AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour a nd date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date sp ecified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or

(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

D. OTHER (Specify type of modification and authority)

E. IMPORTANT:

Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force a nd effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

PREVIOUS EDITION UNUSABLE

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

This form was electronically produced by Elite Federal Forms, Inc.

( ) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

BOP02152

Typewritten Text

BOP02152

Typewritten Text

IFBP011091700001

Abate Attic Asbestos FMC Lexington – Project 1B7Q

The following changes are made to the Statement of Work:

001: page 1 ‘part B.2.b. SCOPE OF WORK’. Change sentence: (Surfaces are to be repaired to condition suitable for finish painting).

CHANGE: Surfaces exposed to view shall be repaired to a condition suitable for finish painting.

Surfaces concealed above drop ceilings may be left as is.

002: Page 1 ‘A. INTRODUCTION’ change sentence (Piping sizes vary from ½” to 4”in diameter, actual sizes cannot be determined due to the fact that they are wrapped in ACM).

CHANGE: PIPING SIZES VARY FROM ½” TO 6” IN DIAMETER, ACTUAL SIZES CANNOT BE DETERMINED

DUE TO THE FACT THAT THEY ARE WRAPPED IN ACM.

003: Pages 1 and 2 ‘B.1.a. SCOPE OF WORK’ change sentence (Piping varies from ½” to 4” in size).

CHANGE: PIPING VARIES FROM ½” TO 6” in size.

004: Pages 1 ‘B.1.d. SCOPE OF WORK’ change sentence (Contractor is to install new (2 ½” thick) pipe fiberglass jacket insulation with PVC fittings and insulation inserts.

CHANGE: CONTRACTOR IS TO INSTALL NEW PIPE FIBERGLASS JACKET INSULATION WITH PVC FITTINGS

AND INSULATION INSERTS.

004 - Page 2 ‘SCOPE OF WORK’ replace B.3 with the following.

B.3.1. Basement Corridor and Inside Recreation (Basement Level)

1. Thermal system insulation removal and replacement:

a. Approximately 600 linear feet of steam line.

b. Approximately 1,100 linear feet of domestic water/ condensate line.

c. Piping varies from ½” to 6”in size.

d. Water/ Condensate: New pipe insulation is required to be 2” insulation. Conductivity range 0.25-0.29 btu-in / h-ft2-F. Temperature rating 125 degrees F

e. Steam: New pipe insulation is required to be 5” insulation. Conductivity range 0.32-0.34 btu-in / h-ft2-F. Temperature rating 250 degrees F

2. Suspended acoustical ceiling tile removal and replacement:

a. Approximately 3,000 Square feet.

b. Tile sizes vary from 2’ x 2’ to 2’ x 4’.

B3.2 Physical Therapy (1st Floor)

1. Suspended acoustical ceiling tile removal and replacement.

a. Approximately 2,100 square feet.

IFBP011091700001

Abate Attic Asbestos FMC Lexington – Project 1B7Q

b. Tile sizes vary from 2’ x 2’ to 2’ x 4’.

2. Glue dot and 1’ x 1’ tile removal:

a. Approximately 2,100 square feet.

B.3.3 Hospital Administration Lobby and Closet (2nd Floor)

a. Approximately 40 linear feet of steam line.

b. Piping varies from ½” to 6”in size.

c. Steam: Steam: New pipe insulation is required to be 5” insulation. Conductivity range 0.32-

0.34 btu-in / h-ft2-F. Temperature rating 250 degrees F

B.3.4. Health Care Unit Lobby and Closet (3rd Floor)

a. Approximately 100 linear feet of steam line.

b. Piping varies from ½” to 6”in size.

c. Steam: New pipe insulation is required to be 5” insulation. Conductivity range 0.32-0.34 btu-in / h-ft2-F. Temperature rating 250 degrees F

NO OTHER CHANGES ARE MADE AT THIS TIME.

Flap B Tab 2 - Amendment 0002 - LEX
Flap B Tab 2 - Amendment 0001 page 1
Flap B Tab 2 - Amendment 0001
contract_id_code:
first_page: 1
last_page: 3
modification_no: 0002
effective_date: 03/24/2017
requisition_no: 0188-17
project_no: 1B7Q
issued_by: FEDERAL BUREAU OF PRISONS

MID ATLANTIC REGIONAL OFFICE

302 SENTINEL DRIVE, SUITE 200

ANNAPOLIS JUNCTION, MD 20701

code_2:
contractor_name_address:
administered_by:
check_1: Yes
amendment_solicitation_no: IFBP01091700001
dated: 03/01/2017
check_2: Off
contract_order_no:
dated_2:
code:
faculty_code:
checkbox_1: Yes
copies: 01
acct_and_appropriation:
check_a: Off
change_order:
check_b: Off
contract_order_modified:
check_c: Off
authority_of:
check_d: Off
other:
number_of_copies_return:
amendment_description: AMENDMENT IS AS FOLLOWS:

A. See pages 2 and 3 for all changes.

NO OTHER CHANGES OR INFORMATION IS PROVIDED AT THIS TIME.

signer_name_title:
contracting_name_title:
date_signed_contractor:
clear_form:
save_form_data:
Email Form:
checkbox_2: Off
checkbox_3: Yes
checkbox_4: Yes
checkbox_5: Off
date_signed_contracting_officer:

File details come from the government source that posted it. Updated .