PRICE SCHEDULE

LSO MAMOEKETSI PRIMARY SCHOOL

MASERU, LESOTHO

03-May-2023

PRICE SCHEDULE

IMPROVE WATER SUPPLY FOR TSAGHKABER & ARVASHOGH COMMUNITIES

TSAGHKABER & ARVASHOGH, ARMENIA

29-NOV-22

Offerors shall provide pricing for all base and option items.

The following items include providing all labor, materials, equipment, and services necessary to complete the design and construction of the work identified in the attached Plans, Specifications, Statement of Work (SOW), Request for Proposal and Base Contract. It also includes preparation of all documents, submittals, and schedules; inspections; and compliance with all technical, quality control, administrative, and safety requirements. All work shall be performed in accordance with these documents. Refer to Specification Section 01 22 00 Price and Payment Procedures for additional description of the work associated with each of the items.

Period of Performance: Refer to clause COMMENCEMENT PROSECUTION AND EXECUTION OF WORK (52.211-10) in the Request for Proposal for the period of performance for all base and option items.

Liquidated Damages: Refer to clause LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) in the for Proposal for the liquidated damages for all base and option items.

Option Items: The Government reserves the right to award the options up to 90 calendar days from contact award. See Section 01 22 00 for additional information regarding the award of options.

Item No.
Title
Quantity
Unit
Unit Price
Amount

BASE ITEMS

0001
New School Laboratory
1
Job
$
$
0002
Existing Classroom Buildings’ Repair
1
Job
$
$
0003
Existing Latrine Repair
1
Job
$
$
0004
New Latrine Building
1
Job
$
$
0005
New Water Connection
1
Job
$
$
Total of Base Items 0001-0005
$

OPTION ITEMS

0006
Option 1, Existing Kitchen Chimney Repair and New Skylight
1
Job
$
$
0007
Option 2, Existing Classroom Floor Repair
1
Job
$
$
0008
Option 3, New Security Fence
1
Job
$
$
Total of Option Items 0006-0008
$
Total of all Base and Option Items
$

EXTENSIONS: All extensions of the unit prices shown will be subject to verification by the Government. In case of variation between the unit price and the extension, the unit price will be considered to be the offer.

-- END OF PROPOSAL SCHEDULE --