HMA Resurfacing on Various rRoutes
Solicitation number
61M67
Issued by
Kane County, Illinois

About this file

This is a Notice to Bidders and contract specifications document issued by the Illinois Department of Transportation (IDOT) District 1 for Contract No. 61M67, a construction project in Kane County, City of Aurora. The project involves hot-mix asphalt surface course removal, pavement patching, polymerized hot-mix asphalt binder and surface courses, recessed pavement markings, removal and replacement of concrete sidewalks, curb and gutter work, and landscaping along four routes (Galena Boulevard, New York Street, Oak Avenue, and Ohio Street) totaling 18,790 linear feet (3.56 miles gross length; 17,612.6 feet net length). Electronic bids must be submitted to the iCX-Integrated Contractors Exchange system by 12:00 p.m. on September 18, 2026, at which time bids will be publicly opened. The completion date for opening roadways to traffic is October 22, 2027, with an additional 10 working days permitted for cleanup and punch list items. The downtown area (between Lake Street and BNSF railroad bridges) has interim completion requirements with sidewalk work fully open by Friday at 3:00 p.m. weekly, and all downtown work must be substantially completed by August 24, 2027. The contract includes coordination requirements with concurrent City-led projects including the Broadway Streetscape/Galena-New York 2-way conversion project and lead service line replacements along New York Street.

The contract will be awarded to the lowest responsive and responsible bidder. Multiple utility relocations and adjustments are required, including water valves, sanitary and storm sewer manholes, telecom, gas, and electrical facilities, with estimated coordination durations ranging from 5 to 15 days. Contractors must comply with City of Aurora work hour restrictions (7:00 a.m. to 5:00 p.m. Monday through Friday, with weekend and evening work requiring prior written approval), coordinate with the City Police Department for traffic impacts, provide advance notices to affected properties for downtown work, and implement extensive tree protection measures including temporary fencing, trunk protection, and root pruning by licensed arborists. Contractors are responsible for maintaining roadways, protecting existing utilities, sweeping streets daily, and managing site cleanup. The contract documents reference IDOT Standard Specifications for Road and Bridge Construction (Adopted January 1, 2022, Revised January 1, 2026), supplemental specifications, recurring special provisions, and numerous special provisions addressing materials, traffic control, environmental protection, and quality assurance requirements. City water is available at contractor expense with a deposit of approximately $1,600 required.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Letting September 18, 2026

Notice to Bidders, Specifications and Proposal

Contract No. 61M67 KANE County Section 25-00375-00-RS (Aurora) Various Routes Project HKK8-716 () District 1 Construction Funds

Prepared by F

Checked by

(Printed by authority of the State of Illinois)

NOTICE TO BIDDERS

1. TIME AND PLACE OF OPENING BIDS. Electronic bids are to be submitted to the electronic bidding system (iCX-Integrated Contractors Exchange). All bids must be submitted to the iCX system prior to 12:00 p.m.

September 18, 2026 at which time the bids will be publicly opened from the iCX SecureVault.

2. DESCRIPTION OF WORK. The proposed improvement is identified and advertised for bids in the

Invitation for Bids as:

Contract No. 61M67 KANE County Section 25-00375-00-RS (Aurora) Project HKK8-716 () Various Routes District 1 Construction Funds

HMA resurfacing on various routes in Aurora. Includes recessed pavement markings, sidewalk, curb & gutter.

3. INSTRUCTIONS TO BIDDERS. (a) This Notice, the invitation for bids, proposal and letter of award shall, together with all other documents in accordance with Article 101.09 of the Standard Specifications for Road and Bridge Construction, become part of the contract. Bidders are cautioned to read and examine carefully all documents, to make all required inspections, and to inquire or seek explanation of the same prior to submission of a bid.

(b) State law, and, if the work is to be paid wholly or in part with Federal-aid funds, Federal law requires the bidder to make various certifications as a part of the proposal and contract. By execution and submission of the proposal, the bidder makes the certification contained therein. A false or fraudulent certification shall, in addition to all other remedies provided by law, be a breach of contract and may result in termination of the contract.

4. AWARD CRITERIA AND REJECTION OF BIDS. This contract will be awarded to the lowest responsive and responsible bidder considering conformity with the terms and conditions established by the Department in the rules, Invitation for Bids and contract documents. The issuance of plans and proposal forms for bidding based upon a prequalification rating shall not be the sole determinant of responsibility. The Department reserves the right to determine responsibility at the time of award, to reject any or all proposals, to re-advertise the proposed improvement, and to waive technicalities.

By Order of the Illinois Department of Transportation

Gia Biagi, Secretary

CONTRACT 61M67

INDEX

FOR

SUPPLEMENTAL SPECIFICATIONS

AND RECURRING SPECIAL PROVISIONS

Adopted January 1, 2026

This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS.

ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)

SUPPLEMENTAL SPECIFICATIONS

Std. Spec. Sec. Page No.

109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires

1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System 1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment

RECURRING SPECIAL PROVISIONS

The following RECURRING SPECIAL PROVISIONS indicated by an “X” are applicable to this contract and are included by reference:

CHECK SHEET # PAGE NO.

1 Additional State Requirements for Federal-Aid Construction Contracts 2 Subletting of Contracts (Federal-Aid Contracts)

3 EEO

4 Specific EEO Responsibilities Non Federal-Aid Contracts 5 Required Provisions - State Contracts 6 Asbestos Bearing Pad Removal 7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 8 Temporary Stream Crossings and In-Stream Work Pads 9 Construction Layout Stakes

10 Use of Geotextile Fabric for Railroad Crossing 11 Subsealing of Concrete Pavements 12 Hot-Mix Asphalt Surface Correction 13 Pavement and Shoulder Resurfacing 14 Patching with Hot-Mix Asphalt Overlay Removal 15 Polymer Concrete 16 Reserved 17 Bicycle Racks 18 Temporary Portable Bridge Traffic Signals 19 Nighttime Inspection of Roadway Lighting 20 English Substitution of Metric Bolts 21 Calcium Chloride Accelerator for Portland Cement Concrete 22 Quality Control of Concrete Mixtures at the Plant 23 Quality Control/Quality Assurance of Concrete Mixtures 24 Reserved 25 Reserved 26 Temporary Raised Pavement Markers 27 Restoring Bridge Approach Pavements Using High-Density Foam 28 Portland Cement Concrete Inlay or Overlay 29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 30 Longitudinal Joint and Crack Patching 31 Concrete Mix Design – Department Provided 32 Station Numbers in Pavements or Overlays

LOCAL ROADS AND STREETS RECURRING SPECIAL PROVISIONS

Table of Contents

CHECK SHEET # PAGE NO.

LRS 1 Reserved LRS 2 Furnished Excavation LRS 3 Work Zone Traffic Control Surveillance LRS 4 Flaggers in Work Zones LRS 5 Contract Claims LRS 6 Bidding Requirements and Conditions for Contract Proposals LRS 7 Bidding Requirements and Conditions for Material Proposals LRS 8 Reserved LRS 9 Bituminous Surface Treatments LRS 10 Reserved LRS 11 Employment Practices LRS 12 Wages of Employees on Public Works LRS 13 Selection of Labor LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks LRS 15 Partial Payments LRS 16 Protests on Local Lettings LRS 17 Substance Abuse Prevention Program LRS 18 Multigrade Cold Mix Asphalt LRS 19 Reflective Crack Control Treatment

INDEX OF SPECIAL PROVISIONS

SPECIAL PROVISION SHEET

LOCATION OF PROJECT

DESCRIPTION OF PROJECT

AVAILABLE REPORTS (D1 LR)

COMPLETION DATE PLUS WORKING DAYS (d1)

MAINTENANCE OF ROADWAYS (D1)

STATUS OF UTILITIES (D1)

WORK DAYS AND HOURS

DOWNTOWN WORK – SIDEWALKS, NOTIFICATION, COORDINATION, AND INTERIM

COMPLETION

COOPERATION WITH OTHER CONTRACTORS

WATER FOR CONSTRUCTION PURPOSES

UTILITY LOCATIONS

DAMAGE TO EXISTING UTILITIES

STREET SIGN MAINTENANCE

FAILURE TO COMPLETE PLANT CARE AND ESTABLISHMENT WORK ON TIME

SUPPLEMENTAL WATERING

PORTLAND CEMENT CONCRETE SIDEWALK

WATER VALVES TO BE ADJUSTED

GAS VALVE TO BE ADJUSTED

WASHOUT BASIN

TRAFFIC CONTROL PLAN

REMOVE AND REINSTALL BRICK PAVER

DETECTABLE WARNINGS

SITE CLEANUP

PAYMENT FOR SAW CUTTING

HOT-MIX ASPHALT SURFACE REMOVAL

PROTECTION AND RESTORATION OF PROPERTY

PAINT CURB

FRAMES AND LIDS TO BE ADJUSTED (SPECIAL)

SANITARY MANHOLES TO BE ADJUSTED

DRIVEWAY REMOVAL AND REPLACEMENT

PROTECTION OF EXISTING TREES

ADJUSTMENTS AND RECONSTRUCTIONS (D1)

DRAINAGE AND INLET PROTECTION UNDER TRAFFIC (D1)

TEMPORARY INFORMATION SIGNING

CURB OR COMBINATION CURB AND GUTTER REMOVAL AND REPLACEMENT (D1)

PUBLIC CONVENIENCE AND SAFETY (D1)

HOT-MIX ASPHALT BINDER AND SURFACE COURSE (D1)

FRICTION AGGREGATE (D1)

MINERALIZED CARBON DIOXIDE CONCRETE (D-1)

HOT-MIX ASPHALT – MIXTURE DESIGN VERIFICATION AND PRODUCTION (D1)

REBUILD EXISTING HANDHOLE, DOUBLE HANDHOLE, OR HEAVY-DUTY HANDHOLE

DETECTOR LOOP REPLACEMENT AND/OR INSTALLATION (ROADWAY GRINDING,

RESURFACING, & PATCHING OPERATIONS)

IDOT TRAINING PROGRAM GRADUATE ON-THE-JOB TRAINING

LR107-4

LR 1030-2

BDE SPECIAL PROVISIONS

The following special provisions indicated by an “X” are applicable to this contract. An * indicates a new or revised special provision for the letting.

File Name Pg. Special Provision Title Effective Revised 80099 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 _ 80274 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 Automated Flagger Assistance Device Jan. 1, 2008 April 1, 2023 80173 57 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 April 1, 2026 80475 Bridge Deck Concrete Overlays Jan. 1, 2026 80241 Bridge Demolition Debris July 1, 2009

5053I Building Removal Sept. 1, 1990 Aug. 1, 2022 5026I Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022

80460 59 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 76 Compensable Delay Costs June 2, 2017 April 1, 2019 80198 Completion Date (via calendar days) April 1, 2008 80199 Completion Date (via calendar days) Plus Working Days April 1, 2008 80461 Concrete Barrier Jan. 1, 2025 80453 Concrete Sealer Nov. 1, 2023 80261 80 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 Deck Slab Repair Jan. 1, 2026

* 80029 82 Disadvantaged Business Enterprise Participation Sept. 1, 2000 July 2, 2026 80467 Erosion Control Blanket Aug. 1, 2025 80229 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 Guardrail Nov. 1, 2025 80472 High Friction Surface Treatment Nov. 1, 2025 80456 Hot-Mix Asphalt Jan. 1, 2024 April 1, 2026 80446 86 Hot-Mix Asphalt – Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80483 88 Inlet Filters April 1, 2026

* 80477 Longitudinal Tining Jan. 1, 2026 July 1, 2026 80450 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 90 Pavement Marking April 1, 2025 Nov. 1, 2025 80468 91 Pavement Patching Aug. 1, 2025 80441 92 Performance Graded Asphalt Binder Jan 1, 2023 April 1, 2026 80459 Preformed Plastic Pavement Marking June 2, 2024 3426I 98 Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 Raised Reflective Pavement Markers Nov. 1, 2025 80455 99 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2026 80474 Residential Driveway Temporary Signal Nov. 1, 2025

* 80445 Seeding Nov. 1, 2022 July 1, 2026 80457 101 Short Term and Temporary Pavement Markings April 1, 2024 April 2, 2024 80462 105 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 Sinusoidal Rumble Strips Jan. 1, 2026 80469 Slope Wall Aug. 1, 2025 80448 107 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 109 Structural Repair of Concrete Jan. 1, 2026 80397 116 Subcontractor and DBE Payment Reporting April 2, 2018 80391 117 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019 80463 118 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025

File Name Pg. Special Provision Title Effective Revised 80482 119 Submission of Payroll Records – Federal Aid Contract April 1, 2026 80437 Submission of Payroll Records – State Contract April 1, 2021 April 1, 2026 80435 121 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 127 Surveying Services April 1, 2025 80481 Temporary Concrete Barrier Jan. 1, 2026 80466 Temporary Rumble Strips April 1, 2025

* 80484 Tolerance in Thickness for Continuously Reinforced PCC Pavement July 1, 2026 80470 Traffic Signal Backplate Aug. 1, 2025 20338 128 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022 80439 131 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2022 80458 Waterproofing Membrane System Aug. 1, 2024 80302 132 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 Wood Sign Support Nov. 1, 2023 80427 133 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026

* 80485 136 Work Zone Width Restriction July 1, 2026 80071 Working Days Jan. 1, 2002

FAU 1521, 1522, 1522B, 1522C, 3902 and FAP 0360 (Galena Blvd, New York St, Oak Ave, and Ohio St)

Section 25-00375-00-RS City of Aurora, Kane County

STATE OF ILLINOIS

SPECIAL PROVISIONS

The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction”, Adopted January 1, 2022, the “Supplement Specifications and Recurring Special Provisions”, Adopted January 1, 2026, the latest edition of the “Manual of Uniform Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids, the latest edition of the Standard Specifications for Water and Sewer Main Construction in Illinois, all applicable requirements of the Illinois Environmental Protection Agency, municipality, ordinances of authorities having jurisdiction and all addenda therein, and the Recurring Special Provisions indicated on the Check Sheet included herein which apply to and govern the construction FAU 1521, 1522, 1522B, 1522C, 3902, and FAP 0360 (Galena Blvd, New York St, Oak Ave, and Ohio St) at various locations throughout the City of Aurora, Section 25-00375-00-RS, Project Number HKK8(716), Job Number C-91-226-26 in Kane County, and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.

CONTRACT NO. 61M67

LOCATION OF PROJECT

The project is located along the routes shown in the table below in the City of Aurora, Kane County, IL. The gross length is 18,790.0 ft (3.56 miles) and the net length is 17,612.6 ft (3.34 miles).

FAU Route Local Name From To FAU 1522 Oak Ave Galena Blvd New York St FAU 1521 Galena Blvd Locust St Ohio St

FAU 1522, 3902,

1522B, & 1522C

New York St Oak Ave Ohio St

FAP 0360 Ohio St New York St Galena Blvd

DESCRIPTION OF PROJECT

This work consists of hot-mix asphalt surface course removal, pavement patching, polymerized hot-mix asphalt binder course, hot-mix asphalt surface course, recessed pavement markings, removal and replacement of concrete sidewalk and curb and gutter, landscaping, and all other appurtenant work required to complete the project in accordance with the plans, specifications and all other applicable standards.

Section 25-00375-00-RS City of Aurora, Kane County

AVAILABLE REPORTS (D1 LR)

Effective: July 1, 2021

☐ No project specific reports were prepared.

When applicable, the following checked reports and record information is available for Bidders’ reference upon request:

☒ Record structural plans

☐ Preliminary Site Investigation (PSI) (IDOT ROW)

☐ Preliminary Site Investigation (PSI) (Local ROW)

☐ Preliminary Environmental Site Assessment (PESA) (IDOT ROW)

☐ Preliminary Environmental Site Assessment (PESA) (Local ROW)

☐ Soils/Geotechnical Report

☐ Boring Logs

☒ Pavement Cores

☐ Location Drainage Study (LDS)

☐ Hydraulic Report

☐ Noise Analysis

☐ Other: ______________________

Those seeking these reports should request access from:

Alex Nugent, PE, Professional Engineer I City of Aurora 630-256-3223 nugenta@aurora.il.us 7:00 AM to 3:30 PM Monday - Friday

Section 25-00375-00-RS City of Aurora, Kane County

COMPLETION DATE PLUS WORKING DAYS (D1)

Effective: September 30, 1985 Revised: January 1, 2007

Revise Article 108.05 (b) of the Standard Specifications as follows:

"When a completion date plus working days is specified, the Contractor shall complete all contract items and safely open all roadways to traffic by 11:59 PM on, October 22, 2027 except as specified herein.

The Contractor will be allowed to complete all clean-up work and punch list items within 10 working days after the completion date for opening the roadway to traffic. Under extenuating circumstances the Engineer may direct that certain items of work, not affecting the safe opening of the roadway to traffic, may be completed within the working days allowed for clean up work and punch list items. Temporary lane closures for this work may be allowed at the discretion of the Engineer.

There are additional interim completion dates for work in downtown areas as described in the “DOWNTOWN WORK – SIDEWALKS, NOTIFICATION, COORDINATION, AND INTERIM COMPLETION” special provision.

Article 108.09 or the Special Provision for “Failure to Complete the Work on Time”, if included in this contract, shall apply to both the completion date and the number of working days.

MAINTENANCE OF ROADWAYS (D1)

Effective: September 30, 1985 Revised: November 1, 1996

Beginning on the date that work begins on this project, the Contractor shall assume responsibility for normal maintenance of all existing roadways within the limits of the improvement. This normal maintenance shall include all repair work deemed necessary by the Engineer, but shall not include snow removal operations. Traffic control and protection for maintenance of roadways will be provided by the Contractor as required by the Engineer.

If items of work have not been provided in the contract, or otherwise specified for payment, such items, including the accompanying traffic control and protection required by the Engineer, will be paid for in accordance with Article 109.04 of the Standard Specifications.

Section 25-00375-00-RS City of Aurora, Kane County

STATUS OF UTILITIES (D1)

Effective: June 1, 2016 Revised: April 1, 2025

Utility companies and/or municipal owners located within the construction limits of this project have provided the following information regarding their facilities and the proposed improvements.

The tables below contain a description of specific conflicts to be resolved and/or facilities which will require some action on the part of the Department’s contractor to proceed with work. Each table entry includes an identification of the action necessary and, if applicable, the estimated duration required for the resolution.

UTILITIES TO BE ADJUSTED

Conflicts noted below have been identified by following the suggested staging plan included in the contract. The company has been notified of all conflicts and will be required to obtain the necessary permits to complete their work; in some instances, resolution will be a function of the construction staging. The responsible agency must relocate, or complete new installations as noted below; this work has been deemed necessary to be complete for the Department’s contractor to then work in the stage under which the item has been listed.

STAGE/ LOCATION TYPE DESCRIPTION

RESPONSIBLE

AGENCY

DURATION OF

TIME

Throughout Project Limits

Water Valve

Water valve in pavement; adjust elevation following surface removal and prior to final pavement placement

City of Aurora/ Contractor

5 days (constructed concurrently with milling and resurfacing operations)

Throughout Project Limits

Sanitary Manhole

Sanitary manhole in pavement;

adjust elevation following surface removal and prior to final pavement placement

City of Aurora/ Contractor

Throughout Project Limits

Storm Sewer Manhole

Storm sewer manhole in pavement; adjust elevation following surface removal and prior to final pavement placement

City of Aurora/ Contractor

Section 25-00375-00-RS City of Aurora, Kane County

River/New York Smith/New York Ohio/New York (3) Oak/Galena +/- Sta 308+50, 22’ RT +/- Sta 313+00, 18’ RT River/Galena (2) Stolp/Galena +/- Sta 322+65, 16’ LT +/- Sta 326+30, 15’ LT +/- Sta 331+50, 10’ LT +/- Sta 333+30, 5’ LT (2) +/- Sta 333+75, 5’ LT Lincoln/Galena W Park/Galena E Park/Galena Root/Galena Anderson/Galena Union/Galena East/Galena Smith/Galena (All as marked on plans)

Telecom Manhole

Telecom manhole in pavement;

adjust elevation following surface removal and prior to final pavement placement

AT&T

5 days (constructed concurrently with milling and

Oak/New York-Road River/New York-Road River/New York (3)-SW Lincoln/New York-Road Lincoln/New York (4)-SW W Park/New York-Road Root/New York (2)-SW Spencer/New York-SW East/New York-Road Smith/New York (3)-SW Hickory/New York-Road Ohio/New York-Road Stolp/Galena (2)-Road +/- Sta 207+25, 12’ RT Lincoln/Galena (4)-Road Anderson/Galena (2)-SW Jackson/Galena-Road Smith/Galena-SW

Gas Valve

Gas valves in pavement or sidewalk. Adjust elevation following surface removal and prior to final pavement placement in roadway. Adjust after removal and before final pour in PCC sidewalk.

Nicor

5 days (constructed concurrently with milling and resurfacing operations) for roadway valves.

5 days (constructed concurrently with sidewalk placement) for sidewalk valves.

Sta 114+21, 11’ LT Sta 124+98, 12’ LT Sta 125+24, 12’ RT Sta 126+61, 4’ RT Sta 127+11, 5’ RT Sta 128+30, 2’ RT Sta 133+91, 9’ RT

Electrical Manhole/ Handhole

Electrical manhole/ handhole in pavement. Adjust in coordination with milling and paving operations.

Comed

15 days (constructed concurrently with milling and

Section 25-00375-00-RS City of Aurora, Kane County

Sta 305+00, 5’ RT Sta 306+80, 5’ RT Sta 309+00, 10’ RT Sta 312+27, 5’ RT Sta 314+00, 1’ RT Sta 315+53, 3’ RT Sta 316+82, 12’ LT Sta 321+23, 2 Lids Sta 321+41, 17’ LT Sta 322+76, 13’ RT Sta 323+80, 3’ LT Sta 326+19, 8’ LT Sta 326+40, 9’ LT Sta 328+95, 0’ RT Sta 330+80, 4’ RT Sta 331+93, 7’ RT Sta 332+97, 12’ RT Sta 334+70, 18’ RT Sta 335+71, 7’ RT

____15____ Days Total Installation

The following contact information is what was used during the preparation of the plans as provided by the Agency/Company responsible for resolution of the conflict.

Agency/Company Responsible to

Resolve Conflict

Name of contact

Phone E-mail address

City of Aurora Mike Houston (331) 254-2026 houstonm@aurora.il.us AT&T Tom Laskowski (630) 779-4722 tl7895@att.com Nicor Karey Johnson (224) 471-9356 karejohn@southernco.com Comed Bill Mitchell (708) 528-0128 William.Mitchell@comed.com

UTILITIES TO BE WATCHED AND PROTECTED

The areas of concern noted below have been identified by following the suggested staging plan included for the contract. The information provided is not a comprehensive list of all remaining utilities, but those which during coordination were identified as ones which might require the Department’s contractor to take into consideration when making the determination of the means and methods that would be required to construct the proposed improvement. In some instances, the contractor will be responsible to notify the owner in advance of the work to take place so necessary staffing on the owner’s part can be secured.

Section 25-00375-00-RS City of Aurora, Kane County

STAGE / LOCATION TYPE DESCRIPTION OWNER

Throughout project limits Electric

Overhead and underground electrical lines. Contractor to watch and protect when excavating (UG) or operating tall equipment/trucks (aerial).

ComEd

Throughout project limits Gas

4-6” gas main, generally along back of ROW. Includes laterals at cross streets.

Contractor to watch and protect when excavating.

Nicor

Along New York St from Wilder St to River St (Aerial), Along Galena Blvd from Lake St to Hoyt Pl (UG), Along Ohio from New York St to Galena Blvd (Aerial)

Fiber

Overhead and underground fiber lines.

Contractor to watch and protect when excavating (UG) or operating tall equipment/trucks (aerial).

Metronet

The following contact information is what was used during the preparation of the plans as provided by the owner of the facility.

Agency/Company Responsible to

Resolve Conflict

Name of contact

Phone E-mail address

AT&T Distribution G11629@ATT.com

AT&T

Transmission

Tom Laskowski (630) 573-5643 g05256@att.com

Comcast (Xfinity) Martha Gieras (224) 229-5862 Martha_gieras@cable.comcast.com ComEd

Cassie Evans (630) 576-7094 plansubmittalsandmaprequests@ exeloncorp.com

MCI/Verizon Investigations investigations@verizon.com Midwest Fibernet Nathan Wright (414) 459-3546 utilitylocates@midwestfibernet.com Metro Fibernet (812) 213-1050 811design@metronet.com Nicor Karey Johnson (224) 471-9356 karejohn@southernco.com Zayo Fiber John Ferraresi (847) 417-9609 locatedesk@zayo.com

The above represents the best information available to the Department and is included for the convenience of the bidder. The days required for conflict resolution should be considered in the bid as this information has also been factored into the timeline identified for the project when setting the completion date. The applicable portions of the Standard Specifications for Road and Bridge Construction shall apply.

Estimated duration of time provided above for the first conflicts identified will begin on the date of the executed contract regardless of the status of the utility relocations. The responsible agencies will be working toward resolving subsequent conflicts in conjunction with contractor activities in the number of days noted.

Section 25-00375-00-RS City of Aurora, Kane County

The estimated relocation duration must be part of the progress schedule submitted by the contractor. A utility kickoff meeting will be scheduled between the Department, the Department’s contractor, and the utility companies when necessary.

The contractor is responsible for contacting JULIE (or DIGGER within the City of Chicago) prior to any excavation work. Please note that IDOT electrical facilities are not part of the one-call locating services, such as JULIE or DIGGER.

If the contract requires the services of an electrical contractor, it is the contractor’s responsibility, at their own expense, to locate existing IDOT electrical facilities before commencing work. For contracts that do not require an electrical contractor, the contractor may request one free locate of IDOT electrical facilities by contacting the Department’s Electrical Maintenance Contractor.

Additional locate requests will be at the contractor’s expense.

The Department’s Electrical Maintenance Contractor must be notified at least 72 hours in advance of the work by calling 773-287-7600 or emailing dispatch@meade100.com to arrange for the locating of underground electrical facilities.

Please note, the marking of underground facilities does not absolve the contractor of their responsibility to repair or replace any facilities damaged during construction at their expense.

Section 25-00375-00-RS City of Aurora, Kane County

WORK DAYS AND HOURS

The Contractor shall not perform any work on City holidays (New Year’s Eve/Day, MLK Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Veteran’s Day, Thanksgiving Day/Friday after, and Christmas Eve/Day), Saturday, or outside of regular working hours without prior written approval from the City. No work shall be done on Sundays or federal Holidays.

Regular working hours are between 7:00 AM and 5:00 PM, Monday through Friday.

If work is approved after regular working hours or on Saturdays, the allowed working hours need to be agreed upon but shall be between 7:00 AM and 7:00 PM, Monday through Friday and between 8:00 AM and 5:00 PM on Saturdays. At no time shall the Contractor be permitted to violate City Ordinance O04-57 regarding noise.

Equipment shall not be started before 6:45 AM.

The Contractor shall install and maintain temporary signs in the parkway 24 hours prior to starting work on each street. The signs shall be 18” x 24”, white plastic with red lettering on both sides stating NO PARKING, 7:00 AM - 5:00 PM MON – FRI THANK YOU “contractor name”. Signs shall be spaced on both sides (min. 3 signs each side, each block) as needed to notify motorists. Immediately following each stage of work on each street, the Contractor shall remove the signs and reinstall them as needed.

DOWNTOWN WORK – SIDEWALKS, NOTIFICATION, COORDINATION, AND INTERIM

COMPLETION

For this project, “downtown” and “downtown area” shall refer to all roadways within the project limits between Lake St (IL 31) and the BNSF railroad bridges. This specification only applies to work within that downtown area.

Sidewalks

The downtown area is host to numerous regular and special events throughout the year. Within the downtown area, any sidewalk work must be scheduled such that sidewalks are fully open to pedestrian traffic by Friday at 3:00 PM. This may require special care in timing removals and concrete work. There may be instances where there are no downtown events happening and the rule can be relaxed but will be on a case-by-case basis and will require written approval from the Engineer.

Any slurry from sawcutting operations must be fully cleaned by the end of each work day.

Before any removal begins for the week, the Contractor shall provide the City with the planned removal limits for the week for discussion.

Notification

The Contractor shall contact the City of Aurora, Police Department non-emergency number prior to closing any streets to through traffic, installing temporary no parking signage, or any work that may impede the flow of traffic through the downtown area.

Section 25-00375-00-RS City of Aurora, Kane County

If requested by the City, the Contractor shall deliver a notice to each address that will be affected by work to be performed on each downtown street. The notice shall be a 2-sided document on a form supplied by the City. Notices shall be distributed 7 to 14 days in advance of the start of work.

Notices will be required for all sidewalk work located in the downtown area, unless otherwise specified by the City.

Coordination

Work in the downtown area will overlap with a City-led permit project (Permit 045-92304) to convert New York St and Galena Blvd to 2-way operation. This includes ADA ramp/curb work at the intersections of Galena/Stolp, Galena/Broadway, and New York/Broadway with some additional signal work and minor sidewalk work at Galena/Lake and New York/Lake.

The Contractor shall coordinate with the Contractor on the permit project. The projects may require extensive cooperation, and it is understood that the Contractor for this resurfacing project may have to adjust their schedule for work in the downtown area to facilitate this work.

Interim Completion

The Contractor may not begin any work in the downtown area until June 14, 2027.

The Contractor must have all work in the downtown area significantly completed by August 24, 2027. No open pavement or open holes will be permitted after this date. Pavement marking, landscaping, and other similar work may be complete after this date, but must be completed on a Monday or Tuesday.

This specification is not intended to limit any work activities outside the downtown area as described above. The completion for the entire project is subject to Working Days.

COOPERATION WITH OTHER CONTRACTORS

There are several other projects occurring within the limits or adjacent to this project. The Contractor shall coordinate work activities with the contractors of these other projects. At no time shall any surface course be placed in an area that will be disturbed by another project’s work without express written approval from the Engineer. Currently known projects are listed below; this list is not exhaustive, and this provision applies to any other work occurring within the project limits:

Broadway Streetscape/Galena-New York 2-way conversion (additional coordination described in Downtown Work specification about) o Along Galena Blvd and New York St from west project limits to Broadway and along Broadway within the project area o City-led project under IDOT permit 045-92304 o Anticipated to be let in Fall 2026; construction throughout 2027 o Surface course placement will not be allowed prior to construction of Galena/Stolp, Broadway/New York, and Broadway/Galena curb ramps/curb returns.

Lead service line replacements o Along New York St throughout the project limits o City-led project pending federal funding o Anticipated to be let in Fall 2026; construction in Spring 2027 o Surface course placement will not be allowed prior to service line completion

Section 25-00375-00-RS City of Aurora, Kane County

WATER FOR CONSTRUCTION PURPOSES

City water for construction purposes will be available to the Contractor at their cost according to the prevailing rates in effect at the time. The Contractor shall secure a City water meter by presenting the required deposit (approximately $1,600) in the form of a certified check made out to The City of Aurora to the Water Billing Department on the First Floor of 44 E. Downer Place, Aurora, Illinois. The name of the Contractor and their Tax ID number will be required. The Contractor will take the resulting forms to the Water & Sewer Maintenance Division located at 2185 Liberty Street, Aurora, Illinois where the City water meter shall be provided. The Contractor and/or sub-contractor will be fined, according to ordinance, which will be deducted from moneys due, for each unauthorized use of City water regardless of the amount of water used or the reason for unauthorized use.

UTILITY LOCATIONS

The location of existing drainage structures, storm sewers, water mains, sanitary sewers, and any other public or private utility as shown on the plans is approximate and their exact location is to be determined in the field by the Contractor. This work shall be considered as included in the unit bid prices of the contract and no additional compensation will be allowed.

DAMAGE TO EXISTING UTILITIES

The contractor shall be responsible for the protection of all underground and surface utilities even if not shown on the plans. Any utility property damaged during construction shall be repaired.

STREET SIGN MAINTENANCE

The contractor shall be required to temporarily reset all signs that interfere with construction operations. All such signs must be maintained straight and clean for the duration of the temporary setting and must be re-erected at a temporary location in a workmanlike manner and be visible to the traffic for which it is intended. This work will not be paid for separately, but shall be included in the cost of the Traffic Control and Protection items.

FAILURE TO COMPLETE PLANT CARE AND ESTABLISHMENT WORK ON TIME

Should the Contractor fail to complete the plant care and/or supplemental watering work as per the standard specifications or within 36 hours notification from the Engineer, or within such extended times as may have been allowed by the Department, the Contractor shall be liable to the Department in the amount of:

• $20.00 per sq yd sod/per day not as penalty but as liquidated damages, for each calendar day or a portion thereof of overrun in the contract time or such extended time as may have been allowed.

Section 25-00375-00-RS City of Aurora, Kane County

In fixing the damages as set out herein, the desire is to establish a mode of calculation for the work since the Department’s actual loss, in the event of delay, cannot be predetermined, would be difficult of ascertainment, and a matter of argument and unprofitable litigation. This said mode is an equitable rule for measurement of the Department’s actual loss and fairly takes into account the loss of the tree(s ) if the watering or plant care is delayed. The Department shall not be required to provide any actual loss in order to recover these liquidated damages provided herein, as said damages are very difficult to ascertain. Furthermore, no provision of this clause shall be construed as a penalty, as such is not the intention of the parties.

A calendar day is every day shown on the calendar and starts at 12:00 midnight and ends at the following 12:00 midnight, twenty-four hours later.

SUPPLEMENTAL WATERING

This work will include watering sod at the rates specified and as directed by the Engineer.

Schedule: Watering will only begin after the successful completion of all period of establishment requirements. Water sod a minimum of twice a week. The Engineer may direct the Contractor to adjust the watering rate and frequency depending upon weather conditions.

Watering must be completed in a timely manner. When the Engineer directs the Contractor to do supplemental watering, the Contractor must begin the watering operation within 24 hours of notice. The Contractor shall give an approximate time window of when they will begin at the work location to the Engineer. The Engineer shall be present during the watering operation. A minimum of 10 units of water per day must be applied until the work is complete.

Should the Contractor fail to complete the work on a timely basis or within such extended times as may have been allowed by the Department, the Contractor shall be liable to the Department liquidated damages as outlined in the “Failure to Complete Plant Care and Establishment Work on Time” special provision.

In fixing the damages as set out herein, the desire is to establish a mode of calculation for the work since the Department’s actual loss, in the event of delay, cannot be predetermined, would be difficult of ascertainment, and a matter of argument and unprofitable litigation. This said mode is an equitable rule for measurement of the Department’s actual loss and fairly takes into account the loss of the trees if the watering is delayed. The Department shall not be required to provide any actual loss in order to recover these liquidated damages provided herein, as said damages are very difficult to ascertain. Furthermore, no provision of this clause shall be construed as a penalty, as such is not the intention of the parties.

A calendar day is every day shown on the calendar and starts at 12:00 midnight and ends at the following 12:00 midnight, twenty-four hours later.

Source of Water: The Contractor shall notify the Engineer of the source of water used and provide written certification that the water does not contain chemicals harmful to plant growth.

Rate of Application: The normal rates of application for watering are as follows. The Engineer will adjust these rates as needed depending upon weather conditions.

Section 25-00375-00-RS City of Aurora, Kane County

27 gallons per square yard for Sodded Areas

Method of Application: Watering of plants in beds shall be applied in such a manner that all plant holes are uniformly saturated without allowing the water flow beyond the periphery of the bed.

Water shall slowly infiltrate into soil and completely soak the root zone. The Contractor must supply metering equipment as needed to assure the specified application rate of water.

Method of Measurement: Supplemental watering will be measured in units of 1000 gallons of water applied as directed.

Basis of Payment: This work will be paid for at the contract unit price per unit of SUPPLEMENTAL WATERING, measured as specified. Payment will include the cost of all water, equipment and labor needed to complete the work specified herein and to the satisfaction of the Engineer.

PORTLAND CEMENT CONCRETE SIDEWALK

Sidewalk curb ramps shall be constructed according to current PROWAG requirements, the Highway Standards in the plans, and as directed by the Engineer. Additional side curb may be required at locations not explicitly shown on the Highway Standards or plans, such as on the back side of the sidewalk at the common square on perpendicular curb ramps (See Highway Standard 424001-12 PERPENDICULAR CURB RAMPS FOR SIDEWALKS). Per Article 424.12, all side curbs are measured for payment as sidewalk. This includes any side curb required at any location for a curb ramp, even if the side curb is not explicitly called out in a particular location on the Highway Standards. It should be assumed that side curb will be required at most ramp locations.

The Contractor shall be responsible for setting any stakes, hubs, lines, or any other layout items necessary for the construction of sidewalk curb ramps to current PROWAG standards. This work will not be paid for separately, but shall be included in the cost of PORTLAND CEMENT CONCRETE SIDEWALK of the appropriate depth.

Replace the third paragraph of Article 424.12 with the following:

Earth excavation will not be measured for payment.

Replace the third paragraph of Article 424.13 with the following:

Earth excavation will not be measured for payment. Any earth excavation required to properly place, form, or otherwise construct any sidewalk, curb ramp, landing, or side curb shall be considered included in the price of Portland Cement Concrete Sidewalk.

Section 25-00375-00-RS City of Aurora, Kane County

WATER VALVES TO BE ADJUSTED

Description. This work shall be done in accordance with Section 602 of the Standard Specifications and shall consist of adjusting water valves as determined by the Engineer. Care shall be taken to keep the inside of the extension and box completely free of any material which would prevent the opening and closing of the water valve.

Method Of Measurement. This work will be measured for payment in place for each water valve adjusted. It will be the Contractor’s responsibility to determine the type of water valve box and materials required to complete the adjustment.

Basis of Payment. This work shall be paid for at the contract unit price per EACH for WATER VALVES TO BE ADJUSTED, which price shall include all materials and labor necessary for adjusting and resetting the water valve box including excavation and backfilling.

GAS VALVE TO BE ADJUSTED

Description: This item of work shall consist of furnishing all labor, equipment, and materials necessary to adjust gas valve in the locations shown on the plans. Gas valve adjustments shall meet requirements specified in Article 107.38 and or as directed by the Engineer.

The contractor shall coordinate this work with the owner of any gas valves needing adjustment within the scope of the project.

Basis of Payment: The work shall be paid for at the contract unit price per each for GAS

VALVES TO BE ADJUSTED.

WASHOUT BASIN

The work shall consist of constructing and maintaining a washout basin for concrete trucks and other construction vehicles in accordance with IUM-654SB as detailed in the plans and include general maintenance and removal of all construction debris.

This item will be paid for at the contract unit price per lump sum for WASHOUT BASIN.

Section 25-00375-00-RS City of Aurora, Kane County

TRAFFIC CONTROL PLAN

Traffic Control shall be according to the applicable sections of the Standard Specifications, the Supplemental Specifications, the "Illinois Manual on Uniform Traffic Control Devices for Streets and Highways", any special details and Highway Standards contained in the plans, and the Special Provisions contained herein.

Special attention is called to Article 107.09 of the Standard Specifications and the following Highway Standards, Details, Quality Standard for Work Zone Traffic Control Devices, Recurring Special Provisions and Special Provisions contained herein, relating to traffic control.

The Contractor shall contact the City of Aurora at (630) 256-3200 and the District One Bureau of Traffic at least 72 hours in advance of beginning work.

STANDARDS:

701006 701101 701106 701301 701311 701427 701501 701502 701601 701606 701611 701701 701801 701901

DETAILS:

TC-10 (Traffic Control and Protection for Side Roads, Intersections, and Driveways) TC-13 (District One Typical Pavement Markings) TC-16 (Short Term Pavement Marking Letters and Symbols) TC-22 (Arterial Road Information Sign) TC-26 (Driveway Entrance Signing)

SPECIAL PROVISIONS:

- Maintenance of Roadways (D1)

- Temporary Information Signing (D1)

- Public Convenience and Safety (D1)

- Pavement and Shoulder Resurfacing (Recurring CS #13)

- Pavement Marking (BDE)

- Short Term and Temporary Pavement Markings (BDE)

- Work Zone Traffic Control Surveillance (Local Roads CS #3)

- Vehicle and Equipment Warning Lights (BDE)

- Work Zone Traffic Control Devices (BDE)

- Work Zone Width Restriction (BDE)

Section 25-00375-00-RS City of Aurora, Kane County

REMOVE AND REINSTALL BRICK PAVER

Description. This work shall consist of removing, salvaging, stockpiling, storing, securing, and reinstalling brick pavers at the locations of existing brick sidewalk border as directed by the Engineer.

Any excess pavers not needed or not reusable, as determined by the Engineer, shall be disposed of offsite.

All non-reusable pavers shall be replaced with the same style and color from the original manufacturer or as approved by the Engineer. When an adequate quantity of pavers to construct the proposed improvements are not available, the Contractor shall furnish pavers matching the same style, size, and color from the original manufacturer or as approved by the Engineer.

Material. Materials shall be according to the following Articles of Division 1000 - Materials of the Standard Specifications.

Item Article/Section Fine Aggregate (Note 1) ...........................................1003.01, 1003.02(d) Portland Cement Concrete………………..…………..1020 Paving Brick………………………………...…………..1041.03

Note 1. The fine aggregate used for the bedding course and joint filling shall be sand, silica sand, or slag sand. It shall also be Class A quality and dry. For the bedding course, the gradation shall be FA 1 or FA 2. For joint filling, the gradation shall be FA 9.

Equipment. Equipment shall conform to the following Articles of Division 1100 - Equipment of the Standard Specifications.

Pneumatic-Tired Rollers ..........................................1003.01, 1003.02(d) Masonry Saw (Note 1) Vibrator/Compactor (Note 2)

Note 1. The masonry saw shall be a wet or dry saw capable of clean and accurate cuts.

Note 2. The vibrator/compactor shall be either a plate compactor with a high frequency, low amplitude plate or a rubber-roller mechanical vibrator.

Construction Requirements.

Removal.

When brick border ribbon is present in sidewalk areas marked for removal, a reasonable amount of brick pavers shall be removed as needed to construct the sidewalk improvements. The Contractor shall take care to note the existing paver layout and not cause damage to the existing pavers.

Preparation of Subgrade.

The subgrade shall be prepared according to Section 301of the Standard Specifications, except Articles 301.05 and 301.06 will not apply.

Section 25-00375-00-RS City of Aurora, Kane County

Bedding Course. The fine aggregate for bedding shall be placed and screeded, without compaction, to a uniform thickness of 1 to 1.5 in. (25 to 38 mm). Prepared areas shall not be left overnight, unless they are protected from disturbance and moisture. Stockpiled material shall be kept covered. Any saturated bedding aggregate shall be removed and replaced.

Installation. The bricks or pavers shall be laid in a pattern to replace the existing pattern to the satisfaction of the Engineer with a joint width from 1/8 to 1/4 in. (3 to 6 mm) on all sides. The contractor shall document existing brick locations in order to replace them in the same location.

After the entire pavement or sidewalk has been laid, it shall be set into the bedding course by one pass of the vibrator/compactor. Construction equipment shall not be driven on the new surface until the joints have been filled.

Joint Filling. The fine aggregate for joint filling shall be spread over the pavement or sidewalk and hand broomed into the joints. The aggregate shall then be worked down into the joints with multiple passes of the vibrator/compactor. Each pass shall be alternated 90 degrees from the previous pass. This process shall be repeated until the joints are completely filled. Excess fine aggregate shall be removed by hand brooming. All bricks and pavers within 6 ft (1.8 m) of the laying face shall be compacted and the joints completely filled with sand at the end of each workday.

Method of Measurement. This work will be measured for payment as follows:

Paver removal and replacement will be measured for payment in place and the area computed in square feet.

Basis of Payment. This work will be paid for at the contract unit price per square foot for REMOVE

AND REINSTALL BRICK PAVER.

DETECTABLE WARNINGS

This work shall consist of the installation of pre-fabricated panel of truncated domes twenty-four inches (24”) wide on concrete sidewalk accessibility ramps at locations as directed by the Engineer.

Truncated domes shall be in accordance with Article 424.09 of the Standard Specifications. The domes shall parallel the pavement crosswalk in accordance with the latest Highway Standard.

The panel shall be Red. The panel shall meet the requirements of ASTM C1028 – Slip Resistance, ASTM G155 – Accelerated Weathering, and the latest PROWAG.

The Detectable Warning Panel shall be ADA Solutions, Inc. Cast-in-Place. The product and method used for installing detectable warnings shall come with the following documents which shall be given to the Engineer prior to installation:

(a) Manufacturer’s certification stating the product is fully compliant with ADAAG.

(b) Manufacturer’s specifications stating the required materials, equipment, installation procedures and conformance to ASTM C1028

This work will be paid for at the contract unit price per SQUARE FOOT for DETECTABLE

WARNINGS.

Section 25-00375-00-RS City of Aurora, Kane County

SITE CLEANUP

The Contractor shall be responsible for sweeping and cleaning streets of any debris and material that has accumulated as a result of the construction activity. A mechanical sweeper, mechanically driven air and/or handwork with shovel and broom shall be utilized to provide a clean street for the motoring public and pedestrians. If sweeping is not completed as requested by the Engineer, an Erosion and Sediment Control Deficiency Deduction may be applied to monies due or that might become due the Contractor as described in Article 105.03(a) of the Standard Specifications.

Further, any loose material deposited in the flowline of drainage structures which obstructs the natural flow of water shall be removed at the end of each working day. Prior to acceptance of the completed improvement, all drainage structures shall be free of dirt and debris. This work will not be paid for separately, but shall be considered as included in the cost of Hot-mix asphalt surface removal.

PAYMENT FOR SAW CUTTING

Saw cutting of pavements, curbs, sidewalk, etc. shall be to full depth and shall result in a clean straight edge on the portion remaining. All SAW CUTTING shall be considered included in the price of the item removed.

HOT-MIX ASPHALT…