CLIN Type Requirement Description PWS Section Base Period Option 1 Option 2 Option 3 Option 4 6- month extension
| CLIN 1 | FFP | Task 1: Preventative Maintenance Services Monthly figure | 6.1 | | | | | | $0.00 |
| | (calculated by 12 months and evaluated on a yearly price) | | 12 | 12 | 12 | 12 | 12 | 6 |
| | | CLIN Annual Subtotal: | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| CLIN 2 | FFP | Task 2: Unscheduled (Emergency) Maintenance & Repair (24x7) - quote at the individual service call level - quote fully burdened labor rate IAW the Scenario provided in Attachment 2 | 6.2 | | | | | | |
| | Service Call each | | | | | | | $0.00 |
| | ***evaluated by 1 service call | CLIN Annual Ceiling: | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 10,000.00 | $ 5,000.00 |
| CLIN 3 | FFP | Task 3: Unscheduled maintenance - Bid fully burdened labor rate IAW the Scenario provided in Attachment 2 | 6.3 | | | | | | |
| | **potential materials/equipment are identified in the Site Equipment List (attachment to the PWS) | | | | | | | |
| | Core hour rate | | | | | | | $0.00 |
| | **** evaluated by 10 hours times the quoted labor rate | CLIN Annual Ceiling: | $16,000.00 | $16,000.00 | $16,000.00 | $16,000.00 | $16,000.00 | $8,000.00 |
| CLIN 4 | FFP | Task 4: Capacitor Replacement- quote fully burdened labor rate IAW the PWS and Table 1 | 6.4 |
| | **potential materials/equipment are identified in the Table 1 (attachment to the PWS). Provide breakout for all equipment/ material in quote | |
| | Total Price of the replacement | CLIN Annual Subtotal: |
| CLIN 5 | OPTIONAL FFP | Task 5: OPTIONAL -DC Power Plant Battery Replacement- quote fully burdened labor rate IAW the PWS and Table 1 | 6.5 |
| | **potential materials/equipment are identified in the Table 1 (attachment to the PWS). Provide breakout for all equipment/ material in quote | |
| | Total price of the replacement | CLIN Annual Subtotal: |
| Total Evaluated Price/ option year | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| Total Evaluated Price of all options | $0.00 | | | | | |
| *FOR EVALUATION PURPOSES ONLY. PROVIDE PRICING FOR OPTIONAL 6-MO EXTENSION AUTHORIZED IAW FAR 52.217-8 (CLIN(S) WILL NOT APPEAR ON CONTRACT. ASSUME ALL PREVIOUS OPTION PERIODS HAVE BEEN EXERCISED.) THE "6 MONTH OPTION" IS AUTO-CALCULATED TO BE HALF OF THE OPTION PERIOD 4 ANNUAL AMOUNT. | | | | | | | |
| *** Evaluated Price will be different than the Contract Lifecycle and CLIN pricing. CLINs 2 and 3 will be priced at their ceiling values while they are evaluated IAW with their individual evaluation methods described above. | | | | | | | |