Building 20 Evaporation Units
Solicitation number
GS-08P-12-JA-C-XXXX
Issued by

About this file

Wage Determination

View the file

Other files

File Type Posted
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Form SF1442 Solicitation.pdf PDF
Agreement.pdf PDF
Solicitation.pdf PDF
Representations and Certifications.pdf PDF
Attachment 01 B20 Evaporation Units SOW.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building 20 Evaporation Units Solicitation GS-08P-12-JA-C-0054

Attachment 2: Wage Determination

General Decision Number: CO120007 07/27/2012 CO7

Superseded General Decision Number: CO20100007

State: Colorado

Construction Type: Building

Counties: Jefferson and Mesa Counties in Colorado.

BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Modification Number Publication Date

0 01/06/2012

1 01/13/2012

2 01/27/2012

3 02/24/2012

4 05/18/2012

5 06/01/2012

6 07/27/2012

BRCO0007-008 01/01/2011

JEFFERSON COUNTY

Rates Fringes

BRICKLAYER.......................$ 22.13 9.89

CARP9901-005 05/01/2009

CARPENTER

All Other Work..............$ 26.60 8.89

ELEC0068-006 06/01/2011

ELECTRICIAN

(Including Low Voltage

Wiring and Installation of

Fire Alarms, Telephones, Communications Systems and

Temperature Controls).......$ 31.60 12.57

ELEC0969-004 06/01/2009

MESA COUNTY

ELECTRICIAN

(Including Low Voltage

Wiring and Installation of Fire Alarms, Telephones, Communications

Systems and Temperature

Controls)...................$ 20.31 8.56

ELEV0025-002 01/01/2012

Elevator Constructor.............$ 39.34 23.535

FOOTNOTE:

a. Employer contributes 8% of basic hourly rate for over 5 years' service and 6% basic hourly rate for 6 months' to 5 years' service as Vacation Pay Credit.

PAID HOLIDAYS: New Year's Day; Memorial Day; Independence

Day; Labor Day; Veterans Day; Thanksgiving Day; Friday after Thanksgiving Day; and Christmas Day.

IRON0024-001 07/01/2011

IRONWORKER, STRUCTURAL...........$ 23.80 10.91

LABO0720-002 05/01/2009

Laborers:

Brick Tender/Finisher.......$ 16.52 6.84

PAIN0079-003 08/01/2010

PAINTER

(Excluding Drywall

Finishing/Taping)...........$ 17.99 6.11

PAIN0930-001 01/01/2012

GLAZIER..........................$ 27.95 7.28

PLAS0577-001 08/01/2011

Cement Mason/Concrete Finisher...$ 23.00 10.75

* PLUM0003-007 07/01/2012

PLUMBER

(Excluding HVAC work).......$ 33.18 11.44

PLUM0145-003 01/01/2011

MESA COUNTY

PLUMBER

(Excluding HVAC work) &

PIPEFITTER (Including

HVAC pipe)..................$ 24.58 10.47

PLUM0208-006 01/01/2012

PIPEFITTER

(Including HVAC pipe).......$ 32.60 11.52

SHEE0009-001 01/01/2011

Sheet metal worker

(Includes HVAC duct and installation of HVAC systems)....................$ 31.66 10.98

SUCO2001-017 12/20/2001

Carpenters:

Acoustical, Drywall

Hanging/ Framing and

Metal Studs.................$ 15.95 1.31

Formbuilding/Formsetting....$ 17.55 3.70

Drywall Finisher/Taper...........$ 14.43

Laborer, common..................$ 10.40 2.62

Mechanical Insulator/Asbestos

Worker

(Includes application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems)....................$ 12.05 .48

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be

July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rate.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007

5/13/2010. SU indicates the rates are not union rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

File details come from the government source that posted it. Updated .