORCED assemblies may be omitted when this assembly would normally be placed within 1500 feet of the END WORK ZONE SPEED LIMIT sign. If existing speed limit is over 65mph then additional signage should be installed per 701400.
b. Existing Speed Limit of 45mph. The advance 55mph work zone speed limit assembly shown in 701400 shall be replaced with a 45mph assembly. Additional work zone 45mph assemblies shall be used as required according to Article 701.14(b) and as shown in the Highway Standards and plans. WORK ZONE SPEED LIMIT 55 PHOTO ENFORCED assemblies shall be eliminated in all cases.
END WORK ZONE SPEED LIMIT signs are required.
(3) Exit Signs. The exit gore signs as shown in Standard 701411 shall be a minimum size of 48 inch by 48 inch with 12 inch capital letters and a 20 inch arrow. EXIT OPEN AHEAD signs shown in Standard 701411 shall be a minimum size of 48 inch by 48 inch with 8 inch capital letters.
(4) Uneven Lanes Signs. The Contractor shall furnish and erect “UNEVEN LANES” signs
(W8-11) on both sides of the expressway, at any time when the elevation difference between adjacent lanes open to traffic equals or exceeds one inch. Signs shall be placed 500’ in advance of the drop-off, within 500’ of every entrance, and a minimum of every mile.
(c) Drums/Barricades. Check barricades shall be placed in work areas perpendicular to traffic every 1000', one per lane and per shoulder, to prevent motorists from using work areas as a traveled way. Check barricades shall also be placed in advance of each open patch, or excavation, or any other hazard in the work area, the first at the edge of the open traffic lane and the second centered in the closed lane. Check barricades, either Type I or II, or drums shall be equipped with a flashing light.
To provide sufficient lane widths (10' minimum) for traffic and also working room, the Contractor shall furnish and install vertical barricades, in lieu of Type II or drums, along the cold milling and asphalt paving operations. The vertical barricades shall be placed at the same spacing as the drums.
(d) Vertical Barricades. Vertical barricades shall not be used in lane closure tapers, lane shifts, exit ramp gores, or staged construction projects lasting more than 12 hours. Also, vertical barricades shall not be used as patch barricades or check barricades. Special attention shall be given, and ballast provided per manufacture’s specification, to maintain the vertical barricades in an upright position and in proper alignment.
(e) Temporary Concrete Barrier Wall. Prismatic barrier wall reflectors shall be installed on both the face of the wall next to traffic, and the top of sections of the temporary concrete barrier wall as shown in Standard 704001. The color of these reflectors shall match the color of the edgelines (yellow on the left and crystal or white on the right). If the base of the temporary concrete barrier wall is 12 inches or less from the travel lane, then the lower slope of the wall shall also have a 6 inch wide temporary pavement marking edgeline (yellow on the left and white on the right).
(f) Flaggers. One flagger will be required for each separate activity of an operation that requires frequent construction vehicles to enter or leave a work zone to or from a lane open to traffic. Temporary traffic control and flagger position shall be according to District One Detail TC-18 – Expressway Flagging, or as directed by the Engineer.
(g) Full Expressway Closures. Full Expressway Closures will only be permitted for a maximum of 15 minutes during the allowable hours listed in the Keeping the Expressway Open to Traffic Special Provision. During Full Expressway Closures, the Contractor will be required to close off all lanes except one, using Freeway Standard Closures. The Contractor will be required to provide one changeable message sign to be placed at the direction of the Engineer. The sign shall display a message as directed by the Engineer.
A Maintenance of Traffic Plan shall be submitted to the District One Expressway Traffic Control Supervisor 14…
This is the start of the file's text. The full file is on GovTribe.