Attachment_2_Pricing_Sheet_HC102817R0078_7272017.xls
XLS spreadsheet 55 KB Posted
- Attached to
- Enterprise-Wide Integrated Security System Operations and Maintenance (O&M) Services Federal contract opportunity
- Solicitation number
- HC102817R0078
- Issued by
- Defense Information Systems Agency
About this file
changed future site to warner robins
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Atch 2 Pricing Sheet
| Attachment 2 HC102817R0078 Revised 7/14/2017 | ||||||||
| Pricing Sheet Enterprise-Wide Integrated Security Systems | ||||||||
| Sub-CLIN / CLIN | X001 Preventive Maintenance (PM) | X002 Emergent Service Calls | X003 Routine Service Calls | X004 Realign, Adds, Mods | Hourly rates for CLINs X002, X003 and X004 | Grand total of all CLINS for the period of performance | ||
| Base Year | ||||||||
| (Oct 2017- Sep 2018) | Denver | |||||||
| Mechanicsburg | ||||||||
| Montgomery | ||||||||
| Ogden | ||||||||
| Oklahoma City | ||||||||
| St. Louis | ||||||||
| San Antonio | ||||||||
| Warner Robins | ||||||||
| Total for Base Year | ||||||||
| Option Year 1 | ||||||||
| (Oct 2018 - Sep 2019) | Denver | |||||||
| Mechanicsburg | ||||||||
| Montgomery | ||||||||
| Ogden | ||||||||
| Oklahoma City | ||||||||
| St. Louis | ||||||||
| San Antonio | ||||||||
| Warner Robins, GA | ||||||||
| Total for Option Yr 1 | ||||||||
| Option Year 2 | ||||||||
| (Oct 2019 - Sep 2020) | Denver | |||||||
| Mechanicsburg | ||||||||
| Montgomery | ||||||||
| Ogden | ||||||||
| Oklahoma City | ||||||||
| St. Louis | ||||||||
| Warner Robins GA | ||||||||
| Total for Option Yr 2 | ||||||||
| Option Year 3 | ||||||||
| (Oct 2020 - Sep 2021) | Denver | |||||||
| Mechanicsburg | ||||||||
| Montgomery | ||||||||
| Ogden | ||||||||
| Oklahoma City | ||||||||
| St. Louis | ||||||||
| San Antonio | ||||||||
| Warner Robins, GA | ||||||||
| Total for Option Yr 3 | ||||||||
| Option Year 4 | ||||||||
| (Oct 2021 - Sep 2022) | Denver | |||||||
| Mechanicsburg | ||||||||
| Montgomery | ||||||||
| Ogden | ||||||||
| Oklahoma City | ||||||||
| St. Louis | ||||||||
| San Antonio | ||||||||
| Warner Robins, GA | ||||||||
| Total for Option Yr 4 | ||||||||
| Grand total of Base/4 option periods | ||||||||
| Sub-CLIN / CLIN | X001 Preventive Maintenance (PM) | X002 Emergent Service Calls | X003 Routine Service Calls | X003 Realign, Adds, Mods | Hourly rates for CLINs X002, X003 and X004 | Grand total for all CLINS | ||
| Six-Month Extension (In accordance with Clause 52.217-8) | ||||||||
| (Oct 2022 - Mar 2023) | Denver | |||||||
| Mechanicsburg | ||||||||
| Montgomery | ||||||||
| Ogden | ||||||||
| Oklahoma City | ||||||||
| St. Louis | ||||||||
| San Antonio | ||||||||
| Warner Robins, GA | ||||||||
| Total cost for 6 months | ||||||||
| Grand total of 6 month period. | ||||||||
| Grand Total Base/4 option periods and the 6 month extension. | ||||||||
| Technical Requirement (TR) Scenario | TR secenario total price for each location | A separate quote shall be submitted with pricing details which shall be the offeror's quote. | ||||||
| Denver | ||||||||
| Mechanicsburg | ||||||||
| Montgomery | ||||||||
| Ogden | ||||||||
| Oklahoma City | ||||||||
| St. Louis | ||||||||
| San Antonio | ||||||||
| Warner Robins, GA | ||||||||
| Total cost for TR Scenario | $ | Grand total base/4 option periods, the 6 months extension and the TR scenario | $ | (evaluated price) |
IGCE Future Site
| Future Datacenter | |||
| Equipment Upgrade: | Qty | Unit Cost Installed | Total Cost |
| CCTV System | |||
| Motion Sensitive IP Cameras | 60 | $2,500.00 | $150,000.00 |
| DVR | 1 | $35,000.00 | $35,000.00 |
| Monitors | 4 | $1,200.00 | $4,800.00 |
| Port Switch | 4 | $2,000.00 | $8,000.00 |
| ISS Server | 2 | $15,000.00 | $30,000.00 |
| Workstations | 4 | $3,500.00 | $14,000.00 |
| Cabling, Connectors & Conduit (lump sum) | 1 | $75,000.00 | $75,000.00 |
| ACS System | |||
| Card Readers & components | 75 | $2,000.00 | $150,000.00 |
| Scramble Pad Reader & Components | 16 | $2,400.00 | $38,400.00 |
| Magnetic Locks | 20 | $500.00 | $10,000.00 |
| Electric Strikes | 50 | $200.00 | $10,000.00 |
| Combination X-10 Locks | 6 | $2,000.00 | $12,000.00 |
| Badging software & printer | 2 | $8,500.00 | $17,000.00 |
| Badge Camera System | 1 | $5,000.00 | $5,000.00 |
| Smart Card Encoder/Printer/Test reader | 1 | $1,500.00 | $1,500.00 |
| Biometrics & Signature Capture Pads | 2 | $1,500.00 | $3,000.00 |
| Access Monitors | 4 | $800.00 | $3,200.00 |
| KVM Head-End Router | 2 | $2,600.00 | $5,200.00 |
| Cabling, conduit & connectors (Lump Sum) | 1 | $75,000.00 | $75,000.00 |
| Power Distribution and connections (LS) | 1 | $35,000.00 | $35,000.00 |
| Public Address System with Aiphone stations | 1 | $15,000.00 | $15,000.00 |
| Smart Card Encoder/Printer/Test reader | 400 | $5.50 | $2,200.00 |
| IDS System | |||
| Sensors, glass-break | 20 | $65.00 | $1,300.00 |
| Motion Sensors, 360-degree | 60 | $100.00 | $6,000.00 |
| Strobe Lights & associated switches | 15 | $280.00 | $4,200.00 |
| Alarm Detection Monitors/Controllers | 20 | $200.00 | $4,000.00 |
| Arm/Dis-arm Panels on Security Zones | 20 | $300.00 | $6,000.00 |
| Distress Alarm Buttons | 6 | $165.00 | $990.00 |
| Cabling, conduit & connectors (lump sum) | 1 | $75,000.00 | $75,000.00 |
| Equipment & Material Sub-Total: | $796,790.00 | ||
| Labor: | |||
| Government | N/A | $0.00 | |
| Contractor | Installation, Testing & Training | $500,000.00 | |
| Travel: | |||
| Government | N/A | $0.00 | |
| Contractor | N/A | $0.00 | |
| Direct Cost Sub-Total: | $1,296,790.00 | ||
| Other Costs: | |||
| Engineering Design 10% | $129,679.00 | ||
| Contractor OH&P 15% | $194,518.50 | ||
| Contingency 5% | $64,839.50 | ||
| Security Escorts (8 month project support) | $25,000.00 | ||
| Contracting Fees: (Direct + Indirect costs) | |||
| Indirect Sub-Total: | $414,037.00 | ||
| Total Cost Estimate: | $1,710,827.00 |