IFB FYE27-4411 INSTALLATION OF GENERATOR AT JOHNSON MANOR copy copy.pdf
PDF 4 MB Posted
- Attached to
- Installation of Generator at Johnson Manor Apts
- Solicitation number
- FYE27-4411
- Issued by
- Orange County, Orlando City, Florida
About this file
Summary
This is an Invitation for Bids (IFB) issued by the Housing Authority of the City of Orlando, Florida for the installation of a backup generator at Johnson Manor Apartments, a senior residential complex located at 4775 Curry Ford Road, Orlando, Florida 32812. The scope of work includes removal and disposal of the existing 100kW diesel generator and 250-gallon fuel tank, removal of the existing 250A automatic transfer switch (ATS), provision and installation of a new 100kW natural gas generator, installation of a new 250A ATS, modification of the existing enclosure and concrete pad, testing and replacement of conductors if necessary, natural gas connection installation, and required testing and commissioning. The pre-bid conference and worksite walkthrough is scheduled for Thursday, July 9, 2026 at 10:00 AM EST. Questions must be submitted in writing by Monday, July 20, 2026 at 2:00 PM EST. Sealed bids are due on August 3, 2026 at 2:00 PM EST at the Orlando Housing Authority, 390 North Bumby Avenue, Orlando, Florida 32803. Bid opening occurs on August 3, 2026 at 2:30 PM EST at the Matilda Roman Center. The contract period shall be 180 calendar days from the Notice to Proceed, with normal working hours Monday through Friday, 8:00 AM to 4:30 PM ET.
The bid shall be submitted as a firm-fixed fee with all costs inclusive of labor, materials, equipment, permits, and other necessary expenses. A bid bond equivalent to 10% of the bid price is required for bids exceeding $50,000. The successful bidder must provide performance and payment bonds for 100% of the contract price or equivalent alternatives, workers' compensation insurance, general liability insurance with the Agency as an additional insured (minimum $1,000,000 each occurrence), and automobile insurance ($1,000,000 combined single limit). The contractor must comply with Davis-Bacon wage rates for construction contracts exceeding $2,000 and obtain all required state, county, and local permits and licenses. Progress payments will be made at 30-day intervals based on percentage of work completed, with 10% retainage withheld from each payment until final project completion. The contractor is responsible for providing temporary facilities, maintaining daily debris removal, obtaining maintenance manuals, and providing operator training to Agency personnel.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JULY 02, 2026
INVITATION FOR BIDS (IFB)
FYE27-4411
INSTALLATION OF A GENERATOR
FOR JOHNSON MANOR APTS.
Housing Authority of the City of Orlando, Florida (OHA) 390 N. Bumby Avenue Orlando, Florida 32803
407-895-3300
INVITATION FOR BIDS (IFB) FYE27-4411 INSTALLATION OF A GENERATOR AT
JOHNSON MANOR APTS.
ORLANDO HOUSING AUTHORITY
Table of Contents [Table No. 1]
Section Description Page Introduction 3 IFB Information at a Glance 4
1.0 The Agency’s Reservation of Rights 5
2.0 Scope of Work/Technical Specifications 6
2.1 General Scope of Work 6
2.2 Contractor Responsibilities (in alpha order) 6
3.0 Bid Format 14
3.1 Tabbed Bid Submittal 14
3.2 Entry of Proposed Fees 17
3.3 Additional Information Pertaining to the Pricing Items 18
3.4 Bonds 20
3.5 Bid Submission 22
3.6 Bidder's Responsibilities — Contact with the Agency 23
3.7 Bidder's Responsibilities — Equal Employment Opportunity and
Supplier Diversity
3.8 Pre-bid Conference 26
3.9 Recap of Attachments 26
4.0 Bid Evaluation 28
4.1 Public Opening 28
4.2 Responsive Evaluation 29
4.3 Responsible Evaluation 29
4.4 Restrictions 29
5.0 Contract Award 29
5.1 Contract Award Procedure 29
5.2 Contract Conditions 30
5.3 Contract Period 30
5.4 Licensing and Insurance Requirements 31
5.5 Contract Services Standards 31
5.6 Prompt Return of Contract Documents 32
Index of Tables 32
INTRODUCTION
The Housing Authority of the City of Orlando, Florida (OHA) was established in January of 1938 under Chapter 421 of the State of Florida Statutes. A seven-member board of Commissioners, which includes an OHA resident, governs the Authority. The Mayor of the City of Orlando appoints board members. It is managed by a President/CEO and is subject to the requirements of Title 24 of the Code of Federal Regulations (hereinafter, “CFR”) and the Agency’s procurement policy. OHA is not a city Agency. OHA has been a Moving To Work (MTW) agency since 2011. The OHA manages and operates 11 traditional public housing developments (1315 units) in the City of Orlando and Orange County, providing quality housing to thousands of low-income residents. OHA oversees 207 tax credit units in three developments and 456 affordable non-public housing units. In addition, OHA administers the Section 8 program for approximately 4,500 vouchers for rental assistance.
The OHA manages and maintains 456 affordable market-rate units throughout Orange County, Florida. Services to all residents go beyond bricks and mortar as the OHA delivers a wide range of social services to enhance the quality of life and promote the self-sufficiency of its residents and clients.
Orlando Housing Authority Mission:
"To offer a choice of safe and affordable housing options and opportunities for economic independence for residents of Orlando and Orange County. "
In keeping with its mandate to provide efficient and effective services, OHA is now soliciting bids from qualified, licensed, and insured entities to provide the above-noted services to the Agency. All bids submitted in response to this solicitation must conform to all the requirements and specifications outlined within this document and any designated attachments in its entirety.
IFB INFORMATION AT A GLANCE
[Table No. 2]
HOW TO OBTAIN THE IFB DOCUMENTS
DOWNLOAD DOCUMENTS BY ACCESSING
1. The Housing Agency Marketplace-@ ha.internationaleprocurement.com
2. Euna OpenBids at https://network.demandstar.com/
PRE-BID CONFERENCE & WORKSITE
WALKTHROUGH
Thursday, July 09, 2026, 10:00 AM EST.
Johnson Manor Apts. at 4775 Curry Ford Road, Orlando, FL 32812.
DEADLINE TO SUBMIT QUESTIONS All questions pertaining to this IFB must be submitted in writing to Liza Martinez at liza.martinez@orl-oha.org by Monday, July 20, 2026, at 2:00 PM EST.
HOW TO FULLY RESPOND TO THIS IFB BY
SUBMITTING A BID SUBMITTAL
1. As instructed within Section 3.0 of the IFB document, submit 1 copy of your "hard copy" bid to the Orlando Housing Authority.
BID SUBMISSION RETURN & DEADLINE
August 03, 2026 @ 2:00 P.M. EST.
Sealed bids are due at the following location:
The Orlando Housing Authority
Attention: Liza Martinez 390 North Bumby Avenue Orlando, Florida 32803
The sealed bid package must have the following notation on the bottom left-hand corner:
“BID FOR: INSTALLATION OF A GENERATOR AT
JOHNSON MANOR APTS. IFB FYE27-4411”
BID OPENING TIME AND LOCATION
August 03, 2026, AT 2:30 PM EST.
BID OPENING WILL TAKE PLACE AT THE MATILDA
ROMAN CENTER LOCATED AT 325 NORTH HILLSIDE
AVENUE, ORLANDO, FL 32803
1.0 THE AGENCY’S RESERVATION OF RIGHTS. The Agency reserves the right to:
1.1 Right to Reject, Waive, or Terminate the IFB. Reject any or all bids, to waive any informality in the IFB process, or to terminate the IFB process at any time, if deemed by the Agency to be in its best interests.
1.2 Right to Not Award. Not to award a contract pursuant to this IFB.
1.3 Right to Terminate. Terminate a contract awarded pursuant to this IFB, at any time for its convenience, upon a 10-day written notice to the successful bidder(s).
1.4 Right to Determine Time and Location. Determine the days, hours, and locations that the successful bidder(s) shall provide the services called for in this IFB.
1.5 Right to Retain Bids. Retain all bids submitted and to not permit withdrawal for a period of 60 days subsequent to the deadline for receiving bids without the written consent of the Agency Contracting Officer (CO).
1.6 Right to Reject Any Bid. Reject, and to not consider any bid that does not meet the requirements of this IFB, including but not necessarily limited to incomplete bids and/or bids offering alternate or non-requested services.
1.7 No Obligation to Compensate. Has no obligation to compensate any bidder for any costs incurred in responding to this IFB.
1.8 Right to Prohibit. At any time during the IFB or contract process to prohibit any further participation by a bidder or reject any bid submitted that does not conform to any of the requirements detailed herein. By accessing DemandStar and the eProcurement Marketplace (hereinafter also “the Marketplace”) and by downloading this document, each prospective bidder is thereby agreeing to abide by all terms and conditions listed within this document and further agrees that he/she will inform the CO in writing within 5 days of the discovery of any item listed herein or of any item that is issued thereafter by the Agency that he/she feels needs to be addressed.
Failure to abide by this time frame shall relieve the Agency, but not the prospective bidder, of any responsibility pertaining to such an issue.
2.0 SCOPE OF WORK/TECHNICAL SPECIFICATIONS. The Agency is seeking bids from qualified and licensed entities by the state of Florida, bonded and insured to provide the Agency with the following detailed services:
2.1 General Scope of Work.
Provide materials, equipment, labor, supervision, engineering, permits/inspections, and associated fees, to install a backup generator at a senior residential complex, Johnson Manor Apts., located at 4775 Curry Ford Rd, Orlando, FL 32812, as follows:
1. Remove and dispose of the existing 100kW diesel generator and the existing 250-gallon fuel tank.
2. Remove and dispose of the existing 250A automatic transfer switch (ATS).
3. Provide and install a new 100kW natural gas generator.
4. Provide and install a new 250A ATS, non-service entrance rated.
5. Modify the existing enclosure and concrete pad as needed to accommodate the new generator.
6. Test the existing conductors between the generator and the ATS; replace All such conductors, if any of the conductors fail the insulation resistance Test.
7. Provide and install the natural gas connection from the generator to the natural gas utility meter location
8. Provide required testing and commissioning of the new equipment.
2.2 Contractor Responsibilities (in alpha order).
2.2.1 Access for Emergency Vehicles. The Contractor shall ensure that any equipment and/or vehicles that he/she places on the work site shall not be placed in such a position to interfere with access by any emergency vehicles or traffic by the public at large. The Agency reserves the right to approve or reject (and demand the movement) of the placement of such equipment or vehicles at any time during the performance of the contracted work if, in the opinion of the Agency, the placement of such equipment or vehicles does interfere with such traffic.
2.2.2 As-built Record Documents. Do not use Record Documents for construction purposes; the documents shall be protected from loss in a secure location; provide access to Record Documents for the Agency's reference.
2.2.2.1 If issued, maintain a clean, undamaged set of blue or black line white-prints of Contract Drawings and Shop Drawings. Mark-up these drawings to show the actual installation. Mark whichever drawing is most capable of showing conditions accurately. Give particular attention to concealed elements that would be difficult to measure and record at a later date.
2.2.3 Build America, Buy America (BABA) Act Requirements. If applicable, by receipt of a contract award, it shall be the responsibility of the successful bidder to agree, certify, and eventually show proof that the work and products provided and installed by the contractor are in full compliance with the requirements of the noted Act. More information can be obtained at the following link: https://www.hud.gov/baba.
2.2.4 Communication. The Agency shall be the primary on-site point of contact for the Contractor pertaining to this work. The Contractor shall be free to converse and communicate with the Agency during or between visits;
however, all requests for changes or decisions shall be submitted to the Agency and approved by the Executive Director after receipt and consideration of written request from the Agency. The Agency anticipates that it will typically make a decision in such matters within 3 work days of receipt, though such response time-frame may be shorter or longer depending on the situation; accordingly, the Contractor shall be required to submit such written requests in as timely a manner as reasonably possible. When construction commences, all communication must be directed to the designated Agency contact person only.
2.2.5 Contract End Items. Upon completion of the project the Contractor must submit the following:
2.2.5.1 A separate payment request for the retainage;
2.2.5.2 A one-year warranty letter from the Contractor;
2.2.5.3 Consent of Surety to Final Payment;
2.2.5.4 Contractor’s Affidavit of Release of Liens;
2.2.5.5 Contractor’s Certificate and Release; and
2.2.5.6 As- built’s (Mark-ups delivered to Agency).
2.2.6 Contractor’s Request for Payment. As detailed within Chapter 9, Procurement and Contract Administration, of Handbook 7485.1.
2.2.6.1 The Agency is responsible for making progress payments.
Typically, progress payments for acceptable work and materials delivered and stored on the site will be made at 30-day intervals.
2.2.6.2 Payment will be based on the percentage of work completed during a one-month period.
2.2.6.3 A 10% retention will be withheld on each payment request. A separate payment request for the return of the retention will be required at the completion of the work.
2.2.6.4 Request for Payment Forms. The Contractor shall submit a request for payment for this project on the following forms, each as may be appropriate:
[Table No. 3] (1)
IFB
Section
(2) Attachment
No.
(3)
Form Description
2.2.6.4.1 G-6 form HUD-51000 (1/2014), Schedule of Amounts
for Contract Payments; NOTE: The Agency also retains the right to require any bidder (but most likely the apparent low bidder) to submit this fully completed form to the Agency at any point after the bid submittal deadline—this typically will occur when the Agency wishes to do an analysis of the bidder’s proposed cost to ascertain as to whether or not the bidder’s proposed cost is realistic, fair, and/or reasonable.
2.2.6.4.2 G-7 form HUD-51001 (1/2014), Periodic Estimate for
Partial Payment
2.2.6.4.3 G-8 form HUD-51002 (1/2014), Schedule of Change
Orders
2.2.6.4.4 G-9 form HUD 51003 (1/2014), Schedule of Materials
Stored
2.2.6.4.5 G-10 form HUD-51004 (1/2014), Summary of Materials
Stored
2.2.6.4.6 G-11 form HUD-5372(1/2014), Construction Progress
Schedule
2.2.6.4.7 G-12 All relevant Subcontractors Weekly Certified
Payrolls must accompany the payment request utilizing form WH-347
2.2.6.4.8 N/A Retainage. The Request for Payment form must
list and clearly identify the retainage in the amount of 10% as a deduction to the subtotal of charges on the Request for Payment.
2.2.6.5 Review and Approval. The Agency will review each such
Contractor request for payment and will approve the payment only if the following listed conditions are met. If the Contractor requests payment items which have not been completed in a satisfactory manner (“satisfactory,” as determined at the sole discretion of the Agency), the Agency shall hold payment for the unsatisfactory items, and pay the balance of the request (i.e., the undisputed portion). The Agency shall ensure:
2.2.6.5.1 The request for payment is consistent with the
Agency-approved schedule of amounts for contract payments; and,
2.2.6.5.2 As further detailed within the preceding Section
2.2.5.3 herein, the total of the request for payment does not include the amount to be retained by the Agency under the contract (retention or retainage); and,
2.2.6.5.3 The work covered by the request for payment
has been performed in accordance with the construction documents; and,
2.2.6.5.4 The Periodic Estimate for Partial Payment has
been properly executed on all applicable supporting documentation submitted; and,
2.2.6.5.5 The Contractor has submitted all required
reports such as payroll reports.
2.2.6.6 Distribution of Documents. The Contractor shall submit 2 original copies, and 1 additional copy of all documentation required. The Agency shall retain the 2 original Periodic Estimate for Partial Payment requests and all applicable supporting documentation for its file and return 1 copy of all such forms to the Contractor.
2.2.7 Debris. The Contractor shall clean work areas daily, at the end of the workday, of all work-generated debris which may endanger the safety of the others (the public; Agency residents; etc.).
2.2.7.1 All work areas must be kept sanitary and clean of any trash.
Debris from work must be removed from living areas.
2.2.7.2 The Contractor must examine the work area and determine any unsuitable work condition.
2.2.7.3 Any required removal or replacement of this work caused by unsuitable conditions will be just cause for the Contractor to bear the expense. Notice of unsuitable conditions shall be brought to the Agency’s representative in written form.
2.2.7.4 The Contractor shall provide a construction dumpster as needed to dispose and removal all debris. The use of the Agency dumpsters is prohibited.
2.2.8 Delivery of Materials. The Contractor and each Subcontractor shall inspect the site and determine the availability of storage space and trucking facilities to bring material or equipment into the building, or any other factors affecting the work under this Contract.
2.2.8.1 Long lead items should be ordered as soon as possible, after contracts are signed, to expedite shop drawings and delivery of materials to site. Advance planning will be important to ensure timely delivery of materials.
2.2.9 Final Inspection and Punch List. The Agency shall provide one (1) final inspection site visit to develop the final Punch List when the following are completed:
2.2.9.1 All new construction and installations are 100% complete and operational.
2.2.9.2 A test and balance report has been completed and delivered to the Agency for review.
2.2.9.3 All final inspections and permits have been closed and delivered to the Agency and Agency.
2.2.9.4 When the Contractor has completed all the required work and feels substantial completion has been achieved, the Contractor must document and request a final inspection and punch list be performed by the Agency. This will document the one (1) final inspection and punch list by the Agency.
2.2.9.5 When the Contractor has completed all the punch list items, the Contractor shall document and request a final re-inspection by the Agency.
2.2.9.6 The Agency will provide one (1) final site visit for re-inspection of the punch list items.
2.2.9.7 If the Agency feels the punch list items have not been completed satisfactorily, notice will be given to the Contractor.
2.2.9.8 All punch list items must be completed at the time of substantial and final acceptance.
2.2.9.9 If the final punch list items are not complete at the time of the final inspection, the retention will be withheld until final acceptance by the Agency.
2.2.10 Lay-out and Dimensions. The Contractor and each Subcontractor shall verify, and field check, all plan dimensions, elevations, and quantities on both the existing building and the new work under their respective responsibilities before proceeding with work. Discrepancies must be brought to the attention of the Agency in writing for clarification or correction. Any Contractor failing to exercise such precautions shall be held responsible for the cost of correcting any resulting errors.
2.2.11 Maintenance Manuals (if applicable). Organize maintenance data into sets of manageable size. Bind in individual heavy-duty 2-inch, 3-ring vinyl-covered binders, with pocket folders for folded sheet information.
Mark identification on front and spine of each binder. Include the following information:
2.2.11.1 Maintain Emergency instructions;
2.2.11.2 Spare parts list;
2.2.11.3 Copies of warranties;
2.2.11.4 Wiring diagrams;
2.2.11.5 Recommended "turn around" cycles;
2.2.11.6 Inspection procedures; and
2.2.11.7 Shop Drawings and Product Data.
2.2.12 Operating and Maintenance Instructions. Arrange for the installer of equipment that requires regular maintenance to meet with the Owner's personnel to provide instruction in proper operation and maintenance.
Include a detailed review of the following:
2.2.12.1 Maintenance manuals;
2.2.12.2 Spare parts and materials;
2.2.12.3 Tools;
2.2.12.4 Lubricants;
2.2.12.5 Control sequences;
2.2.12.6 Hazards;
2.2.12.7 Warranties and bonds;
2.2.12.8 Maintenance agreements and similar continuing
commitments;
2.2.12.9 Start up and shutdown;
2.2.12.10 Emergency operations;
2.2.12.11 Noise and vibration adjustments; and
2.2.12.12 Safety procedures.
2.2.13 “Or Equal” Specifications. Herein, or within the attached specifications, whenever the Agency has listed a specific brand name the words “or equal” shall automatically apply thereto. This term “or equal” means that the apparent successful bidder may propose to provide an alternate product as long as such proposed alternate product, in the opinion of the Agency, meets the minimum specifications. As detailed within Section 9.3.B.3 of HUD Procurement Handbook 7460.8 REV 2, brand names are listed herein for “establishing design and quality standards” for the product identified. If a bidder wishes to provide a different product than the product the Agency has identified, the Agency will be pleased to respond to any specific written request from a bidder with a listing of the “essential characteristics” for any such product (the bidder may also, if he/she wishes, wait to see if the firm is the apparent successful bidder then submit such written request after the bid submittal deadline when the Agency will evaluate such alternate products, if submitted).
2.2.14 Payroll Reports. The Contractor shall, during the term of the work, within
7 days of the end of any weekly payroll period, forward to the Agency a copy of the weekly payroll.
2.2.14.1 The Contractor is hereby made aware that the Agency will conduct periodic on-site wage surveys of the Contractor's staff working at the site. It is the responsibility of the Contractor to ensure that such work staff cooperate fully with the Agency interviewer. Relating to such interviews, please also see form HUD-11 (08/2004), Attachment G-13, attached hereto.
2.2.15 Permits. The Contractor shall obtain any and all required permits pertaining to any assigned work at his/her expense.
2.2.16 Required Licensing. The Contractor(s) shall be in possession of any current appropriate licensing that may be required by the State of Florida and Orange County and the City of Orlando, FL.
2.2.17 Retainage. Retainage for this work shall be in the amount of 10 percent, which shall be applied to each payment until final payment, at which time all retainage held will be paid by the Agency to the Contractor.
2.2.18 Safety. It shall be the responsibility of the Contractor to ensure, at all times during the performance of the work, to the maximum extent feasible, to protect the safety of Agency residents and staff, the Contractor's staff, and subcontractors, and the public. This shall include, but not be limited to, compliance with all OSHA-related Federal and local laws, codes, and regulations.
2.2.19 Security during Work. The Contractor shall take all means necessary to maintain the security of the area in which they are working. These security measures must be carried out on a twenty-four-hour basis, not just during normal work hours.
2.2.20 Site Assessment. The Contractor and contracted subcontractors are strongly encouraged to examine the project site before submitting a bid.
2.2.20.1 A Pre-bid Conference and walk-through is scheduled as noted within the preceding Table No. 2 herein. Due to the complexity of the project attendance is strongly encouraged, although not mandatory.
2.2.20.2 Additional site visits after the Pre-bid Conference may be scheduled. The Contractor must contact the Agency Contact Person listed within the preceding Table No. 2 herein to schedule a site visit. Allow a minimum of three (3) business days to schedule an appointment. Unscheduled visits are prohibited.
2.2.21 Temporary Facilities. It shall be the responsibility of the Contractor to provide any temporary facilities that may be required, including, but not limited to temporary toilets; water; fencing; barricades; lighting;
planking; signage; guardrails; etc. Accordingly, it shall be the responsibility of the Contractor to secure and maintain such items during the term of the work.
2.2.22 Time of Completion. The Contractor shall commence work under the ensuing contract on a date to be specified within the Notice to Proceed (NTP) form issued by the Agency and shall fully complete all work thereunder within 180 calendar days of execution of the NTP. NOTE: Any bidder who may have any concerns pertaining to the noted time of completion may bring this up at the Pre-bid Conference. Normal working hours shall be Monday through Friday, 8:00 AM to 4:30 PM ET. All other working hours require pre-approval. Provide a minimum of five (5) working days for approval and planning.
2.2.23 Tools/Equipment/Materials. The Contractor shall ensure that at all times during the work tools, equipment, and material are handled, placed, and stored in a secure and safe manner so as to protect all parties, including, but not limited to, the Contractor's workers, Agency tenants and staff, and the public at large. The Contractor shall ensure that during non-working hours such items are not left unattended on the job site when such safety may be compromised. If applicable, as the building the Contractor will be working in is occupied by housing tenants, including a number of elderly/disabled or special needs persons, it will be especially important that traffic areas are clear for access and egress.
2.2.24 Weekends. Unless otherwise approved by the Agency in writing, the
Contractor shall not perform work on Agency property during a holiday or weekend days (Saturday or Sunday).
2.2.25 Work Standards. It is the Contractor's responsibility to ensure that each worker provided by the Contractor shall be fully trained and qualified to provide any assigned work. Accordingly, all work provided shall be guaranteed by the Contractor to be performed in a workmanlike manner and in accordance with all applicable laws, codes, and/or regulations, including those issued by, but not limited to, the Orange County (and/or, if applicable, any city jurisdiction therein in which work will be performed), and/or the State of Florida, or any applicable Federal Agency. Smoking is prohibited within the building and on the building property boundaries.
3.0 BID FORMAT.
3.1 Two-step Bidding Process. All bidders will initially submit the documentation/ information detailed within the following listed Step #1 of Table No. 3. Then, the Agency anticipates that it will notify the apparent low bidder to submit, within 5 days after being notified to do so, the information detailed within the following detailed Step #2 within the same Table.
3.1.1 Tabbed Bid Submittal. As may be further described herein, the Agency intends to retain a Contractor pursuant to a “Low Bid” basis, also taking into consideration responsiveness and responsibility. Therefore, so that the Agency can properly evaluate the offers received, all bids submitted in response to this IFB must be formatted in accordance with the sequence noted within the table below. Each category must be separated by numbered index dividers, which number extends so that each tab can be located without opening the bid and labeled with the corresponding tab reference also noted below. None of the proposed services may conflict with any requirement the Agency has published herein or has issued by addendum.
[Table No. 4]
(1)
IFB
Section
(2) Tab No.
(3)
Description
3.1.1.1 Step #1: The following listed initial documentation/
information is to be completed and submitted where provided for within the eProcurement Marketplace prior to the posted bid submittal deadline.
3.1.1.1.1 1 Form of Bid. This Form is attached hereto as Attachment A to this IFB document. This 2-page Form must be fully completed, executed where provided thereon and submitted under this tab as a part of the initial bid submittal.
3.1.1.1.2 2 form HUD-5369-A (11/92), Representations, Certifications, and Statements of Bidders, Public and Indian Housing Programs. This Form is attached hereto as Attachment B to this IFB document. This 4-page Form must be fully completed, executed where provided thereon and submitted under this tab as a part of the bid submittal.
3.1.1.1.3 3 Bid Bond. If required, the Bid Bond as detailed within the following Section 3.4.1 herein.
3.1.1.1.4 4 Bidder Price From
3.1.1.1.5 5 Addendum (s) (If applicable when an addendum has been issued
3.1.1.2 Step #2: Documentation/information to be submitted, within 5 days, only by the apparent low bidder when directed to do so by the Agency.
3.1.1.2.1 1 Licensing. Submit under this Tab the license(s) detailed within the following Section 5.4.4 herein.
3.1.1.2.2 2 Proposed Services. As more fully detailed within Section 2.0, Scope of Bid/Technical Specifications, of this document, and the Specifications. The bidder shall, at a minimum, clearly detail within the information submitted under this tab documentation showing:
3.1.1.2.2.1 A brief description of the proposed safety and
quality assurance program.
3.1.1.2.2.2 *Fully completed form HUD-2530 (02/2013), Previous Participation Certification, Attachment I, attached hereto.*
3.1.1.2.2.3 *Fully completed form HUD-51000 (/2014), Schedule of Amounts for Contract Payments, Attachment G-6 attached hereto, one completed for each site (i.e., each Pricing Item as detailed within the following Table No. 4 herein).*
3.1.1.2.2.4 *NOTE: Based on the amount of the eventual award (meaning, for smaller awards), the requirements to completed and submit either of these two immediate-preceding-noted forms may, at the Agency’s discretion, be waived by the Agency for the apparent successful bidder.
3.1.1.2.3 3 Profile of Firm Form. The Profile of Firm Form is attached hereto as Attachment C to this IFB document. This 2-page Form must be fully completed, executed and submitted under this tab as a part of the bid submittal.
3.1.1.2.4 4 Managerial Capacity/Financial Viability. The bidder entity must submit under this tab a concise description of its managerial and financial capacity to deliver the proposed services, including brief professional resumes for the persons identified within areas (5) and (6) of Attachment C, Profile of Firm Form. Such information shall include the bid’s qualifications to provide the services, including a description of the background and current organization of the firm.
3.1.1.2.5 5 Client Information. The bidder shall submit a listing of former or current clients, including multi-family housing (i.e., apartment complexes of a similar nature), for whom the bidder has performed similar or like services to those being proposed herein. The listing shall, at a minimum, include:
3.1.1.2.5.1 The client’s name;
3.1.1.2.5.2 The client’s contact name;
3.1.1.2.5.3 The client’s telephone number and e-mail address;
3.1.1.2.5.4 A brief narrative description and scope of the
service(s) and the dates the services were/are provided.
3.1.1.2.6 6 Equal Employment Opportunity/Supplier Diversity.
The bidder must submit under this tab a copy of its Equal Opportunity Employment Policy and a complete description of the positive steps it will take to ensure compliance, to the greatest extent feasible, with the regulations detailed within the following Section 3.7 herein pertaining to supplier diversity (i.e., small, minority-, and women-owned businesses).
3.1.1.2.7 7 Subcontractor/Joint Venture Information (Optional Item). The bidder shall identify hereunder whether or not he/she intends to use any subcontractors for this job, if awarded, and/or if the bid is a joint venture with another firm. Such information pertaining to subcontractors shall include for each such firm the: firm name; name of contact person;
telephone and email address; and the State of Florida contractor license number.
3.1.1.2.8 8 Payment & Performance Bonds (as detailed within the following Section 3.4 herein).
3.1.1.2.9 9 Other Information (Optional Item). The bidder may include hereunder any other general information that the bidder believes is appropriate to assist the Agency in its evaluation.
3.1.1.2.10 Insurance Certificates. The apparent successful bidder will also direct its insurance broker or carrier to deliver directly to the Agency (by email is preferred) the insurance certificates detailed within the following Sections 5.4.1 through 5.4.3 herein. NOTE: The apparent successful bidder will NOT deliver these certificates to the Agency, as the insurance broker or carrier will do so.
3.1.1.2.11 Optional Tabs. If no information is to be placed under any of the above-noted tabs (especially the “Optional” tabs), please place there under a statement such as “NO INFORMATION IS BEING PLACED UNDER THIS TAB” or “THIS TAB LEFT INTENTIONALLY BLANK.” DO NOT eliminate any of the tabs.
3.2 Entry of Proposed Fees.
3.2.1 The proposed fees shall be submitted by the bidder and received by the Agency as part of the “hard copy” bid submittal.
3.2.2 Pricing Items. Unless otherwise stated herein, the proposed fees are all-inclusive of all related costs that the successful bidder will incur to be provide the in the bid, including, but not limited to: employee wages and benefits; clerical support; overhead; profit; licensing; insurance;
materials; supplies; tools; equipment; long distance telephone calls;
travel; and document copying not specifically agreed to by the Agency;
etc.
[Table No. 5] (1)
IFB
Section
(2) Pricing Item No.
(3)
Qty
(4)
U/M
(5)
Description
3.2.2.1 1 1 Each Firm-fixed Fee to remove and install a Generator at Johnson Manor Apts.
3.3 Additional Information pertaining to the preceding listed Pricing Items.
3.3.1 Quantities. All quantities entered by the Agency herein, especially within the immediate-preceding Table No. 5, and within the corresponding Pricing Items within the bid are for calculating purposes only. As may be further detailed herein, the Agency does not guarantee any minimum or maximum amount of work as a result of any award ensuing from this IFB, as the Agency anticipates that the ensuing contract may be a Requirements Contract, in which case the Agency shall retain one contractor only and shall retain the right to order from that contractor (successful bidder), on a task order basis, any amount of services the Agency requires.
3.3.2.1 Realistic Cost for each Pricing Item. Each bidder is strongly encouraged to submit a realistic cost for the Pricing Item. For example, if a bidder enters what the Agency deems to be an unrealistic sum such as $20,000 Pricing Item (bidders typically do so in an effort to improve their position in regards receiving an award), then the $20,000 is what the successful bidder will charge the Agency to complete all of the construction work that the Agency has listed herein and within Attachment H, attached hereto. Accordingly, it is the Agency’s opinion that it is very much in the best interests of the bidder to propose a realistic firm-fixed fee for the Pricing Item. If, despite this warning, the successful bidder proposes a fee that the Agency deems is not realistic, then the Agency reserves the right to declare that the bidder is non-responsive, and the Agency may reject the bidder’s offer.
3.3.2.1.1 Review Proposed Fees. The bidder will NOT be
able to correct this entry after the posted deadline has expired, which means that the Agency will utilize such entry, correct or incorrect, to determine the apparent low bidder.
3.3.2.1.1 No Post-submittal Deadline Corrections
Allowed. The Agency WILL NOT, after the submittal deadline, negotiate an increase to any unit costs or fees proposed prior to the submittal deadline; accordingly, bidders are strongly cautioned to submit a realistic price for the Pricing Items identified within the preceding Table No. 5 herein.
3.3.2.1.2 Review of the Entry of Proposed Fees. After a
bid is submitted and accepted, the bidder will NOT be able to correct this entry after the posted deadline has expired, which means that the Agency will utilize such an entry, correct or incorrect, to calculate who the apparent low bidder is.
3.3.3 No Escalation of Firm-fixed Fees. There shall be no escalation of the proposed firm-fixed fee amounts proposed and awarded at any time during the ensuing contract periods (except for, as designated by HUD, appropriate Agency-approved change orders awarded for “unforeseen conditions” within the general scope of work).
3.3.4 Prior Agency Approval Required. Please note that the successful bidder shall NOT conduct any additional work without the prior written authorization of the Agency representative. Failure to abide by this directive shall release the Agency of any obligation to pay the successful bidder for any work conducted without the noted prior written authorization.
3.3.5 No Deposit/No Retainer. The Agency will NOT pay any deposit or retainer fees at any time as a result of an award of the ensuing contract (though the Agency may consider, under certain circumstances, a reasonable and justified payment for mobilization).
3.3.6 Davis Bacon Federal Wage Rates. As detailed within pertinent HUD and
Federal regulation, the Contractor is required to pay Davis-Bacon wage rates (for all “construction contracts in excess of $2,000”). The applicable Wage Rates pertaining to the work detailed herein are attached hereto and detailed within Attachment G-16. This work will be subject to all the requirements pertaining to Davis-Bacon work, including the applicable Federal forms and procedures (i.e., on-site interviews; certified payrolls;
etc.).
3.4 Bonds. As this solicitation pertains to public works or construction, the bonds that are required include (each required for construction bids and/or contracts in excess of $50,000):
3.4.1 Bid Bond. The bid bond or guarantee shall be included in the bid package submitted by each bidder for any proposed fee that is greater than $50,000 (please see the preceding Section 3.1.1.1.3 herein). This bond ensures that if awarded the contract, the bidder will accept and perform the work under the contract. It also ensures that the bidder will not attempt to withdraw or otherwise not fulfill the contract. Finally, the bid bond ensures that the bidder will execute the contractual documents that are required within the time specified in the solicitation or forfeit all or part of the guarantee. A certified check, bank draft, U.S. Government Bonds at par value, bid bond secured by an acceptable surety company, or other negotiable instrument may be accepted as a bid guarantee. If the successful bidder refuses to sign the contract after award, the bid bond is forfeited, and the award will then go to the next lowest responsive and responsible bidder. If a bid bond or guarantee is not submitted with the bid, the Agency will reject the bid as non-responsive. The Agency anticipates that it will not return any bid bonds until the contract has been awarded and the required performance and payments bonds have been furnished until all bids have been rejected; or the time specified for acceptance of bids has expired. In fairness to the other bidders, the Agency may also choose to return the bid bonds if the Agency has a firm and reasonable assurance that the responsive and responsible bidder who submitted the lowest cost will execute the contract.
3.4.2 Performance Bond. The performance bond is meant to ensure that the contract is successfully completed. The performance bond guarantees that if the Contractor is unable to complete the contract, the surety company will step in to finish the work. In the case of a letter of credit or cash escrow, the Agency may use these funds to complete the contract work.
3.4.3 Payment Bond. The payment bond is a method of ensuring that the
Contractor pays the subcontractors and suppliers. By requiring payment bonds, the Agency avoids becoming entangled in disputes concerning payment of subcontractors and suppliers by the general contractor. The surety underwriting the payment bond ensures the contractors and suppliers will be paid. Often, performance and payment bonds are combined into a single document. Failure to pay subcontractors for work performed in commercial contracts may often lead to the subcontractor filing a mechanic’s lien against the property owners to obtain payment for services rendered. The Agency contract requires the payment bond to prevent this problem and ensure that no lien will be filed against any Agency building or lot of ground. As a reminder, Clause 24 of form HUD- 5370, General Conditions of the Contract for Construction (Attachment G- 1 attached hereto) clearly forbids the placement of any liens and is binding on any contractor, subcontractor, and material supplier.
3.4.4 Bonding Companies. An acceptable surety (bonding) company is one that is authorized to do business in the State of Florida and is acceptable to HUD and the Agency. The surety must be listed on the most recently published U.S. Treasury Circular 570 (often referred to as the T-List).
Individual sureties are not permitted. Circular 570 is available from the U.S. Department of the Treasury, Financial Management Service, Surety Bond Branch, Room #262C, 401 14th Street, S.W., Washington, D.C.
20227. The T-List may also be accessed on the Internet at:
http://www.fms.treas.gov/c570/index.html.
3.4.5 Bonding Requirements. In order to encourage participation by a broad range of competitors, including small and minority firms, HUD has provided for alternate bid and contract guaranties. These apply to all construction projects greater than $50,000 (though, at the Agencies discretion, may apply to smaller projects), whether development or modernization, funded pursuant to the U.S. Housing Act of 1937, as amended. As a result, the contractors for all construction projects shall be required to submit the following bid and contract guarantees. Please note that only the bid bond is required at the time of bid; however, one of the purposes of the bid bond is to provide the Agency with assurance that the successful bidder will indeed obtain the necessary performance and payment bonds. The required bonds include a bid guarantee from each bidder, equivalent to 10% of the bid price and, from the successful bidder, one of the following:
3.4.5.1 A performance and payment bond for 100% of the contract price; or
3.4.5.2 Separate payment and performance bonds each for 50% or more of the contract price; or,
3.4.5.3 A 20% cash escrow; or,
3.4.5.4 A 25% irrevocable letter of credit.
3.4.6 Inadequate Surety. If the low bidder fails to provide an acceptable assurance of completion (payment and performance bonds) after the award of the contract, the Agency may consider the bid guarantee forfeited and notify the surety company. The contract is then terminated for default. The amount to be recovered from the bid bond or guarantee will typically equal at least the difference between the defaulted bid and the next higher acceptable bid or the amount by which the bid accepted by re-soliciting exceeds the defaulted contract.
3.3.2.2 Prior Agency Approval Required. Please note that the
successful bidder shall NOT conduct any additional work without the prior written authorization of the Agency representative (via delivery of a Task Order, which may take the form of an e-mail). Failure to abide by this directive shall release the Agency of any obligation to pay the successful bidder for any work conducted without the noted prior written authorization.
3.5 Bid Submission. All Sealed “hard-copy” bids must be submitted and time-stamped and received in the designated Agency office by no later than the submittal deadline stated herein (or within any ensuing addendum). A total of 1 original signature copy of the Step #1 bid submittal detailed within the preceding Table No. 3 herein shall be placed unfolded in a sealed package and addressed and delivered to:
Attention: Liza Martinez 390 North Bumby Avenue
Orlando, FL 32803
Exterior of Submittal Package. The package exterior must clearly denote the above-noted IFB number and must have the bidder’s name and return address. Bids received after the published deadline will not be accepted.
3.5.1 Late Bids. Bids received after the published deadline will not be accepted or considered.
3.5.2 Submission Conditions. DO NOT FOLD OR MAKE ANY ADDITIONAL MARKS, NOTATIONS, OR REQUIREMENTS ON THE DOCUMENTS TO BE SUBMITTED!
Bidders are not allowed to change any requirements or forms contained herein, either by making or entering onto these documents or the documents submitted any revisions or additions; and if any such additional marks, notations or requirements are entered on any of the documents that are submitted to the Agency by the bidder, such may invalidate that bid. If, after accepting such a bid, the Agency decides that any such entry does not change the intent of the bid that the Agency intended to receive, the Agency may accept the bid, and the bid shall be considered by the Agency as if those additional marks, notations, or requirements were not entered on such. By accessing the eProcurement Marketplace/Demand Star, registering and downloading these documents, each prospective bidder that does so is thereby agreeing to confirm all notices that the
Agency delivers to him/her as instructed, and by submitting a bid, the bidder is thereby agreeing to abide by all terms and conditions published herein and by addendum pertaining to this IFB.
3.5.3 Submission Responsibilities. It shall be the responsibility of each bidder to be aware of and to abide by all dates, times, conditions, requirements and specifications set forth within all applicable documents issued by the Agency, including the IFB document, the documents listed within the following Section 3.8, and any addenda and required attachments submitted by the bidder. By virtue of completing, signing and submitting the completed documents, the bidder is stating his/her agreement to comply with the all conditions and requirements set forth within those documents. Written notice from the bidder not authorized in writing by the CO to exclude any of the Agency requirements contained within the documents may cause that bidder to not be considered for award.
3.6 Bidder's Responsibilities — Contact with the Agency. It is the responsibility of the bidder to address all communication and correspondence pertaining to this IFB process to the designated CO only. Bidders must not make inquiry or communicate with any other Agency staff member or official (including members of the Board of Commissioners) pertaining to this IFB. Failure to abide by this requirement may be cause for the Agency to not consider a bid submittal received from any bidder who may Agency not abided by this directive.
3.6.1 Addenda. All questions and requests for information must be addressed in writing to the CO. The CO anticipates that it will respond to all such inquiries in writing by addendum to all prospective bidders (i.e., firms or individuals that have obtained the IFB Documents). During the IFB solicitation process, the CO will NOT conduct any ex parte (a substantive conversation—“substantive” meaning, when decisions pertaining to the IFB are made—between the Agency and a prospective bidder when other prospective bidders are not present) conversations that may give one prospective bidder an advantage over other prospective bidders. This does not mean that prospective bidders may not call the CO—it simply means that, other than making replies to direct the prospective bidder where his/her answer Agency already been issued within the solicitation documents, the CO may not respond to the prospective bidder’s inquiries but will direct him/her to submit such inquiry in writing so that the CO may more fairly respond to all prospective bidders in writing by addendum.
3.7 Bidder's Responsibilities — Equal Employment Opportunity and Supplier Diversity.
Both the Contractor and the Agency have, pursuant to HUD regulation, certain responsibilities pertaining to the hiring and retention of personnel and subcontractors.
3.7.1 Within 2 CFR §200.321 it states:
3.7.1.1 Contracting with small and minority businesses, women's business enterprises, and labor surplus area firms.
3.7.1.2 (a) The non-Federal entity must take all necessary affirmative steps to assure that minority businesses, women's business enterprises, and labor surplus area firms are used when possible.
3.7.1.3 (2) Affirmative steps must include:
3.7.1.3.1 (1) Placing qualified small and minority businesses and women's business enterprises on solicitation lists; and,
3.7.1.3.2 (2) Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are potential sources; and,
3.7.1.3.3 (3) Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority business, and women's business enterprises; and,
3.7.1.3.4 (4) Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority business, and women's business enterprises; and,
3.7.1.3.5 (5) Using the services and assistance, as appropriate, of such organizations as the Small Business Administration and the Minority Business Development Agency of the Department of Commerce; and,
3.7.1.3.6 (6) Requiring the prime contractor, if subcontracts are to be let, to take the affirmative steps listed in paragraphs (1) through
(5) of this section.
3.7.2 Within HUD Procurement Handbook 7460.8 REV 2 such states:
3.7.2.1 Section 15.5.A, Required Efforts. Consistent with Presidential Orders 11625, 12138, and 12432, the [Agency] shall make every effort to ensure that small businesses, MBEs, WBEs, and labor surplus area businesses participate in [Agency] contracting.
3.7.2.2 Section 15.5.B, Goals. [The Agency] is encouraged to establish goals by which they can measure the effectiveness of their efforts in implementing programs in support of . . . contracting with disadvantaged firms. It is important to ensure that the means used to establish these goals do not have the effect of limiting competition and should not be used as mandatory set-aside or quota, except as may otherwise be expressly authorized in regulation or statute. Some localities have adopted minority contracting set-aside policies or geographic limitations, which may be in conflict with Federal requirements for full and open competition.
3.7.3 Within our Agency Procurement Policy it states that our Agency will:
3.7.3.1 Assistance to Small and Other Business, Required Efforts:
3.7.3.1.1 Including such firms, when qualified, on
solicitation mailing lists; and,
3.7.3.1.2 Encouraging their participation through direct
solicitation of bids or bids whenever they are potential sources; and,
3.7.3.1.3 Dividing total requirements, when economically
feasible, into smaller tasks or quantities to permit maximum participation by such firms;
and,
3.7.3.1.4 Establishing delivery schedules, where the
requirement permits, which encourage participation by such firms; and,
3.7.3.1.5 Using the services and assistance of the Small
Business Administration, and the Minority Business Development Agency of the Department of Commerce; and,
3.7.3.1.6 Requiring prime contractors, when
subcontracting is anticipated, to take the positive steps listed above.
3.7.4 Requirements. Accordingly, please see Section 3.1.7 within Table No. 3 herein which details the information pertaining to this issue that the bidder must submit in response to this bid showing compliance, to the greatest extent feasible, with these regulations.
3.8 Pre-bid Conference. The scheduled pre-bid conference identified on Page 2 of this document, pursuant to pertinent HUD regulation, is not mandatory. Many prospective bidders have previously responded to an IFB with a multi-tabbed submittal and may feel comfortable in doing so without attending the pre-conference. Typically, such conferences last 1 hour or less (not including the ensuing walk-through of the properties, if the bidder chooses to do so), though such is not guaranteed.
This is the start of the file's text. The full file is on GovTribe.