BEB On-Route Charging Infrastructure Summary

This Invitation for Bid (IFB) is issued by the Spokane Transit Authority (STA) for a public works project involving the installation of four depot-style pantograph chargers and associated electrical infrastructure at two locations: Valley Transit Center (VTC) in Spokane Valley and Liberty Lake Park and Ride (LLPR) in Liberty Lake, Washington. The project scope includes conduit, wiring, housekeeping pads, structural supports, frames, electrical equipment installation, and coordination of owner-furnished contractor-installed (OFCI) charging equipment and pantograph assemblies. The pre-bid walkthrough is scheduled for 9:00 AM on June 10, 2026, at the STA Boone North West Garage. Sealed bids are due by 10:00 AM Pacific Time on Monday, June 22, 2026, with public bid opening at the same time. The contract term is 365 calendar days from the Notice to Proceed, with work phased between both locations and a scheduled shutdown period from November 1, 2026, through March 30, 2027, due to weather conditions. VTC work must begin first with all underground and structural work substantially complete by November 1, 2026, while LLPR construction must coordinate with 36-40 week equipment lead times and extend into the 2027 construction season.

Bid prices must include all labor, materials, equipment, overhead, permits, Washington State Sales Tax, trench safety provisions, and prevailing wage compliance costs. A bid guarantee of five percent of the Base Bid is required for bids exceeding $35,000. The project is partially funded by a Washington State Green Transportation Grant. Bidders must be licensed contractors in Washington, possess a current UBI number, maintain industrial insurance coverage, and comply with prevailing wage rates as determined by the Washington Department of Labor and Industries. Responsible bidders must demonstrate a minimum of three prior projects valued at $2,000,000 or more, completed within the last eight years, with experience in multi-phase construction, utility coordination, electrical infrastructure installation, and coordination of long-lead equipment. Building permits for the City of Spokane Valley and City of Liberty Lake are reimbursable costs not included in the bid price. All work is subject to inspection and acceptance by STA's project manager, and the contractor must maintain insurance coverage for two years after final acceptance.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1230 W Boone Ave Spokane, WA 99201 www.spokanetransit.com

INVITATION FOR BID

2026-11230

BEB On-Route Charging Infrastructure

ISSUE DATE: Sunday, May 31, 2026

PROPOSAL DUE DATE: Monday, June 22, 2026 10 AM Pacific Time http://www.spokanetransit.com/

Spokane Transit Authority Section 00 Contract # 2026-11230 Table of Contents Project Name: BEB On-Route Charging Infrastructure

00-1 V. 082725

TABLE OF CONTENTS

DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS

Section Title

001100 Advertisement for Bids

002100 Instructions to Bidders

003100 Project Description & Scope of Work

004200 Bid Submittal Checklist

004213 Bid Proposal Form

004215 Bid Response Form

004512 Bidder Responsibility Criteria

004546.B Wage Payment Statutes—Certificate of Compliance

005000 Contract

007200.1 Public Works General Conditions

007300 Supplemental Conditions

007346.1 Washington Prevailing Wage Rates – Spokane County

DIVISION 01 – ELECTRICAL SPECIFICATIONS

Section Title

260500 Common Work Results

260519 Electrical Power Conductors and Cables

260526 Grounding and Bonding

260529 Hangers and Supports

260533 Raceways and Fittings

260540 Outlet, Junction and Pull Boxes

260543 Underground Ducts and Raceways for Electrical Systems

260553 Identification

260573 Short Circuit Device Coordination & Arc Flash Study

260800 Commissioning for Electrical Systems

262200 Low-Voltage Transformers

262413 Switchboards

262416 Panelboards

262726 Wiring Devices

262813 Fuses

262816 Enclosed Switches and Circuit Breakers

END OF SECTION 00

Spokane Transit Authority Section 001100 Contract # 2026-11230 Advertisement for Bids Project Name: BEB On-Route Charging Infrastructure

001100-1 V. 082725

ADVERTISEMENT FOR BIDS

Sealed bids will be accepted for the following project:

Project No.: 2026-11230

Project Title: BEB On-Route Charging Infrastructure

Agency: Spokane Transit Authority (STA) 1230 W Boone Ave.

Spokane, WA 99201

Purchasing Manager: Haley Wilson Purchasing Manager hwilson@spokanetransit.com 509-325-6076

Public Bid Opening: 10:00 AM, June 22, 2026 Spokane Transit Authority

Pre-Bid Walk-through: 9:00 AM, June 10, 2026 Spokane Transit Authority Boone North West Garage 1224 N Cedar Spokane, WA 99201

Project Summary: This public works project consists of the installation of four (4) depot style pantograph chargers and associated infrastructure, including conduit, wiring, housekeeping pads, structural supports and frames. This project is partially funded by a Washington State Green Transportation Grant.

Please direct all questions regarding this project to the Purchasing Manager stated above.

State of Washington prevailing wage rates are applicable for this public works project located in Spokane County. Bidders are responsible to verify and use the most recent prevailing wage rates. The “Effective Date” for this project is the Bid Form due date above. The applicable prevailing wage rates may be found on the Department of Labor & Industries website located at:

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx.

No Bidder may withdraw their bid after the bid due date and time unless contract award is delayed for a period exceeding ninety (90) days.

The Agency reserves the right to accept or reject any or all bids and to waive informalities in the solicitation process.

Use of Minority and Women’s Business Enterprise (MWBE) contractors and suppliers is encouraged, but not mandatory. Bidders may contact the Office of Minority and Women's Business Enterprise at http://OMWBE.wa.gov/ to obtain information on certified firms. Bidders may also utilize Veteran-owned Businesses at http://www.dva.wa.gov/program/certified-veteran-and-servicemember-owned-businesses.

https://fortress.wa.gov/lni/wagelookup/prvWagelookup.aspx http://omwbe.wa.gov/ http://www.dva.wa.gov/program/certified-veteran-and-servicemember-owned-businesses

Spokane Transit Authority Section 001100 Contract # 2026-11230 Advertisement for Bids Project Name: BEB On-Route Charging Infrastructure

001100-2 V. 082725

Spokane Transit Authority is an Equal Employment Opportunity (EEO) organization which does not discriminate on the basis of race, color, creed, national origin, sex, sexual orientation, gender identity, or presence of any sensory, mental or physical disability in the consideration of contract award. The successful Bidder will be required to comply with all federal, state and local EEO laws and regulations.

Spokane Transit Authority assures nondiscrimination in accordance with Title VI of the Civil Rights Act of 1964. For more information, visit www.spokanetransit.com.

Upon request, alternative formats of this information will be produced for individuals with disabilities. The public bid opening facility is accessible for individuals using wheelchairs. For other accommodations, please call (509) 325-6094 (TTY WA Relay 711) at least forty-eight (48) hours in advance.

END OF SECTION 001100

http://www.spokanetransit.com/

Spokane Transit Authority Section 002100 Contract # 2026-11230 Instructions to Bidders Project Name: BEB On-route Charging Infrastructure

002100-1

V 082725

INSTRUCTIONS TO BIDDERS

DEFINITIONS

A. Addenda are written or graphic instruments, approved and issued by the Owner prior to the time designated for opening of bids, which amend, modify or interpret the solicitation documents by identifying additions, deletions, clarifications or corrections.

B. Bid Option is the amount stated in the Bid to be added or deducted from the amount of the Base Bid if the corresponding change in project scope or materials or methods of construction described in the solicitation documents is accepted.

C. Architect, Engineer or A/E means a person or entity lawfully entitled to practice architecture or engineering, representing Owner within the limits of its delegated authority.

D. Base Bid is the sum stated in the Bid for which the Bidder offers to perform the work described as the Base, to which work may be added or deducted from sums stated in Alternate Bids (if any).

E. Bid is the submission of a complete and properly signed Bid Proposal Form together with a bid guarantee, when applicable, and the certifications and representations required to comply with this solicitation.

F. Bidder is one who submits a Bid for a Contract with the Owner for the Work described in the construction documents.

G. Bid Proposal Form is the form provided in Section 004213 of this solicitation.

H. Contract is the formal written executed agreement between Owner and Contractor authorizing Contractor to perform the Work in accordance with the Contract Documents.

I. Contractor is the Bidder who has been awarded a Contract to perform the Work in accordance with the Contract Documents.

J. Contract Documents means the Advertisement for Bids, Instructions to Bidders, executed Bid Proposal Form and Bidder certifications, Contract, General Conditions, Modifications to the General Conditions, Supplemental Conditions, Federal Terms & Conditions, Drawings, Specifications, any addenda and/or modifications thereof, any or all supporting documentation required by the above, special forms, or as requested by Owner.

K. Federal Assistance means project funding provided, in whole or in part, by the US Department of Transportation, Federal Transit Administration (“FTA”).

L. Non-responsive Bid means any Bid which fails to conform in all respects to the material requirements of this solicitation, imposes conditions which would modify requirements of this solicitation, or would limit a Bidder's liability to the Owner so as to give the Bidder an advantage over other Bidders as determined by the Owner.

M. Owner means the Spokane Transit Authority, “STA” or its authorized representative with the authority to enter into, administer and/or terminate the Work in accordance with the Contract Documents, and make related determinations and findings.

N. Responsible Bidder means a contractor who meets the criteria listed in RCW 39.04.350.

O. Unit Price is an amount stated in the Bid as a price per unit of measurement or materials or services as described in the construction documents as defined in the General Conditions of the Contract.

Project Name: BEB On-route Charging Infrastructure

002100-2

V 082725

PART 1 - GENERAL

1.1 INTRODUCTION

A. Scope of Work. The general description and scope of work for the project can be found in Section 003100 of this solicitation.

B. Schedule. Work may begin when the Contractor receives a formal “Notice to Proceed.”

Contractor shall proceed with promptness and dispatch and shall complete the project within 365 calendar days beginning on the day of commencement as stated in a Notice to Proceed.

This schedule assumes a construction shutdown period from approximately November 1, 2026 – March 30, 2027 where site and/or underground construction may not be feasible due to weather conditions.

Contractor must sequence/phase work between both locations. Valley Transit Center (VTC)’s work must begin first and all underground, steel frame structures, concrete placement, etc. must be complete or substantially complete no later than November 1, 2026. Contractor may continue aboveground work after this period, as weather permits, and upon coordination and approval by an authorized Spokane Transit Authority (STA) representative.

Liberty Lake Park and Ride (LLPR) has a different charger support configuration and additional manufacturer coordination requirements. LLPR’s construction must be coordinated around the charging equipment lead time (approximately 36-40 weeks) and weather conditions.

STA anticipates that all OFCI charging equipment will be procured prior to contract award and delivered prior to the start of 2027 construction season.

Contractor acknowledges that work will extend into the following construction season (2027), with potential for site shutdown from approximately November 1, 2026 – March 30, 2027, due to equipment lead times, manufacturer coordination, permitting, and weather conditions.

C. Public Records. Materials submitted in response to this competitive procurement shall become the property of Spokane Transit Authority. All received Bids shall be deemed public records as defined in Chapter 42.56 RCW Public Records Act. Any information in the Bid that the Bidder desires to claim as confidential and exempt from disclosure under the provisions of state law shall be clearly designated as “Confidential”. Each page claimed to be exempt from disclosure must be clearly identified by the word “Confidential” printed on it. Marking the entire Bid exempt from disclosure will not be honored. STA will consider a Bidder’s request for exemption from disclosure; however, STA will make a decision predicated upon state law and regulations. If any information is marked as Confidential in the Bid, it will not be made available until the affected Bidder has been given a reasonable opportunity to seek a court injunction against the requested disclosure. STA assumes no liability for disclosure of Confidential material submitted by Bidders. Bid submittals shall be considered public documents under applicable Washington state law and shall be available for inspection and copying by the public, except to the extent portions of the submittals are otherwise protected under applicable law. Each Bidder will be responsible for protecting any disclosure of its submittal under applicable law.

D. Request for Information. Any prospective Bidder desiring an explanation or interpretation of this solicitation, drawings, specifications, etc., must submit a request in writing to the A/E seven (7) calendar days before the bid due date. Oral explanations or instructions given before the award of Contract will not be binding. Any information given a prospective Bidder concerning a solicitation will be furnished promptly to all other prospective Bidders by addendum to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective Bidders.

Project Name: BEB On-route Charging Infrastructure

002100-3

V 082725

E. Disadvantaged Business Enterprise. STA is committed to ensuring that all firms regardless of race, color, sex or national origin have equal opportunity to participate in STA contracts.

Therefore, STA has established an annual agency goal for Disadvantaged Business Enterprise (DBE) participation in its contracting opportunities. In accordance with the legislative findings and policies set forth in Chapter 39.19 RCW, STA encourages participation in all of its contracts by Minority Business Enterprises (MBE), Women Owned Business Enterprise (WBE), and Minority Women Owned Business Enterprise (MWBE) firms certified by the Office of Minority and Women’s Business Enterprises (OMWBE). Participation may be either on a direct basis in response to this solicitation or as a subcontractor to a contractor submitting bids. However, unless required by federal statutes, regulations, grants or contract terms referenced in the Contract Documents, no preference will be included in the evaluation of Bids, no minimum level of DBE/MBE/WBE/MWBE participation shall be required as a condition for receiving an award, and Bids will not be rejected or considered non-responsive on that basis. Any affirmative action requirements set forth in federal regulations or statutes included or referenced in the Contract Documents will apply.

1.2 PREPARATION OF BIDS – CONSTRUCTION

A. Bids must be: (1) submitted on the Bid Proposal Form, or copies thereof, furnished by Owner or Owner’s agent, and (2) signed in ink. The person signing a Bid must initial each change appearing on any Bid Proposal Form. If the Bid is made by a corporation, it shall be signed by the corporation’s authorized designee. The address of the Bidder shall be typed or printed on the bid form in the space provided.

B. The Bid Proposal Form may require Bidders to submit bid prices for one or more items on a varying basis, including: (1) lump sum base bid; (2) lump sum bid option prices; (3) unit prices;

or (4) any combination of items 1 through 3 above.

C. If the solicitation includes bid option items, failure to provide a price on any Bid Options may disqualify the Bid. If bidding on all items is not required, Bidders should insert the words “No Bid” in the space provided for any item on which no price is submitted.

D. Substitute bid proposals will not be considered unless this solicitation authorizes their submission.

1.3 BID PRICES

A. The bid prices shown for each item on the Bid Proposal Form shall include all labor, material, equipment, overhead and compensation to complete all of the work for that item.

B. The actual cost of building permit (only) and the public utility hookup fees will be a direct reimbursement to the Contractor or paid directly to the permitting agency by the Owner. Fees for these permits should not be included by the Bidder in the bid amount.

C. The Bidder agrees to hold all Bid prices for ninety (90) days from date of bid opening.

1.4 ADDITIVE OR DEDUCTIVE BID ITEMS

A. The low Bidder, for purposes of award, shall be the responsive Bidder offering the low aggregate amount for the Base Bid, plus Bid Options selected by the Owner, and within funds available for the project.

B. The Bidder agrees to hold all Bid Options prices for ninety (90) days from date of bid opening.

Project Name: BEB On-route Charging Infrastructure

002100-4

V 082725

1.5 TAXES

A. This work qualifies as a “public road construction” as described in WAC 458-20-171 (“Rule 171”). Refer to Section 007200 Supplemental Conditions.

B. NOTE: Contractor must bond for total contract amount including WSST.

1.6 BID GUARANTEE

A. When the sum of the Base Bid plus all Bid Options is $35,000.00 or less, a bid guarantee is not required. When the sum of the Base Bid plus all Bid Options is greater than $35,000.00, a bid guarantee in the amount of five percent (5%) of the Base Bid amount is required. Failure of the Bidder to provide a bid guarantee when required shall render the Bid non-responsive.

B. Acceptable forms of bid guarantee are: A bid bond, U. S. postal money order, or certified check or cashier’s check made payable to Spokane Transit Authority. The Owner will return bid guarantees (other than bid bond) to unsuccessful Bidders as soon as practicable, but not sooner than the execution of a contract with the successful Bidder. The bid guarantee of the successful Bidder will be returned to the successful Bidder with its official notice to proceed with the Work.

C. The Bidder will allow ninety (90) days from the bid opening date for acceptance of its Bid by the Owner. The Bidder will return to Owner a signed Contract, insurance certificate and requisite bond(s) or bond waiver within fifteen (15) days after receipt of the Contract. If the apparent successful Bidder fails to sign all contract documents, provide the bond and insurance as required, or return the documents within fifteen (15) days after receipt of the Contract, the Owner may terminate the award of the Contract.

D. In the event a Bidder discovers an error in its Bid following the bid opening, the Bidder may request to withdraw its Bid under the following conditions:

1. Written notification is received by the Owner within twenty-four (24) hours following bid opening.

2. The Bidder provides written documentation of the claimed error to the satisfaction of the Owner within seventy-two (72) hours following the bid opening.

The Owner will approve or disapprove the request for withdrawal of the Bid in writing. If the Bidder’s request for withdrawal of its Bid is approved, the Bidder will be released from further obligation to the Owner without penalty. If it is disapproved, the Owner may retain the Bidder’s bid guarantee.

1.7 ACKNOWLEDGEMENT OF ADDENDA

Bidders shall acknowledge receipt of all addenda to this solicitation by identifying the addenda numbers in the space provided for this purpose on the Bid Proposal Form. Failure to do so may result in the bid being declared non-responsive.

1.8 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK

A. The Bidder acknowledges that it has taken steps necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling and storage of materials; (2) the availability of labor, water, electric power and road; (3) uncertainties of weather, river stages, tides or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during the work. The Bidder also

Project Name: BEB On-route Charging Infrastructure

002100-5

V 082725 acknowledges that it has satisfied itself as to character, quality and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including exploratory work done by the Owner, as well as from the drawings and specifications made a part of this solicitation. Any failure of the Bidder to take the actions described and acknowledged in this paragraph will not relieve the Bidder from responsibility for estimating properly the difficulty and cost of successfully performing the work.

B. If Bidder is unable to attend the scheduled pre-bid meeting, please contact STA to arrange a separate site visit. Bids submitted by Bidders that have not either attended a pre-bid meeting or inspected the sites in the presence of STA staff shall be considered non-responsive.

1.9 PREVAILING WAGE

A. The Work for this project constitutes a public work under RCW 39.04 Public Works. In accordance with RCW 39.12 Prevailing Wages on Public Works, the Contractor shall pay the highest prevailing wage rate by trade or occupation as specified by the State of Washington, Department of Labor and Industries.

B. If this Project is subject to Federal Assistance, the Contractor shall pay the greater of prevailing wages paid in accordance with the Davis Bacon and Related Acts or RCW 39.12 Prevailing Wages on Public Works. See Section 007200.1 Public Works General Conditions.

1.10 SUBMISSION OF BIDS

A. Bids must be submitted on or before the time specified in the Advertisement for Bids or as extended by written addenda to this solicitation.

B. Bids shall be submitted in a sealed envelope addressed to the office specified in the Advertisement for Bids. Oral, telephonic, electronic or facsimile bids are invalid and will not receive consideration. The envelope shall have printed on the outside:

1. The project number and description.

2. The name and address of the Bidder.

3. Identification as Bid Proposal.

C. Prior to the bid opening, the Owner’s representative will designate the official bid clock. Any part of the Bid or Bid modification not received prior to the times specified, per the designated bid clock, will not be considered and the Bid will be returned to the Bidder unopened.

D. A Bid may be withdrawn in person by the authorized representative of the Bidder before bid opening. The representative of the Bidder will be required to show ID and sign the bid summary sheet before the Bid will be released to Bidder.

E. Individuals with disabilities who wish to request special accommodation, (e.g., sign language interpreters, Braille, etc.) need to contact the Owner ten (10) working days prior to the scheduled bid opening.

1.11 CONSIDERATION OF BIDS

A. Owner shall have the right to reject any or all Bids, to reject Bids considered non-responsive, including but not limited to, Bids not accompanied by any required bid guarantee, Bidder certifications or data required by the solicitation, or a Bid not signed by the Bidder’s authorized representative.

Project Name: BEB On-route Charging Infrastructure

002100-6

V 082725

B. The Owner shall have the right to waive any informality or irregularity in any Bid received.

C. In the event that a single Bid is received, Owner will conduct a cost/price analysis of the Bid.

This analysis will compare the price and quality of the proposed equipment with that involved in recent similar purchases with similar specifications made by this or other governmental agencies in an attempt to determine the competitive integrity of the submitted Bid.

1.12 BID RESULTS

After the bid opening, Bidders may obtain bid results from the Owner.

1.13 RESPONSIBLE BIDDER

A. To be considered a “Responsible Bidder”, at the time of Bid submittal, Bidders must meet all requirements specified in Section 004512 Bidder Responsibility Criteria.

B. Supplemental Responsibility Criteria: In addition to the mandatory Bidder responsibility criteria, the Owner may adopt relevant supplemental criteria for determining Bidder responsibility applicable to a project which the Bidder must meet. Where applicable, such supplemental criteria shall be attached to this solicitation.

1. At least seven (7) days prior to the bid submittal deadline, a potential Bidder may request the Owner modify the supplemental responsibility criteria. The Owner will evaluate the information submitted by the potential Bidder and respond before the Bid submittal deadline.

If the evaluation results in a change of the supplemental responsibility criteria, the Owner will issue an addendum to this solicitation identifying the new and/or modified criteria.

2. Upon Owner’s request, the apparent low Bidder must supply the requested responsibility information within two (2) business days of request by Owner. Withholding information or failure to submit all the information requested within the time provided may render the Bid non-responsive.

3. Upon request of the Owner, a Bidder whose Bid is under consideration for award of Contract shall submit promptly satisfactory evidence of his/her financial resources, experience, organization, and equipment available for performance of the Contract on AIA Form A305 “Contractor’s Qualification Statement” or similar form approved by the Owner.

C. Not-responsible Bidder Notification.

1. If the Owner determines that the apparent low Bidder is not responsible, the Owner will notify the Bidder of its preliminary determination in writing.

2. Within three (3) days after receipt of the preliminary determination, the Bidder may withdraw its Bid or request a hearing where the Bidder may appeal the preliminary determination and present additional information to the Owner.

3. The Owner will schedule a hearing within three (3) working days of receipt of the Bidder’s request. The hearing members will include a STA Executive or their designee, and Project Manager.

4. The Owner will issue a final determination after reviewing information presented at the hearing.

5. If the Owner determines a Bidder to be not responsible, the Owner will provide, in writing, the reasons for the determination. If the final determination affirms that the Bidder is not responsible, the Owner will not execute a Contract with any other responsible Bidder until

Project Name: BEB On-route Charging Infrastructure

002100-7

V 082725 two (2) business days following submittal of the final determination to the not responsible Bidder.

6. The Owner’s final determination is specific to this project and will have no effect on other or future projects.

1.14 CONTRACT AWARD

A. The Owner will evaluate Bid responsiveness and responsibility.

1. A Bid will be considered responsive if it meets the following requirements:

a. It is received at the proper time and place.

b. It meets the stated requirements of this solicitation.

c. It is accompanied by a bid guarantee, when required.

2. A Bid will be considered responsible if it meets the following requirements:

a. It is submitted by a licensed/registered contractor within the state of Washington at the time of bid opening and is not banned from bidding on Public Works projects as determined by the Department of Labor and Industries; and

b. It meets the mandatory responsibility criteria established in RCW 39.04.350 for prime contractors and subcontractors and an overall accounting of the supplemental responsibility criteria established for the project.

B. The Owner reserves the right to accept or reject any or all Bids and to waive informalities.

C. The Owner may negotiate Bid price adjustments with the low responsive Bidder, including changes in the Contract Documents, to bring the Bid within the available funding per RCW 39.04.015.

D. The apparent low Bidder, for purpose of award, shall be the responsive and responsible Bidder offering the low aggregate amount for the Base Bid plus selected Bid Options and meeting all other bid submittal requirements.

E. The Contract will only become effective when signed by the Owner. Prior to the Owner’s signature, any and all costs incurred shall be the sole responsibility of the Bidder.

F. The Contractor must purchase and maintain insurance coverages as stated in Section 007200.1 General Conditions.

G. Note: AIA Payment Bond and Performance Bond forms (A312) are required. These forms will not be provided by the Owner.

1.15 CONTRACT DOCUMENTS

A. The Contract Documents under which it is proposed to execute this work consists of all material bound herein, plus any addenda incorporated into the documents.

B. The Contract Documents are intended to be mutually cooperative and to provide all details reasonably required for the execution of the Work. Any person contemplating the submission of a Bid shall have thoroughly examined all of the various parts of the Contract Documents, and should there be any doubt as to the meaning or intent of the Contract Documents, the Bidder should request in writing to the A/E at least seven (7) working days prior to bid opening, an interpretation thereof. Any interpretation or change in the Contract Documents will be made only in writing, in the form of an addendum to the Contract Documents and will be furnished to

Project Name: BEB On-route Charging Infrastructure

002100-8

V 082725 all prospective Bidders receiving a set of documents, who shall indicate receipt of same in the space provided on the Bid Proposal Form. The Owner will not be responsible for any other explanation or interpretation of said documents.

1.16 DISCREPANCIES & CONTRACT DOCUMENT REVIEW

A. The intent of Spokane Transit Authority and Federal Funded Project Contract Documents is to describe a complete Project. These Contract Documents are complimentary. What is required by one part of the Contract Documents shall be binding as if required by all.

B. In the event of a discrepancy between Spokane Transit Authority and Federal Funded Project Contract Documents, the Contractor will use the Contract Document that imparts the highest cost to their Bid and/or longest delay in their schedule. It is the responsibility of the Contractor to bring these discrepancies to the attention of the Architect as soon as they are discovered.

1.17 PROTEST PROCEDURES

STA maintains a set of protest procedures. If any Bidder desires this information, it may be obtained by calling STA’s Senior Procurement Manager, at (509) 325-6032.

PART 2 - PRODUCTS (Not used)

PART 3 - EXECUTION (Not used)

END OF SECTION 002100

Spokane Transit Authority Section 003100 Contract # 2026-11230 Project Description and Scope of Work Project Name: BEB On-Route Charging Infrastructure

003100-1 V. 082725

PROJECT DESCRIPTION AND SCOPE OF WORK

PROJECT DESCRIPTION

This public works project consists of the installation of four (4) depot style pantograph chargers and associated infrastructure, including conduit, wiring, housekeeping pads, structural supports and frames. This project is partially funded by a Washington State Green Transportation Grant.

PROJECT LOCATION

Spokane Transit Authority’s Valley Transit Center (VTC) and Liberty Lake Park and Ride (LLPR) located at located at 10501 E 4th Ave., Spokane Valley, WA and 22501 E Mission Ave, Liberty Lake, WA respectively.

PROJECT SCHEDULE

Work may begin when the Contractor receives a formal “Notice to Proceed”. Contractor shall proceed with promptness and dispatch. The Contractor shall complete the project within 365 calendar days, beginning on the day of commencement as stated on the Notice to Proceed.

This schedule assumes a construction shutdown period from approximately November 1, 2026 – March 30, 2027 where site and/or underground construction may not be feasible due to weather conditions.

Contractor must sequence/phase work between both locations. Valley Transit Center (VTC)’s work must begin first and all underground, steel frame structures, concrete placement, etc. must be complete or substantially complete no later than November 1, 2026. Contractor may continue aboveground work after this period, as weather permits, and upon coordination and approval by an authorized Spokane Transit Authority (STA) representative.

Liberty Lake Park and Ride (LLPR) has a different charger support configuration and additional manufacturer coordination requirements. LLPR’s construction must be coordinated around the OFCI charging equipment delivery and weather conditions. STA anticipates that all OFCI charging equipment will be procured prior to contract award and delivered prior to the start of 2027 construction season.

Contractor acknowledges that work will extend into the following construction season (2027), with potential for site shutdown from approximately November 1, 2026 – March 30, 2027, due to equipment lead times, manufacturer coordination, permitting, and weather conditions.

PROJECT EXCLUSIONS

Charging equipment, pantograph assemblies, pole/mast assemblies, and proprietary anchor/mounting hardware will be Owner-Furnished Contractor-Installed (OFCI) unless otherwise noted on the plans or in the specifications.

PROJECT GENERAL SCOPE OF WORK

The project shall generally consist of:

1. Obtain and pay for all trade-specific permits and fees (to be included in bid price)

2. Obtain and pay for the City of Spokane Valley and City of Liberty Lake Building permits (cost not included in bid price). These fees will be reimbursable to the Contractor by STA with no markup

3. Establish and maintain jobsite safety and traffic control measures

a. Prepare and submit a site-specific safety plan to STA for review and approval

b. Prepare and submit project phasing plans for both sites to STA for review and approval

Project Name: BEB On-Route Charging Infrastructure

003100-2 V. 082725

c. Maintain pedestrian access outside of construction work areas, including adding temporary fencing/ramping/signage/striping to control access, to allow access to bus boarding area(s)

d. Install and maintain temporary signage for pedestrian access, parking, etc.

e. No interruption to STA’s operations is allowed

4. Remove existing striping, paint striping as directed per plans and specifications

5. Protect existing structures, equipment, utilities, etc. to remain

6. Selective demolition as directed per plans and specifications

7. Construct structural steel frame, including foundation, and install as directed per plans and specifications

8. Construct equipment enclosures as directed per plans and specifications

9. Construct equipment pads as directed per plans and specifications

10. Install electrical conduit, wiring, transformers, meters, switches, etc. as directed per plans and specifications

11. Install owner-provided charge cabinets on housekeeping pads as directed per plans and specifications

12. Install owner-provided pantograph chargers, including pole/mast and footing, as directed per plans and specifications

13. Contractor to coordinate receiving, unloading, storage/protection, installation and final assembly of all OFCI equipment unless specifically excluded

14. If the bid option to reconfigure the existing Appleway Blvd. driveway entrance is selected, perform all work per plans and specifications and in accordance with assumed construction schedule

15. Coordinate and schedule with ABB for pole planning, commissioning, and UL stickering once equipment is installed

16. Coordinate and schedule with utility providers for transformer and meter installation as directed per plans and specifications

17. Coordinate with STA for final locations of bus wheel stops prior to installation as directed per plans and specifications

18. Record all “as-built” information and deliver to Owner as required for final closeout

19. All work to be completed as shown and specified in the associated plans and specifications

PROJECT-SPECIFIC NOTES

• OFCI charging equipment is currently 36-40 weeks lead time.

• Special Inspections will be performed by Budinger & Associates, Inc. STA will contract for this work, however, the Contractor is responsible for coordination and scheduling all required inspections.

• STA will maintain operations around the work area. The public will also require access to the facilities around the work areas.

• Work hours are assumed to be 7AM – 5PM. Facility hours of operation are 4AM – 12AM (VTC) and 5AM

– 12:30AM (LLPR). Work may be permissible during non-operation hours with a minimum of 3 days (72 hours) notice and approval from an authorized STA representative.

• All work shall meet or exceed all applicable codes, utility locating, rules and regulations, as set forth by the City of Spokane Valley, City of Liberty Lake, Spokane County and the State of Washington.

Project Name: BEB On-Route Charging Infrastructure

003100-3 V. 082725

• Contractor is responsible for the supply of all equipment, materials and labor, and otherwise do all things necessary for or incidental to completion of the Project.

• Contractor shall coordinate all weather-sensitive work accordingly and include temporary protection measures as necessary.

• Contractor is responsible for making arrangements for staging of materials and equipment, if necessary.

• STA will provide a staging location for Contractor use. Contractor responsible for any necessary fencing, signage, monitoring, etc. to secure materials stored on site.

• Contractor shall be responsible for the removal of all trash and waste materials from this project. All items that are disposed of shall be approved by the Project Manager and/or designee. Damages resulting from Contractor negligence shall be repaired immediately at no cost to STA. The Contractor shall take all precautions necessary to protect private property and the public during the construction period.

• Contractor shall keep all STA facilities, landscaping, and vehicles safe from damage during construction.

Damages resulting from Contractor negligence shall be repaired immediately at no cost to STA. The Contractor must take all precautions necessary to protect private property and the public during the course of construction.

• All work will be subject to inspection and acceptance by STA’s project manager or their designee prior to payment.

• STA reserves the right to increase or decrease the amount of related services listed in the scope of work for a fairly negotiated price.

END OF SECTION 003100

Spokane Transit Authority Section 004200 Contract # 2026-11230 Bid Submittal Checklist Project Name: BEB On-Route Charging Infrastructure

004200-1 V 082725

BID SUBMITTAL CHECKLIST

This checklist must be completed in its entirety, executed and included with the submittal of your signed Bid Proposal Form. By executing below, the Bidder attests all referenced forms are accurate, complete and fully executed. Failure by Bidder to properly complete, execute and include this checklist and all referenced forms with its Bid Proposal Form shall render the Bid non-responsive and shall be grounds for rejection of the Bid.

CHECKLIST

Section 004200 Bid Submittal Checklist

Section 004213 Bid Proposal Form

Section 004215 Bid Response Form

Section 004512 Bidder Responsibility Criteria

Section 004546.B Wage Payment Statutes—Certificate of Compliance

Bid Guarantee See subsection 1.6 of Section 002100 Instructions to Bidders.

Bid submitted in a sealed envelope identifying the following on the front of the envelope:

• Project Name: BEB On-Route Charging Infrastructure

• Contract Number: 2026-11230

• Bidder Name: XXX

• Bidder Address: XXX

If Bid is submitted via mail, the sealed envelope required above shall be in addition to the envelope used for mailing.

STATEMENT OF COMPLIANCE

The undersigned has reviewed and fully understands the required Bid Documents and this Bid Submittal Checklist and certifies that all required documents, as marked herein and required by the specifications, are included in its Bid Proposal.

Authorized Signature: Date:

Name: Title:

Bidder Name:

END OF SECTION 004200

Spokane Transit Authority Section 004213 Contract # 2026-11230 Bid Proposal Form Project Name: BEB On-Route Charging Infrastructure

004213-1 V. 082725

BID PROPOSAL FORM

Bidder Name:

Each Bid item below shall constitute an offer to STA as outlined herein. By executing below and submitted its Bid, Bidder acknowledges no Bidder may withdraw its Bid after the hour and date set for the bid opening except as permitted by Section 002100, Instructions to Bidders.

STA reserves the right to accept or reject any or all Bids within ninety (90) days of the Bid Due Date.

Bidder understands and agrees any additional taxes, permits, bonds, business licenses, contractor registrations, prevailing wages, certifications and fees, and any other ancillary charges, as applicable, have been included in the respective Bid item.

Basis of Award. The “Lowest Bid” shall be lowest sum of the Base Bid and accepted Bid Option, if any.

Award of Contract, if any, shall be to the responsive and responsible Bidder submitting the Lowest Bid.

In compliance with the Contract Documents, the following Bid Proposal is submitted:

BASE BID

(Please print dollar amount in space above) INCLUDE Washington State Sales Tax

TRENCH EXCAVATION SAFETY PROVISIONS $

If the bid amount contains any work which requires trenching excavation exceeding a depth of four (4) feet, all costs for trench safety shall be included in the Base Bid for adequate trench safety systems in compliance with Chapters 39.04 RCW & 49.17 RCW and WAC 296-155-650.

$ amount included in Base Bid

$ above.

BID OPTION - Appleway Blvd. Driveway Reconfiguration (Sheet C-450) .

(Please print dollar amount in space above) DO NOT INCLUDE Washington State Sales Tax

CONTINUED ON NEXT PAGE

Spokane Transit Authority Section 004213 Contract # 2026-11230 Bid Proposal Form Project Name: BEB On-Route Charging Infrastructure

004213-2 V. 082725

UNIT PRICES

Hot Mix Asphalt (HMA) $ / TON

DO NOT INCLUDE

Crushed Aggregate Base $ / CY

DO NOT INCLUDE

Striping Replacement (incl. standard and ADA parking, ADA loading)

$ / LF

DO NOT INCLUDE

Washington State Sales Tax

Sawcut Asphalt Pavement $ / LF

DO NOT INCLUDE

Washington State Sales Tax

Asphalt Demolition / Removal

$ / SF

DO NOT INCLUDE

Washington State Sales Tax

Unit prices shall include full compensation for the cost of labor, materials, equipment, overhead, profit and any additional cost associated with the unit bid.

The undersigned agrees to perform the Work in accordance with the Contract Documents as bid herein.

Signature: Date:

Name:

END OF SECTION 004213

Spokane Transit Authority Section 004215 Contract # 2026-11230 Bid Response Form Project Name: BEB On-Route Charging Infrastructure

Section 004215 - 1 of 11 V 082725

BID RESPONSE FORM

Bidder Name:

The Bid shall constitute an offer to STA as outlined herein and in the Bid Proposal Form. No Bidder may withdraw its Bid following the Bid Due Date, except as allowed under Section 002100 – Instructions to Bidders.

1. EXAMINATION OF DOCUMENTS

A. Having carefully examined all Contract Documents, as well as the site and local conditions affecting the Work, the undersigned proposes to perform all Work in accordance with the Contract Documents for compensation to be computed from prices submitted on the Bid Proposal Form.

B. By executing this form, the Bidder acknowledges receipt of the following Addenda:

Addendum No. Addendum Date:

Addendum No. Addendum Date:

Addendum No. Addendum Date:

Addendum No. Addendum Date:

Addendum No. Addendum Date:

C. STA reserves the right to reject any or all Bids, portions or parts thereof, and to waive minor informalities in the Bid process.

2. TIME FOR COMPLETION

The Bidder agrees to coordinate the completion of all Work within 365 Days of receipt of the Notice to Proceed.

3. FREIGHT

Bid prices shall include all freight costs to each project site and shall be FOB Destination.

4. ANTI-KICKBACK

No officer or employee of STA, having the power or duty to perform an official act or action related to this Bid, shall have or acquire any interest in this submittal, or have solicited, accepted or granted a present or future gift, favor, service or other thing of value from or to any person involved in this Bid.

5. FEDERAL DEBARMENT

The undersigned represents that the Bidder and all offices with any controlling interest herein are not currently, and have not previously, been on any debarred bidders list maintained by the United States Government.

6. UBI CERTIFICATION

I CERTIFY that no final determination of violation of RCW 50.12.070(1)(b) or 82.32.070(1)(b) has been made by the Washington State Departments of Employment Security, Labor and Industries or Revenue respectively dated within two (2) years of the Bid Due Date. I understand further that no Bid may be submitted, considered or contract awarded for a public work to any person or entity that has a determination of violation of the above reference statutes within two (2) years from the date that a violation is finally determined and the Bid Due Date.

Project Name: BEB On-Route Charging Infrastructure

Section 004215 - 2 of 11 V 082725

7. AWARD OF CONTRACT

A. If written notice of acceptance of all or part of this Bid is mailed, sent electronically or delivered to the undersigned within ninety (90) Days after the Bid Due Date, the undersigned will, within fifteen

(15) Days after date of such notice, execute and deliver to Owner the Contract as specified and furnish all requisite documentation including, but not limited to, Certificates of Insurance (send to coi@spokanetransit.com) and Payment and Performance Bonds, as required. Payment & Performance Bonds must be submitted in their original form. Electronic copies will not be accepted.

B. If the undersigned fails to complete the above requirements, the Bidder’s Guarantee shall be forfeited to the Owner.

I CERTIFY, to the best of my knowledge, the information contained in this Bid is accurate and complete and that I have the legal authority to commit this firm to a contractual agreement. I realize the final funding for any service is based upon budget levels and the approval of the Spokane Transit Authority’s Board of Directors.

Bidder Name:

(as registered with the State of Washington)

Authorized Signature: Date:

Printed Name and Title:

mailto:coi@spokanetransit.com

Project Name: BEB On-Route Charging Infrastructure

Section 004215 - 3 of 11 V 082725

1. BIDDER ADMINISTRATIVE INFORMATION

Company Name:

(as registered with the State of Washington)

Physical Address:

Mailing Address:

Telephone: Fax:

Primary Contact:

Phone: Email:

Washington Contractor License No.:

Washington UBI No.:

Washington Industrial Insurance Account No.:

Federal Tax Identification No.:

2. BIDDER INSURANCE COMPANY

Agency Name:

Mailing Address:

Telephone: Fax:

Primary Contact:

Phone: Email:

3. BIDDER SURETY

Surety Name:

Mailing Address:

Telephone: Fax:

Primary Contact:

Phone: Email:

I certify the information above is true and correct:

Project Name: BEB On-Route Charging Infrastructure

Section 004215 - 4 of 11 V 082725

BIDDER QUALIFICATION STATEMENT

The following statements of experience, personnel, equipment, and general qualifications of the Bidder are submitted with the assurance that the Owner can rely on its accuracy and truthfulness. If more space is required for your answers, please attach a continuation sheet(s) to the corresponding bid response page referencing the item number.

1. The Company has been in business continually since (month & year).

2. The Company has experience equivalent to that required under this Invitation for Bid:

a. As a prime contractor for 10 years.

b. As a subcontractor for 15 years.

3. List below work previously completed that is equal to or greater than the scope and complexity of that required under this Invitation to for Bid.

Required Relevant Experience:

The Company shall demonstrate successful completion, as Prime Contractor, of a minimum of three

(3) projects within the last eight (8) years meeting the following criteria:

a. Contract value of not less than $2,000,000 each

b. Multi-phase construction performed over multiple mobilizations and/or seasonal shutdown periods

c. Multi-site or campus infrastructure construction

d. Installation of heavy electrical infrastructure, power distribution systems, utility coordination, EV charging systems, transportation infrastructure, industrial equipment, or similarly complex systems

e. Coordination of multiple trades, long-lead equipment procurement, equipment delivery logistics, and manufacturer/vendor coordination

f. Underground utility installation, duct banks, concrete foundations, and above-grade electrical/mechanical equipment installation

g. Work requiring scheduling through weather limitations, phased turnover requirements, or operational constraints

h. Work on sites that are occupied by and around Owner operations

Specialized Project Understanding

The Company acknowledges that this Project includes:

a. Phased construction at two separate sites

b. Seasonal schedule constraints

c. Long-lead equipment coordination

d. Handling and installation of owner-furnished and/or manufacturer-sensitive charging equipment

Project Name: BEB On-Route Charging Infrastructure

Section 004215 - 5 of 11 V 082725

e. Heavy equipment placement and precision installation requirements

f. Extensive coordination between civil, electrical, utility, and equipment suppliers

Year Project Name Project Location Contract $ Project Owner & contact info

4. List supervisory personnel and/or project manager(s) currently employed by the Bidder that will be responsible for the Work on this project. Attach a brief (1 page maximum) resume for each individual listed.

Personnel Requirements:

a. A dedicated Superintendent assigned full-time during major construction activities with a minimum of seven (7) years of field supervision experience on comparable projects. See also General Conditions Section 007200.1 Part 5.01B for competent persons requirements.

b. A dedicated Project Manager with a minimum of seven (7) years of experience managing comparable electrical/infrastructure projects

Name Title Experience (years)

5. List all projects and/or contracts the Bidder has undertaken in the previous five (5) years which have resulted in:

a. Arbitration or litigation:

Year Project Name Project Location

Project Name: BEB On-Route Charging Infrastructure

Section 004215 - 6 of 11 V 082725

b. Claims and/or violations filed by the Federal Government and/or the State of Washington Department of Labor & Industries, Department of Revenue or Employment Security Department:

Year Project Name Project Location

c. Liens filed by suppliers and/or subcontractors:

Year Project Name Project Location

I certify the information above is true and correct:

Project Name: BEB On-Route Charging Infrastructure

Section 004215 - 7 of 11 V 082725

SUBCONTRACTOR LIST

The Owner requests the Bidder list subcontractors and consultants, if applicable, of each work discipline applicable to the performance of Work. If no subcontractors and/or consultants are listed, it will be considered the Bidder’s affirmation that it does not intend to use any subcontractors and/or consultants in its performance of the Work.

For projects that are estimated to exceed $1 million dollars, in accordance with RCW 39.30.060, Bidders may submit (1) within one (1) hour after the Bid Due Date, the names of subcontractors with whom the Bidder, if awarded a Contract, will subcontract with for the performance of HVAC (heating, ventilation, and air conditioning), plumbing as described in RCW 18.106, and electrical as described in RCW 19.28, or to name itself for the work; and (2) within forty-eight (48) hours after the Bid Due Date, the names of subcontractors with whom…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .