Questions and Answers 3.doc

DOC document 28 KB Posted

Attached to
USCGC SENECA DOCKSIDE REPAIRS
Solicitation number
HSCG80-11-Q-P45610
Issued by

About this file

Questions and Answers

View the file

Other files

File Type Posted
Amendment 3.pdf PDF
SENECA —
Amendment 2.pdf PDF
SENECA —
Questions and Answers 2.doc DOC document
SENECA —
SENECA —
SENECA —
Amendment.pdf PDF
SENECA RFQ.doc DOC document
CGC SENECA DS 2011.doc DOC document
SENECA —
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question: Work item #19 The requirement is to renew the air overflow vent terminations. It appears the tanks must be cleaned and gas free in order to accomplish this. Will the ship be able to transfer fuel out of these tanks and what would the remaining amount be left in the tanks.

Answer: Work Item #19: Ship's force will we be able to transfer fuel out of the tanks; low suction on the tanks is usually 150-200 gals.