IQO INQUIRY

FM: PL8211

TO: Contractors

DATE (MM/DD/YYYY): 6/7/2018

SUBJECT: HC101318QB031-0001 Amend: 0001

A. TYPE ACTION: ADMIN AMEND

1. PURPOSE: *** The purpose of amend 0001 is to update the proposal due date, the service date and to add the following reaward language.

THIS IS A REAWARD OF A CURRENT SERVICE, (CSA: CTLL 000060EBM ). IF THE

INCUMBENT QUOTE IS EVALUATED AS THE LOWEST PRICE TECHNICABLLY ACCEPTABLE,

THE CURRENT CSA WILL BE ADMINISTRATIVELY DISCONTINUED WITHIN 30 DAYS OF

INCUMBENT CONTRACTOR RECEIVING AWARD. INCUMBENT CONTRACTORS SHALL

SUBMIT NOTICE OF COMPLETION (NOC) WITHIN 30 DAYS.

All else remains unchanged.***

1. A. SUMBIT QUOTE TO PROVIDE, INSTALL AND MAINTAIN A 10GB WAVE SERVICE

BETWEEN BLDG 1645,

ROOM 10 (SWITCH ROOM), 1645 RANDOLPH ROAD, FORT SILL, OK., AND BLDG 200,

COMPUTER ROOM #2, 3326

GENERAL HUDNELL DRIVE, SAN ANTONIO, TX.

-CONTRACTORS SHALL MEET RTD OF 10 MILLISECONDS. SEE UNIQUE INSTALL FACTORS.

VENDORS MUST CLEARLY STATE IN QUOTES THEIR COMPLIANCE WITH GOVERNMENT

TESTING AND ACCEPTANCE REQUIREMENTS

2. ESTABLISH TSP.

3. THIS REQUIREMENT MUST BE WORKED IN CONJUNCTION WITH SOLICITATION

HC101318QB030 /TSR SG13APR185824 AND MUST BE ENGINEERED AND PROVISIONED

TOTALLY DIVERSE END TO END FROM THE GOVERNMENT SERVICE DELIVERY POINTS

(SDP) FROM TSR SG13APR185824; MEANING THE PHYSICAL PATHS ARE TOTALLY

SEPARATE INCLUDING MAN HOLES, CONDUIT, CENTRAL OFFICE LOCATIONS, AND FIBER

BUILDS. ADDITIONALLY AS A MINIMUM MUST HAVE 50 METERS PHYSICAL SEPARATION

FROM TSR SG13APR185824.

4. EACH CONTRACTOR IS RESPONSIBLE FOR READING AND COMPLYING WITH ALL

TECHNICAL ASPECTS OF THIS SOLICITATION, TO INCLUDE READING AND AGREEING

WITH THE STANDARD PROVISIONS, ATTACHMENTS LISTING SPECIFIC TECHNICAL

REQUIREMENTS, PRICE QUOTE REQUIREMENTS, AND REQUESTED SERVICE DATE.

FAILURE TO READ AND ADHERE TO ANY PORTION OF THE INQUIRY SHALL RENDER THE

HC101318QB031-0001

QUOTE NON-COMPLIANT AND RESULT IN IT BEING EXCLUDED FROM EVALUATION AND

AWARD.

5. THE SERVICE DATE TO BE MET IS: 26 NOV 18 (SIP). THE GOVERNMENT ASSUMES

THAT CONTRACTORS HAVE CONSIDERED ALL ISSUES THAT MAY IMPACT THE SERVICE

DATE. THE GOVERNMENT MAY CANCEL, TERMINATE, OR REQUEST CONSIDERATION

IAW STANDARD PROVISION 42 FOR FAILURE TO MEET CONTRACTUAL SERVICE DATE OR

COMPLY WITH ANY CONTRACT TERMS OR CONDITIONS.

6. CONTRACTORS SHALL SUBMIT QUOTES IAW STANDARD PROVISION 04.

QUOTES SHALL INCLUDE SUFFICIENT DETAIL FOR EFFECTIVE EVALUATION AND SHOULD

NOT SIMPLY REPHRASE OR RESTATE THE GOVERNMENT REQUIREMENTS. RATHER,

THEY MUST PROVIDE CONVINCING RATIONALE TO ADDRESS HOW THE CONTRACTOR

INTENDS TO MEET THE REQUIREMENT. IN RESPONSE TO THIS SOLICITATION, NO

TERMS OR CONDITIONS PLACED UPON THE GOVERNMENT, NOR ASSUMPTIONS WILL BE

ACCEPTED. CONTRACTORS ARE ENCOURAGED TO SUBMIT QUESTIONS AND REQUEST

CLARIFICATIONS OF THE REQUIREMENT (S) BEFORE SUBMITTING QUOTES. QUESTIONS

SHALL BE SUBMITTED TO CONTRACT SPECIALIST AND CONTRACTING OFFICER DURING

THE SOLICITATION PHASE ONLY, AND RESPONSES FOR ALL INTERESTED PARTIES WILL BE

POSTED TO FEDBIZOPPS. QUOTES MUST BE UPLOADED TO IDEAS.

7. CONTRACTOR SHALL PROVIDE COLOR POWERPOINT DRAWINGS SHOWING THE ROUTES

FROM THE COMMERCIAL DEMARKS TO THE SUPPORTING CENTRAL OFFICES AND/OR

WIRING CENTERS, ENSURING THE PHYSICAL END TO END DIVERSITY REQUIREMENTS ARE

BEING MET. DRAWINGS MUST INCLUDE SEPARATION DISTANCES, TOTAL FIBER MILES

AND ROUND TRIP DELAY BASED ON ACTUAL DISTANCE IN MILES. REFER TO STANDARD

PROVISION 39 FOR SPECIFIC DOCUMENTATION REQUIREMENTS. SAMPLE DRAWINGS ARE

INCLUDED THE ATTACHMENTS.

8. WAVE SERVICE TESTING MUST BE COORDINATED WITH CUSTOMER ACCEPTANCE

AUTHORITY AT BOTH LOCATIONS BEFORE NOTICE OF COMPLETION IS SUBMITTED

TO DITCO. FOR DISA WAVE REQUIREMENTS THE ACCEPTING AUTHORITY IS:MICHAEL

REEVES, MICHAEL.B.REEVES.CTR@MAIL.MIL (618) 220-8973 OR CLARENCE

MOORE, CLARENCE.S.MOORE.CTR@MAIL.MIL, (618) 220-9935 DISA CONUS/

D312-770-8691,C618-220-8691

9. COMPLETION REPORT: SERVICE WILL BE ACCEPTED ON BEHALF OF THE U.S.

GOVERNMENT BY DISA CONUS/D770-8691,C618-220-8691 WHO WILL SUBMIT A COMPLETION

REPORT IAW DISAC 310-130-1, CHAP 2 OF DISAC 310-70-1, CHAP 8. REPORT WILL BE

ADDRESSED TO THE ORGINATOR AND ALL ADDRESSEES OF THIS TSO. IMPLEMENTATION

ASSISTANCE: FOR DISN CORE CIRCUIT ACTIVATION ASSISTANCE OR SERVICE

IMPLEMENTATION INQUIRIES/SCHEDULING, CONTACT DISA CONUS DISN CORE

IMPLEMENTATION TEAM AT DSN 312-770-8751; COML 618-220-8751.. SINGLE MODE FIBER

MUST BE ENGINEERED/PROVISIONED IN SUCH A WAY THAT THE GOVERNMENT CAN

CHANGE/REVISE CHANNELIZATION WITHOUT TELECOMM PROVIDER INTERVENTION. A.

NOTE 1 (JITTER).: IN A STEADY-STATE CONDITION, THE PATTERN OF SYNCHRONOUS

TRANSPORT SIGNAL (STS) POINTER ADJUSTMENTS, SDN TO SDN (END-TO-END THROUGH

THE SERVICE PROVIDED NETWORK OUTPUTS), SHALL BE NO MORE STRESSFUL (I.E.,

CREATE MORE JITTER THROUGH THE DESYNCHRONIZER AS DESCRIBED IN TABLE 6 OF

ANSI T1.105.03-1994) THAN THE POINTER ADJUSTMENT SEQUENCE IN FIGURE 5 OF ANSI

T1.105.03-1994. DURING TRANSIENT EVENTS (WHICH SHALL OCCUR NO MORE THAN 2

TIMES PER DAY), THE PATTERN OF STS POINTER ADJUSTMENTS, SDN TO SDN (END-

TO-END THROUGH THE SERVICE PROVIDED NETWORK OUTPUTS), SHALL BE FOUR OR

LESS PER HOUR. ADDITIONALLY, THE MAXIMUM TIME INTERVAL ERROR (MTIE) OVER A

PERIOD OF S SECONDS, OR WANDER, SHALL NOT EXCEED (.01S + 10000) NANOSECONDS

FOR VALUES OF S GREATER THAN 10,000. B. WAVELENGTH TRANSMISSION SERVICES:

WAVELENGTH TRANSMISSION SERVICES FOR RATES OF 10GBPS SHALL BE IN

ACCORDANCE WITH ITU-T RECOMMENDATIONS G.709(03/2003), G.707(12/03), G.957(03/06), G.692(10/98) & TELCORDIA GR253-IE4. THE PROVIDED WAVELENGTH TRANSMISSION

SERVICE SHALL NOT INHIBIT GOVERNMENT OPERATION OFUNDERLYING PROTOCOLS

AND TRANSPORT SYSTEMS SUCH AS, BUT NOT LIMITED TO, SONET/SDH, IP, ATM,

GIGABIT ETHERNET, AND ENCRYPTION. THE WAVELENGTH TRANSMISSION SERVICE

PROVIDED SHALL PASS ALL PAYLOAD, PATH AND LINE OVERHEAD BYTETRANSPARENTLY

(UNTOUCHED/UNALTERED) AND WITHOUT MONITORING SDP TO SDP. THERE SHALL NOT

BE ANY LINE TERMINATING EQUIPMENT (LTE) BETWEEN SDP AND SDP.

ONCE TELECOMM PROVIDER HAS COMPLETED INSIDE WIRING FROM THE DWDM

EQUIPMENT SUITE TO THE GOVERNMENT SERVICE DELIVERY POINT (SDP) AT EACH

LOCATION, THEY MUST ENSURE THE LIGHT LEVEL READINGS (DB LOSS) ARE ADJUSTED

TO READ -3 TO -9 LOSS. ADDITIONALLY, THESE LEVELS MUST BE DOCUMENTED ON THE

NOTICE OF COMPLETION (NOC) SENT TO DITCO 2. CIRCUIT REQUIRES THE FOLLOWING

PARAMETERS: (A) FIBER TERMINATION: SINGLE-MODE INTERFACE REQUIREMENT/

INTERFACE DATA RATE: LINE CODING, FRAME FORMAT, PHYSICAL CONNECTOR, 10 GBPS,

NRZ, SCRAMBLED PER ANSI T1.104-1991 (R2003). ALL OPTIONS DEFINED SC CONNECTOR,

SINGLE-MODE FIBER PER ANSI T1.105.06-2002 (SR-0, SR-1, IR-1, IR-2, LR-1, LR-2, LR-3).

M. ADDITIONAL INFORMATION:

3. TSR NUMBER: SG13APR185825

4. CCSD: 69F5

Z. DITCO CONTACT:

Gabriel Zuccarelli gabriel.f.zuccarelli.civ@mail.mil

Angelina Hutson

DITCO Contracting Officer

Unless otherwise specified, all other terms and conditions are unchanged.

Paragraph E.SERVICE DATE change from:

Nov 19, 2018

To:

Nov 26, 2018

Paragraph V.QUOTE DUE DATE AND TIME change from:

Jun 13, 2018 12:30:00 PM CDT

To:

Jun 20, 2018 12:30:00 PM CDT