HOLLYHOCK___HSCG85-15-Q-P45B21_-_Amendment_00002.docx
DOCX document 29 KB Posted
- Attached to
- DOCKSIDE REPAIRS FOR USCGC HOLLYHOCK
- Solicitation number
- HSCG85-15-Q-P45B21
About this file
AMENDMENT 0002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| HOLLYHOCK___HSCG85-15-Q-P45B21_-_Amendment_00003.docx | DOCX document | |
| HOLLYHOCK_(WLB_225B)_DS_FQ3_MJW_15Rev1.docx | DOCX document | |
| AMEND0001.doc | DOC document | |
| HOLLYHOCKDSSECTB.xls | XLS spreadsheet | |
| HOLLYHOCKDSSPECS.doc | DOC document | |
| USCGCHOLLYHOCK420DSFY15.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IDIQ MASTER PAGE 62 OF __
HSCG85-15-Q-P45B21
Amendment A00002 Dated 26 June 2015
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1. CONTRACT ID CODE |
| PAGE |
OF PAGES
2. AMENDMENT/MODIFICATION
A00002
3. EFFECTIVE DATE
26JUN2015
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO.
6. ISSUED BY CODE: 52000
USCG SURFACE FORCES LOGISTICS CENTER
Attn: Crystal Elliott 300 E Main Street, Suite 600 Norfolk, VA 23510
7. ADMINISTERED BY CODE:
8. NAME AND ADDRESS OF CONTRACTOR (No, street, county, state and Zip Code)
CODE: FACILITY CODE:
9a. AMENDMENT OF SOLICITATION NO.
HSCG85-15-Q-P45B21
9b. DATED (SEE ITEM 11) 10a. MODIFICATION OF CONTRACT NO.
10b. DATED (SEE ITEM 13)
12. ACCOUNTING AND APPROPRIATION DATA (IF REQUIRED)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO DESCRIBED IN ITEM 14.
(x)
A. This change order is issued pursuant to: (Specify authority) The changes set forth in Item 14 are made in the contract order no in item 10A.
B. The above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, appropriation data, etc.) set forth in Item 14 pursuant to the authority of FAR 43.103(b).
C. This supplemental agreement is entered into in pursuant to authority of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _1____ copies to the issuing office.
14. Description of amendment/modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
USCGC HOLLYHOCK FY15 Dockside
1. The following solicitation is hereby amended to extend the quote due date and time to 1 July 2015 at 9:00 am (EST).
2. Work Item D-019 Buoy Crane, Inspect and Service Task #11 is hereby corrected. See attached table 1 Recurring Tasks (REV. 1)
3. All other terms and conditions remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type/Print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
BY____________________________________
(Signature of Contracting Officer)
16C. DATE SIGNED
Revision 1 Table 1 - RECURRING TASKS
ADDITIONAL REQUIREMENTS
| # |
| TASK TYPE |
| QTY |
| COMPONENT OR ASSEMBLY |
| APPENDIX AND PARA. FROM SFLC STD SPEC 5000 |
| OTHER |
| 1 |
| Operate and Inspect |
| 1 |
| Buoy Crane Assembly |
| 3.2.1 (Operate and Inspect) |
Appendix A (General Inspection Requirements) In addition to components listed in Appendix A of SFLC Std Spec 5000, additional components for inspection include, but are not limited to:
Wire rope and fittings; block fittings, hooks, links, shackles and associated pins, swivels, hydraulic controls and fittings, winches and slewing gear brake, bearings, motors, and gear boxes.
Submit a CIR.
| 2 |
| Disassemble, Inspect, and Preserve |
| 1 |
| Boom Assembly |
Boom, and Turret Assembly
3.2.3 (Disassemble and Inspect)
3.2.4 (Preserve) Unship the boom to inspect, pins and bushings.
Submit CIR.
Renew slide pads, pucks, and shim sets. Install GFP turret to pedestal fasteners.
Renew all other fasteners.
| 3 |
| Service and Inspect |
| 2 |
| Boom Hinge Bushings and Pins Assemblies |
| 3.2.2 (Service and Inspect) |
| Service a CFR. |
Install GFP.
| 4 |
| Disassemble and Inspect |
| 2 |
| Luffing Cylinders |
| 3.2.3 (Disassemble and Inspect) |
| Inspect each luffing cylinder rod. |
Submit a CIR.
Renew wiper and cylinder seals, pins and bushings.
| 5 |
| Service and Inspect |
| 1 each |
| Main Winch Assembly and Aux Winch Assembly |
| D2.1 (Fastener assemblies) |
D2.4 (Open gearing and gear reducers) C2.8.1 Flushing Remove winches for inspection of hydraulic motors, brakes, drums, gears and controls.
Submit a CFR Renew foundation bolts. Flush and renew winch oil.
| 6 |
| Disassemble and Inspect |
| 1 |
| Main Winch Brake Assembly |
| D2.3 (Brake and clutch) |
| Submit a CIR. |
| 7 |
| Disassemble and Inspect |
| 1 |
| Aux Winch Brake, Assembly |
| D2.3 (Brake and clutch) |
| Submit a CIR. |
| 8 |
| Service and Inspect |
| 5 |
| Slew Drive Assemblies |
| D2.1 (Fastener assemblies) |
D2.4 (Open gearing and gear reducers) C2.8.1 Flushing Remove units for inspection of hydraulic motors, brakes, pinion gears, planetary gear reducers and controls.
Submit a CFR.
Renew foundation bolts.
Flush and renew each unit oil.
| 9 |
| Disassemble and Inspect |
| 5 |
| Slew Drive Brake Assemblies |
| D2.3 (Brakes and clutches) |
| See CG TP 3557, Section 573-C. |
Submit a CIR.
| 10 |
| Service and Inspect |
| 1 |
| Swivel Head Bearing |
| 3.2.2 (Service and Inspect) |
| Mark the location of the bearing. Clean and inspect. Upon reinstallation locate the bearing 180 degree from old position. Re-lubricate. |
Submit a CFR.
| 11 |
| Service and Inspect |
Disassemble and Inspect
| 1 |
| Extension Cylinder |
| 3.2.2 (Service and Inspect) |
(Disassemble and Inspect Inspect cylinder rod. Renew wiper and cylinder seals, pins and bushings.
Submit CFR.
| 12 |
| Service and Inspect |
| 1 |
| Extension Boom |
| 3.2.2 (Service and Inspect) |
| Submit CFR. |
| 13 |
| Service and Inspect |
| 2 |
| Main Hoist Sheave Assemblies |
| 3.2.2 (Service and Inspect) |
| Submit CFR. |
Renew bearing and seals.
| 14 |
| Service and Inspect |
| 1 |
| Aux Hoist Sheave Assemblies |
| 3.2.2 (Service and Inspect) |
| Submit CFR. |
Renew bearing and seals.
| 15 |
| Service and Inspect |
| 1 |
| Hydraulic Control Block Assembly |
| 3.2.2 (Service and Inspect) |
| Submit a CFR. |
| 16 |
| Service and Inspect |
| 1 |
| Crane Block |
| 3.2.2 (Service and Inspect) |
| Submit a CFR. |
| 17 |
| Service and Inspect |
| 1 |
| Overhaul Ball |
| 3.2.2 (Service and Inspect) |
| Submita CFR. |
| 18 |
| Renew |
| 1 |
| Main Hoist Wire Rope Assembly |
| D2.2(Wire Rope assemblies) |
| GFP |
Submit a CFR.
| 19 |
| Renew |
| 1 |
| Aux Hoist Wire Rope Assembly |
| D2.2(Wire Rope assemblies) |
| GFP |
Submit a CFR.
| 20 |
| Service and Inspect |
| 1 |
| Hydraulic Swivel |
| 3.2.2 (Service and Inspect) |
| Submit a CFR. |
Renew all seals, O-rings, and gaskets.
| 21 |
| Service and Inspect |
| 1 |
| Control Cal |
| 3.2.2 (Service and Inspect) |
| Renew gaskets |
Submit CFR
| 22 |
| Renew |
| All |
| Crane System |
GFP.
| 23 |
| Partially-Preserve |
| All |
| Crane Exterior Surfaces |
| 3.2.4 (Preservation) |
| Surfaces to be preserved are all previously-painted surfaces, including but not limited to: boom, cylinder bodies, turret, hydraulic motor case, pedestal/foundation, winch body, control stand, foundation bolts and flange, etc. |
Disconnect components, as necessary, to facilitate partial-preservation.
| 24 |
| Set and tag in place |
| All |
| System Pressure Control Valves (E.G. Relief Valves, etc.) |
| C2.4 (Valves and manifolds) |
| Perform in conjunction with “Groom, Lubricate, and Op Test and Weight Test Buoy Crane Assembly”. |
| 25 |
| Renew |
| All |
| Pressure, Return and Hydraulic Oil Reservoir Filter Elements and Breather |
See CG TP-3557, SWBS 573C.
| 26 |
| The contractor shall renew hydraulic fluid to the original full level |
| Renew Hydraulic fluid to the original full level |
| Hydraulic Fluid |
| C2.1 (Fluids) |
| See CG TP-3557, SWBS 573C. |
| 27 |
| Groom and Lubricate |
| 1 |
| Buoy Crane Assembly |
| 3.2.6 (Groom and lubricate) |
| 28 |
| Lubricate |
| 1 |
| Swing Bearing Assembly |
Rotate the crane during lubrication.
| 29 |
| Final test |
| 1 |
| Buoy Crane Assembly |
| B2.4 (Boom and Crane) |
| Perform operational and weight testing. Refer to Paragraph 6-6 of TP-3557. |
See Table 2 for test weights.
Submit a CFR.
| 30 |
| Fabricate and Install |
| 1 |
| Label plate |
| B2.9 (Label plates) |
| 31 |
| Weatherize |
| All |
| Hose fittings |
| C2.2.1.2.2 (Weatherization). |