J.05_20011206_EA_Replacement_of_Old_American_Canal.pdf
PDF 22 MB Posted
- Attached to
- Replacement of American Canal-Upper Reach Federal contract opportunity
- Solicitation number
- IBM16B0003
About this file
J.05 20011206_EA_Replacement_of_Old_American_Canal
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E N C O N INTERNATIONAL, INC.
Engineering, Environmental & Technical Services
FINAL
ENVIRONMENTAL ASSESSMENT FOR
"Replacement of the Old American Canal"
Located in El Paso, Texas
Prepared for:
United States Section, International Boundary and Water Commission Contract No. IBM 99-27
Prepared by:
ENCON International, Inc.
7307 Remcon Circle, Suite 101 El Paso, Texas 79912
December 6, 2001 ENCON Project #127-00
El Paso Office: 7307 Remcon Circle, Suite 101 • El Paso, Texas 79912 • Fax 915-581-2049 • Phone 915-833-3740
Administrator Table of Contents
NOTICE OF AVAILABILITY
UNITED STATES SECTION
INTERNATIONAL BOUNDARY AND WATER COMMISSION
Replacement of the Old American Canal, Located in El Paso, Texas; Notice of Final Finding of No Significant Impact
AGENCY: United States Section, International Boundary and Water Commission, United States and Mexico
ACTION: Notice of Availability of a Final Finding of No Significant Impact and a Final Environmental Assessment
SUMMARY: Based on the Draft Environmental Assessment (EA) and the public comments received, the United States Section, International Boundary and Water Commission (USIBWC), finds that the proposed action of replacement of the existing American Canal is not a major federal action that would have a significant adverse effect on the quality of the human environment. An Environmental Impact Statement will not be prepared for the project. The Final Finding of No Significant Impact (FONSI) and Final EA have been forwarded to the United States Environmental Protection Agency and various Federal, State and local agencies and interested parties for information only. No comments are requested. The final FONSI and EA are also available on the USIBWC web Page at http://www.ibwc.gov under “Reports & Studies” and at the reference desk at The University of Texas at El Paso Library and the El Paso Main Library. A limited number of copies of these documents are available upon request from Mr. Fox at USIBWC, 4171 North Mesa Street #C-310, El Paso, TX 79902; Telephone: (915) 832-4736;
The proposed replacement and enlargement of the 1.98-mile-long American Canal involves demolishing the deteriorating concrete open channel segments of the canal and replacing them with reinforced concrete-lined canal segments. The USIBWC is authorized under the Rio Grande American Canal Extension Act of 1990 (“RGACE” or the Act of 1990), Public Law 101-438, dated October 15, 1990, to construct, operate, and maintain an extension of the existing American Canal in El Paso, Texas; which would provide for a more equitable distribution of waters between the United States and Mexico, reduce water losses, and minimize many hazards to public safety.
Water for both irrigation and domestic use in El Paso County is diverted into the American Canal at the American Dam located on the Rio Grande approximately 3 miles upstream from downtown El Paso. The American Dam and American Canal were constructed from 1937 to 1938, within United States territory to divert United States waters away from the Rio Grande, and to allow into the international reach of the Rio Grande only those waters assigned to the Republic of Mexico under the Convention of 1906. This ensured that United States waters diverted at the American Dam would be completely retained within the United States.
In the Act of 1990, the United States Congress also authorized the negotiation of international agreements for the RGACE to convey Mexican waters authorized under the 1906 Convention. In view of the conveyance water losses and the safety issues inherent in Mexico’s existing canal system, the RGACE was designed to accommodate Mexico’s annual 60,000 acre-foot allotment of water at 335 cubic feet per second (cfs), should Mexico request its allotment delivered at this location.
Alternatives Considered:
Five alternatives were considered during the preparation of the environmental assessment, including the Open Channel Alternative (the Proposed Action Alternative) and the No Action Alternative. All four action alternatives include 1) increasing the canal capacity to 1535 cfs, 2) demolition of existing canal structures and open channel concrete lining, 3) reconstructing and enlarging the 400-foot open channel segment immediately downstream from the headgates and the 100-foot open channel segment upstream from the gaging station, 4) not repairing or replacing the two closed conduit segments under West Paisano Drive, 5) installing fences to minimize entrance into the canal, 6) installing safety equipment to reduce canal drownings, 7) removing the Smelter Bridge and the abutments of Harts Mill Bridge, and 8) providing mitigation for the loss of the Smelter Bridge by preparing Historic American Engineering Record (HAER) Level III documentation of the structure (including existing and original construction drawings, captioned photographs, and written data).
The alternatives are summarized below:
Alternative 1 - Closed Conduit Alternative: All existing open channel segments (Upper, Middle, and Lower) between the American Dam and International Dam would be replaced with closed conduits, with the two excepted open reaches in the Upper Open Channel segment. This Alternative would be the most expensive to construct and would lose the historic predominantly open visual character of the canal.
Alternative 2 - Closed Conduit/Open Channel Alternative A: The Middle Open Channel segment would be replaced with a closed conduit. The Upper and Lower Open Channel segments would be reconstructed and enlarged. This alternative would accomplish all the stated objectives, but would lose some of the historic predominantly open visual character of the canal. Choosing this alternative would likely both reduce the number of drownings in the canal, but increase the number of pedestrian traffic fatalities on nearby highways. If final engineering design studies determine the necessity of a closed conduit for the middle canal segment, this alternative would become the preferred alternative.
Alternative 3 - Closed Conduit/Open Channel Alternative B: The Middle and Lower Open Channel segments would be replaced with closed conduits. The Upper Open Channel segment would be reconstructed and enlarged. This alternative would accomplish all the objectives, but at a cost second highest among the action alternatives. It would also likely triple the number of pedestrian traffic deaths on nearby highways.
Alternative 4 - Open Channel Alternative (the Proposed Action Alternative): The Upper, Middle, and Lower Open Channel segments would be reconstructed and enlarged. This Alternative would accomplish all the necessary objectives at the lowest construction cost. It would result in the lowest number of pedestrian traffic fatalities on nearby highways. Though the original canal lining would be replaced, this Alternative would preserve the historic predominantly open visual character of the canal. (It should be noted that if final engineering design studies for the replacement of the old
American Canal determine the necessity of a closed conduit for the middle canal segment, the proposed action alternative would become Alternative 2.)
Alternative 5 - No Action Alternative: The three open channel segments would be left untouched, with no replacements, enlargements, or repairs of any canal segments. While this alternative preserves intact the historic Smelter Bridge, it does not accomplish any of the stated objectives. The annual number of drownings in the Canal would not be reduced. Without reconstruction or major repair of the canal, a serious canal failure is likely within the next five years, especially during the peak irrigation period with the highest canal flow. Such a canal failure would likely close the American Canal for at least one month during costly emergency repairs. If the canal flow was disrupted for just one month due to repairs, the El Paso Water Utilities production of potable water would be reduced by 80 to 120 million gallons per day, and over a thousand El Paso County farmers could lose their crops, likely resulting in up to 500 bankruptcies. The No Action Alternative is not considered to be a viable alternative.
The preliminary engineering design studies for the replacement of the old American Canal indicate that a closed design may become the preferred alternative for the middle canal segment. Limited right-of-way constraints and existing infrastructure restrictions will dictate the proper design and construction methods to minimize the adverse effects to the public and adjacent landowners along the project. The reported project conditions will remain the same, but the aesthetics of the predominantly open canal will change. The USIBWC will consult with the Texas State Historic Preservation Officer should the preliminary canal design study recommend that the subject portion of the open canal be replaced with pre-cast box culvert.
The Draft FONSI and Draft EA were distributed November 21, 2000. The Notice of Draft FONSI for the Draft EA was published in the Federal Register on November 29, 2000. The Legal Notice of the Draft FONSI and Draft EA was published in the El Paso Times on December 2, 2000. The Public Comment period extended from November 21, 2000 through January 2, 2001. Public comments received were compiled into the Final EA, dated October 31, 2001. The Final EA finds that the proposed action does not constitute a major federal action that would cause a significant local, regional, or national adverse impact on the environment, because the Proposed Action Alternative would:
1. Improve structural stability of the American Canal, providing a reliable conveyance structure to transport flows of allocated water from the Rio Grande to El Paso County farms and to existing and planned El Paso Water Utilities water treatment facilities. The Rio Grande will be unchanged from existing conditions under USIBWC jurisdiction;
2. Minimize seepage loss through the cracks in the canal lining;
3. Provide the full design capacity (1535 cfs) influent into the RGACE;
4. Improve safety and reduce the risk of accidental drownings in the American Canal by installing fences and safety equipment;
5. Preserve the historic predominantly open channel character of the Canal; and
6. Preserve historical and photographic documentation of the historic Smelter Bridge per HAER Level III Standard.
Based on the Final Environmental Assessment and the implementation of the proposed historical mitigation, it has been determined that the proposed action will not have a significant adverse effect on the environment, and an Environmental Impact Statement is not warranted.
Mario Lewis Date General Counsel
TABLE OF CONTENTS
1.0 INTRODUCTION
1.1 IBWC Background Information
1.2 Location And Description Of The American Canal
1.3 Clarification Of “A” and “B” Terminology Used To Identify Canal Segments In Maps
1.4 Condition Of American Canal Segments
1.5 Historical And Legislative Background
1.6 Other Recent American Canal Replacement Actions
1.7 Organization Of This Document
2.0 PURPOSE OF AND NEED FOR ACTION
2.1 Rationale For Change
2.2 Previous Related Environmental Assessments
2.3 Explanation Of Need For Decision
2.4 Scoping Of Major Issues And Their Indicators
3.0 ALTERNATIVES INCLUDING THE PROPOSED ACTION
3.1 Alternative 1 – Closed Conduit Alternative
3.2 Alternative 2 – Closed Conduit/Open Channel Alternative A
3.3 Alternative 3 – Closed Conduit/Open Channel Alternative B
3.4 Alternative 4 – Open Channel Alternative (Proposed Action)
3.5 Alternative 5 – No Action Alternative
3.6 Alternatives Considered But Eliminated
3.6.1 Repairing The Existing Concrete Lining
3.6.2 Repairing The Existing Concrete Lining
And Raising The Ramparts Of The Canal
3.6.3 Replacing All Five Canal Segments With A
Continuous Open Channel
3.7 Proposed Mitigation Measures for all Four Action Alternatives
4.0 DESCRIPTION OF KEY ISSUES OR RESOURCES OF THE AFFECTED
ENVIRONMENT
4.1 Air Quality
4.2 Habitats, Wetlands, Endangered Species, Fish And Wildlife
4.3 Real Estate, Utilities, Easements And Rights-Of-Way
4.4 Transportation
4.5 Environmental Justice
4.6 Historical / Cultural
4.7 Water And Soil
4.8 Hazardous Waste Disposal
4.9 Miscellaneous Issues: Costs, Maintenance, Etc
5.0 SUMMARY OF CONSEQUENCES OR EFFECTS TO
ENVIRONMENTAL RESOURCES
5.1 Discussion Of Effects Of Alternative 1
5.2 Discussion Of Effects Of Alternative 2
5.3 Discussion Of Effects Of Alternative 3
5.4 Discussion Of Effects Of Alternative 4
5.5 Discussion Of Effects Of Alternative 5
APPENDICES:
A. LIST OF PREPARERS
B. LIST OF AGENCIES
C. INTRODUCTION - SECTION 1.0 DOCUMENTS (MAPS, ETC.)
D. PURPOSE AND NEEDS - SECTION 2.0 DOCUMENTS
E. ALTERNATIVES - SECTION 3.0 DOCUMENTS (Cross Sections)
F. AIR QUALITY
G. HABITATS, WETLANDS, ENDANGERED SPECIES, FISH AND
WILDLIFE SECTION
H. REAL ESTATE, UTILITIES, EASEMENTS, AND RIGHTS-OF-WAY
I. TRANSPORTATION
J. ENVIRONMENTAL JUSTICE
K. HISTORICAL / CULTURAL [Human Systems Research, Inc. (HSR) and Parsons Engineering Science (Parsons) Reports]
L. WATER AND SOIL
M. HAZARDOUS WASTE DISPOSAL
N. REFERENCES
O. GLOSSARY OF ABBREVIATIONS
1.0 INTRODUCTION
1.1 IBWC Background Information
For centuries the Rio Grande River has been used as a source of irrigation water for agriculture in the El Paso – Juarez area. Even before the Spanish settlement of the area in the later half of the 17th Century, irrigation canals had already been constructed to convey water from the Rio Grande to cultivated fields. By the early 1900s, nearly 9,000 acres of the Rio Grande Valley in the El Paso-Juarez area were being irrigated with water from the river, as detailed in the Historical/Cultural Section of this Assessment, included as Appendix K (“Controlling Water on the Border:
The American Canal System, International Boundary and Water Commission, El Paso, Texas” submitted November 1999 by Human Systems Research, Inc., and a Supplemental Report submitted April 2000 by Parsons Engineering Science). Currently in El Paso County, Rio Grande water is used to irrigate approximately 69,000 acres of farmlands and to produce nearly half of El Paso’s potable water.
In 1889 the governments of the United States and Mexico established the International Boundary Commission (IBC), which a 1944 Treaty later renamed the International Boundary and Water Commission or IBWC.
One of the early actions of the IBC was to discuss delivery of Rio Grande water to Mexico. During the Mexican-American Convention of 1906, the two countries agreed to deliver 60,000 acre-feet of water annually to Mexico at the headgates of the Acequia Madre facility on the southern shore of the Rio Grande in Cd. Juarez, Chihuahua, opposite El Paso, Texas. Presently, the IBWC fulfills the following international boundary and water responsibilities:
• Land boundary demarcation,
• River boundary maintenance,
• International flood control,
• Appropriation of the boundary river waters,
• Operation of international dams and reservoirs, and
Solutions to boundary water quality issues. •
The International Boundary and Water Commission is actually a single international commission, with an American Commissioner heading the US Section of the IBWC (USIBWC), and a Mexican Commissioner heading the Mexican Section of the IBWC (MXIBWC). Each Section is responsible for the IBWC functions or structures within each separate country.
1.2 Location and Description of the American Canal
The area under study in this document for the American Canal reconstruction alternatives comprises a narrow strip of land bordering the 1.98-mile long American Canal. The American Canal extends from the head gates at the American Dam to the upstream end of the Rio Grande
American Canal Extension (RGACE) adjoining the downstream International Dam. Replacement of the Old American Canal is also referred to as Reconstruction of the American Canal. The Canal is located east of the Rio Grande, on the American side of the international boundary between the United States and Mexico. Generally, the Canal parallels West Paisano Drive (US Highway 85) and the Burlington Northern Santa Fe Railroad tracks, which also occupy the same very narrow strip of land.
The Canal is located on the USGS map titled “Smeltertown, TX-NM Map #31106-G5-TF-024”, portions of which are included as Figures 1, 2, and 3 in Appendix C. The study area forms a northwest-southeast trending polygon approximately 225 meters (738 feet) wide by 3,200 meters (10,497 feet) long, situated in UTMG Zone 13 with corner points at approximate locations as follows:
NW Corner E 355350 N 3517400 NE Corner E 355600 N 3517400 SW Corner E356920 N 3514800 SE Corner E357200 N 3514800
The American Canal is a concrete-lined canal consisting of three open channel segments generally paralleling West Paisano Drive, and two closed conduit segments under West Paisano Drive. Although the RGACE continues over 15 miles from the International Dam downstream to the Riverside Dam, the entire American Canal evaluated in this Assessment is only approximately two miles long.
It should be noted that some structures or roadways have been renamed since they were used in old maps of the American Canal area. For instance, the International Dam is labeled “Mexican Dam” in many of the older maps. West Paisano Drive is referred to by its former name, Doniphan Drive. The 1961 USIBWC map is contained in the Historical / Cultural Section of this document. This map was also used as the map source for “Figure 4: Map of the Utilities Located in the American Canal Area”, (Appendix C).
1.3 Clarification Of “A” and “B” Terminology Used To Identify Canal
Segments In Maps Both the original 1938 Bureau of Reclamation map and also the 1961 USIBWC map of the Canal area (developed from the 1938 BOR map), use the “A” and “B” designations to describe the cross-sectional shape of the Open Channel Segment, rather than the location of the segment. As the location, rather than the shape of the canal segment is important for this Environmental Assessment, the “A” and “B” designations have not been used in the maps or for the descriptions of open channel segments
Parsons Reports contained in Appendix K]. For example, in this document the segments previously labeled “Lower Open Channel “A” or “B” will both be called simply, “Lower Open Channel.”
MAP REFERENCES OF AMERICAN CANAL SEGMENTS
Designation in this Document Designation on 1938 & 1961 Maps Upper Open Channel Upper Open Channel A Closed Channel A, or Conduit A Conduit A Middle Open Channel Middle Open Channel B Closed Channel B, or Conduit B Conduit B Lower Open Channel Lower Open Channel B and Lower Open
Channel A
1.4 Condition Of American Canal Segments
The five segments of the American Canal appear to be in various stages of deterioration. The open channel segments appear to have suffered much more deterioration than the closed conduits, perhaps because the open channel segments are constructed of only three-inch thick concrete, and are more exposed to weathering (e.g., sun and wind) than are the closed conduits.
Because of the continuing deterioration of the concrete lining of the open channel segments of the American Canal, the flow capacity is now greatly diminished. The USIBWC is concerned that at some time in the near future the Canal will be unable to safely convey its design capacity of 1200 cfs due to loss of foundation material through cracks in the concrete lining from turbulence caused by normal canal flows. Subjecting the existing lining to the anticipated higher design flow of 1535 cfs desired for the American Canal, would accelerate this foundation deterioration, and hasten the failure of the concrete canal lining.
1.5 Historical and Legislative Background
For a full history and legislative background of the American Canal, refer to Appendix K of this Assessment to review the November 1999 Human Systems Research, Inc. report titled, “Controlling Water on the Border:
The American Canal System, US Section of International Boundary and Water Commission, El Paso, Texas and the April 2000 Supplemental Report by Parsons Engineering Science, Inc.” The 1993 “Final Environmental Assessment, Rio Grande American Canal Extension, El Paso, Texas,” published by the USIBWC can also be used as a relevant background reference.
The construction of the American Dam and American Canal were authorized by the Act of August 29, 1935 (Ch. 305, 49 Stat. 961). Then by the Act of June 4, 1936 (Ch. 500, 49 Stat. 1463), the USIBWC was authorized to “construct, operate, and maintain the Rio Grande Canalization Project from downstream of the Percha Diversion Dam in New Mexico to the American Canal at El Paso, Texas.”
Both the RGACE described in Section 1.6 and the present reconstruction alternatives for the American Canal were authorized by the “Rio Grande American Canal Extension Act of 1990,” (refer to Appendix C of this document).
During the planning of the RGACE, the Mexican Section of the IBWC expressed interest in later receiving its annual 60,000-acre foot water allotment from the end of the RGACE near Riverside Dam rather than at the head gates of the Acequia Madre at the International Dam. For that reason, the USIBWC increased the design capacity of the RGACE by 60,000 acre-feet per year at a maximum delivery rate of 335 cubic feet per second (cfs). The final design capacity of the RGACE was 1535 cfs (1200 cfs + 335 cfs).
1.6 Other Recent American Canal Replacement Actions
As detailed within the Historical/Cultural Section at Appendix K, some of the original Canal structures (i.e., bridges) have been removed, but most were never replaced. During the last five years, however, a portion of the earthen Franklin Canal (which delivered water through the City of El Paso to farms in El Paso’s Lower Valley) was replaced with the concrete RGACE structure. According to personnel from the El Paso County Water Improvement District #1 (EPCWID #1), the RGACE saves many thousands of acre-feet of water per year due to reduced seepage losses.
1.7 Organization Of This Document
The U.S. Council of Environmental Quality (CEQ) which is responsible for interpreting the National Environmental Policy Act (NEPA) requirements, has asked that under normal circumstances, Environmental Assessments be confined to 15 pages of text which should be easily understood by persons without a science, engineering or other technical background. In order to comply with CEQ guidelines, this document incorporates the single most important indicator effect to represent the many effects to a given environmental issue (e.g., Air Quality). Those selected indicator effects for each issue are listed in charts for ease of comparing alternatives.
Only summary information from each section (i.e., Transportation Corridor) of the Assessment is included in this text. More complete assessment documentation for each section is included in its specific appendix, followed by any supporting documentation.
2.0 PURPOSE OF AND NEED FOR ACTION
2.1 Rationale For Change
Capacity
• The American Canal was originally designed to convey 1200 cfs of irrigation water, but its capacity has diminished due to structural deterioration.
• The RGACE was constructed from 1997 – 1998 to convey 1535 cfs of water, but actually receives much less from the deteriorating American Canal.
• The El Paso Water Utilities – Public Service Board (EPWU-PSB) presently produces 80 MGD (124 cfs) of potable water from the Canal, but plans to increase production to 120 MGD (186 cfs) during the next five years.
• Within approximately five years, the EPWU-PSB plans year-round potable water production from the Canal.
• Mexico is considering producing potable water from its Rio Grande allotment and receiving its water allotment via a siphon beneath the Rio Grande at the end of the RGACE near Riverside Dam, rather than at the head gates of the Acequia Madre near the International Dam.
However, Mexico has not finalized this change in point of delivery at this time.
• Much water is currently lost by seepage through existing cracks in the American Canal.
Stability
• The existing American Canal is over 70 years old, and has suffered many cracks over the years.
• The concrete lining of the Canal is only three inches thick. At least four-inch thick reinforced concrete is preferred for open channels.
• Merely patching the Canal would not utilize newer concrete industry improvements for canal design and construction.
Safety
• When the Canal was originally constructed, there was little thought of persons drowning in the Canal. Many safety structures can now be installed to assist in saving the lives of the persons who fall into the Canal.
• When the Canal was constructed in the 1930's for delivery of irrigation water, the designers were probably not concerned about infiltration of potentially contaminated groundwater into the Canal through the under drain system or through future cracks in the canal lining. However, the current use of the Canal as El Paso’s principle potable water source raises this concern of protecting the water quality within the Canal structure.
2.2 Previous Related Environmental Assessments
Prior to construction activities of the 15.4-mile long RGACE, an Environmental Assessment was published by the USIBWC in December, 1993, titled, “Final Environmental Assessment, Rio Grande American Canal Extension.” Following the recommendations of that document, the USIBWC constructed a concrete-lined canal that begins at the downstream end of the approximately 2-mile long American Canal, and ends at Riverside Dam near the Zaragoza International Bridge.
This previous assessment of the RGACE described in detail, the need for added safety features, for reducing water losses, and for conveying water to Mexico near Riverside Dam.
2.3 Explanation Of Need For Decision
Reconstruction of the American Canal is needed to increase canal security, to physically stabilize the structure, and to increase flow capacity to obtain the full benefits of the RGACE. The American Canal segments are shown in Figure Nos. 1-3 located in Appendix C. At several locations, the reinforced concrete panels of the Canal have deteriorated and are in structural distress. Reconstruction of the Canal is necessary to increase its conveyance capacity to equal that of the RGACE; to improve the structural integrity of the existing, deteriorated concrete lining; and to allow for the continued operation of the Canal over the life of the new RGACE.
Further, structural stability may be increased by installation of: 1) a thicker concrete lining; 2) improved panel joints which contain smooth dowels to permit longitudinal thermal expansion and contraction while limiting transverse movement; and 3) flexible joint filler material between the concrete panels, and/or reinforced concrete lining. Installation of high fences, warning signs, safety ladders, and safety cables set at intervals along the Canal will minimize accidental physical access and reduce the chance for human injury. One important physical constraint in the area is the limitation of space between the Rio Grande and the very steep slope rising to Interstate 10, especially in the Middle Open Channel Segment, which has very limited right-of-way for any construction alternative.
2.4 Scoping of Major Issues and Their Indicators
The NEPA process of grouping environmental concerns into areas of investigation is often called the scoping of major issues. In this assessment, the phrases “environmental resources” and “environmental issues” are used interchangeably. The environmental issues have been grouped or scoped into the following areas of investigation:
• Air Quality,
• Habitats, Wetlands, Endangered Species, Fish and Wildlife,
• Real Estate, Utilities, Easements, and Rights-of-Way,
• Transportation Corridor,
• Environmental Justice,
• Historical/Cultural,
• Water and Soil,
• Hazardous Waste, and
• Miscellaneous.
3.0 ALTERNATIVES INCLUDING THE PROPOSED ACTION
Most construction activities will take place during the non-irrigation or dry season from mid October through mid February except those activities not affecting water conveyance in the Canal, i.e., contractor staging and mobilization, fence installation, etc. (Refer to Location Maps in Appendix C.) The construction performance period is anticipated to extend through two non-irrigation periods beginning in the fall of 2003 and concluding in the spring of 2005.
3.1 Alternative 1 – Closed Conduit Alternative
Replace all existing open channel segments (Upper, Middle, and Lower) between the American Dam and International Dam with closed conduits, with the exception of a 400-foot length of open channel immediately below the headgates and a 100-foot length of open channel immediately above the gauging station in the Upper Open Channel segment. The two excepted sections of open channel would be reconstructed and enlarged.
Because the existing segments of the closed conduit under Paisano Drive are in good repair and appear adequate to carry the projected flows, those culverts would be left in place.
3.2 Alternative 2 – Closed Conduit/Open Channel Alternative A Replace the Middle Open Channel segment with a closed conduit.
Reconstruct and enlarge the Upper and Lower Open Channel segments.
No repairs or replacement of the closed conduit segments would be performed.
3.3 Alternative 3 - Closed Conduit/Open Channel Alternative B Replace the Middle and Lower Open Channel segments with a closed conduit. Reconstruct and enlarge the Upper Open Channel segment. No repairs or replacement of the closed conduit segments would be performed.
3.4 Alternative 4 – Open Channel Alternative (the Proposed Action) Replace the Upper, Middle, and Lower Open Channel segments with enlarged open channel segments. No repairs or replacement of the closed conduit segments would be performed.
3.5 Alternative 5 – No Action Alternative
Leave the three open channel segments untouched, with no replacements, enlargements, or repairs of any canal segments.
3.6 Alternatives Considered But Eliminated
3.6.1 Repairing The Existing Concrete Lining
This Alternative would have been similar to the No Action Alternative, but would have patched the original 3-inch thick concrete lining as needed, without increasing the capacity of the Canal. As the existing Canal is in poor condition and inadequately sized, this Alternative was not studied in depth.
3.6.2 Repairing the Existing Concrete Lining and Raising the
Ramparts Above the Concrete Lining of the Canal This Alternative would have patched the original 3-inch thick concrete lining, and increased the capacity of the Canal to approximately 1535 cfs by building ramparts vertically above the existing lip of the Canal. This Alternative would probably cause more stress to the existing concrete lining, creating a greater potential safety concern. Therefore, this Alternative was not studied in depth.
3.6.3 Replacing All Five Canal Segments with a Continuous Open Channel Located Between West Paisano Drive and the Rio Grande In the area of the Middle Open Channel of the Canal where the Rio Grande nearly abuts West Paisano Drive, the Rio Grande flood plain (much of it owned by ASARCO) is too narrow for construction of a new canal. For this same reason, the same Canal segment was not built on the west side of Paisano Drive in 1938; therefore, this Alternative was not further studied.
3.7 Proposed Mitigation Measures for All Four Action Alternatives All four action alternatives require the removal of the 1938 Smelter Bridge at the entrance to ASARCO. The loss of the bridge will be mitigated by preparation of Level III Historic American Engineering Record (HAER) documentation including drawings, photographs, and written data. The proposed mitigation is fully detailed in the Parsons Report contained in Appendix K of this document
4.0 DESCRIPTION OF KEY ISSUES OR RESOURCES OF THE AFFECTED
ENVIRONMENT
The issues summarized below are thoroughly discussed and evaluated in the Appendix corresponding to that particular issue. For each environmental issue, the most important indicator was chosen to evaluate the issue in a matrix of representative effects from the five different reconstruction alternatives.
DESCRIPTION OF ENVIRONMENTAL ISSUES AFFECTED BY REPLACEMENT ALTERNATIVES
Most Important Effects for Each Environmental Resource Resource
(Issue) ↓ 1 2 3 4 5 6 Effect Chosen as Indicator
Air Quality Will construction add excessive CO to air?
Will construction add excessive ozone to air?
Will construction add excessive particulates to air?
High risk of delays during Canal reconstruction due to air quality?
Will construction add excessive particulates to air?
Habitat , Wetlands, Endangered Species, Fish & Wildlife
# Acres of wetlands remaining
# Endangered species displaced during construction
# Endangered species habitats in Canal area
# Permanent fish population in Canal area
# Cliff Swallow nesting sites in Canal area
Population of Cliff Swallows in Canal area
Population of Cliff Swallows in Canal area
Real Estate, Utilities, Easements, Rights-of-way
Length of underground utility mains and lines relocated for construction
% Change in values of commercial properties
Length of overhead electric lines relocated during construction
Length of TxDoT right-of- way used for staging during construction
$ loss to El Paso agribusiness from 30-day canal failure
# local farm bankruptcies resulting from 30-day canal failure & repair
# local farm bankruptcies resulting from 30-day canal failure & repair
Transportation Corridor
# Automobiles per day on W. Paisano during construction
# Automobiles per day on Yandell Drive overpass during canal construction
# Buses per day on Paisano during construction
# W. Paisano northbound lanes closed during construction
# Annual pedestrian traffic deaths on W. Paisano & I-10
# Annual pedestrian traffic injuries on W. Paisano & I-10
# Annual pedestrian deaths on W. Paisano & I-10
Environmental Justice
# local residents to be relocated by construction
# Drownings in American Canal annually
% Increase in illegal crossings through Canal
# Annual crimes reported to police in Canal area
Annual cost for additional Border Patrol Agents
# Local residents permanently employed through Canal reconstruction
# Drownings in American Canal annually
Historical, Cultural
# Original 1938 bridges remaining
# Original 1938 bridge abutments remaining
# Original 1938 closed conduits remaining
Length of closed conduit remaining
Length of open channel remaining
Length of original 1938 open channel lining remaining
Length of open channel remaining
Water and Soil Maximum water delivery capacity (cfs)
Stormwater capture capacity (cfs)
Lost EPWU–PSB daily drinking water production during construction (MGD)
EPCWID #1 - $
costs during Canal reconstruction
Availability of ASARCO oil/water separator during reconstruction
Direct financial loss to farmers during reconstruction
Lost EPWU–PSB daily drinking water production during construction
Hazardous Wastes
Residents at risk from potential airborne heavy metals?
Residents at risk from potential airborne hydrocarbons?
Construction workers at risk from potential airborne heavy metals?
Workers at risk from potential airborne hydrocarbons?
Disposal of heavy metal-soil or water as hazardous waste?
Disposal of hydrocarbon-soil or water as hazardous waste?
Disposal of hydrocarbon-soil or water as hazardous waste?
Miscellaneous Contractor construction costs
Contractor construction costs
Note: Some environmental issues have fewer than six effects, resulting in some blanks in the chart above.
4.1 Air Quality
A conformity determination has been made under 40 CFR, Part 51.858 using analytical methods. The Federal action is in conformity with the specific requirements and the purposes of the Texas State Implementation Plan pursuant to the USIBWC's affirmative obligation under Section 176
(c) of the Clean Air Act in accordance with the requirements of 40 CFR, Ch. 1, Part 51, Subpart W. The Federal action is in compliance with the Clean Air Act.
As detailed in Appendix F, El Paso is located in an EPA designated “non-attainment area.” The non-attainment designation indicates that at least once per year, the area exceeded the Maximum Air Concentration (MAC) for ozone, carbon monoxide, or particulates. However, because of significantly improved air quality tin the area since 1992 the "non-attainment" status may be redesignated as a "maintenance" area by the time of construction. In the El Paso area during the proposed Canal reconstruction period from October through February, carbon monoxide and particulates are more serious concerns than ozone, especially when air inversion layers trap airborne contaminants near the land surface during the hours from sunset through mid-morning. Either airborne particulate or carbon monoxide concentrations could have been selected as the indicator issue, but particulates are more visible to the public.
Therefore, Air Particulate Concentration was chosen as the indicator for this issue.
4.2 Habitats, Wetlands, Endangered Species, Fish And Wildlife Before onsite reconstruction activities begin, the preparation of a Construction Stormwater Pollution Prevention Plan (S3P) will be required by the TNRCC and the City of El Paso. The S3P will include a section of "Best Management Practices" such as hay bales, silt fences, or other similar erosion prevention techniques as also requested by Texas Parks and Wildlife Department. The Canal area contains no wetlands, populations of endangered species, habitats, or permanent fish populations. Because of the extent of concrete lining, the Canal area does not have the number of animal or plant populations of other nearby areas like those on the earthen banks of the nearby Rio Grande. As planned, all the reconstruction alternatives would avoid disturbance of migratory bird nesting sites during the early March through late July breeding season, and therefore, comply with the provisions of the Migratory Bird Treaty of 1918. Because Cliff Swallows nest in the Canal area and feed mainly on water insects that live in the same area, the population of Cliff Swallows was chosen as the indicator issue.
4.3 Real Estate, Utilities, Easements And Rights-Of-Way
During any of the construction alternatives, utility lines and mains do not generally appear to require relocation. Nor does it appear that rights-of-way or easements need to be purchased or permanently changed. Local real estate values in the Canal area do not appear to be affected by the choice of any alternative. However, the farms that are irrigated from the American Canal are more greatly affected by the Canal than properties in the Canal area. The estimated Number of Farm Bankruptcies due to a canal failure was chosen as the indicator of this issue.
4.4 Transportation
None of the alternatives will permanently affect any transportation resources, except pedestrian traffic deaths on West Paisano Drive (US
85) and Interstate 10, which are expected to rise proportionately to the number of persons crossing the border illegally via the Canal area. The only temporary construction effect to transportation in the Canal area is the necessary temporary closure of one lane of northbound traffic on West Paisano Drive. Therefore, the Number of Pedestrian Traffic Fatalities was chosen as the most important indicator of effects to transportation.
4.5 Environmental Justice
None of the alternatives would temporarily or permanently displace local poor persons or change the number of available jobs in the Canal area.
The alternatives would affect the number of persons crossing into the US (potentially smuggling drugs and weapons) while passing through the river and Canal. These illegal crossings would require different numbers of US Border Patrol Agents and El Paso Police Officers to protect the area. But even though the cost to the Border Patrol could be very considerable, the worth of a human life saved from drowning is even higher. Especially since safety is one of the principal reasons for construction listed in the “Purpose and Needs” statement of this Document. Therefore, the number of Canal Drownings was chosen as the indicator to Environmental Justice.
4.6 Historical / Cultural
It is difficult to quantify the effects to cultural and/or historical resources in this Assessment. None of the five alternatives will disrupt the flow of water in the Rio Grande in the area of the Zaragoza Bridge where the Ysleta del Sur Pueblo (Tribe) uses the River and its waters for certain tribal religious ceremonies at locations held sacred by the Tribe. None of the Tribe's sacred locations would be accessed as part of any of the five reconstruction alternatives. Therefore, none of the five alternatives should disrupt the religious practices of the Tribe.
All historically or culturally important sites dating before 1937 are considered to have been either destroyed by the annual flooding of the shifting alluvium in the Rio Grande floodplain prior to construction of Elephant Butte Dam, or highly disturbed by construction activities of the American Canal in the 1930s. If archaeological sites or historical structures that may qualify for designations as State Archaeological
Landmarks, or that may be eligible for listing on the National Register of Historic Places in accordance with 36 CFR Part 800 are discovered after work begins, the contractor will immediately cease operations in that particular area and notify the client, the Texas State Historic Preservation Officer (SHPO), the Ysleta del Sur Pueblo Tribe (Tribe), other appropriate agencies, and the USIBWC. The contractor will take reasonable steps to protect and preserve the discoveries until they have been inspected by the client, SHPO, Tribe, other appropriate agencies, and the USIBWC, and will assist obtaining any necessary approvals or permits to enable the work to continue. The contractor will not resume work in the area of the discovery until authorized to do so by the client, SHPO, Tribe, other appropriate agencies, and the USIBWC. If human remains are discovered, the Tribe will be notified immediately and consulted with in a timely and meaningful manner to provide information and address rights under the Native American Graves Protection and Repatriation Act. (See appendix B.4 regarding the Tribe’s enthnographic spiritual connection to the Rio Grande).
As the American Canal is one of only two remaining American systems constructed to implement international water treaties, the remaining historical structures (i.e., the Smelter Bridge at the entrance to ASARCO) may have more importance to historians than to the public. The loss of the historic Smelter Bridge, which is required by the four Action Alternatives, will be mitigated by preparation of Level III Historic American Engineering Record (HAER) documentation including drawings, photographs, and written data. The proposed mitigation is fully detailed in the Parsons Report contained in Appendix K of this document. To best portray the original open visual character of the Canal, the length of open channel segments was chosen as the indicator effect for the Historical / Cultural Resource.
4.7 Water And Soil
As the primary source of local groundwater (the Hueco Bolson) is being rapidly depleted, the EPWU-PSB will soon rely on the American Canal as its primary sustainable source of drinking water. Currently, water from the Canal is used by El Paso County farmers to irrigate crops with annual production of over $300 million which essentially pays the salaries of nearly 50,000 local people in agriculture-related jobs. During peak irrigation and water production seasons, an emergency canal shutdown with related-repairs caused by possible contaminated groundwater entering the undersized and deteriorating canal would drastically disrupt the lives of all El Pasoans. Therefore, the lost daily EPWU–PSB Drinking Water Production was chosen as the indicator to this resource.
4.8 Hazardous Waste Disposal
Historic manufacturing facilities and railroad tracks were used in the area long before chemical or petroleum releases were regulated by the government. In the 1960s, the former community of Smeltertown adjoining the Upper Open Channel segment was condemned and closed because of high concentrations of lead in both the blood of Smeltertown residents and in the local soil. More important than the lead concentrations in soil are the presence of other heavy metals in groundwater and soil. Arsenic, cadmium and selenium have been detected in the soil of the Canal area, likely originating from nearby past industrial usage. It is unlikely that area residents or employees will be affected by heavy metals during reconstruction, however, construction workers will need personal protection equipment (i.e., respirators, etc.) if airborne heavy metal exposures occur.
There have been several known hydrocarbon releases in the vicinity of the American Canal. Although there have been discussions of possible spills or releases before the existence of TNRCC, no other hazardous waste releases are known with certainty. Based on a review of available data of soil and groundwater analyses, there is a possibility of encountering diesel or gasoline plumes in all three open channel sections of the Canal.
Therefore, Disposal of Hydrocarbon-Contaminated Groundwater and Soil was chosen as the indicator for the issue of Hazardous Waste Disposal.
4.9 Miscellaneous Issues: Costs, Maintenance, Etc.
Based on similar recent construction, the USIBWC estimates contractor construction cost to be approximately $1 million per mile ($190 per foot) for open channel construction, and approximately $3 million per mile ($570 per foot) for closed conduits. No direct cost estimates were available either for extensive repairs to the Canal or for annual maintenance for each alternative. Therefore, Contractor Construction Cost was chosen as the indicator. However, the construction cost estimates do not include any costs for expected slope shoring in the Middle Section to maintain the required slope for the BNSF Railroad. Cost estimates for shoring will be determined later during the design phase.
5.0 SUMMARY OF CONSEQUENCES OR EFFECTS TO ENVIRONMENTAL
RESOURCES
None of the alternatives would encounter or disturb wetlands, endangered species, or threatened wildlife habitats. None of the alternatives would cause any permanent detrimental effect to local wildlife populations. Generally, the beneficial lowering of drowning deaths in the Canal is roughly offset by increases in pedestrian traffic fatalities on nearby highways. The first four alternatives appear to safeguard a steady flow of El Paso County’s only renewable source of domestic and irrigation water; Alternative 5 (the No Action Alternative) does not.
The CEQ regulations require including direct and indirect effects and their significance, and cumulative effects. A comparison of consequences of each alternative is matrixed in the following table. Summary descriptions of expected consequences caused by each alternative follow the matrix.
MATRIX CHART SHOWING EXPECTED CONSEQUENCES OF EACH ALTERNATIVE
TO INDICATOR EFFECTS OF ENVIRONMENTAL RESOURCES
Expected Consequences to Resources of Each Alternative Action Alternative →
Resource (Issue) ↓ ALT 1 ALT 2 ALT 3 ALT 4 ALT 5
Air Quality Canal reconstruction will not add excessive PM-10 particulates to air.
Canal reconstruction will not add excessive PM-10 particulates to air.
Canal reconstruction will not add excessive PM-10 particulates to air.
Canal reconstruction will not add excessive PM-10 particulates to air.
Canal reconstruction will not add excessive PM-10 particulates to air.
Habitat, Wetlands, Endangered Species, Fish and Wildlife
Population of 25 Cliff Swallows in Canal area
Population of 25 Cliff Swallows in Canal area
Population of 25 Cliff Swallows in Canal area
Population of 25 Cliff Swallows in Canal area
Population of 25 Cliff Swallows in Canal area
Real Estate, Utilities, Easements, Rights–of-Way
0 Local Farm Bankruptcies resulting from canal repair shutdown
0 Local Farm Bankruptcies resulting from canal repair shutdown
0 Local Farm Bankruptcies resulting from canal repair shutdown
0 Local Farm Bankruptcies resulting from canal repair shutdown
500 Local Farm Bankruptcies resulting from canal repair shutdown
Transportation Corridor 4.5 Annual Pedestrian Highway Traffic Deaths
3 Annual Pedestrian Highway Traffic Deaths
4.5 Annual Pedestrian
Highway Traffic Deaths
1.5 Annual Pedestrian
Highway Traffic Deaths
1.5 Annual Pedestrian
Highway Traffic Deaths
Environmental Justice 0 Drownings in American Canal annually
3* Drownings in American Canal annually
1* Drowning in American Canal annually
5* Drownings in American Canal annually
5 Drownings in American Canal annually
Historical, Cultural 675 feet of Open Channel
4959 feet of Open Channel
2239 feet of Open Channel
7979 feet of Open Channel
7804 feet of Open Channel
Water and Soil 0 MGD lost daily EPWU
– PSB Drinking Water Production
0 MGD lost daily EPWU
– PSB Drinking Water Production
0 MGD lost daily EPWU
– PSB Drinking Water Production
0 MGD lost daily EPWU
– PSB Drinking Water Production
80 – 120 MGD lost daily EPWU – PSB Drinking Water Production
Hazardous Wastes Disposal of hydrocarbon-contaminated soil or water as hazardous waste is likely
Disposal of hydrocarbon-contaminated soil or water as hazardous waste is likely
Disposal of hydrocarbon-contaminated soil or water as hazardous waste is likely
Disposal of hydrocarbon-contaminated soil or water as hazardous waste is likely
Disposal of hydrocarbon-contaminated soil or water as hazardous waste is likely (at future time)
Miscellaneous
Approximately $4.6 million Contractor Construction Cost
Approximately $2.8 million Contractor Construction Cost
Approximately $3.7 million Contractor Construction Cost
Approximately $1.6 million Contractor Construction Cost
Approximately $0 million Contractor Construction Cost (Does not include future Contractor Emergency Repair Costs)
*Note: Construction of additional fences and new safety equipment would probably significantly reduce the number of drownings from these estimates.
5.1 Discussion Of Effects Of Alternative 1
(The Closed Conduit…