SOS_CYPRESS_(WLB_225B)_DD_dated_17Nov2015.xls
XLS spreadsheet 39 KB Posted
- Attached to
- CGC CYPRESS DRY DOCK FY16 Federal contract opportunity
- Solicitation number
- HSCG85-16-Q-P45009
About this file
Revised Stated of Service (SOS) dated 17 November 2015
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_A0003.pdf | ||
| CYPRESS_(WLB_225B)_DD_FQ2_MJW_REV-2.pdf | ||
| A0002_Amendment_to_a_Sol.pdf | ||
| Spec_CYPRESS_(WLB_225B)_DD_FQ2_MJW_REV-1.pdf | ||
| Amendment_A0001_CGC_CYPRESS_DD.pdf | ||
| Solicitation_CYPRESS_FY16_DD.pdf | ||
| Spec_CYPRESS_(WLB_225B)_DD_FQ2_MJW_REV-0.pdf | ||
| Spec_CYPRESS_(WLB_225B)_DD_FQ2_MJW_REV-0.pdf | ||
| Pre_Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: | |||||
| USCGC CYPRESS (WLB-225B) DRYDOCK AVAILABILITY FY2016 | |||||
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Hull Plating (U/W Body), Inspect | JOB | 1 | $0.00 | |
| D-002 | Hull Plating (U/W Body), Ultrasonic Testing | JOB | 1 | $0.00 | |
| D-003 | Appendages (U/W), Leak Test | JOB | 1 | $0.00 | |
| D-004 | Propulsion Shaft Fairwaters and Rope Guards, Inspect | JOB | 1 | $0.00 | |
| O-005 | Appendages (U/W) - Internal, Preserve | JOB | 1 | $0.00 | |
| D-006 | Tanks (Potable Water), Clean and Inspect | JOB | 1 | $0.00 | |
| D-007 | Propulsion Shafting; Remove, Inspect, and Reinstall | JOB | 1 | $0.00 | |
| D-008 | Controllable Pitch Propeller, System Maintenance | JOB | 1 | $0.00 | |
| D-009 | Controllable Pitch Propeller Hub, General Maintenance, Perform | JOB | 1 | $0.00 | |
| D-010 | Main Diesel Engine (MDE) Exhaust Piping, Commercial Clean | JOB | 1 | $0.00 | |
| D-011 | Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean | JOB | 1 | $0.00 | |
| D-012 | Fathometer Transducer, General Maintenance | JOB | 1 | $0.00 | |
| D-013 | Fwd Scan Sonar Transducer, General Maintenance, Perform | JOB | 1 | $0.00 | |
| D-014 | Sea Strainers - Duplex (All Sizes), Overhaul | JOB | 1 | $0.00 | |
| D-015 | Sea Strainers - Simplex (All Sizes), Clean and Inspect | JOB | 1 | $0.00 | |
| D-016 | Sea Bay, Clean and Inspect | JOB | 1 | $0.00 | |
| D-017 | Sea Bay, Preserve 100% | JOB | 1 | $0.00 | |
| D-018 | Thruster Units (Bow And Stern), Overhaul | JOB | 1 | $0.00 | |
| D-019 | Crossdeck Winches, Inspect and Service | JOB | 1 | $0.00 | |
| D-020 | Hydraulic Inhaul Winch, Inspect and Service | JOB | 1 | $0.00 | |
| D-021 | Mechanical Chain Stoppers, Inspect and Service | JOB | 1 | $0.00 | |
| D-022 | Anchor Windlass, Inspect and Service | JOB | 1 | $0.00 | |
| D-023 | Anchor Chain(s) and Ground Tackle, Inspect and Repair | JOB | 1 | $0.00 | |
| D-024 | Single Point Davit - RHIB, Inspect and Service | JOB | 1 | $0.00 | |
| D-025 | Buoy Crane, Inspect and Service | JOB | 1 | $0.00 | |
| D-026 | Buoy Cargo Hold Deck, Preserve 100% | JOB | 1 | $0.00 | |
| D-027 | U/W Body, Preserve (100%) | JOB | 1 | $0.00 | |
| O-028 | Stern Tube Interior Surfaces, Preserve 100% | JOB | 1 | $0.00 | |
| D-029 | Impressed Current Cathodic Protection System, Inspect and Maintain | JOB | 1 | $0.00 | |
| D-030 | Impressed Current Cathodic Protection System Anodes, Renew | JOB | 1 | $0.00 | |
| D-031 | Impressed Current Cathodic Protection System Reference Cells, Renew | JOB | 1 | $0.00 | |
| O-032 | Impressed Current Cathodic Protection System Dielectric Shield, Repair | JOB | 1 | $0.00 | |
| O-033 | Impressed Current Cathodic Protection System Dielectric Shield (Capastic Fairing), Renew | JOB | 1 | $0.00 | |
| D-034 | Drydock | JOB | 1 | $0.00 | |
| D-035 | Temporary Services, Provide - Cutter | JOB | 1 | $0.00 | |
| D-036 | SSDG ISOLATION MOUNT RENEWAL | JOB | 1 | $0.00 | |
| D-037 | Hydraulic Steering Cooler, Install | JOB | 1 | $0.00 | |
| D-038 | Main Diesel Engine, Mount Upgrade | JOB | 1 | $0.00 | |
| D-039 | Reverse Osmosis Desalination Plant, Renew | JOB | 1 | $0.00 | |
| D-040 | Hull Plating Freeboard, Preserve “100%” | JOB | 1 | $0.00 | |
| D-041 | Deck Covering, Electrical Matting, Renew | JOB | 1 | $0.00 | |
| D-042 | Deck Covering (Interior Wet/Dry), Renew | JOB | 1 | $0.00 | |
| D-043 | Small Boat Fueling Station Piping, Renew | JOB | 1 | $0.00 | |
| D-044 | Buoy Deck Fueling Station Piping, Renew | JOB | 1 | $0.00 | |
| D-045 | Fuel Oil Return Pipe, Renew | JOB | 1 | $0.00 | |
| D-046 | Handrail Stanchions and Safety Rail, Renew | JOB | 1 | $0.00 | |
| D-047 | Decks – Exterior (Buoy or Construction Deck), Preserve 100% | JOB | 1 | $0.00 | |
| D-048 | Portlight Renew | JOB | 1 | $0.00 | |
| D-049 | Bilges (Machinery Space), Stern Thruster, Preserve | JOB | 1 | $0.00 | |
| D-050 | Waste Oil Discharge Pipes, Renew | JOB | 1 | $0.00 | |
| D-051 | Waste Oil Vent Pipe, Renew | JOB | 1 | $0.00 | |
| D-052 | Firemain Isolation Valves, Renew | JOB | 1 | $0.00 | |
| D-053 | Potable Water System Valves, Overhaul or Renew | JOB | 1 | $0.00 | |
| D-054 | Deck Covering, Carpeting, Renew | JOB | 1 | $0.00 | |
| D-055 | Refrigeration Lines, Restore to Original Configuration | JOB | 1 | $0.00 | |
| O-00A | Composite Labor Rate | Hour | 200 | $0.00 | |
| D-00B | GFP Report | NSP | EA | $0.00 | |
| D-00C | Travel and Perdiem | $500.00 | JOB | $0.00 | |
| O-00Z | Laydays | Day | 5 | $0.00 | |
| Total Price of Definite Items | $0.00 | ||||
| Total Price of Option Items | $0.00 | ||||
| Total Price of Definite and Optional Items | $0.00 |
&C(6/4/2015) Draft-2 - Page &P of &N
CostEstimateBreakdowns
| Composite Labor Rate | 55 | ||||||||||||||||||||||||
| Assumed G&A Factor | 15% | ||||||||||||||||||||||||
| Assumed Profit Factor | 10% | Direct Labor | Direct Material/Subs Cost | ||||||||||||||||||||||
| ITEM | DESCRIPTION | UNIT PRICE | Sub-Contracted (put a "1" in the blank) | Total Labor Hours | Total Material & Subs (cost + G&A + profit) | Eng Tech | Machinest/Pipe Fitter | Electrician | Shipfitter | Welder | Firewatch | Insulator/Lagger | Painter | Gen Labor/Helper/Rigger | Supt/QA/NDT | Mat/Sub Cost 1 | Mat/Sub Cost 2 | Mat/Sub Cost 3 | Mat/Sub Cost 4 | Lab Rate | Area | WorkItemID | WIFileID | LoadData | |
| 1 | 62 | Baltimore, MD | |||||||||||||||||||||||
| 1 | 52 | Biloxi, MS | |||||||||||||||||||||||
| 1 | 56 | Boston, MA | |||||||||||||||||||||||
| 1 | 50 | Charleston, SC | |||||||||||||||||||||||
| 1 | 60 | Corpus Christi, TX | |||||||||||||||||||||||
| 1 | 51 | Hampton Roads | |||||||||||||||||||||||
| 1 | 64 | Honolulu, HI | |||||||||||||||||||||||
| 1 | 55 | Houston, TX | |||||||||||||||||||||||
| 1 | 56 | Los Angeles, CA | |||||||||||||||||||||||
| 1 | 55 | Median Rate | |||||||||||||||||||||||
| 1 | 49 | Miami | |||||||||||||||||||||||
| 1 | 50 | Narragansett Bay, RI | |||||||||||||||||||||||
| 1 | 55 | New London, CN | |||||||||||||||||||||||
| 1 | 45 | New Orleans | |||||||||||||||||||||||
| 1 | 62 | NYNY | |||||||||||||||||||||||
| 1 | 49 | Panama City, FL | |||||||||||||||||||||||
| 1 | 60 | Philadelphia, PA | |||||||||||||||||||||||
| 1 | 51 | Portland, ME | |||||||||||||||||||||||
| 1 | 55 | San Diego, CA | |||||||||||||||||||||||
| 1 | 67 | San Francisco, CA | |||||||||||||||||||||||
| 1 | 55 | Santa Barbara, CA | |||||||||||||||||||||||
| 1 | 55 | SE North Carolina | |||||||||||||||||||||||
| 1 | 65 | Seattle, WA | |||||||||||||||||||||||
| 1 | 48 | Tampa-St. Petersburg | |||||||||||||||||||||||
| 1 | 60 | Wilmington, DE | |||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| Decks – Exterior (Buoy or Construction Deck), Preserve 100% | 1 | ||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| 1 | |||||||||||||||||||||||||
| Firemain Isolation Valves, Renew | 1 | ||||||||||||||||||||||||
| Potable Water System Valves, Overhaul or Renew | 1 | ||||||||||||||||||||||||
| Deck Covering, Carpeting, Renew | 1 | ||||||||||||||||||||||||
| Refrigeration Lines, Restore to Original Configuration | 1 | ||||||||||||||||||||||||
| Machinery Exhaust Stack Insulation, Renew | 1 | ||||||||||||||||||||||||
| Rudder and Rudder Stock, Remove and Inspect | 1 | ||||||||||||||||||||||||
| Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renewal | 1 | ||||||||||||||||||||||||
| 200 | 0 |
&C(6/4/2015) Draft-2 - Page &P of &N
CostEstimateTemplate
File details come from the government source that posted it. Updated .