RFP_QA_HC102818R0102_Armed_Guards.pdf

PDF 49 KB Posted

Attached to
DISA Armed Guards Federal contract opportunity
Solicitation number
HC102818R0102
Issued by
Defense Information Systems Agency

View the file

Other files for this federal contract opportunity

Other files attached to DISA Armed Guards, newest first.
File Type Posted
RFP_QA_HC102818R0102_Armed_Guards_4.pdf PDF
RFP_QA_HC102818R0102_Armed_Guards_3.pdf PDF
RFP_QA_HC102818R0102_Armed_Guards_2.pdf PDF
Attach_6_NDA.docx DOCX document
Attach_2_Solicitation_DD254.pdf PDF
Attach_3_Pricing_Spreadsheet.xlsx XLSX spreadsheet
Attach_1_QASP.docx DOCX document
RFP_HC102818R0102.docx DOCX document
Attach_4_Eval_Table.doc DOC document
Attach_5_Past_Performance_References.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP HC102818R0102 Armed Guards Questions and Answers

1. Will DISA sponsor a contractor for their FCL under this solicitation?

RESPONSE: The SOW requires contractors to have a Final Secret FCL to work this contract. Since it has been taking over a year to get final FCL we cannot accept vendor’s without already having a final clearance.

2. Is this a new opportunity or follow on contract? If this is a follow on, what is the incumbent contract number and who is the incumbent? What is the total value of the current contract if this is a follow-on contract?

RESPONSE: This is a new requirement for the DISA ecosystem restructure.

3. Will the government be sponsoring a company for the secret clearance as required in this RFP?

RESPONSE: The SOW requires contractors to have a Final Secret FCL to work this contract. Since it has been taking over a year to get final FCL we cannot accept vendor’s without already having a final clearance.

4. The base PoP says 1 June 2019 - 31 May 2020 however your proposal closing date is 2 October 2018. Is this PoP correct and you will expect any offerors to honor a proposal acceptance period 9 month from submission? Or will the PoPs be adjusted with an earlier award decision?

RESPONSE: The RFP PoP is correct.

5. Your clause at 52.232-19, Availability of Funds for the Next Fiscal Year is incomplete. Can you please advise of these "fill-in" dates.

RESPONSE: The fill-in dates are To Be Determined