About this file

This is an Invitation for Bids (IFB) issued by the Maryland Department of the Environment (MDE) for Radiation Meter Calibration services, solicitation number U00R5600123. The IFB seeks a contractor to calibrate and maintain radiation detection meters used for facility inspections, with bids due on April 15, 2025 at 2:00 p.m. EST. The contract will be an indefinite quantity, fixed-price agreement with a two-year duration, performed at the contractor's place of business. The primary objective is to ensure the accuracy and safety of radiation measurement equipment through precise calibration and maintenance. No pre-bid conference or site visit is scheduled, and bids will not be opened publicly.

The contract requires the selected bidder to be certified to perform radiological meter calibrations, with a valid Nuclear Regulatory Commission License or state license agreement required. The evaluation will be based solely on the Total Bid Price, with the contract awarded to the responsible bidder submitting the most favorable price. There are no specific Minority Business Enterprise (MBE) or Veteran-Owned Small Business Enterprise (VSBE) subcontracting goals for this solicitation. The contractor must maintain comprehensive insurance coverage, including commercial general liability, errors and omissions, crime insurance, and workers' compensation. The state is not using federal funding for this procurement, and the contract will be executed through the competitive sealed bidding method under Maryland procurement regulations.

View the file

Other files for this state and local contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF MARYLAND

DEPARTMENT OF THE ENVIRONMENT

(MDE)

INVITATION FOR BIDS (IFB)

RADIATION METER CALIBRATION

SOLICITATION # U00R5600123

ISSUE DATE: APRIL 4, 2025

A Prospective Bidder that has received this document from a source other than eMarylandMarketplace Advantage (eMMA) https://procurement.maryland.gov should register on eMMA https://emma.maryland.gov/

NOTICE TO BIDDERS

MINORITY BUSINESS ENTERPRISES ARE ENCOURAGED TO RESPOND TO THIS

SOLICITATION.

https://procurement.maryland.gov/ https://emma.maryland.gov/

SOLICITATION TITLE RADIATION METER CALIBRATION

eMMA #: BPM049200 Solicitation# U00R5600123

IFB for Maryland Department of the Environment Page 2 of 23

KEY INFORMATION SUMMARY SHEET

Invitation for Bids Service, Radiation Meter Calibration

Solicitation Number:

U00R5600123

IFB Issue Date: April 4, 2025

IFB Issuing Office:

Maryland Department of the Environment Air and Radiation Administration

Procurement Officer:

Jacqueline F. Harrison Maryland Department of the Environment 1800 Washington Blvd. Baltimore, Maryland 21230

Email:

Phone Number:

jacqueline.harrison1@maryland.gov

410-537-3079

Bids are to be sent to:

All submissions must be via emma.maryland.gov If you have difficulties uploading or navigating the eMMA system, please reach out to eMMA.helpdesk@maryland.gov To submit a bid, bidders must first register on emma.maryland.gov. We recommend registering in advance to become acquainted with the site.

No Bid Notice Feedback Form

If you are not submitting a bid for this solicitation, submit Attachment 1 with your reasons why.

Pre-Bid Conference:

N/A

Scheduled Site Visit

N/A

Questions Due Date and Time:

April 9, 2025, 2:00 p.m. EST

Bid Due (Closing) Date and Time:

April 15, 2025, 2:00 p.m. EST.

Bidders are reminded that a completed Feedback Form is requested if a no-bid decision is made (see Attachment 1 - No Bid Notice/Vendor Feedback Form).

https://emma.maryland.gov/page.aspx/en/usr/login?ReturnUrl=%2fpage.aspx%2fen%2fbuy%2fhomepage mailto:eMMA.helpdesk@maryland.gov

IFB for Maryland Department of the Environment Page 3 of 23

Public Bid Opening Date, Time, and Location

Bids will not be opened publicly.

MBE

Subcontracting Goal:

N/A

VSBE

Subcontracting Goal:

N/A

Procurement Method:

A Contract will be awarded in accordance with the Competitive Sealed Bidding method under COMAR 21.05.02.

Multiple or Alternate Bids:

Multiple or alternate Bids will not be accepted.

Contract Type: Indefinite Quantity, Fixed Price

Contract Duration:

2 Years

Primary Place of Performance:

Contractor’s place of Business.

SBR Designation: No

Federal Funding: No

IFB for Maryland Department of the Environment Page 4 of 23

NO BID NOTICE/VENDOR FEEDBACK FORM

To help us improve the quality of State solicitations, and to make our procurement process more responsive and business friendly, please provide comments and suggestions regarding this solicitation.

Please return your comments with your response. If you have chosen not to respond to this solicitation, please email or fax this completed form to the attention of the Procurement Officer (see Key Information Summary Sheet below for contact information).

Title: Radiation Meter Calibration Solicitation No: U00R5600123

1. If you have chosen not to respond to this solicitation, please indicate the reason(s) below:

Other commitments preclude our participation at this time

The subject of the solicitation is not something we ordinarily provide

We are inexperienced in the work/commodities required

Specifications are unclear, too restrictive, etc. (Explain in REMARKS section)

The scope of work is beyond our present capacity

Doing business with the State is simply too complicated. (Explain in REMARKS section)

We cannot be competitive. (Explain in REMARKS section)

Time allotted for completion of the Bid is insufficient

Start-up time is insufficient

Bonding/Insurance requirements are restrictive (Explain in REMARKS section)

Bid requirements (other than specifications) are unreasonable or too risky (Explain in REMARKS section)

MBE or VSBE requirements (Explain in REMARKS section)

Prior State of Maryland contract experience was unprofitable or otherwise unsatisfactory. (Explain in REMARKS section)

Payment schedule too slow

Other: __________________________________________________________________

2. If you have submitted a response to this solicitation, but wish to offer suggestions or express concerns, please use the REMARKS section below. (Attach additional pages as needed.)

REMARKS:

Vendor Name: ________________________________ Date: _______________________

Contact Person: ________________________________ Phone (____) _____ - _________________

Address: ______________________________________________________________________

E-mail Address: ________________________________________________________________

IFB for Maryland Department of the Environment Page 5 of 23

1 Minimum Qualifications

1.1. The awarded Contractor shall be certified to perform radiological meter calibrations or possess a state license to perform meter calibrations.

1.1.1 As proof of meeting this requirement, a copy of a valid Nuclear Regulatory Commission License or valid State License Agreement must be submitted with the bid.

THE REMAINDER OF THIS PAGE IS INTENTIONALLY LEFT BLANK.

IFB for Maryland Department of the Environment Page 6 of 23

2 Contractors Requirements: Scope of Work

2.1 Summary Statement

2.1.1 The State of Maryland Department of the Environment (“MDE” or the "Department") is issuing this Invitation for Bids (IFB) in order to procure the services, as specified in this IFB, to perform calibration of radiation detection meters of the Department used for radiation measurement/testing.

2.1.2 It is the State’s intention to obtain goods and services, as specified in this IFB, from a contract between the selected Bidder and the State.

2.1.3 This is a single IFB award. See IFB Section 4.21 Bid Evaluation Criteria and Award Basis for more Contract award information. A Contract award does not ensure a Contractor will receive all or any State business under the Contract.

2.2 Background and Purpose

MDE’s Radiological Health Program (RHP) is mandated by Title 8: “Radiation” of the Annotated Code of Maryland, Environmental Article, to control the uses of radiation and to protect public health and safety and the environment from inadvertent and unnecessary radiation exposure.

RHP regulates the use of both radiation machines and radioactive materials. To prevent unnecessary exposures to radiation, the RHP inspects x-ray machines at dental and veterinary facilities every three years to determine whether the machines are performing according to rigid specifications and whether the machine operators are following proper safety procedures. The RHP also certifies the performance of medical, industrial and academic electronic radiation machines following inspection by State-licensed inspectors and performs inspections of State mammography facilities under contract with the federal Food and Drug Administration.

2.3 Project Goals

2.3.1 Obtain a Contractor who can calibrate/maintain the equipment used to inspect facilities and other sources of radiation. The equipment must be maintained in good working order and calibrated at specified times during the life cycle of the equipment to ensure accuracy and safety of the citizens.

2.3.2 State Staff and Roles

In addition to the Procurement Officer and Contract Monitor, the State will assign a point of contact to schedule the shipping of the instruments to be calibrated to the Contractor and/or delivery of repaired equipment to MDE.

2.3.3 Contractor Responsibilities and Tasks

2.3.3.1 Must be authorized/certified to calibrate and maintain all equipment listed in Attachment B.

2.3.3.2 Must be capable of servicing or obtaining services for defective equipment and return it to

MDE.

2.3.3.3 Upon discovery of a malfunction or need for repair, notification will be made to the Contract Monitor and approval must be granted prior to initiation of any repairs.

IFB for Maryland Department of the Environment Page 7 of 23

2.3.4 The Contractor shall Calibrate and maintain specific radiation equipment supplied by MDE.

A. The Contractor shall calibrate each unit according to the Manufacturer's recommendation at the Contractor’s facility.

B. The Contractor shall ensure that each Unit will accurately calculate the amount of radiation during a response.

C. The Contractor shall return all serviced equipment in good condition after repairs are completed and shall do so within 20 days.

D. The Contractor shall calibrate ten to twenty instruments per Order.

E. MDE shall send instruments to the Contractor for Calibration on an as needed basis.

F. The Contractor shall mail each unit back to MDE.

G. The Contractor shall fix/repair any broken unit upon prior approval from the Contract Monitor.

H. The Contractor shall provide documentation of the calibration of each Unit The survey meter calibration records shall include the procedure used, the data obtained, and the following information:

1) A description of the instrument, including the manufacturer’s name, model number, serial number, and type of detector.

2) A description of the NIST-traceable calibration source, including the calibration procedure, exposure rate, distance at which it was measured, and date of measurement.

3) For each calibration point, the calculated exposure rate, the indicated exposure rate, the calculated correction factor (the calculated exposure rate divided by the indicated exposure rate), and the scale selected on the instrument.

4) The exposure reading indicated with the instrument in the “battery check” mode (if available on the instrument);

5) For instruments with external detectors, the angle between the radiation flux field and the detector (i.e., parallel or perpendicular);

6) For instruments with internal detectors, the angle between the radiation flux field and a specified surface of the instrument.

7) For detectors with removable shielding, an indication of whether the shielding was in place or removed during the calibration procedure.

8) The exposure rate from a check source, if used.

9) The name of the person who performed the calibration and the date it was performed.

I. The following information shall be attached to the instrument as a calibration sticker or tag:

1) The source that was used to calibrate the instrument.

2) The proper deflection in the battery check mode (unless this is clearly indicated on the instrument);

3) Special use conditions (e.g., an indication that a scale or decade was checked only for function but not calibrated);

4) The date of calibration and the next calibration due date.

5) The apparent exposure rate from the check source, if used.

6) Additional measurement related instrument specific technical information of meters, if applicable.

IFB for Maryland Department of the Environment Page 8 of 23

5 Required Standards for Calibration A. Model Procedure for Calibrating Survey Instruments

This model provides acceptable procedures for survey instrument calibrations. Licensees may either adopt these model procedures or develop their own procedures to meet the requirements of 10 CFR Part 20 and 10 CFR 35.61. (Detailed information about survey instrument calibration may be obtained by referring to IEEE/ANSI N323AB-2013, “Radiation Protection Instrumentation Test and Calibration, Portable Survey Instruments.” Copies may be obtained from the American National Standards Institute at 25 West 43rd Street, 4th Floor, New York, NY 10036, or by ordering electronically from http://www.ansi.org.

B. Procedures for calibration of survey instruments

Radiation survey instruments will be calibrated with a radioactive source that satisfies the requirements in 10 CFR 35.61. Electronic calibrations alone are not acceptable. Model calibration procedures can be found in the IAEA Safety Reports Series No. 16 – Calibration of Radiation Protection Monitoring Instruments. This document can be accessed through IAEA’s website or by using the following link: Safety Report Series No. 16. Survey meters must be calibrated at least annually, before first use, and after servicing or repairs that affect calibration. (Battery changes are not considered “servicing.”) Instruments used to monitor higher energies are most easily calibrated in known radiation fields produced by sources of gamma rays of approximately the same energies as those to be measured. An ideal calibration source would emit the applicable radiation (e.g., alpha, beta, or gamma) with an energy spectrum similar to that to be measured and have a suitably long half-life.

C. Use a radioactive sealed source(s) that:

1) Approximates a point source;

2) Is a certified, NIST-traceable, standard source that has an activity or exposure rate accurate to within 5%; if the activity or exposure rate is determined by measurement, document the method used to make the determination and traceability to NIST.

3) Emits the type of radiation measured.

4) Approximates the same energy (e.g., Cs-137, Co-60) as the environment in which the calibrated device will be employed; and

5) Provides a radiation- dose rate sufficient to reach the full scale (<1000 mR/hr) of the instrument calibrated. Use the inverse square and radioactive decay laws, as appropriate, to correct changes in exposure rate due to changes in distance or source decay.

D. A record must be made of each survey meter calibration and retained for 3 years after each record is made (10 CFR 20.2103(a) and 10 CFR 35.2061).

E. Before use, perform a daily check (with a dedicated check source) and battery checks.

about:blank

IFB for Maryland Department of the Environment Page 9 of 23

F. Instrument readings should be within ± 10% of known radiation values at calibration points;

however, readings within ± 20% are acceptable if a calibration chart or graph is prepared and made available with the instrument.

G. The kinds of scales frequently used on radiation survey meters should be calibrated as follows:

1) Calibrate Linear-Readout Instruments at no fewer than two points on each scale. Calibration will be checked near the ends of each scale (at approximately 20% and 80%).

2) Calibrate Logarithmic-Readout Instruments at two points on each decade.

3) Calibrate Digital-Readout Instruments with either manual or automatic scale switching for indicating exposure rates at no fewer than two points on each scale. Check calibrations near the ends of each scale (at approximately 20% and 80% of each scale).

4) Calibrate Digital-Readout Instruments without scale switching for indicating exposure rates at two points on each decade.

5) Calibrate Integrating Instruments at two dose rates (at approximately 20% and 80% of the dose rate range).

H. Reading above 1000 mR/ hr (250 microcoulomb/kilogram of air per hour) need not be calibrated;

however, such scales may be checked for operation and approximately correct response.

MDE will notify the Contractor when there is equipment ready to be sent for repair or calibration and provide the quantity of equipment being shipped.

Equipment must be shipped via UPS, Federal Express or other registered carrier with tracking capabilities. No equipment may be sent via the United States Postal Service.

Equipment is to be returned to MDE at 1800 Washington Boulevard, Baltimore Maryland 21230 Attention: ALANNA JENKINS 410 537-3102. The Contractor shall contact MDE when equipment is shipped.

The Contractor assumes responsibility to replace any equipment damaged in shipping or not returned in working condition.

IFB for Maryland Department of the Environment Page 10 of 23

3 Additional Requirements

3.1 Contract Initiation Requirements

Once all approvals have been obtained and the Contract is fully executed, the Procurement Officer may schedule a kickoff meeting to be held prior to commencement of Contract performance.

3.2 End of Contract Transition

The Contractor shall cooperate in the orderly transition of services from it to a subsequent contractor at the end of the contract term or upon receipt of a Notice of Termination from the State. Transition shall be provided in a prompt and timely manner and shall proceed in accordance with the schedule provided to the Contractor by the State in the Notice of Transition. Additional instructions regarding transition services may be provided in the event of a Notice of Termination issued by the State.

3.3 Invoicing

Submission of an invoice constitutes the Contractor’s verification that the information in the invoice is accurate as of the time of submission.

An invoice not satisfying the requirements of a Proper Invoice (as defined in COMAR 21.06.09) will not be processed for payment. To be considered a Proper Invoice, invoices must include the following information, without error:

A. Contractor name and address;

B. Remittance address;

C. Federal taxpayer identification (FEIN) number, social security number, as appropriate;

D. Invoice period (i.e. time period during which services covered by invoice were performed);

E. Invoice date;

F. Invoice number;

G. State assigned Contract number;

H. State assigned (Blanket) Purchase Order number(s);

I. Goods or services provided;

J. Amount due; and

K. Any additional documentation required by regulation or the Contract.

Invoices that contain both fixed price and labor hour or time and material items shall clearly identify each item as either fixed price, and labor hour, or time and material billing.

The State reserves the right to reduce or withhold Contract payment in the event the Contractor does not provide all required deliverables within the time frame specified in the Contract or otherwise breaches the terms and conditions of the Contract until such time as the Contractor brings itself into full compliance with the Contract.

The State is generally exempt from federal excise taxes, Maryland sales and use taxes, District of Columbia sales taxes and transportation taxes. The Contractor, however, is not exempt from such sales and use taxes and may be liable for the same.

IFB for Maryland Department of the Environment Page 11 of 23

Invoices for final payment shall be clearly marked as “FINAL” and submitted when all work requirements have been completed, and no further charges are to be incurred under the Contract. In no event shall any invoice be submitted later than 60 calendar days from the Contract termination date.

3.3.1 Invoice Submission Schedule

The Contractor shall submit invoices in accordance with the following schedule:

A. All Invoices must be submitted via email to ap.mde@maryland.gov

B. For items of work for which there is one-time pricing (see Attachment B –The Price Form), those items shall be billed in the month following the acceptance of the work by the State. Acceptance shall be upon MDE inspecting returned equipment and verifying that an invoice may be submitted.

3.3.2 Travel Reimbursement

Travel will not be reimbursed under this IFB.

3.4 Liquidated Damages

3.4.1 MBE Liquidated Damages

Inapplicable because there is no MBE goal for this IFB.

3.4.2 Liquidated Damages other than MBE

This section is inapplicable to this IFB.

3.4.3 Problem Escalation Procedure

No later than ten (10) Business Days after notice of the recommended award or after the date of the Notice to Proceed, whichever is earlier, the Contractor must provide, and thereafter, maintain a Problem Escalation Procedure (PEP) for both routine and emergency situations. The PEP must state how the Contractor will address problem situations as they occur during the performance of the Contract, especially problems that are not resolved to the satisfaction of the State within appropriate timeframes and must include:

A. Contact information B. The process for establishing the existence of a problem;

C. Names, titles, and contact information for progressively higher levels of personnel in the Contractor’s organization who would become involved in resolving a problem;

D. For each individual listed in the Contractor’s PEP, the maximum amount of time a problem will remain unresolved with that individual before the problem escalates to the next contact person listed in the Contractor’s PEP;

E. Expedited escalation procedures and any circumstances that would trigger expediting them;

F. The method of providing feedback on resolution progress, including the frequency of feedback to be provided to the State;

G. Contact information for persons responsible for resolving issues after normal business hours (e.g., evenings, weekends, holidays) and on an emergency basis; and

H. A process for updating and notifying the Contract Monitor of any changes to the PEP.

mailto:ap.mde@maryland.gov

IFB for Maryland Department of the Environment Page 12 of 23

I. The PEP must be updated within ten (10) Business Days after any change in circumstance which changes the PEP but not less than annually within ten (10) Business Days after the start of each Contract year .

Nothing in this section shall be construed to limit any rights of the Contract Monitor or the State which may be allowed by the Contract or applicable law.

3.5 Work Orders

This section is inapplicable to this IFB.

3.6 Payments by Electronic Funds Transfer

By submitting a Bid in response to this solicitation, the Bidder, if selected for award:

Agrees to accept payments by electronic funds transfer (EFT) unless the State Comptroller’s Office grants an exemption. Payment by EFT is mandatory for contracts exceeding $200,000. The successful Bidder shall register using the COT/GAD X-10 Vendor Electronic Funds (EFT) Registration Request Form.

Any request for exemption must be submitted to the State Comptroller’s Office for approval at the address specified on the COT/GAD X-10 form, must include the business identification information as stated on the form, and must include the reason for the exemption. The COT/GAD X-10 form may be downloaded from the Comptroller’s website at:

http://comptroller.marylandtaxes.com/Vendor_Services/Accounting_Information/Static_Files/GA DX10Form20150615.pdf.

3.7 Prompt Payment Policy

This procurement and the Contract(s) to be awarded pursuant to this solicitation are subject to the Prompt Payment Policy Directive issued by the Governor’s Office of Small, Minority & Women Business Affairs (GOSBA) and dated August 1, 2008. Promulgated pursuant to Md. Code Ann., State Finance and Procurement Article, §§ 11-201, 13-205(a), and Title 14, Subtitle 3, and COMAR 21.01.01.03 and 21.11.03.01, the Directive seeks to ensure the prompt payment of all subcontractors on non-construction procurement contracts. The Contractor shall comply with the prompt payment requirements outlined in the Contract, Section 31 “Prompt Pay Requirements” (see Exhibit 2 - Sample Contract). Additional information is available on GOSBA’s website at:

http://www.gomdsmallbiz.maryland.gov/documents/legislation/promptpaymentfaqs.pdf.

3.8 Federal Funding Acknowledgement

This Contract does not contain federal funds.

3.9 Conflict of Interest Affidavit and Disclosure

The Bidder shall complete and sign the Conflict-of-Interest Affidavit and Disclosure (Attachment I) and submit it with its Bid.

By submitting a Conflict-of-Interest Affidavit and Disclosure, the Contractor shall be construed as certifying that all Contractor Personnel and subcontractors are also without a conflict of interest as defined in COMAR 21.05.08.08A.

IFB for Maryland Department of the Environment Page 13 of 23

Additionally, a Contractor has an ongoing obligation to ensure that all Contractor Personnel are without conflicts of interest prior to providing services. For policies and procedures applying specifically to Conflict of Interests, the Contract is governed by COMAR 21.05.08.08.

Participation in Drafting of Specifications: Disqualifying Event: Bidders are advised that Md. Code Ann. State Finance and Procurement Article §13-212.1(a) provides generally that “an individual who assists an executive unit in the drafting of specifications, an invitation for bids, a request for proposals for a procurement, or the selection or award made in response to an invitation for bids or a request for proposals, or a person that employs the individual, may not: (1) submit a bid or proposal for that procurement; or (2) assist or represent another person, directly or indirectly, who is submitting a bid or proposal for that procurement.” Any Bidder submitting a Bid in violation of this provision shall be classified as “not responsible.”

3.10 Non-Disclosure Agreement

3.10.1 Non-Disclosure Agreement (Bidder/Offeror)

A Non-Disclosure Agreement (Bidder/Offeror) is not required for this procurement.

3.10.2 Non-Disclosure Agreement (Contractor)

A Non-Disclosure Agreement (Contractor) is not required for this procurement.

3.11 Maryland Healthy Working Families Act Requirements

On February 11, 2018, the Maryland Healthy Working Families Act went into effect. All Bidders should be aware of how this Act could affect your potential contract award with the State of Maryland. See the Department of Labor, Licensing and Regulations website for Maryland Healthy Working Families Act Information: https://dllr.state.md.us/paidleave/.

3.12 The State of Maryland’s Commitment to Purchasing Environmentally Preferred Products and Services (EPPs)

Maryland’s State Finance & Procurement Article §14-410 defines environmentally preferable purchasing as “the procurement or acquisition of goods and services that have a lesser or reduced effect on human health and the environment when compared with competing goods or services that serve the same purpose.” Accordingly, Bidders are strongly encouraged to offer EPPs to fulfill this contract, to the greatest extent practicable.

https://dllr.state.md.us/paidleave/ https://trackbill.com/bill/maryland-house-bill-629-environmentally-preferable-procurement-maryland-green-purchasing-committee/647077/

IFB for Maryland Department of the Environment Page 14 of 23

3.13 Insurance Requirements

3.14 The Contractor shall maintain, at a minimum, the insurance coverages outlined below, or any minimum requirements established by law if higher, for the duration of the Contract, including option periods, if exercised:

3.15 The following type(s) of insurance and minimum amount(s) of coverage are required

3.15.1 Commercial General Liability - of $1,000,000 combined single limit per occurrence for bodily injury, property damage, and personal and advertising injury and $3,000,000 annual aggregate. The minimum limits required herein may be satisfied through any combination of primary and umbrella/excess liability policies.

3.15.2 Errors and Omissions/Professional Liability - $1,000,000 per combined single limit per claim and $3,000,000 annual aggregate.

3.15.3 Crime Insurance/Employee Theft Insurance - to cover employee theft with a minimum single loss limit of $1,000,000 per loss, and a minimum single loss retention not to exceed $10,000. The State of Maryland and the Maryland Department of the Environment should be added as a “loss payee.”

3.15.4 Worker’s Compensation - The Contractor shall maintain such insurance as necessary or as required under Workers’ Compensation Acts, the Longshore and Harbor Workers’ Compensation Act, and the Federal Employers’ Liability Act, to not be less than. one million dollars ($1,000,000) per occurrence (unless a state’s law requires a greater amount of coverage). Coverage must be valid in all states work is performed.

3.15.5 All insurance policies shall be endorsed to include a clause requiring the insurance carrier to provide the Procurement Officer, by certified mail, not less than 30 days’ advance notice of any non-renewal, cancellation, or expiration. The Contractor shall notify the Procurement Officer in writing, if policies are cancelled or not renewed within five (5) days of learning of such cancellation or nonrenewal. The Contractor shall provide evidence of replacement insurance coverage to the Procurement Officer at least 15 days prior to the expiration of the insurance policy then in effect.

3.15.6 Any insurance furnished as a condition of the Contract shall be issued by a company authorized to do business in the State.

3.16 The recommended awardee must provide current certificate(s) of insurance with the prescribed coverages, limits and requirements set forth in this section within five (5) Business Days from notice of recommended award. During the period of performance for multi-year contracts, the Contractor shall provide certificates of insurance annually, or as otherwise directed by the Contract Monitor.

IFB for Maryland Department of the Environment Page 15 of 23

3.17 The Contractor shall require any subcontractors to obtain and maintain comparable levels of coverage and shall provide the Contract Monitor with the same documentation as is required of the Contractor.

3.18 Security Requirements

Security Requirements are not required for this procurement.

IFB for Maryland Department of the Environment Page 16 of 23

4 Bid Submission Information and Instructions

4.1 eMaryland Marketplace Advantage (eMMA) eMMA is the electronic commerce system for the State of Maryland. The IFB, Pre-Bid Conference (Conference)summary and attendance sheet, Bidders’ questions and the Procurement Officer’s responses, addenda, and other solicitation-related information will be made available via eMMA.

To receive a contract award, a vendor must be registered on eMMA. Registration is free. Go to emma.maryland.gov, click on “New Vendor? Register Now” to begin the process, and then follow the prompts.

4.2 Electronic Means

The following transactions related to this procurement and any Contract awarded pursuant to it are not authorized to be conducted by electronic means:

A. Submission of Bond documents determined by the State to require original signatures; or

B. Any transaction, submission, or communication where the Procurement Officer has specifically directed that a response from the Contractor or Offeror be provided in writing or hard copy.

Any e-mail transmission is only authorized to the email addresses for the identified person as provided in the solicitation, the Contract, or in the direction from the Procurement Officer or Contract Monitor.

“Electronic means” refers to exchanges or communications using electronic, digital, magnetic, wireless, optical, electromagnetic, or other means of electronically conducting transactions.

Electronic means includes e-mail, internet-based communications, electronic funds transfer, specific electronic bidding platforms (e.g., https://procurement.maryland.gov), and electronic data interchange.

4.3 Pre-Bid Conference

N/A

4.4 Questions

All questions, including concerns regarding any applicable MBE or VSBE participation goals, shall identify in the subject line the Solicitation Number and Title for this IFB and must be submitted in writing via e-mail or eMMA to the Procurement Officer no later than the date and time specified in the Key Information Summary Sheet. The Procurement Officer, based on the availability of time to research and communicate an answer, shall decide whether an answer can be given before the Bid due date.

4.4.1 Answers to all questions that are not clearly specific only to the requestor will be distributed via the same mechanism as for IFB amendments and posted on eMMA.

4.4.2 The statements and interpretations contained in responses to any questions, whether responded to verbally or in writing, are not binding on the State unless it issues an amendment to the solicitation in writing.

https://emma.maryland.gov/page.aspx/en/usr/login?ReturnUrl=%2fpage.aspx%2fen%2fbuy%2fhomepage https://procurement.maryland.gov/

IFB for Maryland Department of the Environment Page 17 of 23

4.5 Bid Due (Closing) Date and Time

Bids must be received by the Procurement Officer no later than the Bid due date and time indicated on the Key Information Summary Sheet to be considered. Except as provided in COMAR

21.05.02.10. Bids received after that date will not be considered. Requests for an extension of this date or time shall not be granted.

For Bids accepted via email, the time stamp to indicate receipt of the Bid by the State, is the posted date and time in the Procurement Officer’s email inbox.

Bids may be modified or withdrawn by written notice received by the Procurement Officer before the time and date set forth in the Key Information Summary Sheet for receipt of Bids.

Potential Bidders not responding to this solicitation are requested to submit the “No Bid/Proposal Notice/Vendor Feedback” form Attachment 1, which includes company information and the reason for not responding (e.g., too busy, cannot meet mandatory requirements).

4.6 Receipt, Opening and Recording of Bids

Upon receipt, each Bid and any timely modification(s) to a Bid shall be stored in a secure place until the time and date set for Bid Opening. Before Bid opening, the State may not disclose the identity of any Bidder.

Bids will not be opened publicly.

4.7 Duration of Bids

Bids submitted in response to this IFB are irrevocable for the latest of the following: 120 days following the Bid due date and time or the date any protest concerning this IFB is finally resolved.

This period may be extended at the Procurement Officer’s request only with the Bidder’s written agreement.

4.8 Revisions to the IFB

4.8.1 All revisions to the IFB before the due date for Bids will be published in an addendum to the IFB and posted on eMMA and reasonable effort will be made to provide such addenda to all prospective Bidders that were sent this IFB or are otherwise known by the Procurement Officer to have obtained this IFB. It is the responsibility of all prospective Bidders to check eMMA for any addenda issued prior to the submission of Bids.

4.8.2 Bidders shall acknowledge in the Bid the receipt of all addenda to this IFB issued before the Bid due date.

4.8.3 Failure to acknowledge receipt of an addendum does not relieve the Bidder from complying with the terms, additions, deletions, or corrections set forth in the addendum, and may cause the Bid to be deemed not responsive.

4.9 Cancellations

4.9.1 This IFB may be cancelled as provided in COMAR 21.06.02.02

4.9.2 The State reserves the right to cancel this IFB, accept or reject any and all Bids, in whole or in part, received in response to this IFB and to waive or permit the cure of minor irregularities.

IFB for Maryland Department of the Environment Page 18 of 23

4.9.3 In the event a government entity proposes and receives the recommendation for award, this procurement may be canceled, and the award processed in accordance with COMAR 21.01.03.01.A(4).

4.9.4 If the services that are the subject of the IFB are currently being provided under an interagency agreement with a public institution of higher education and the State determines that the services can be provided more cost effectively by the public institution of higher education, then the IFB may be canceled in accordance with Md. Code Ann., State Finance and Procurement Art., § 3- 207(b)(2).

4.10 Incurred Expenses

The State will not be responsible for any costs incurred by any Bidder in preparing and submitting a Bid or performing any other activities related to submitting a Bid in response to this solicitation.

4.11 Protest/Disputes

Any protest or claim related to this IFB or the Contract award hereunder shall be subject to the provisions of COMAR 21.10 (Administrative and Civil Remedies).

4.12 Bidder Responsibilities

4.12.1 A Bidder, either directly or through its subcontractor(s), must be able to provide all goods and services and meet all of the requirements requested in this solicitation and the successful Bidder (the Contractor) shall remain responsible for Contract performance regardless of subcontractor participation in the work.

4.12.2 If applicable, subcontractors utilized in meeting the established MBE or VSBE participation goal(s) for this solicitation shall be identified using Attachment D or Attachment E as appropriate. Guidance for completing the Attachments is provided in the appropriate Appendix or Appendices to this IFB (see “Appendix 4 - MBE Participation Goal” and “Appendix 5 - VSBE Participation Goal”).

4.12.3 If the Bidder is the subsidiary of another entity, all information submitted by the Bidder, including but not limited to references, financial reports, or experience and documentation (e.g., insurance policies, bonds, letters of credit) used to meet minimum qualifications, if any, shall pertain exclusively to the Bidder, unless the parent organization will guarantee the performance of the subsidiary. If applicable, the Bidder’s Bid shall contain an explicit statement, signed by an authorized representative of the parent organization, stating that the parent organization will guarantee the performance of the subsidiary.

4.12.4 A parental guarantee of the performance of the Bidder under this section will not automatically result in crediting the Bidder with the experience or qualifications of the parent under any evaluation criteria pertaining to the actual Bidder’s experience and qualifications. Instead, the Bidder’s responsibility will be assessed to the extent to which the State determines that the experience and qualifications of the parent are applicable to and shared with the Bidder, any stated intent by the parent to be directly involved in the performance of the Contract, and the value of the parent’s participation as determined by the State.

4.13 Acceptance of Terms and Conditions

By submitting a Bid in response to this IFB, the Bidder, if selected for award, is deemed to have accepted the terms and conditions of this IFB and the Contract, attached hereto as Exhibit 2 –

IFB for Maryland Department of the Environment Page 19 of 23

Sample Contract. Any questions or exceptions to this IFB or the Contract must be submitted by the “Questions Due Date and Time” prior to Bid submission. Changes to the solicitation, including the Bid Form or Contract, made by the Bidder may result in Bid rejection.

4.14 Compliance with Laws/Arrearages

By submitting a Bid in response to this IFB, the Bidder, if selected for award, agrees that it will comply with all federal, State, and local laws applicable to its activities and obligations under the Contract.

By submitting a response to this solicitation, each Bidder represents that it is not in arrears in the payment of any obligations due and owing the State, including the payment of taxes and employee benefits, and shall not become so in arrears during the term of the Contract if selected for Contract award.

4.15 Verification of Registration and Tax Payment

Before a business entity can do business in the State, it must be registered with the State Department of Assessments and Taxation (SDAT). SDAT is located at State Office Building, Room 803, 301 West Preston Street, Baltimore, Maryland 21201. For registration information, visit https://egov.maryland.gov/BusinessExpress/.

It is strongly recommended that any potential Bidder complete registration prior to the Bid due date and time. The Bidder’s failure to complete registration with SDAT may disqualify an otherwise responsive successful Bidder from final consideration and recommendation for Contract award.

4.16 False Statements

Bidders are advised that Md. Code Ann., State Finance and Procurement Article, § 11-205.1 provides as follows:

In connection with a procurement contract a person may not willfully:

A. Falsify, conceal, or suppress a material fact by any scheme or device.

B. Make a false or fraudulent statement or representation of a material factor C. Use a false writing or document that contains a false or fraudulent statement or entry of a material fact.

A person may not aid or conspire with another person to commit an act under this section.

A person who violates any provision of this section is guilty of a felony and on conviction is subject to a fine not exceeding $20,000 or imprisonment not exceeding five (5) years or both.

4.17 Confidentiality of Bids / Public Information Act Notice

The Bidder should give specific attention to the clear identification of those portions of its Bid that it considers to contain confidential and/or proprietary commercial information or trade secrets, and provide justification for why such materials, upon request, should not be disclosed by the State under the Public Information Act, Md. Code Ann., General Provisions Article, Title 4. This information should be identified by page number and placed in the Transmittal Letter with the Bid.

The Bids shall be tabulated or a Bid abstract made. The opened Bids shall be available for public inspection at a reasonable time after Bid opening, but in any case before contract award, except to the extent the Bidder designates trade secrets or other proprietary data to be confidential as set forth in https://egov.maryland.gov/BusinessExpress/

IFB for Maryland Department of the Environment Page 20 of 23 this solicitation. Material designated as confidential shall accompany the Bid and shall be readily separable from the Bid to facilitate public inspection of the non-confidential portion of the Bid, including the Total Bid Price.

For requests for information made under the PIA, the Procurement Officer shall examine the Bids to determine the validity of any requests for nondisclosure. Nondisclosure is permissible only if approved by the Office of the Attorney General.

4.18 Use of Bidder’s Form Not Binding on State

The Bidder may not substitute, modify, or provide any other document in lieu of the documents provided with this Bid. Only those forms and documents provided with this solicitation and by the Procurement Officer will be considered acceptable as bid submission.

4.19 Attachments and Documents Required with the Bid (Table A) A Bidder shall include the following Attachments with its Bid as a single Bid Package:

Attachments A through E = Bid will be rejected if the required Attachment is not submitted or is incomplete.

Attachments F through I = Bid may be rejected if the required Attachment is not submitted or is incomplete.

TABLE A - Attachments and Documents Required with the Bid

Attachment Attachment Name

A

Bid/Proposal Affidavit A Bid submitted by the Bidder must be accompanied by a completed Bid/Proposal

Affidavit.

https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf

B

The Price Form (as specified within eMMA) Do not alter this Price Form or the Bid may be determined to be not responsive.

The Price Form must be signed and dated, where requested, by an individual who is authorized to bind the Bidder to the prices entered on the Bid Form.

(See Appendix 2 for specific Price Form Instructions.)

F

Bidder Information Sheet https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-F.-Bidder-Offeror-Information- Sheet.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-F.-Bidder-Offeror-Information-Sheet.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-F.-Bidder-Offeror-Information-Sheet.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-F.-Bidder-Offeror-Information-Sheet.pdf

IFB for Maryland Department of the Environment Page 21 of 23

TABLE A - Attachments and Documents Required with the Bid

Attachment Attachment Name

I Conflict of Interest Affidavit and Disclosure https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf.

L

Reference Checks (Each reference shall be from a customer for whom the Bidder has provided goods or services within the most recent past five years) https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf

U Contract Affidavit https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf

Additional Required Documents to submit with the Bid.

Acknowledgement of all addenda to this IFB.

A copy of the Contractors’ valid Nuclear Regulatory Commission License or valid State License Agreement and /or certified to perform radiological meter calibrations.

Certificate of Insurance

4.20 Bid Delivery Instructions

Each Bidder shall submit its Bid Package as specified below.

Bids shall only be accepted via the State’s internet-based electronic procurement system, eMMA.

Bidders shall provide their Bids in one submission through eMMA following the Quick Reference Guides (QRG) labeled “4 - eMMA QRG Responding to Solicitations (IFB)” for single envelope submissions.

4.21 Bid Evaluation Criteria and Award Basis

The Bids will be evaluated based on the Total Bid Price, as per COMAR 21.05.02.13. All Bids will be ranked from the lowest (most favorable) to the highest (least favorable) price based on the Total Bid Price as submitted in its Bid.

A Contract shall be awarded to the responsible Bidder(s) submitting a responsive Bid with the most favorable Bid Price that meets the requirements to provide the service as specified in this IFB.

https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-I.-Conflict-of-Interest-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-L.-Reference-Checks.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf https://procurement.maryland.gov/emma-qrgs/ https://procurement.maryland.gov/emma-qrgs/

IFB for Maryland Department of the Environment Page 22 of 23

4.22 Tie Bids

Tie Bids will be decided pursuant to COMAR 21.05.02.14.

4.22 Reciprocal Preference

Although Maryland law does not authorize procuring agencies to favor resident Bidders in awarding procurement contracts, many other states do grant their resident businesses preferences over Maryland contractors. COMAR 21.05.01.04 permits procuring agencies to apply a reciprocal preference under the following conditions:

A. The Maryland resident business is a responsible Bidder.

B. The lowest responsive Bid is from a responsible Bidder whose principal office, or principal base of operations, is in another state;

C. The other state gives a preference to its resident businesses through law, policy, or practice; and

D. The preference does not conflict with a federal law or grant affecting the procurement Contract.

The preference given shall be identical to the preference that the other state, through law, policy, or practice gives to its resident business.

IFB for Maryland Department of the Environment Page 23 of 23

4.23 Documents Required upon Notice of Recommendation for Contract Award (Table B)

Upon receipt of a notification of recommendation for contract award, along with submitting the signed Contract (see Sample Contract), the following documents shall be completed and submitted by the recommended awardee within ten (10) business days, unless otherwise directed by the Procurement Officer.

Click the link to download each required Attachment in Table B below:

TABLE B - Documents Required upon Notice of Recommendation for Contract Award

Attachment Attachment Name

A

Bid/Proposal Affidavit A Bid submitted by the Bidder must be accompanied by a completed

Bid/Proposal Affidavit.

https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal- Affidavit.pdf

B

The Price Form (as specified within eMMA) Do not alter this Price Form or the Bid may be determined to be not responsive. The Price Form must be signed and dated, where requested, by an individual who is authorized to bind the Bidder to the prices entered on the Bid Form.

(See Appendix 2 for specific Price Form Instructions.)

Exhibit 2 Contract

Certificate of Insurance

U

Contract Affidavit https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract- Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-A.-Bid-Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2024/07/Attachment-U.-Contract-Affidavit.pdf

1 Minimum Qualifications
2 Contractors Requirements: Scope of Work
2.1 Summary Statement
2.1.3 This is a single IFB award. See IFB Section 4.21 Bid Evaluation Criteria and Award Basis for more Contract award information. A Contract award does not ensure a Contractor will receive all or any State business under the Contract.
2.2 Background and Purpose
2.3 Project Goals
2.3.1 Obtain a Contractor who can calibrate/maintain the equipment used to inspect facilities and other sources of radiation. The equipment must be maintained in good working order and calibrated at specified times during the life cycle of the equipme...
2.3.2 State Staff and Roles
2.3.3 Contractor Responsibilities and Tasks
2.3.3.1 Must be authorized/certified to calibrate and maintain all equipment listed in Attachment B.
2.3.3.3 Upon discovery of a malfunction or need for repair, notification will be made to the Contract Monitor and approval must be granted prior to initiation of any repairs.
5 Required Standards for Calibration
A. Model Procedure for Calibrating Survey Instruments
3 Additional Requirements
3.1 Contract Initiation Requirements
3.2 End of Contract Transition
3.3 Invoicing
3.3.1 Invoice Submission Schedule
3.3.2 Travel Reimbursement
3.4 Liquidated Damages
3.4.1 MBE Liquidated Damages
3.4.2 Liquidated Damages other than MBE

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .