The file's text, extracted by GovTribe without its formatting.
Cost Roll-Up
| PRIME CONTRACTOR COST ROLL-UP | | | | | | | | | | | |
| Contractor: | Insert contractor name | | | | | | | | | | |
| HQ0147-16-R-0017 - Agency Advisory and Analytical Support | | | | | | | | | | | |
| Stakeholder | CLIN | Description | CFY 1 | CFY 2 | CFY 3 | CFY 4 | CFY 5 | CFY 6 | Total | Crosscheck | Unreconciled |
| ALL | All CLINs | Labor Hours | 1,920 | 2,400 | 880 | 2,000 | 2,000 | 1,600 | 10,800 | 10,800 | - 0 |
| | Labor | $20,022 | $31,760 | $10,352 | $11,984 | $16,524 | $16,524 | $107,166 | $107,166 | $0 |
| | IWTA | $0 | $0 | $4,813 | $28,511 | $15,254 | $0 | $48,578 | $98,950 | $0 |
| | Subcontracts | $937 | $1,464 | $355 | $1,954 | $22,832 | $22,832 | $50,373 | | |
| | Subcontractor Fee | $28 | $44 | $11 | $67 | $704 | $704 | $1,558 | $1,558 | $0 |
| | Procurement Overhead | $48 | $75 | $18 | $101 | $1,177 | $1,177 | $2,597 | | |
| | G&A | $101 | $158 | $520 | $3,063 | $3,997 | $2,471 | $10,310 | | |
| | Total Labor Cost | $21,137 | $33,502 | $16,069 | $45,680 | $60,486 | $43,707 | $220,581 | | |
| | Fixed Fee | $1,055 | $1,673 | $803 | $2,281 | $2,989 | $2,150 | $10,951 | | |
| | Total CPFF | $22,192 | $35,175 | $16,872 | $47,961 | $63,476 | $45,857 | $231,532 | | |
| 0206, 1206, 2206, 3206 | BC Travel | $37,000 | Surge break-out | |
| 0208, 1208, 2208, 3208 | DE Travel | $250,000 | Cost | $10,929,524 |
| 0218, 1218, 2218, 3218 | GM Travel | $593,000 | Fee % | 5% |
| 0223, 1223, 2223, 3233 | TH Travel | $82,000 | Fixed Fee | $546,476 |
| 0227, 1227, 2227, 3227 | DT Travel | $440,000 | Total CPFF | $11,476,000 |
| 0020 | SN Travel | $10,000 | | |
| 0004 | Total Surge | $11,476,000 | | |
| SUBTOTAL ALL CLINS | $13,119,532 | | |
| 4001 | Cost for Option to extend services (see FAR Clause 52.217-8) | $85,746 | | |
| 4001 | Fee for Option to extend services (see FAR Clause 52.217-8) | $4,217 | | |
| TOTAL ALL CLINS | $13,209,496 | | |
Error Check Good Good Good Good Good Good Good
| This tab rolls up the labor hours, labor cost, IWTA cost, subcontract cost, and subcontract fee by CLIN. | | | | | | | |
| RFP-specified amounts are used for Travel and Surge. | | | | | | | |
| Procurement, overhead, G&A and Fee rates are carried forward (linked) from the Rates tab. | | | | | | | |
| Procurement overhead, G&A on non-labor costs, and fixed fee is calculated on this tab. | | | | | | | |
| Offerors, IWTAs and major subcontractors must correct and tailor to eliminate errors and to conform to their estimating and accounting systems so that each rate/factor calculation uses the correct allocation base. | | | | | | | |
| Prime offerors may NOT propose fee on subcontractor fee. | | | | | | | |
| Column Index Reference | 5 | 6 | 7 | 8 | 9 | 10 |
| Rates Applied Below | Procurement Overhead | 5.00% | 5.00% | 5.00% | 5.00% | 5.00% | 5.00% |
| G&A | 10.00% | 10.00% | 10.00% | 10.00% | 10.00% | 10.00% |
| Fixed Fee | 5.00% | | | | | |
| BC-TI0001 | 0006-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $1,394 | $2,033 | $469 | $0 | $0 | $0 | $3,896 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $1,394 | $2,033 | $469 | $0 | $0 | $0 | $3,896 |
| | Fixed Fee | $70 | $102 | $23 | $0 | $0 | $0 | $195 |
| | Total CPFF | $1,464 | $2,134 | $492 | $0 | $0 | $0 | $4,090 |
| 1006-1 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $369 | $1,723 | $0 | $0 | $2,092 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $369 | $1,723 | $0 | $0 | $2,092 |
| Fixed Fee | $0 | $0 | $18 | $86 | $0 | $0 | $105 |
| Total CPFF | $0 | $0 | $388 | $1,809 | $0 | $0 | $2,197 |
| 2006-1 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $400 | $1,846 | $0 | $2,246 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $40 | $185 | $0 | $225 |
| Total Labor Cost | $0 | $0 | $0 | $440 | $2,031 | $0 | $2,471 |
| Fixed Fee | $0 | $0 | $0 | $22 | $102 | $0 | $124 |
| Total CPFF | $0 | $0 | $0 | $462 | $2,132 | $0 | $2,594 |
| 3006-1 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,846 | $1,846 | $3,692 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $55 | $55 | $111 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $95 | $95 | $190 |
| G&A | $0 | $0 | $0 | $0 | $200 | $200 | $399 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,196 | $2,196 | $4,393 |
| Fixed Fee | $0 | $0 | $0 | $0 | $107 | $107 | $214 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,303 | $2,303 | $4,607 |
All Total CPFF $1,464 $2,134 $880 $2,271 $4,436 $2,303 $13,488
| DE-TI0001 | 0008-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | Fixed Fee | $35 | $58 | $15 | $0 | $0 | $0 | $108 |
| | Total CPFF | $732 | $1,220 | $308 | $0 | $0 | $0 | $2,259 |
| 1008-1 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| Fixed Fee | $0 | $0 | $18 | $83 | $0 | $0 | $100 |
| Total CPFF | $0 | $0 | $372 | $1,737 | $0 | $0 | $2,110 |
| 2008-1 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $532 | $2,383 | $0 | $2,915 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $53 | $238 | $0 | $292 |
| Total Labor Cost | $0 | $0 | $0 | $585 | $2,622 | $0 | $3,207 |
| Fixed Fee | $0 | $0 | $0 | $29 | $131 | $0 | $160 |
| Total CPFF | $0 | $0 | $0 | $614 | $2,753 | $0 | $3,367 |
| 3008-1 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $76 | $76 | $153 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $99 | $99 | $198 |
| G&A | $0 | $0 | $0 | $0 | $208 | $208 | $416 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,290 | $2,290 | $4,581 |
| Fixed Fee | $0 | $0 | $0 | $0 | $111 | $111 | $221 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,401 | $2,401 | $4,802 |
All Total CPFF $732 $1,220 $680 $2,352 $5,154 $2,401 $12,538
| DE-TI0002 | 0008-2 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | Fixed Fee | $41 | $65 | $16 | $0 | $0 | $0 | $122 |
| | Total CPFF | $854 | $1,372 | $338 | $0 | $0 | $0 | $2,564 |
| 1008-2 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $492 | $2,215 | $0 | $0 | $2,708 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $492 | $2,215 | $0 | $0 | $2,708 |
| Fixed Fee | $0 | $0 | $25 | $111 | $0 | $0 | $135 |
| Total CPFF | $0 | $0 | $517 | $2,326 | $0 | $0 | $2,843 |
| 2008-2 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $369 | $1,723 | $0 | $2,092 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $37 | $172 | $0 | $209 |
| Total Labor Cost | $0 | $0 | $0 | $406 | $1,895 | $0 | $2,302 |
| Fixed Fee | $0 | $0 | $0 | $20 | $95 | $0 | $115 |
| Total CPFF | $0 | $0 | $0 | $426 | $1,990 | $0 | $2,417 |
| 3008-2 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,969 | $1,969 | $3,938 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $59 | $59 | $118 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $101 | $101 | $203 |
| G&A | $0 | $0 | $0 | $0 | $213 | $213 | $426 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,343 | $2,343 | $4,685 |
| Fixed Fee | $0 | $0 | $0 | $0 | $114 | $114 | $228 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,457 | $2,457 | $4,914 |
All Total CPFF $854 $1,372 $855 $2,753 $4,447 $2,457 $12,738
| DE-TI0003 | 0008-3 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | Fixed Fee | $46 | $73 | $18 | $0 | $0 | $0 | $137 |
| | Total CPFF | $976 | $1,525 | $369 | $0 | $0 | $0 | $2,870 |
| 1008-3 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $325 | $1,537 | $0 | $0 | $1,862 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $325 | $1,537 | $0 | $0 | $1,862 |
| Fixed Fee | $0 | $0 | $16 | $77 | $0 | $0 | $93 |
| Total CPFF | $0 | $0 | $341 | $1,613 | $0 | $0 | $1,955 |
| 2008-3 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $384 | $1,788 | $0 | $2,172 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $38 | $179 | $0 | $217 |
| Total Labor Cost | $0 | $0 | $0 | $423 | $1,966 | $0 | $2,389 |
| Fixed Fee | $0 | $0 | $0 | $21 | $98 | $0 | $119 |
| Total CPFF | $0 | $0 | $0 | $444 | $2,065 | $0 | $2,508 |
| 3008-3 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $57 | $57 | $114 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $98 | $98 | $196 |
| G&A | $0 | $0 | $0 | $0 | $206 | $206 | $412 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,268 | $2,268 | $4,537 |
| Fixed Fee | $0 | $0 | $0 | $0 | $111 | $111 | $221 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,379 | $2,379 | $4,758 |
All Total CPFF $976 $1,525 $711 $2,057 $4,443 $2,379 $12,090
| DE-TI0004 | 0008-4 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | Fixed Fee | $35 | $58 | $15 | $0 | $0 | $0 | $108 |
| | Total CPFF | $732 | $1,220 | $308 | $0 | $0 | $0 | $2,259 |
| 1008-4 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $369 | $1,723 | $0 | $0 | $2,092 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $369 | $1,723 | $0 | $0 | $2,092 |
| Fixed Fee | $0 | $0 | $18 | $86 | $0 | $0 | $105 |
| Total CPFF | $0 | $0 | $388 | $1,809 | $0 | $0 | $2,197 |
| 2008-4 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $431 | $1,969 | $0 | $2,400 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $43 | $197 | $0 | $240 |
| Total Labor Cost | $0 | $0 | $0 | $474 | $2,166 | $0 | $2,640 |
| Fixed Fee | $0 | $0 | $0 | $24 | $108 | $0 | $132 |
| Total CPFF | $0 | $0 | $0 | $498 | $2,274 | $0 | $2,772 |
| 3008-4 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $2,462 | $2,462 | $4,923 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,462 | $2,462 | $4,923 |
| Fixed Fee | $0 | $0 | $0 | $0 | $123 | $123 | $246 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,585 | $2,585 | $5,169 |
All Total CPFF $732 $1,220 $695 $2,307 $4,859 $2,585 $12,397
| DE-TI0005 | 0008-5 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | Fixed Fee | $46 | $73 | $18 | $0 | $0 | $0 | $137 |
| | Total CPFF | $976 | $1,525 | $369 | $0 | $0 | $0 | $2,870 |
| 1008-5 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| Fixed Fee | $0 | $0 | $18 | $83 | $0 | $0 | $100 |
| Total CPFF | $0 | $0 | $372 | $1,737 | $0 | $0 | $2,110 |
| 2008-5 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $355 | $1,668 | $0 | $2,023 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $35 | $167 | $0 | $202 |
| Total Labor Cost | $0 | $0 | $0 | $390 | $1,835 | $0 | $2,225 |
| Fixed Fee | $0 | $0 | $0 | $20 | $92 | $0 | $111 |
| Total CPFF | $0 | $0 | $0 | $410 | $1,927 | $0 | $2,337 |
| 3008-5 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,788 | $1,788 | $3,575 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $54 | $54 | $107 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $92 | $92 | $184 |
| G&A | $0 | $0 | $0 | $0 | $193 | $193 | $387 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,127 | $2,127 | $4,253 |
| Fixed Fee | $0 | $0 | $0 | $0 | $104 | $104 | $207 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,230 | $2,230 | $4,460 |
All Total CPFF $976 $1,525 $742 $2,147 $4,157 $2,230 $11,776
| DE-TI0006 | 0008-6 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | Fixed Fee | $46 | $73 | $18 | $0 | $0 | $0 | $137 |
| | Total CPFF | $976 | $1,525 | $369 | $0 | $0 | $0 | $2,870 |
| 1008-6 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $308 | $1,477 | $0 | $0 | $1,785 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $308 | $1,477 | $0 | $0 | $1,785 |
| Fixed Fee | $0 | $0 | $15 | $74 | $0 | $0 | $89 |
| Total CPFF | $0 | $0 | $323 | $1,551 | $0 | $0 | $1,874 |
| 2008-6 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $431 | $1,969 | $0 | $2,400 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $43 | $197 | $0 | $240 |
| Total Labor Cost | $0 | $0 | $0 | $474 | $2,166 | $0 | $2,640 |
| Fixed Fee | $0 | $0 | $0 | $24 | $108 | $0 | $132 |
| Total CPFF | $0 | $0 | $0 | $498 | $2,274 | $0 | $2,772 |
| 3008-6 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,969 | $1,969 | $3,938 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $59 | $59 | $118 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $101 | $101 | $203 |
| G&A | $0 | $0 | $0 | $0 | $213 | $213 | $426 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,343 | $2,343 | $4,685 |
| Fixed Fee | $0 | $0 | $0 | $0 | $114 | $114 | $228 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,457 | $2,457 | $4,914 |
All Total CPFF $976 $1,525 $692 $2,048 $4,731 $2,457 $12,429
| DE-TI0007 | 0008-7 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | Fixed Fee | $41 | $65 | $16 | $0 | $0 | $0 | $122 |
| | Total CPFF | $854 | $1,372 | $338 | $0 | $0 | $0 | $2,564 |
| 1008-7 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $473 | $2,127 | $0 | $0 | $2,600 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $47 | $213 | $0 | $0 | $260 |
| Total Labor Cost | $0 | $0 | $520 | $2,340 | $0 | $0 | $2,860 |
| Fixed Fee | $0 | $0 | $26 | $117 | $0 | $0 | $143 |
| Total CPFF | $0 | $0 | $546 | $2,457 | $0 | $0 | $3,003 |
| 2008-7 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $414 | $1,907 | $0 | $2,320 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $41 | $191 | $0 | $232 |
| Total Labor Cost | $0 | $0 | $0 | $455 | $2,097 | $0 | $2,552 |
| Fixed Fee | $0 | $0 | $0 | $23 | $105 | $0 | $128 |
| Total CPFF | $0 | $0 | $0 | $478 | $2,202 | $0 | $2,680 |
| 3008-7 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| Fixed Fee | $0 | $0 | $0 | $0 | $95 | $95 | $191 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,002 | $2,002 | $4,004 |
All Total CPFF $854 $1,372 $885 $2,935 $4,204 $2,002 $12,252
| DE-TI0008 | 0008-8 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | Fixed Fee | $46 | $73 | $18 | $0 | $0 | $0 | $137 |
| | Total CPFF | $976 | $1,525 | $369 | $0 | $0 | $0 | $2,870 |
| 1008-8 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $308 | $1,477 | $0 | $0 | $1,785 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $31 | $148 | $0 | $0 | $178 |
| Total Labor Cost | $0 | $0 | $338 | $1,625 | $0 | $0 | $1,963 |
| Fixed Fee | $0 | $0 | $17 | $81 | $0 | $0 | $98 |
| Total CPFF | $0 | $0 | $355 | $1,706 | $0 | $0 | $2,061 |
| 2008-8 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $400 | $0 | $0 | $400 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $40 | $0 | $0 | $40 |
| Total Labor Cost | $0 | $0 | $0 | $440 | $0 | $0 | $440 |
| Fixed Fee | $0 | $0 | $0 | $22 | $0 | $0 | $22 |
| Total CPFF | $0 | $0 | $0 | $462 | $0 | $0 | $462 |
| 3008-8 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,723 | $1,723 | $3,446 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $52 | $52 | $103 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $89 | $89 | $177 |
| G&A | $0 | $0 | $0 | $0 | $186 | $186 | $373 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,050 | $2,050 | $4,100 |
| Fixed Fee | $0 | $0 | $0 | $0 | $100 | $100 | $200 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,150 | $2,150 | $4,300 |
All Total CPFF $976 $1,525 $725 $2,168 $2,150 $2,150 $9,692
| DE-TI0009 | 0008-9 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | Fixed Fee | $35 | $58 | $15 | $0 | $0 | $0 | $108 |
| | Total CPFF | $732 | $1,220 | $308 | $0 | $0 | $0 | $2,259 |
| 1008-9 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $35 | $165 | $0 | $0 | $201 |
| Total Labor Cost | $0 | $0 | $390 | $1,820 | $0 | $0 | $2,210 |
| Fixed Fee | $0 | $0 | $20 | $91 | $0 | $0 | $111 |
| Total CPFF | $0 | $0 | $410 | $1,911 | $0 | $0 | $2,321 |
| 2008-9 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $414 | $0 | $0 | $414 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $41 | $0 | $0 | $41 |
| Total Labor Cost | $0 | $0 | $0 | $455 | $0 | $0 | $455 |
| Fixed Fee | $0 | $0 | $0 | $23 | $0 | $0 | $23 |
| Total CPFF | $0 | $0 | $0 | $478 | $0 | $0 | $478 |
| 3008-9 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $2,383 | $2,383 | $4,767 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,383 | $2,383 | $4,767 |
| Fixed Fee | $0 | $0 | $0 | $0 | $119 | $119 | $238 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,503 | $2,503 | $5,005 |
All Total CPFF $732 $1,220 $717 $2,389 $2,503 $2,503 $10,063
| DE-TI0010 | 0008-10 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | Fixed Fee | $41 | $65 | $16 | $0 | $0 | $0 | $122 |
| | Total CPFF | $854 | $1,372 | $338 | $0 | $0 | $0 | $2,564 |
| 1008-10 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $369 | $1,723 | $0 | $0 | $2,092 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $37 | $172 | $0 | $0 | $209 |
| Total Labor Cost | $0 | $0 | $406 | $1,895 | $0 | $0 | $2,302 |
| Fixed Fee | $0 | $0 | $20 | $95 | $0 | $0 | $115 |
| Total CPFF | $0 | $0 | $426 | $1,990 | $0 | $0 | $2,417 |
| 2008-10 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $369 | $0 | $0 | $369 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $37 | $0 | $0 | $37 |
| Total Labor Cost | $0 | $0 | $0 | $406 | $0 | $0 | $406 |
| Fixed Fee | $0 | $0 | $0 | $20 | $0 | $0 | $20 |
| Total CPFF | $0 | $0 | $0 | $426 | $0 | $0 | $426 |
| 3008-10 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,723 | $1,723 | $3,446 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $52 | $52 | $103 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $89 | $89 | $177 |
| G&A | $0 | $0 | $0 | $0 | $186 | $186 | $373 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,050 | $2,050 | $4,100 |
| Fixed Fee | $0 | $0 | $0 | $0 | $100 | $100 | $200 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,150 | $2,150 | $4,300 |
All Total CPFF $854 $1,372 $765 $2,417 $2,150 $2,150 $9,707
| DEI-TI0001 | 0009-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | Fixed Fee | $46 | $73 | $18 | $0 | $0 | $0 | $137 |
| | Total CPFF | $976 | $1,525 | $369 | $0 | $0 | $0 | $2,870 |
| 1009-1 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $473 | $2,127 | $0 | $0 | $2,600 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $47 | $213 | $0 | $0 | $260 |
| Total Labor Cost | $0 | $0 | $520 | $2,340 | $0 | $0 | $2,860 |
| Fixed Fee | $0 | $0 | $26 | $117 | $0 | $0 | $143 |
| Total CPFF | $0 | $0 | $546 | $2,457 | $0 | $0 | $3,003 |
| 2009-1 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $384 | $0 | $0 | $384 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $38 | $0 | $0 | $38 |
| Total Labor Cost | $0 | $0 | $0 | $423 | $0 | $0 | $423 |
| Fixed Fee | $0 | $0 | $0 | $21 | $0 | $0 | $21 |
| Total CPFF | $0 | $0 | $0 | $444 | $0 | $0 | $444 |
| 3009-1 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| Fixed Fee | $0 | $0 | $0 | $0 | $95 | $95 | $191 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,002 | $2,002 | $4,004 |
All Total CPFF $976 $1,525 $915 $2,901 $2,002 $2,002 $10,321
| DV-TI0001 | 0013-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | Fixed Fee | $46 | $73 | $18 | $0 | $0 | $0 | $137 |
| | Total CPFF | $976 | $1,525 | $369 | $0 | $0 | $0 | $2,870 |
| 1013-1 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $308 | $1,477 | $0 | $0 | $1,785 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $31 | $148 | $0 | $0 | $178 |
| Total Labor Cost | $0 | $0 | $338 | $1,625 | $0 | $0 | $1,963 |
| Fixed Fee | $0 | $0 | $17 | $81 | $0 | $0 | $98 |
| Total CPFF | $0 | $0 | $355 | $1,706 | $0 | $0 | $2,061 |
| 2013-1 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $431 | $0 | $0 | $431 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $43 | $0 | $0 | $43 |
| Total Labor Cost | $0 | $0 | $0 | $474 | $0 | $0 | $474 |
| Fixed Fee | $0 | $0 | $0 | $24 | $0 | $0 | $24 |
| Total CPFF | $0 | $0 | $0 | $498 | $0 | $0 | $498 |
| 3013-1 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,969 | $1,969 | $3,938 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $59 | $59 | $118 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $101 | $101 | $203 |
| G&A | $0 | $0 | $0 | $0 | $213 | $213 | $426 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,343 | $2,343 | $4,685 |
| Fixed Fee | $0 | $0 | $0 | $0 | $114 | $114 | $228 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,457 | $2,457 | $4,914 |
All Total CPFF $976 $1,525 $725 $2,203 $2,457 $2,457 $10,342
| GM-TI0001 | 0018-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | Fixed Fee | $41 | $65 | $16 | $0 | $0 | $0 | $122 |
| | Total CPFF | $854 | $1,372 | $338 | $0 | $0 | $0 | $2,564 |
| 1018-1 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $35 | $165 | $0 | $0 | $201 |
| Total Labor Cost | $0 | $0 | $390 | $1,820 | $0 | $0 | $2,210 |
| Fixed Fee | $0 | $0 | $20 | $91 | $0 | $0 | $111 |
| Total CPFF | $0 | $0 | $410 | $1,911 | $0 | $0 | $2,321 |
| 2018-1 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $414 | $0 | $0 | $414 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $41 | $0 | $0 | $41 |
| Total Labor Cost | $0 | $0 | $0 | $455 | $0 | $0 | $455 |
| Fixed Fee | $0 | $0 | $0 | $23 | $0 | $0 | $23 |
| Total CPFF | $0 | $0 | $0 | $478 | $0 | $0 | $478 |
| 3018-1 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $2,383 | $2,383 | $4,767 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,383 | $2,383 | $4,767 |
| Fixed Fee | $0 | $0 | $0 | $0 | $119 | $119 | $238 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,503 | $2,503 | $5,005 |
All Total CPFF $854 $1,372 $748 $2,389 $2,503 $2,503 $10,368
| GM-TI0002 | 0018-2 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 |
| | Fixed Fee | $35 | $58 | $15 | $0 | $0 | $0 | $108 |
| | Total CPFF | $732 | $1,220 | $308 | $0 | $0 | $0 | $2,259 |
| 1018-2 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $338 | $1,600 | $0 | $0 | $1,938 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $34 | $160 | $0 | $0 | $194 |
| Total Labor Cost | $0 | $0 | $372 | $1,760 | $0 | $0 | $2,132 |
| Fixed Fee | $0 | $0 | $19 | $88 | $0 | $0 | $107 |
| Total CPFF | $0 | $0 | $391 | $1,848 | $0 | $0 | $2,239 |
| 2018-2 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $400 | $0 | $0 | $400 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $40 | $0 | $0 | $40 |
| Total Labor Cost | $0 | $0 | $0 | $440 | $0 | $0 | $440 |
| Fixed Fee | $0 | $0 | $0 | $22 | $0 | $0 | $22 |
| Total CPFF | $0 | $0 | $0 | $462 | $0 | $0 | $462 |
| 3018-2 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,723 | $1,723 | $3,446 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $52 | $52 | $103 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $89 | $89 | $177 |
| G&A | $0 | $0 | $0 | $0 | $186 | $186 | $373 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,050 | $2,050 | $4,100 |
| Fixed Fee | $0 | $0 | $0 | $0 | $100 | $100 | $200 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,150 | $2,150 | $4,300 |
All Total CPFF $732 $1,220 $699 $2,310 $2,150 $2,150 $9,260
| DA-TI0002 | 0020-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 |
| | Fixed Fee | $41 | $65 | $16 | $0 | $0 | $0 | $122 |
| | Total CPFF | $854 | $1,372 | $338 | $0 | $0 | $0 | $2,564 |
All Total CPFF $854 $1,372 $338 $0 $0 $0 $2,564
| TH-TI0001 | 0023-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 |
| | Fixed Fee | $46 | $73 | $18 | $0 | $0 | $0 | $137 |
| | Total CPFF | $976 | $1,525 | $369 | $0 | $0 | $0 | $2,870 |
| 1023-1 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $35 | $165 | $0 | $0 | $201 |
| Total Labor Cost | $0 | $0 | $390 | $1,820 | $0 | $0 | $2,210 |
| Fixed Fee | $0 | $0 | $20 | $91 | $0 | $0 | $111 |
| Total CPFF | $0 | $0 | $410 | $1,911 | $0 | $0 | $2,321 |
| 2023-1 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $355 | $0 | $0 | $355 |
| Subcontractor Fee | $0 | $0 | $0 | $11 | $0 | $0 | $11 |
| Procurement Overhead | $0 | $0 | $0 | $18 | $0 | $0 | $18 |
| G&A | $0 | $0 | $0 | $38 | $0 | $0 | $38 |
| Total Labor Cost | $0 | $0 | $0 | $422 | $0 | $0 | $422 |
| Fixed Fee | $0 | $0 | $0 | $21 | $0 | $0 | $21 |
| Total CPFF | $0 | $0 | $0 | $442 | $0 | $0 | $442 |
| 3023-1 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| Fixed Fee | $0 | $0 | $0 | $0 | $95 | $95 | $191 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,002 | $2,002 | $4,004 |
All Total CPFF $976 $1,525 $779 $2,354 $2,002 $2,002 $9,637
| DT-TI0001 | 0027-1 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $968 | $1,513 | $369 | $0 | $0 | $0 | $2,850 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $968 | $1,513 | $369 | $0 | $0 | $0 | $2,850 |
| | Fixed Fee | $48 | $76 | $18 | $0 | $0 | $0 | $142 |
| | Total CPFF | $1,016 | $1,588 | $388 | $0 | $0 | $0 | $2,992 |
| 1027-1 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $492 | $2,215 | $0 | $0 | $2,708 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $49 | $222 | $0 | $0 | $271 |
| Total Labor Cost | $0 | $0 | $542 | $2,437 | $0 | $0 | $2,978 |
| Fixed Fee | $0 | $0 | $27 | $122 | $0 | $0 | $149 |
| Total CPFF | $0 | $0 | $569 | $2,559 | $0 | $0 | $3,127 |
| 2027-1 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $400 | $0 | $0 | $400 |
| Subcontractor Fee | $0 | $0 | $0 | $12 | $0 | $0 | $12 |
| Procurement Overhead | $0 | $0 | $0 | $21 | $0 | $0 | $21 |
| G&A | $0 | $0 | $0 | $43 | $0 | $0 | $43 |
| Total Labor Cost | $0 | $0 | $0 | $476 | $0 | $0 | $476 |
| Fixed Fee | $0 | $0 | $0 | $23 | $0 | $0 | $23 |
| Total CPFF | $0 | $0 | $0 | $499 | $0 | $0 | $499 |
| 3027-1 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $1,846 | $1,846 | $3,692 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $55 | $55 | $111 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $95 | $95 | $190 |
| G&A | $0 | $0 | $0 | $0 | $200 | $200 | $399 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,196 | $2,196 | $4,393 |
| Fixed Fee | $0 | $0 | $0 | $0 | $107 | $107 | $214 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,303 | $2,303 | $4,607 |
All Total CPFF $1,016 $1,588 $956 $3,058 $2,303 $2,303 $11,225
| DT-TI0002 | 0027-2 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $703 | $1,171 | $295 | $0 | $0 | $0 | $2,170 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $703 | $1,171 | $295 | $0 | $0 | $0 | $2,170 |
| | Fixed Fee | $35 | $59 | $15 | $0 | $0 | $0 | $108 |
| | Total CPFF | $738 | $1,230 | $310 | $0 | $0 | $0 | $2,278 |
| 1027-2 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $295 | $1,418 | $0 | $0 | $1,714 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $30 | $142 | $0 | $0 | $171 |
| Total Labor Cost | $0 | $0 | $325 | $1,560 | $0 | $0 | $1,885 |
| Fixed Fee | $0 | $0 | $16 | $78 | $0 | $0 | $94 |
| Total CPFF | $0 | $0 | $341 | $1,638 | $0 | $0 | $1,979 |
| 2027-2 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $414 | $0 | $0 | $414 |
| Subcontractor Fee | $0 | $0 | $0 | $17 | $0 | $0 | $17 |
| Procurement Overhead | $0 | $0 | $0 | $22 | $0 | $0 | $22 |
| G&A | $0 | $0 | $0 | $45 | $0 | $0 | $45 |
| Total Labor Cost | $0 | $0 | $0 | $497 | $0 | $0 | $497 |
| Fixed Fee | $0 | $0 | $0 | $24 | $0 | $0 | $24 |
| Total CPFF | $0 | $0 | $0 | $521 | $0 | $0 | $521 |
| 3027-2 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $1,907 | $1,907 | $3,813 |
| Fixed Fee | $0 | $0 | $0 | $0 | $95 | $95 | $191 |
| Total CPFF | $0 | $0 | $0 | $0 | $2,002 | $2,002 | $4,004 |
All Total CPFF $738 $1,230 $652 $2,159 $2,002 $2,002 $8,782
| DT-TI0003 | 0027-3 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $847 | $1,361 | $338 | $0 | $0 | $0 | $2,547 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $847 | $1,361 | $338 | $0 | $0 | $0 | $2,547 |
| | Fixed Fee | $42 | $68 | $17 | $0 | $0 | $0 | $127 |
| | Total CPFF | $889 | $1,429 | $355 | $0 | $0 | $0 | $2,674 |
| 1027-3 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $338 | $1,600 | $0 | $0 | $1,938 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $34 | $160 | $0 | $0 | $194 |
| Total Labor Cost | $0 | $0 | $372 | $1,760 | $0 | $0 | $2,132 |
| Fixed Fee | $0 | $0 | $19 | $88 | $0 | $0 | $107 |
| Total CPFF | $0 | $0 | $391 | $1,848 | $0 | $0 | $2,239 |
| 2027-3 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $431 | $0 | $0 | $431 |
| Subcontractor Fee | $0 | $0 | $0 | $17 | $0 | $0 | $17 |
| Procurement Overhead | $0 | $0 | $0 | $22 | $0 | $0 | $22 |
| G&A | $0 | $0 | $0 | $47 | $0 | $0 | $47 |
| Total Labor Cost | $0 | $0 | $0 | $517 | $0 | $0 | $517 |
| Fixed Fee | $0 | $0 | $0 | $25 | $0 | $0 | $25 |
| Total CPFF | $0 | $0 | $0 | $542 | $0 | $0 | $542 |
| 3027-3 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $2,462 | $2,462 | $4,923 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $74 | $74 | $148 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $127 | $127 | $254 |
| G&A | $0 | $0 | $0 | $0 | $266 | $266 | $532 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $2,928 | $2,928 | $5,857 |
| Fixed Fee | $0 | $0 | $0 | $0 | $143 | $143 | $285 |
| Total CPFF | $0 | $0 | $0 | $0 | $3,071 | $3,071 | $6,142 |
All Total CPFF $889 $1,429 $746 $2,390 $3,071 $3,071 $11,598
| DT-TI0004 | 0027-4 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $937 | $1,464 | $355 | $0 | $0 | $0 | $2,756 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $937 | $1,464 | $355 | $0 | $0 | $0 | $2,756 |
| | Fixed Fee | $47 | $73 | $18 | $0 | $0 | $0 | $138 |
| | Total CPFF | $984 | $1,537 | $372 | $0 | $0 | $0 | $2,893 |
| 1027-4 | Labor Hours | 0 | 0 | 20 | 80 | 0 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $35 | $165 | $0 | $0 | $201 |
| Total Labor Cost | $0 | $0 | $390 | $1,820 | $0 | $0 | $2,210 |
| Fixed Fee | $0 | $0 | $20 | $91 | $0 | $0 | $111 |
| Total CPFF | $0 | $0 | $410 | $1,911 | $0 | $0 | $2,321 |
| 2027-4 | Labor Hours | 0 | 0 | 0 | 20 | 80 | 0 | 100 |
| Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $355 | $0 | $0 | $355 |
| Subcontractor Fee | $0 | $0 | $0 | $11 | $0 | $0 | $11 |
| Procurement Overhead | $0 | $0 | $0 | $18 | $0 | $0 | $18 |
| G&A | $0 | $0 | $0 | $38 | $0 | $0 | $38 |
| Total Labor Cost | $0 | $0 | $0 | $422 | $0 | $0 | $422 |
| Fixed Fee | $0 | $0 | $0 | $21 | $0 | $0 | $21 |
| Total CPFF | $0 | $0 | $0 | $442 | $0 | $0 | $442 |
| 3027-4 | Labor Hours | 0 | 0 | 0 | 0 | 20 | 80 | 100 |
| Labor | $0 | $0 | $0 | $0 | $1,668 | $1,668 | $3,337 |
| IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Total Labor Cost | $0 | $0 | $0 | $0 | $1,668 | $1,668 | $3,337 |
| Fixed Fee | $0 | $0 | $0 | $0 | $83 | $83 | $167 |
| Total CPFF | $0 | $0 | $0 | $0 | $1,752 | $1,752 | $3,504 |
All Total CPFF $984 $1,537 $782 $2,354 $1,752 $1,752 $9,160
| DA-Option | 0037 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $847 | $1,361 | $338 | $0 | $0 | $0 | $2,547 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $847 | $1,361 | $338 | $0 | $0 | $0 | $2,547 |
| | Fixed Fee | $42 | $68 | $17 | $0 | $0 | $0 | $127 |
| | Total CPFF | $889 | $1,429 | $355 | $0 | $0 | $0 | $2,674 |
All Total CPFF $889 $1,429 $355 $0 $0 $0 $2,674
| DE-Option | 0038 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $937 | $1,464 | $355 | $0 | $0 | $0 | $2,756 |
| | Subcontractor Fee | $28 | $44 | $11 | $0 | $0 | $0 | $83 |
| | Procurement Overhead | $48 | $75 | $18 | $0 | $0 | $0 | $142 |
| | G&A | $101 | $158 | $38 | $0 | $0 | $0 | $298 |
| | Total Labor Cost | $1,115 | $1,742 | $422 | $0 | $0 | $0 | $3,278 |
| | Fixed Fee | $54 | $85 | $21 | $0 | $0 | $0 | $160 |
| | Total CPFF | $1,169 | $1,827 | $442 | $0 | $0 | $0 | $3,438 |
All Total CPFF $1,169 $1,827 $442 $0 $0 $0 $3,438
| DT-Option | 0039 | Labor Hours | 80 | 100 | 20 | 0 | 0 | 0 | 200 |
| | Labor | $968 | $1,513 | $369 | $0 | $0 | $0 | $2,850 |
| | IWTA | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontracts | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Subcontractor Fee | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Procurement Overhead | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | G&A | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| | Total Labor Cost | $968 | $1,513 | $369 | $0 | $0 | $0 | $2,850 |
| | Fixed Fee | $48 | $76 | $18 | $0 | $0 | $0 | $142 |
| | Total CPFF | $1,016 | $1,588 | $388 | $0 | $0 | $0 | $2,992 |
All Total CPFF $1,016 $1,588 $388 $0 $0 $0 $2,992
GRAND TOTAL All $22,192 $35,175 $16,872 $47,961 $63,476 $45,857 $231,532
Labor Resources
| PRIME LABOR RESOURCES AND COST | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| Contractor: | Insert contractor name | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| HQ0147-16-R-0017 - Agency Advisory and Analytical Support | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| The prime offeror will combine their labor resources with submittals from all IWTAs and subcontractors on this one tab. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| Contractors will populate this tab to include the proposed contractor labor resources for all CLINs excluding Surge. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| FBLRs are carried forward (linked) from the prime, IWTA, or subcontractor's FBLR tab. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| To protect proprietary data, the IWTA or subcontractor may elect to copy the FBLRs in columns V:AA and paste as values before submission to the prime contractor, with the result that the IWTA or major subcontractor rates may be hard-coded in the prime offeror’s EPW. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| For submission to the Government, the full detail of the IWTA or subcontractor direct/indirect rates and FBLR rates, and links to the IWTA's or subcontractor's FBLR tab will remain in-tact. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| The prime contractor will also add hours and cost for minor subcontractors TBD. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| Columns B through I, M through R, and T should be populated by the offeror, to present the proposed resources for accomplishing the PWS requirements. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| The example data provided in Columns B through I, M through R, and T are there only for formula and link testing and should not influence the proposed EPW. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | |
| The total proposed labor hours for each CLIN, as listed in Columns M through R, must match the RFP-specified hours listed by CLIN in Section B of the RFP. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 5.00% | << Prime's procurement Overhead Rate | | | | |
| Columns AS through BO are used to apply Prime offeror burdens to calculate Surge and FMS Labor Rates. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | 5.00% | << Prime's procurement Overhead Rate | | | | |
| For Columns AS through BO, Offerors, IWTAs and major subcontractors must correct and tailor to eliminate errors and to conform to their estimating and accounting systems so that each rate/factor calculation uses the correct allocation base. | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | | Subcontractor fee, not prime offeror or IWTA | | | | | | | | Prime offeror procurement overhead on subcontract cost | | | | | |
| Use the drop-down arrows to populate the cells where possible. | | | | | | | | | | | | | | | | | | | | | 9 | 18 | 27 | 36 | 45 | 54 | | | | | | | | | | | | | | | | | | | | | | | |
| PWS | Description | Prime/Subcontractor Name | Prime, IWTA or Subcontractor | Major or Minor | Labor Category | Location | Work Site | CLIN-Pd-ST | Stakeholder | CLIN | Period | CFY 1 Hours | CFY 2 Hours | CFY 3 Hours | CFY 4 Hours | CFY 5 Hours | CFY 6 Hours | Total | BOE Reference | Index Column | CFY 1 FBLR | CFY 2 FBLR | CFY 3 FBLR | CFY 4 FBLR | CFY 5 FBLR | CFY 6 FBLR | AB | CFY 1 Cost | CFY 2 Cost | CFY 3 Cost | CFY 4 Cost | CFY 5 Cost | CFY 6 Cost | Total Cost | AJ | CFY 1 Fee | CFY 2 Fee | CFY 3 Fee | CFY 4 Fee | CFY 5 Fee | CFY 6 Fee | Total Fee | AR | CFY 1 P/O | CFY 2 P/O | CFY 3 P/O | CFY 4 P/O | CFY 5 P/O | CFY 6 P/O |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Contract Program Manager | Hanscom AFB Massachusetts | Gov't Site | 0006-1BaseBC-TI0001 | BC-TI0001 | 0006-1 | Base | 80 | 100 | 20 | | | | 200 | Cost Volume page 10, BOE Number 123456.01 | Contract Program ManagerHanscom AFB MassachusettsGov't Site | $17.42 | $20.33 | $23.44 | $26.37 | $29.30 | $29.30 | | $1,394 | $2,033 | $469 | $0 | $0 | $0 | $3,896 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Contract Technical Lead | Colorado Springs, Colorado | Gov't Site | 0008-1BaseDE-TI0001 | DE-TI0001 | 0008-1 | Base | 80 | 100 | 20 | | | | 200 | | Contract Technical LeadColorado Springs, ColoradoGov't Site | $8.71 | $11.62 | $14.65 | $17.58 | $20.51 | $20.51 | | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | BMDS Subject Matter Expert (SME) | Dahlgren, Virginia | Gov't Site | 0008-2BaseDE-TI0002 | DE-TI0002 | 0008-2 | Base | 80 | 100 | 20 | | | | 200 | | BMDS Subject Matter Expert (SME)Dahlgren, VirginiaGov't Site | $10.16 | $13.07 | $16.12 | $19.05 | $21.98 | $21.98 | | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Advanced SME | Huntsville, Alabama | Gov't Site | 0008-3BaseDE-TI0003 | DE-TI0003 | 0008-3 | Base | 80 | 100 | 20 | | | | 200 | | Advanced SMEHuntsville, AlabamaGov't Site | $11.62 | $14.52 | $17.58 | $20.51 | $23.44 | $23.44 | | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Intermediate SME | Kirtland AFB, New Mexico | Gov't Site | 0008-4BaseDE-TI0004 | DE-TI0004 | 0008-4 | Base | 80 | 100 | 20 | | | | 200 | | Intermediate SMEKirtland AFB, New MexicoGov't Site | $8.71 | $11.62 | $14.65 | $17.58 | $20.51 | $20.51 | | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Basic SME | National Capital Region Washington, DC | Gov't Site | 0008-5BaseDE-TI0005 | DE-TI0005 | 0008-5 | Base | 80 | 100 | 20 | | | | 200 | | Basic SMENational Capital Region Washington, DCGov't Site | $11.62 | $14.52 | $17.58 | $20.51 | $23.44 | $23.44 | | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Technical Writer | Hanscom AFB Massachusetts | Gov't Site | 0008-6BaseDE-TI0006 | DE-TI0006 | 0008-6 | Base | 80 | 100 | 20 | | | | 200 | | Technical WriterHanscom AFB MassachusettsGov't Site | $11.62 | $14.52 | $17.58 | $20.51 | $23.44 | $23.44 | | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Contract Program Manager | Colorado Springs, Colorado | Gov't Site | 0008-7BaseDE-TI0007 | DE-TI0007 | 0008-7 | Base | 80 | 100 | 20 | | | | 200 | | Contract Program ManagerColorado Springs, ColoradoGov't Site | $10.16 | $13.07 | $16.12 | $19.05 | $21.98 | $21.98 | | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Contract Technical Lead | Dahlgren, Virginia | Gov't Site | 0008-8BaseDE-TI0008 | DE-TI0008 | 0008-8 | Base | 80 | 100 | 20 | | | | 200 | | Contract Technical LeadDahlgren, VirginiaGov't Site | $11.62 | $14.52 | $17.58 | $20.51 | $23.44 | $23.44 | | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | BMDS Subject Matter Expert (SME) | Huntsville, Alabama | Gov't Site | 0008-9BaseDE-TI0009 | DE-TI0009 | 0008-9 | Base | 80 | 100 | 20 | | | | 200 | | BMDS Subject Matter Expert (SME)Huntsville, AlabamaGov't Site | $8.71 | $11.62 | $14.65 | $17.58 | $20.51 | $20.51 | | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Advanced SME | Kirtland AFB, New Mexico | Gov't Site | 0008-10BaseDE-TI0010 | DE-TI0010 | 0008-10 | Base | 80 | 100 | 20 | | | | 200 | | Advanced SMEKirtland AFB, New MexicoGov't Site | $10.16 | $13.07 | $16.12 | $19.05 | $21.98 | $21.98 | | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Intermediate SME | National Capital Region Washington, DC | Gov't Site | 0009-1BaseDEI-TI0001 | DEI-TI0001 | 0009-1 | Base | 80 | 100 | 20 | | | | 200 | | Intermediate SMENational Capital Region Washington, DCGov't Site | $11.62 | $14.52 | $17.58 | $20.51 | $23.44 | $23.44 | | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Basic SME | Hanscom AFB Massachusetts | Gov't Site | 0013-1BaseDV-TI0001 | DV-TI0001 | 0013-1 | Base | 80 | 100 | 20 | | | | 200 | | Basic SMEHanscom AFB MassachusettsGov't Site | $11.62 | $14.52 | $17.58 | $20.51 | $23.44 | $23.44 | | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Technical Writer | Colorado Springs, Colorado | Gov't Site | 0018-1BaseGM-TI0001 | GM-TI0001 | 0018-1 | Base | 80 | 100 | 20 | | | | 200 | | Technical WriterColorado Springs, ColoradoGov't Site | $10.16 | $13.07 | $16.12 | $19.05 | $21.98 | $21.98 | | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Contract Program Manager | Dahlgren, Virginia | Gov't Site | 0018-2BaseGM-TI0002 | GM-TI0002 | 0018-2 | Base | 80 | 100 | 20 | | | | 200 | | Contract Program ManagerDahlgren, VirginiaGov't Site | $8.71 | $11.62 | $14.65 | $17.58 | $20.51 | $20.51 | | $697 | $1,162 | $293 | $0 | $0 | $0 | $2,152 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Contract Technical Lead | Huntsville, Alabama | Gov't Site | 0020-1BaseDA-TI0002 | DA-TI0002 | 0020-1 | Base | 80 | 100 | 20 | | | | 200 | | Contract Technical LeadHuntsville, AlabamaGov't Site | $10.16 | $13.07 | $16.12 | $19.05 | $21.98 | $21.98 | | $813 | $1,307 | $322 | $0 | $0 | $0 | $2,442 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | BMDS Subject Matter Expert (SME) | Kirtland AFB, New Mexico | Gov't Site | 0023-1BaseTH-TI0001 | TH-TI0001 | 0023-1 | Base | 80 | 100 | 20 | | | | 200 | | BMDS Subject Matter Expert (SME)Kirtland AFB, New MexicoGov't Site | $11.62 | $14.52 | $17.58 | $20.51 | $23.44 | $23.44 | | $929 | $1,452 | $352 | $0 | $0 | $0 | $2,733 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Advanced SME | National Capital Region Washington, DC | Contractor Site | 0027-1BaseDT-TI0001 | DT-TI0001 | 0027-1 | Base | 80 | 100 | 20 | | | | 200 | | Advanced SMENational Capital Region Washington, DCContractor Site | $12.10 | $15.13 | $18.46 | $21.54 | $24.62 | $24.62 | | $968 | $1,513 | $369 | $0 | $0 | $0 | $2,850 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Intermediate SME | Hanscom AFB Massachusetts | Contractor Site | 0027-2BaseDT-TI0002 | DT-TI0002 | 0027-2 | Base | 80 | 100 | 20 | | | | 200 | | Intermediate SMEHanscom AFB MassachusettsContractor Site | $8.78 | $11.71 | $14.77 | $17.73 | $20.85 | $20.85 | | $703 | $1,171 | $295 | $0 | $0 | $0 | $2,170 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Basic SME | Colorado Springs, Colorado | Contractor Site | 0027-3BaseDT-TI0003 | DT-TI0003 | 0027-3 | Base | 80 | 100 | 20 | | | | 200 | | Basic SMEColorado Springs, ColoradoContractor Site | $10.59 | $13.61 | $16.92 | $20.00 | $23.08 | $23.08 | | $847 | $1,361 | $338 | $0 | $0 | $0 | $2,547 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Technical Writer | Dahlgren, Virginia | Contractor Site | 0027-4BaseDT-TI0004 | DT-TI0004 | 0027-4 | Base | 80 | 100 | 20 | | | | 200 | | Technical WriterDahlgren, VirginiaContractor Site | $11.71 | $14.64 | $17.73 | $20.68 | $23.83 | $23.83 | | $937 | $1,464 | $355 | $0 | $0 | $0 | $2,756 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Contract Program Manager | Huntsville, Alabama | Contractor Site | 1006-1Option 1BC-TI0001 | BC-TI0001 | 1006-1 | Option 1 | | | 20 | 80 | | | 100 | | Contract Program ManagerHuntsville, AlabamaContractor Site | $12.10 | $15.13 | $18.46 | $21.54 | $24.62 | $24.62 | | $0 | $0 | $369 | $1,723 | $0 | $0 | $2,092 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Contract Technical Lead | Kirtland AFB, New Mexico | Contractor Site | 1008-1Option 1DE-TI0001 | DE-TI0001 | 1008-1 | Option 1 | | | 20 | 80 | | | 100 | | Contract Technical LeadKirtland AFB, New MexicoContractor Site | $11.71 | $14.64 | $17.73 | $20.68 | $23.83 | $23.83 | | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | BMDS Subject Matter Expert (SME) | National Capital Region Washington, DC | Contractor Site | 1008-2Option 1DE-TI0002 | DE-TI0002 | 1008-2 | Option 1 | | | 20 | 80 | | | 100 | | BMDS Subject Matter Expert (SME)National Capital Region Washington, DCContractor Site | $18.15 | $21.18 | $24.62 | $27.69 | $30.77 | $30.77 | | $0 | $0 | $492 | $2,215 | $0 | $0 | $2,708 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Advanced SME | Hanscom AFB Massachusetts | Contractor Site | 1008-3Option 1DE-TI0003 | DE-TI0003 | 1008-3 | Option 1 | | | 20 | 80 | | | 100 | | Advanced SMEHanscom AFB MassachusettsContractor Site | $10.25 | $13.18 | $16.25 | $19.21 | $22.34 | $22.34 | | $0 | $0 | $325 | $1,537 | $0 | $0 | $1,862 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Intermediate SME | Colorado Springs, Colorado | Contractor Site | 1008-4Option 1DE-TI0004 | DE-TI0004 | 1008-4 | Option 1 | | | 20 | 80 | | | 100 | | Intermediate SMEColorado Springs, ColoradoContractor Site | $12.10 | $15.13 | $18.46 | $21.54 | $24.62 | $24.62 | | $0 | $0 | $369 | $1,723 | $0 | $0 | $2,092 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.2 | 3.2 BMDS Test Assessments and Recommendations | Prime R Us | Prime | | Basic SME | Dahlgren, Virginia | Contractor Site | 1008-5Option 1DE-TI0005 | DE-TI0005 | 1008-5 | Option 1 | | | 20 | 80 | | | 100 | | Basic SMEDahlgren, VirginiaContractor Site | $11.71 | $14.64 | $17.73 | $20.68 | $23.83 | $23.83 | | $0 | $0 | $355 | $1,655 | $0 | $0 | $2,009 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
| 3.1 | 3.1 BMDS Acquisition, Programmatic, Strategic Planning, and Engineering Technical Assessments and Recommendations | Prime R Us | Prime | | Technical Writer | Huntsville, Alabama | Contractor Site | 1008-6Option 1DE-TI0006 | DE-TI0006 | 1008-6 | Option 1 | | | 20 | 80 | | | 100 | | Technical WriterHuntsville, AlabamaContractor Site | $9.08 | $12.10 | $15.38 | $18.46 | $21.54 | $21.54 | | $0 | $0 | $308 | $1,477 | $0 | $0 | $1,785 | | $0 | $0 | $0 | $0 | $0 | $0 | $0 | | $0 | $0 | $0 | $0 | $0 | $0 |
This is the start of the file's text. The full file is on GovTribe.