USCGC Vigorous (WMEC-627) Specification for Dockside Repairs dated Feb 5/Rev 1

View the file

Other files

File Type Posted
Spec 627 DS Rev 1.pdf PDF
Amendment 01 Vigorous.pdf PDF
Solicitation Vigorous DS Repairs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC VIGOROUS (WMEC-627)

210 FOOT B CLASS MEDIUM ENDURANCE CUTTER

SPECIFICATION FOR DOCKSIDE REPAIRS

Developed By:

LTJG Dan Kahn

Commander (v) Maintenance and Logistics Command, Atlantic 300 E. Main Street, Suite (600) Norfolk, VA 23510-9102

(Feb 05/ Rev-1)

USCGC VIGOROUS (WMEC-627) DOCKSIDE AVAILABILITY 2009

TABLE OF CONTENTS

Work Item Title Page

List of Sketches iii

Revisions Record iv

List of Applicable References v

List of Government-furnished Property x

List of Critical Inspection Items xi

Specification Feedback xii

Principal Characteristics xiii

General Requirements 1

1 Renew CMWDS and Firemain Valves 8

2 Install New Deck Covering System(s) 12

3 Renew Engine Room Sheathing and Piping Insulation 15

4 Overcoat Designated Bilge Surfaces - Pier Side 18

5 Remove Unused Skin Valves 22

6 Renew Laundry Room Bulkhead 25

7 Renew Door 28

8 Renew Partitions 31

9 Clean and Hydrostatically Test Hydro-Pneumatic Tanks 33

10 Repair Hot Water Tank Foundation 37

11 Clean and Inspect Heat Exchangers 39

12 Modify Welin Lambie TW PIV 5.0B Davit Arrangement 43

13 Modify RHIB Cradle and Strengthen the Davit Supporting Structure 48

Page i (Rev-1)

14 Renew and Weight Test Shipboard Davit Crane (Allied Marine Crane Model D5700CT) 50

15 Renew Single Point Davit Control Stand 53

16 Clean Galley, Engine Room, and Laundry Ventilation Systems 55

17 Clean Shipboard Ventilation Systems 58

18 Renew Ventilation Ducting 61

19 Overhaul Stack Dampener 64

Page ii (Rev-1)

List of Sketches

Work Item Sketch Number Page

5 MLCA Sketch 627 WMEC 07400-001 24

10 MLCA Sketch 627 WMEC 55110-001 38

12 MLCA Sketch 627 WMEC 58310-001 46

12 MLCA Sketch 627 WMEC 58310-002 47

18 MLCA Sketch 627 WMEC 51210_001 62

Page iii (Rev-1)

Revisions Record

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package.

Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK ITEM# CHANGES MADE

05Feb09 1 GFP Changed Single Point Davit and Hook from

WI #12 to WI #14

NOTE: All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Page iv (Rev-1)

List of Applicable References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at time of specification writing and during contract execution. Electronic copies of the latest Editions of MLCA Standard Specifications are available on the Internet and may be accessed at the following Internet Uniform Resource Locator (URL) address:

http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp.

Guidance for obtaining copies of all other documents referenced herein is provided in the solicitation.

Order of precedence. In the event of conflicts between text of this specification and the applicable references specified herein, order of precedence shall be in accordance with MLCA Standard Specification 0000_STD, paragraph 3.2 (Order of precedence), unless otherwise specified by the Contracting Officer (KO). The Contractor shall immediately notify the KO in writing of any perceived conflicts contained herein. Nothing in these documents, however, supersedes applicable laws and regulations, unless a specific exemption has been obtained.

FEDERAL AND MILITARY SPECIFICATIONS AND STANDARDS

Commercial Item Description (CID) A-A-59588, Jul 2005, Rubber Silicone

OTHER GOVERNMENT DOCUMENTS, DRAWINGS, AND PUBLICATIONS

DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0000_STD, 2006 Edition, General Requirements

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 5000_STD, 2004 Edition, Auxiliary Machinery Systems

Page v (Rev-1) http://www.uscg.mil/mlclant/vdiv/standard_specifications.asp

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 5100_STD, 2004 Edition, Clean Shipboard Ventilation Systems

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 6341_STD, 2004 Edition, Renew Deck Covering Systems

DRAWINGS

Coast Guard Drawing 627 WMEC 122-001, Rev D, Transverse Watertight Bulkheads FWD & AFT Midships

Coast Guard Drawing 627 WMEC 131-001, Rev D, Second & Main Deck Plating & Supports

Coast Guard Drawing 627 WMEC 136-003, Rev -, Structural Mods Incidental to SPD/RHIB Replacement

Coast Guard Drawing 627 WMEC 167-001, Rev K, Schedule of Steel Doors, Hatches, Scuttles & Manholes

Coast Guard Drawing 627 WMEC 512-010, Rev G, Arrangement Vent & Air Conditioning Second Deck

Coast Guard Drawing 627 WMEC 512-011, Rev H, Arrangement Vent & Air Conditioning Main Deck

Coast Guard Drawing 627 WMEC 512-012, Rev D, Arrangement Vent & Air Conditioning 01 Deck

Coast Guard Drawing 627 WMEC 512-013, Rev E, Arrangement Vent & Air Conditioning 02 Deck and Above

Coast Guard Drawing 627 WMEC 512-029, Rev-, Arrangement Ventilation & Air Conditioning Second Deck

Coast Guard Drawing 627 WMEC 512-001, Rev D, Ventilation Equipment List

Coast Guard Drawing 627 WMEC 512-002, Rev D, Vent Weather Covers and Louvers

Coast Guard Drawing 627 WMEC 512-005, Rev C, Ventilation Diagram Third Deck

Coast Guard Drawing 627 WMEC 512-006, Rev D, Ventilation Diagram Second Deck

Page vi (Rev-1)

Coast Guard Drawing 627 WMEC 512-007, Rev D, Ventilation Diagram Main Deck

Coast Guard Drawing 627 WMEC 512-008, Rev D, Ventilation 01 Deck & Above

Coast Guard Drawing 627 WMEC 513-001, Rev C, Ventilation Arrangement Machinery Spaces

Coast Guard Drawing 627 WMEC 521-001, Rev B, Diagram Firemain, Sprinkling & Washdown

Coast Guard Drawing 627 WMEC 521-002, Rev F, Arr. Of Firemain, Sprinkling & Washdown System Main Deck & Above

Coast Guard Drawing 627 WMEC 521-003, Rev F, Arr. Of Firemain, Sprinkling & Washdown System 2nd Dk & Below

Coast Guard Drawing 627 WMEC 530-002, Rev -, 30” O.D. x 72” Vert Hot Water Storage Heater for US GOV’T

Coast Guard Drawing 627 WMEC 533-001, Rev E, 19 AUG 2002, Diagram Hot& Cold Potable Water System

Coast Guard Drawing 627 WMEC 533-007, Rev A, Reverse Osmosis Declinator Arrangement & Details

Coast Guard Drawing 627 WMEC 536-53, Rev -, Heat Exchangers

Coast Guard Drawing 627 WMEC 583-040, Rev F, OTHB Davit-Davit Arrangement

Coast Guard Drawing 627 WMEC 583-041, Rev D, OTHB Davit-Davit Installation

Coast Guard Drawing 627 WMEC 601-004, Rev C, General Arrangemnet Main and 01 Decks

Coast Guard Drawing 627 WMEC 634-001, Rev D, Deck Coverings

Coast Guard Drawing 627 WMEC 635-003, Rev B, Insulation & Sheathing in Machinery Spaces

Coast Guard Drawing 627 WMEC 644-003, Rev D, Sanitary Partitions

Coast Guard Fleet Drawing FL-3801-67, Rev B, Ventilation, Installation and Details, Sheets 1 through 10 of 50 (General Notes - Ductwork) and Sheet 39 of 50 (Handholes for W.T. & N.W.T. Ducts)

Page vii (Rev-1)

Fleet Drawing FL-2605-038, Rev A, Welin Lambie 5.0B RHI Cradle End Pads

NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation Details

NAVSEA Drawing 804-5959212, 19 Feb 1985, Surface Ship Machinery, Insulation, Installation Details

PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual

Coast Guard Technical Publication (TP) 3485A, Section 583-A, Oct 2008, Boat Davit, Single Point - Models D5000CT And D5700CT

Coast Guard Technical Publication (TP) 3903, July 2002, SWBS 233, Section A, Diesel Engine Overhaul/Maintenance Procedure Matrix – ALCO Model 251

INDUSTRY STANDARDS

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method

ASTM International (ASTM) F683, 2003, Standard Practice for Selection and Application of Thermal Insulation for Piping and Machinery

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002, Butterfly Valves

Page viii (Rev-1)

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning

Page ix (Rev-1)

List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM MTI ITEM

DESCRIPTION NSN/PN QTY

ESTIMATED

COST

($/UNIT)

7 N

66” x 22” Quick-Acting Watertight Door W/8-dogs, LH

2040-00-912-5778 2 ea. 2,675.51

14 Y RHI Single Point Davit

Model: Allied

D5700CT 1 80,000.00

14 N Hook NSN: 4030 01 467 1005 1 400.00

15 N Control Stand PN: 58-672 1 ea. 20,600.00 *Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel, Electronic Systems Support Unit (ESU) or local Electronic Support Detachment (ESD).

Page x (Rev-1)

List of Critical Inspection Items

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see Std Spec 0000_STD, paragraph 3.6.2 (Inspection report particulars)):

Work Item Title

2 Install New Deck Covering System(s)

4 Overcoat Designated Bilge Surfaces - Pier Side

6 Renew Laundry Room Bulkhead

9 Clean and Hydrostatically Test Hydro-Pneumatic Tanks

19 Overhaul Stack Dampener

Page xi (Rev-1)

Specification Feedback

The intent of this section is to inform all users that a spec feedback mechanism is in place, and is located on the MLCA Naval Engineering Division’s website. Spec feedback is a very important part of our overall continuous improvement process, and is crucial to specification development. It will allow spec writers to capture all specification-related lessons learned, and avoid mistakes or ambiguities in follow-on availabilities.

All feedback will be reviewed, evaluated, and responded to in a timely manner.

If you have access to the CGWeb (Intranet), please use the following link, which will connect you to the MLCA(v) Naval Engineering website, for submitting your feedbacks:

http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/defaul t.cfm

If you do not have access to the CGWeb (Intranet), you may still submit your feedbacks, using the following web link:

http://www.uscg.mil/mlclant/vdiv/specfeedback.asp

Page xii (Rev-1) http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default.cfm http://webapps.mlca.uscg.mil/vdiv/specifications/feedback/default.cfm http://www.uscg.mil/mlclant/vdiv/specfeedback.asp

PC_210 A&B WMEC

(07 Jan 2004)

Principal Characteristics

210 (A & B Class) Medium Endurance Cutter

Length Overall 210' 6"

Depth (main deck at side to baseline) 19' 6"

Maximum Beam 34' 0"

Height of Highest Projection (above DWL) 88'0"

Frame Spacing 1' 0"

Full Load Draft 10' 6"

Full Load Displacement 1000 long tons

Shore Tie Voltage Requirements 400A/440V

PROPELLERS / SHAFT

Number of Propellers 2

Number of Blades per Propeller 4

Diameter of Propeller 7' 6"

Pitch controllable

Revolutions per Minute (RPM) 300

Shaft Diameter 8.25"

Page xiii (Rev-1)

00000_PWB_FLT (08 Apr 2008)

General Requirements

1. SCOPE

1.1 Scope. This item describes the general requirements to be followed by the Contractor while conducting this availability.

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in Std Spec 0000_STD and in this item, as applicable, during the performance of this availability.

NOTICE!

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and also to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Contractor-provided fire extinguishers. The Contractor

shall provide portable fire extinguishers.

3.3 Welding and brazing requirements. The Contractor shall

perform all welding and allied processes, and nondestructive inspection (NDI), in accordance with Std Spec 0740_STD.

3.4 Term substitution - COTR for COR. The Contractor shall be aware that the term "COR" (Contracting Officer's Representative) has been discontinued in favor of "COTR" (Contracting Officer's

Page 1 (Rev-1)

Technical Representative); consequently, whenever "COR" is encountered in this specification package, including referenced standard specifications and other referenced documents, it shall refer to "COTR", explicitly.

4. NOTES

4.1 Access to COMDTINST M10360.3. The COMDTINST M10360.3 may

be accessed at the following URL address:

http://www.uscg.mil/directives/cim.asp

4.2 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in Std Spec 0000_STD to be completed and submitted during preservation of "critical-coated surfaces", are provided at the end of this item.

Page 2 (Rev-1) http://www.uscg.mil/directives/cim.asp

QA-1: QUALITY ASSURANCE INSPECTION FORM - PRESERVATION CHECKLIST

CHECKPOINT 1 - COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with COMDTINST M10360.3, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating manufacturer(s).

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-based coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating manufacturer(s).

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down

(maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-12, SP-11, SP-10?).

Verify surface anchor profile (1.5-3.5 mils for abrasive-blasted steel surfaces; 1.0 mil (minimum) for power-tool cleaned surfaces; 1.0-1.5 mils for abrasive-blasted aluminum surfaces); and 1.5 -2.5 for surfaces to be coated w/single coat of inorganic zinc).

Measure soluble salt conductivity (5 measurements per 1000 sqft) - maximum threshold: 70 microsiemens/cm for non-submerged surfaces and 30 microsiemens/cm for submerged surfaces.

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the Coating Manufacturer(s).

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 - STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer's instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 - TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer's instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 - FINAL INSPECTION

Verify final system dry film thickness.

Verify system cure for service resumption - U/W Body surfaces: 5-8 hours @ 77 degrees F; Potable water tanks: 7 days @

77 degrees F.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure (minimum 7 days @ 77 degrees F.), to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

CHECKPOINT 10 - RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Signature of Inspector:______________________________________________________Date:____________

Page 3 (Rev-1)

QA-2: QUALITY ASSURANCE INSPECTION FORM

ENVIRONMENTAL READINGS

(Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat)

DATE TIME

ENTER ACTIVITY

(Surface preparation, primer coat, barrier coat, top coat, etc?)

LOCATION DEW

POINT

SURFACE

TEMP.

% REL.

HUMIDITY

SIGNATURE

OF

INSPECTOR

.Signature of Inspector:__________________________________________________Date:____________

Page 4 (Rev-1)

QA-3: QUALITY ASSURANCE INSPECTION FORM

SURFACE PROFILE LOG

Vessel Name And Hull Number:__________________________________________________

Work Item Title:_______________________________________________________________

Location Of Work (Including Frame Numbers):_____________________________________

Area (Square Feet):_____________

Surface Preparation Method:_____________________________________________________

Abrasive Manufacturer And Size:_________________________________________________

Degreasing Method Used:________________________________________________________

Number Of Hours Surfaces (Steel Only) Left Unpainted:______________________________

Sweep blasting performed to remove flash rusting (steel)? Yes/No:_____________________

Place Surface Profile Replica Tapes In The Spaces Provided Below, To Serve As Permanent QA record.

Maintain separate log for each area/location. When an Area Is Divided Into Separate Sections, Maintain A Separate Log for Each Section.

AVERAGE MILS

(IAW ASTM D4417,

METHOD C)

Place Surface Profile Replica Tape Here

Reading:__________ mils

• Place Surface Profile Replica Tape Here

Date and Time:__________________________________________________

Location of Surface Profile Measurements:___________________________________________________________

Signature of Inspector:____________________________________________________________________________

Page 5 (Rev-1)

QA-4: QUALITY ASSURANCE INSPECTION FORM

SURFACE SOLUBLE SALT CONDUCTIVITY LOG

Vessel Name and Hull Number:__________________________________________________

Work Item Title:_______________________________________________________________

Location of Work (including frame numbers):_______________________________________

Area (square feet):____________

DATE TEST LOCATIONS CONDUCTIVITY

(microsiemens/cm)

Date and Time:_________________________________________

Signature of Inspector:___________________________________

Page 6 (Rev-1)

QA-5: QUALITY ASSURANCE DATA FORM

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC PA-2

(Use one sheet for each sequence)

Vessel Name and Hull Number:__________________________________________________

Work Item Title:______________________________________________________________

Coating Manufacturer:_________________________________________________________

Product Name:________________________________________________________________

Batch Number:________________________________________________________________

Induction Time:_______________________________________________________________

Coating System Sequence (Indicate whether: primer, touch-up primer, barrier coat, 3rd coat?):__________________

DFT

MEASUREMENT

NUMBER

LOCATION OF READINGS MEASURED DFT

Application Method (Airless, Conventional Spray, Rolled):____________________

Average DFT: __________________________________________________________

Date and Time: _________________________________________________________

Signature of Inspector: ___________________________________

Page 7 (Rev-1)

52100_DLA_FLT (18 Mar 2008) S52110_DNK_627(22 Sep 2008)

WORK ITEM 1: Renew CMWDS and Firemain Valves

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the below-designated CMWDS and Firemain valves.

TYPE SIZE

(INCHES) MATERIAL DESCRIPTION

FRAME

LOCATION/

VALVE NO

CONNECTION

RATED

PRESSURE

CLASS (#)

Gate 2.5 Brass CMWDS Isolation 1-141-1 4 Bolt Double Flanged

Gate 2 Brass CMWDS Isolation 1-151-1 4 Bolt Double Flanged

Gate 2.5 Brass CMWDS Isolation 1-64-1 4 Bolt Double Flanged

Gate 2.5 Brass CMWDS Isolation 1-31-1 4 Bolt Double Flanged

Gate 2 Brass CMWDS Isolation 02-80-2 Double Female Brazed

Gate 2.5 Brass Fire Plug 01-114-2 4 Bolt Single Flanged

Gate 2.5 Brass Fire Plug 01-114-1 4 Bolt Single Flanged

Gate 1.5 Brass Fire Plug 1-21-1 Threaded Double Female

Gate 1.5 Brass Fire Plug 2-76-0 4 Bolt Single Flanged

Page 8 (Rev-1)

1.2 Government-furnished property.

None

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, General Requirements

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

American Society of Mechanical Engineers (ASME) B16.34, 2004, Valves-Flanged, Threaded, and Welding End

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2003, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2002, Butterfly Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 1999 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2003 Edition, Bronze Gate, Globe, Angle and Check Valves

Coast Guard Drawing 627 WMEC 521-001, Rev B, Diagram Firemain, Sprinkling & Washdown

Coast Guard Drawing 627 WMEC 521-002, Rev F, Arr. Of Firemain, Sprinkling & Washdown System Main Deck & Above

Coast Guard Drawing 627 WMEC 521-003, Rev F, Arr. Of Firemain, Sprinkling & Washdown System 2nd Dk & Below

3. REQUIREMENTS

3.1 General.

Page 9 (Rev-1)

3.1.1 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to the following:

• Piping.

• Insulation.

3.2 Removal. The Contractor shall remove all designated valves in Section 1.1. Immediately after valve removal, install the appropriate replacement valve. Use Coast Guard Drawing 627 WMEC 521-001, 521-002, and 521-003 as guidance.

3.3 Renewal. The Contractor shall renew all designated with

commercial-standard type valves, conforming to the applicable standard listed in Table I (Valve Standards).

TABLE I. VALVE STANDARDS

VALVE TYPE INDUSTRY STANDARD

Steel Valves MSS SP-61 Butterfly Valve MSS SP-67 Ball Valves, Flanged or Butt-Welded Ends MSS SP-72

Bronze Gate, Globe, Angle and Check Valves

MSS SP-80

All others ASME B16.34

NOTICE!

The Contractor shall replace any mil-std valves listed for renewal with equivalent commercial standard valves.

3.4 Valve reinstallation/installation. Upon completion of all authorized work, the Contractor shall accomplish the following:

• Remove and dispose of all blank flanges and associated gaskets.

• Reinstall/install all new valves with new flange gaskets with neoprene rubber.

• Renew all missing or damaged valve label plates.

• Renew all bolting hardware.

Page 10 (Rev-1)

• Touch-up preserve all new and disturbed surfaces to match existing adjacent areas, in accordance with COMDTINST M10360.3. Abide by all touch-up requirements outlined in paragraph 3.11.9 (Touch-ups and minor coating repairs)) of Std Spec 0000_STD.

3.5 Valve labeling. The Contractor shall install valve label

plates on all new valves in accordance with ASTM F992.

3.6 Leak test. After all authorized repairs of mechanical

(i.e. threaded, bolted, etc.) joints, the Contractor shall perform an operational test of the firemain system using the system fluid at normal operating pressure. Be aware that no visible leakage or deformation is acceptable. Repair all leaks and discrepancies found. Submit a CFR.

4. NOTES

This section is not applicable to this work item.

Page 11 (Rev-1)

S63410_DLA_SWIT (18 Mar 2008) S63410_DNK_627(22 Sep 2008)

WORK ITEM 2: Install New Deck Covering System(s)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to install new deck covering system in compartment 2- 99-0-L.

1.2 Government-furnished property.

None

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, General Requirements

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 6341_STD, Renew Deck Covering Systems

ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method

Coast Guard Drawing 627 WMEC 634-001, Rev D, Deck Coverings

3. REQUIREMENTS

3.1 General.

3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s):

• 3.4 (Inspection)

3.1.2 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to the following:

• Deck drain(s).

Page 12 (Rev-1)

• Sink Foundations.

• Toilets.

• Showers.

3.2 Protective measures. The Contractor shall protect non-

affected vessel’s equipment, components, and spaces during surface preparation and coating application procedures, as specified in paragraph 3.11.4(Protective measures) in Std Spec

0000_STD.

3.3 Deck covering removal. The Contractor shall remove

existing terrazzo decking down to deck plating in compartment 2- 99-0-L.

3.4 Inspection. Upon the removal of the existing terrazzo

decking, the Contractor shall perform a total of 100 thickness measurements of the deck and bulkhead plating, in locations designated by the Coast Guard Inspector. Submit a CIR. If a Change Request has been authorized and released by the KO, the Contractor shall make repairs of the steel deck and bulkhead plating.

3.4.1 Ensure that the ultrasonic apparatus, procedure

requirements, and report shall be in accordance with ASTM E797, and that the report results shall additionally include the following information for each test point:

• Location.

• Original metal thickness.

• Measured metal thickness.

• Percent deterioration (calculation is based on the original metal thickness).

3.4.2 Perform ultrasonic equipment standardization in

accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).

3.5 Deck covering installation particulars. The Contractor

shall install the deck covering system(s), including associated cove base, in the space(s) specified in Table I below, in accordance with Std Spec 6341_STD and as shown on Coast Guard Drawing 627 WMEC 634-001.

3.5.1 Underlayment requirements. Install the new deck covering system(s) over new underlayment.

Page 13 (Rev-1)

TABLE I. DECKING SYSTEM PARTICULARS

COMPARTMENT

NAME/NUMBER

AREA

(*SQFT)

DECK MTL

(A/S**) DECKING SYSTEM TYPE

APPENDIX

(STD SPEC

6341_STD)

Head 2-99-0-L 64 S

Cosmetic Polymeric Epoxy Resin, Type III (One-Step Epoxy System)

S

*Approximated.

**Note: A = Aluminum.

S = Steel.

3.5.2 Deck covering color. Submit a deck covering color chart to Coast Guard Inspector, for the purpose of color selection.

4. NOTES

Page 14 (Rev-1)

S63700_DNK_627(02 Oct 2008)

WORK ITEM 3: Renew Engine Room Sheathing and Piping Insulation

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew sheathing and insulation throughout the engine room.

1.2 Government-furnished property.

None

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0000_STD, 2006 Edition, General Requirements

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Color Manual

Coast Guard Drawing 627 WMEC 635-003, Rev B, Insulation & Sheathing in Machinery Spaces

NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation Details

ASTM International (ASTM) F683, 2003, Standard Practice for Selection and Application of Thermal Insulation for Piping and Machinery

3. REQUIREMENTS

3.1 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to the following:

• Piping

• Wiring

Page 15 (Rev-1)

• Machinery

3.2 Sheathing Renewal. Remove and renew approximately 650

square feet of existing perforated aluminum sheathing for the engine room (4-108-0-E) designated by the Coast Guard Inspector.

Install perforated aluminum sheathing, clips, chromelock tape and rivets as shown on Coast Guard Drawing 627 WMEC 635-003.

Dispose of the removed materials in accordance with local, state, and federal regulations.

3.3 Insulation renewal. The Contractor shall renew the Boiler, SSDG, and MDE system piping insulation as designated in the table below.

APPROXIMATE PIPING INSULATION NEEDED

SYSTEM DIAMETER THICKNESS LINEAR FEET NEEDED

#1 BOILER STEAM 6” 1” 17’ 3”

#1 BOILER STEAM 10” 1” 3’ 1”

#1 SSDG JACKET

WATER 10” 1” 13’ 7”

#1 MDE LUBE OIL 8” 1” 5’ 2”

#1 MDE LUBE OIL 10” 1” 7’

#1 MDE JACKET

WATER 11” 1” 11’ 1”

#1 MDE JACKET

WATER 1’ 4” 1” 1’ 8”

#1 MDE JACKET

WATER 1’ 6” 1” 1’ 7”

#2 MDE LUBE OIL 1’ 1” 1” 11’ 6”

#2 MDE LUBE OIL 1’ 4” 1” 6’ 5”

#2 MDE JACKET

WATER 1’ 5” 1” 4’ 2”

#2 MDE JACKET

WATER 1’ 11” 1” 2’ 11”

#2 SSDG JACKET

WATER 10” 1” 13’ 7”

3.3.1 Removal. Remove all existing insulation material over

the designated piping, including associated pipe hangers, valves, fittings, and flanges. Dispose of all removed materials in accordance with all applicable Federal, state, and local regulations.

3.3.2 Surface preparation. Clean all exposed pipe and pipe

component surfaces, with a soft bristle brush and a mild detergent solution, to remove all visible surface contaminants.

3.3.3 Inspection. The Contractor shall inspect all exposed

piping for corrosion, holes, and all other damage. Submit CFR.

If a Change Request has been authorized and released by the KO, the Contractor shall make all necessary repairs.

Page 16 (Rev-1)

3.3.4 New insulation installation. Install new insulation

material over the exposed pipe surfaces, including associated pipe hangers, valves, fittings, and flanges, in accordance with details in NAVSEA Drawing 804-5959212; select appropriate insulation materials and thicknesses for the application and temperature ranges specified in ASTM F683, Tables S1.1 and 5.

Paint the newly installed insulation system, in accordance with COMDTINST M10360.3, using the system specified for “Insulation Surfaces, Fiberglass Sheet/Closed Cell PVC Foam” in Appendix B (Cutter and Boat Interior Paint Systems).

3.4 Touch-up preservation. The Contractor shall prepare and

coat all new insulation surfaces in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in paragraph 3.11.9 (Touch-ups and minor coating repairs)) of Std Spec 0000_STD.

Page 17 (Rev-1)

S63142_DLA_SWIT (25 Jun 2008) S63142_DNK_627(22 Sep 2008)

WORK ITEM 4: Overcoat Designated Bilge Surfaces - Pier Side

1. SCOPE

1.1 Intent. This statement of work describes the requirements for the Contractor to overcoat the paint locker bilge surfaces while the vessel is waterborne.

1.2 Government-furnished property.

None

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2006 Edition, General Requirements

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2004, Solvent Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s):

• 3.3 (Ultrasonic thickness measurements).

Page 18 (Rev-1)

3.1.1 Protective measures. The Contractor shall protect non-

affected vessel’s equipment, components, and spaces during surface preparation and coating application procedures, as specified in paragraph 3.11.4(Protective measures) in Std Spec

0000_STD.

3.1.2 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to the following:

• Bilge level sensors.

• Piping.

• Deck plates.

3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the bilge level sensors to demonstrate existing operational condition. Submit a CFR.

3.3 Ultrasonic thickness measurement. The Contractor shall

perform a total of 100 thickness measurements of the paint locker hull plating, in locations designated by the Coast Guard Inspector. Submit a CIR.

3.3.1 Ensure that the ultrasonic apparatus, procedure

requirements, and report shall be in accordance with ASTM E797, and that the report results shall additionally include the following information for each test point:

• Location.

• Original metal thickness.

• Measured metal thickness.

• Percent deterioration (calculation is based on the original metal thickness).

3.3.2 Perform ultrasonic equipment standardization in

accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).

3.4 Overcoating procedures. The Contractor shall accomplish

the following overcoating procedures to the designated bilge areas (see paragraph 1.1).

3.4.1 Pre-surface preparation cleaning. Accomplish low-

pressure steam cleaning (less than 3,000 psi) of all affected surfaces to remove soluble chlorides and other surface

Page 19 (Rev-1) contaminants to achieve an SSPC-SP 1 condition. Collect wash water for proper disposal.

3.4.2 Surface preparation.

3.4.2.1 Machine tool damaged surfaces in which mechanical

damage extends into the substrate, or where there is evidence of corrosion to “bare” metal, in accordance with SSPC-SP 11 to produce a minimum 1.0 mil anchor profile. Locations shall be in accordance with Coast Guard Inspector instruction.

3.4.2.2 Roughen/abrade all surfaces where existing top-coating is intact with 100-grit paper to provide a suitable surface profile.

3.4.2.3 Feather edges of topcoating into adjacent bare areas to create a smooth transition.

3.4.2.4 Ensure that all power tools are vacuum-shrouded, to

reduce/eliminate dust or debris. Collect all dust and debris for proper disposal.

3.4.3 Post-surface preparation cleaning. Perform solvent

cleaning of all prepared surfaces, in accordance with SSPC-SP 1, prior to coating application. Collect all debris from solvent cleaning for proper disposal.

3.4.4 Coating application. Coat the designated bilge areas in accordance with COMDTINST M10360.3, using the system specified for “Bilges, Cofferdams, and Forepeaks, Steel, Option III, (Cutters and Boats Interior Painting Systems)”, and in accordance with the following:

3.4.4.1 Using a brush or roller, spot coat all bare areas with the specified system primer coating to a thickness matching that of the existing adjacent undercoating, ensuring that the primer coating extends over the feathered edges of the sound/intact coating to minimize edge lifting and provide a better appearance.

3.4.4.2 Using a brush or roller, apply the specified system top coat to all primed and abraded bilge surfaces to match the existing coating system; ensure a uniform thickness throughout.

NOTICE!

Coating application by brushing or rolling may require additional coats to obtain the required dry film thickness.

Page 20 (Rev-1)

3.5 Inspections. Before surface coating and after surface

preparation, the Contractor shall visually inspect the prepared substrate and submit a CFR.

3.6 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in Std Spec 0000_STD, paragraph titled “Preservation requirements – general”.

NOTICE!

Surfaces being preserved are considered “critical-coated surfaces”. See Std Spec 0000_STD.

3.7 Repair of un-intended damages. The Contractor shall repair all damages, including overspray, incurred to surfaces not covered by the scope of this work item, during surface preparation and paint application procedures.

3.8 Operational test – final. In the presence of the Coast

Guard Inspector, the Contractor shall thoroughly test and prove to be in satisfactory operating condition all disturbed sensors and other disturbed shipboard equipment (see 4.1 (Equipment operation)). Submit a CFR.

4. NOTES

4.1 Equipment operation. Coast Guard personnel will operate

all shipboard machinery and equipment during all tests.

Page 21 (Rev-1)

S07400_DNK_627(22 Sep 2008)

WORK ITEM 5: Remove Unused Skin Valves

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to remove the designated valves and install hull plating inserts.

TYPE MATERIAL DESCRIPTION

FRAME

LOCATION/

VALVE NO

Gate Brass Distillate OVBD

COV 2-119-1

Gate Brass Brine OVBD COV 2-126-1

1.2 Government-furnished property.

None

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0000_STD, General Requirements

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, Welding and Allied Processes

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Coatings and Color Manual

Coast Guard Drawing 627 WMEC 131-001, Rev D, Second & Main Deck Plating & Supports

Coast Guard Drawing 627 WMEC 533-007, Rev A, Reverse Osmosis Declinator Arrangement & Details

3. REQUIREMENTS

Page 22 (Rev-1)

3.1.1 Protective measures. The Contractor shall protect non-

affected vessel’s equipment, components, and spaces during surface preparation and coating application procedures, as specified in paragraph 3.11.4(Protective measures) in Std Spec

0000_STD.

3.1.2 Welding Requirements. The Contractor shall perform all

welding and nondestructive inspection (NDI) in accordance with Std Spec 0740_STD.

3.2 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to the following:

• Perforated Metal Lagging

• Wiring

• R/O OVBD COV

• Feed Water System

3.3 Removal. The Contractor shall remove the valves designated in paragraph 1.1 and corresponding piping designated by the Coast Guard Inspector. Refer to CG Drawing 627 WMEC 533-007 and sketch below (See section 4.1) for further details.

3.4 Hull Plating Installation. The Contractor shall fabricate and install hull plating inserts using CG Drawing 627 WMEC 131- 001 as guidance.

3.5 Nondestructive inspection (NDI). The Contractor shall

perform NDI of all welds in accordance with Std Spec 0740_STD, Appendix C. Submit a CFR.

3.6 Touch-up preservation. The Contractor shall prepare and

coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with COMDTINST M10360.3, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in paragraph 3.11.9 (Touch-ups and minor coating repairs) of Std Spec 0000_STD.

3.8 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in Std Spec 0000_STD, paragraph titled “General preservation requirements”.

Page 23 (Rev-1)

Surfaces being preserved are considered “critical-coated surfaces”.

4. NOTES

4.1 Location of Valves. The following sketch shows the

approximate location of the skin valves. The Contractor may have to use a paint float or other means to access the skin of the ship.

Page 24 (Rev-1)

Valve Location on 2nd Deck.

Approx Waterline

MLCA SKETCH 627 WMEC 07400-001

S12000_DNK_627(23 Sep 2008)

WORK ITEM 6: Renew Laundry Room Bulkhead

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew a damaged section of bulkhead in the Laundry Room, compartment 1-20-0-Q.

1.2 Government-furnished property.

None

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0000_STD, General Requirements

Coast Guard Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0740_STD, Welding and Allied Processes

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Coatings and Color Manual

ASTM International (ASTM) E797, 2005, Standard Practice for Measuring Thickness by Manual Ultrasonic Pulse-Echo Contact Method

Coast Guard Drawing 627 WMEC 122-001, Rev D, Transverse Watertight Bulkheads FWD & AFT Midships

3. REQUIREMENTS

3.1 General.

3.1.1 Critical Inspection Report. The Contractor shall submit a critical inspection report (CIR) for the inspections listed in the following paragraph(s):

• 3.2(Ultrasonic thickness measurement).

Page 25 (Rev-1)

3.1.2 Welding Requirements. The Contractor shall perform all

welding and nondestructive inspection (NDI) in accordance with Std Spec 0740_STD.

3.1.3 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to the following:

• Insulation

• Deck Fittings

• Piping

• Racks and Lockers

• Deep Sink

• Washers

• Quarry Tile Deck

3.2 Ultrasonic thickness measurement. The Contractor shall

perform a total of 25 thickness measurements of the bulkhead and deck plating, in locations designated by the Coast Guard Inspector. Submit a CIR.

3.2.1 Ensure that the ultrasonic apparatus, procedure

requirements, and report shall be in accordance with ASTM E797, and that the report results shall additionally include the following information for each test point:

• Location.

• Original metal thickness.

• Measured metal thickness.

• Percent deterioration (calculation is based on the original metal thickness).

Page 26 (Rev-1)

3.2.2 Perform ultrasonic equipment standardization in

accordance with ASTM E797, Section 7 (Standardization of Apparatus) and Section 8 (Technical Hazards).

3.2.3 The Contractor shall remove, at the COTR’s discretion, any quarry tile necessary to perform this inspection. The Contractor will furnish and replace any disturbed quarry tiles.

3.3 Removal. The Contractor shall crop out the damaged section (approximately 2 square ft) of the laundry room bulkhead as designated by the Coast Guard Inspector.

3.4 Renewal. The Contractor shall fabricate and weld-install a new section of metal for the designated section using Coast Guard Drawing 627 WMEC 122-001 as guidance.

3.5 Nondestructive inspection (NDI). The Contractor shall

perform NDI of all welds in accordance with Std Spec 0740_STD, Appendix C. Submit a CFR.

3.6 Surface preservation. The Contractor shall prepare and

coat all new and disturbed surfaces, including all adjacent structural members, using the system specified for “Bulkheads (Bulkheads and Overheads, Un-insulated Steel), Option I or II” in COMDTINST M10360.3, Appendix B (Cutter and Boat Interior Painting Systems). Select finish/top coat color to match existing adjacent surfaces. If surface preparation involves the removal of lead paint, ensure that no visible coatings remain on any part of the substrate, including pitted areas.

3.7 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in Std Spec 0000_STD, paragraph titled “General preservation requirements.”

Page 27 (Rev-1)

S16700D_SWIT(19 Apr 2005) S16700_DNK_627(19 Sep 2008)

WORK ITEM 7: Renew Door

1. SCOPE

1.1 Scope. This work item describes the requirements for the

Contractor to renew the following closures and associated frames:

FITTING LOCATION SIZE

QAWTD 1-126-1 26” X 66” LH (8-dog)

1.2 Government-furnished property.

MTI ITEM DESCRIPTION NSN/PN QTY

ESTIMATED

COST

($/UNIT)

N

66” x 26” Quick- Acting Watertight Door W/8-dogs, LH

2040-00-912-5778 1 ea. 2,675.51

2. APPLICABLE DOCUMENTS

Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0000_STD, 2004 Edition, General Requirements

Coast Guard Maintenance and Logistics Command Atlantic (MLCA), Standard Specification 0740_STD, 2004 Edition, Welding and Allied Processes

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Mar 2005, Coatings and Color Manual

Coast Guard Drawing 627 WMEC 167-001, Rev K, Schedule of Steel Doors, Hatches, Scuttles & Manholes

3. REQUIREMENTS

3.1 General.

Page 28 (Rev-1) http://isddc.dot.gov/OLPFiles/USCG/010968.pdf

3.1.1 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to the following:

• Sheathing

• Bulkhead insulation.

• Wire runs

3.1.2 Protective measures. The Contractor shall furnish and

install suitable covering to seal off and protect all non-affected surfaces/equipment and spaces in the vicinity of the work area against contamination during the performance of work.

Upon completion of work, remove protective material and inspect for the presence of contamination as specified in paragraph 3.11.4(Protective measures) in Std Spec 0000_STD. Clean all equipment and spaces, contaminated due to improper protection, to original condition of cleanliness.

3.1.3 Protective covering. The Contractor shall provide

protective covering while the door is removed. Ensure that covering is installed daily at the end of the workday.

3.2 Renewal. The Contractor shall crop out and renew (both

frame and door) QAWTD 1-126-1 using Coast Guard Drawing 627 WMEC 167-001 as guidance. Perform all necessary modifications to ensure proper fitting. Provide new gaskets and fasteners, as applicable with the new installation.

3.3 Nondestructive inspection (NDI). The Contractor shall

perform NDI of the new welds in accordance with Std Spec 0740_STD, Appendix C. Submit a CFR.

3.4 Watertight fitting preservation. The Contractor shall

preserve the new door and all other disturbed surfaces to match exiting adjacent surfaces, in accordance with Std Spec 0000_STD, paragraph titled “General preservation requirements”, and in accordance with COMDTINST M10360.3; and as follows:

3.4.1 Interior surfaces. Coat interior surface using the

coating system specified for “Door, Joiner, Option I” in Appendix B (Cutters and Boats Interior Painting Systems).

3.4.2 Exterior surfaces. Coat exterior surfaces using the

coating system specified for “Freeboard/Superstructure/Mast (Freeboard/Superstructure, Steel), Option I” in Appendix A (Cutters and Boats Exterior Painting Systems).

Page 29 (Rev-1)

Do not paint knife-edges, gaskets, or any moving parts; including dogs, nuts, wedges, spindles, yokes, packing, connecting rods and hinge pins.

3.5 Closure. The Contractor shall demonstrate 100 percent

gasket contact and proper dog operation by means of a chalk test for each renewal. Ensure that initial contact between gasket and knife edge occurs throughout extent of gasket before final securing of dogs, and without use of excessive closing force.

If the mark on the gasket is not uniform, adjust as necessary to achieve uniform contact and retest.

4. NOTES

4.1 Damage control markings. The Coast Guard Inspector will

apply appropriate damage control decals onto doors and scuttles as appropriate.

Page 30 (Rev-1)

S64400_DNK_627(06 Oct 2008)

WORK ITEM 8: Renew Partitions

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to replace stall partitions in compartment 1-52-2-L (Crew WR WC & SHR).

1.2 Government-furnished property.

None.

2. APPLICABLE DOCUMENTS

Coast Guard Drawing 627 WMEC 601-004, Rev C, General Arrangemnet Main and 01 Decks

Coast Guard Drawing 627 WMEC 644-003, Rev D, Sanitary Partitions

3. REQUIREMENTS

3.1 General.

3.1.1 Interferences. The Contractor shall be aware that

interferences in way of work include, but are not limited to:

• Decking

• Bulkhead Insulation

• Toilets/Sinks

• Piping

3.2 Renewal. The Contractor shall remove, renew and install

new stall partitions and doors in compartment 1-52-2-L as shown on Coast Guard Drawings 627 WMEC 601-004 and 644-003. The Contractor shall provide all partition and door material.

3.3 Mounts. The Contractor shall renew each of the partition

mounts. The Contractor shall also repair any deck material that is disturbed in the process.

Page 31 (Rev-1)

3.4 Operational test. In the presence of the Coast Guard

Inspector, the Contractor shall thoroughly test and prove to be in satisfactory operating condition all items or shipboard devices that have been disturbed, used, repaired, altered, or installed. Submit a CFR.

4. NOTES