Amendment_0006.pdf
PDF 740 KB Posted
- Attached to
- Building 20 Evaporation Units
- Solicitation number
- GS-08P-12-JA-C-XXXX
About this file
This Amendment is being issued to answer a question that was asked.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0005.pdf | ||
| Amendment 0004.pdf | ||
| Amendment 0003.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Attachment 02 Wage Determination.pdf | ||
| Form SF1442 Solicitation.pdf | ||
| Agreement.pdf | ||
| Solicitation.pdf | ||
| Representations and Certifications.pdf | ||
| Attachment 01 B20 Evaporation Units SOW.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NSN 7540-01-152-8070 STANDARD FORM 30. (Rev. 10-83) Previous Edition unusable Prescribed by GSA FAR (48 CFR) 53.243
Page of Pages AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code
2. AMENDMENT MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (if applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE
(x) 9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
8. NAME AND ADDRESS OF CONTRACTOR (NO., Street, Country, State and ZIP Code)
CODE FACILITY CODE
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning ______ copies of amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OR OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
Check One
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 16B. UNITED STATES OF AMERICA
(Signature of person authorized to sign)
15C. DATE SIGNED
(Signature of Contracting Officer)
16C. DATE SIGNED
Continuation Page
PAGE 2 OF 2 GS-08P-12-JA-C-0054/0006
Continued from Block 14...
This Amendment is being issued to answer the following question:
1) The manufacturer has told us that after we remove the existing evap units, they we need to take measurements of the space, then manufacture the units for proper fit. This means that after removal of the existing units, there will be a 4 week period where there is not evap unit in the air handler, meaning the air handler would be out of operation for 4 weeks. We figure there are three options as a result of this:
Option 1- Remove the evap unit, protect the voided space from weather, and leave the AHU out of operation for 4 weeks. Please keep in mind, this means 6 units would be down for 4 weeks in the base bid.
This would be the cheapest option, but we are not sure if it is feasible to bring these units down as this is an occupied building that might need them.
Option 2- Remove the evap unit, take the measurements, re-install the existing unit. After the new units are manufactured, we then remove the old unit a second time, and install the new one. This would obviously be a substantial cost, as it would require another removal and installation cost (crane included).
Option 3- Remove the evap unit, and provide temporary heating (assuming you do not need cooling for when this project would happen, fall/winter). This would also be a substantial cost to provide temp heating for each unit, for the 4 weeks that it is down.
GOVERNMENT RESPONSE: An overall measurement can be made by the manufacturer to allow them to start fabricating the replacement section. Once they are close to completing the section, the demo can begin. When the section is removed, the manufacturer can take the final measurement for the drain and supply so that a knockout can be made to save time in the field. When dismantling the existing section the bottom or base of that section can be left in place to provide additional protection from the weather. This section would be removed before the new section is placed.
The work will need to be scheduled in conjunction to the laboratory production schedule. This is usually a slow time of year. A two week downtime is probably the most we will be able to get. Once demo has taken place on the first one or two units, production should increase to the point where demo can take place on one unit while dropping in another unit. Depending on the weather and the availability of the new units, there should only be a need for a temporary shut-down of the unit while you are working on it. The unit should be able to be turned back on once you have completed as much work as you could for that day.
Weather proofing- If you choose to remove the entire unit exposing the interior plenum or if you choose to leave the unit base in place, the opening will need to be covered. In the past, the Government has found that plywood and a tarp work well. The air intake will need to be covered as well. The Government suggests using blanket filter media that can be clipped onto the remaining unit. In-case of inclement weather, the opened/covered units should be inspected to divert any accumulation from the unit. The Government suggests daily inspections of the areas below for possible damage.
Descript: Project: Building 20 Evap Units Location: Building 20, Denver Federaal Center, Lakewood, Colorado
...See Continuation Page
| Descript1: |
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT: |
| IDCode: |
| pdfpage1: 1 |
| Pages: 2 |
| DocNo: 0006 |
| EffDate: SEP 24, 2012 |
| ReqNo: 8PSDP-12-0122 |
| ProjNo: |
| IssuedByCode: 8PSDPD |
| IssuedBy: GSA, DFC SERVICE CENTER DIVISION 8PSDPD |
BLDG 41 DFC PO BOX 25546
W 6TH AVE & KIPLING STREET
DENVER CO 80225-0546
| AdminByCode: |
| AdminBy: See Block 6 |
| ContractorCode: |
| FacCode: |
| SolChg: Yes |
| AwdChg: Off |
| SolNo: GS-08P-12-JA-C-0054 |
| SolDate: JUL 31, 2012 |
| AwdNo: |
| AwdDate: |
| NoCopies: 1 |
| Amended: Yes |
| OffrExt: Off |
| OffrNoEx: No |
| ApprData: See Schedule |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).: |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| SignName: |
| SignTitl: |
| ContDate: |
| ContrOfficerInfo: |
| CODate: |
| Contractor Info: |
| ContractorPOC: |
| Contractor: |
| ModAmount: |
| Header: |
| 15B. CONTRACTOR/OFFEROR: |
| Footer1: |
| signature: |
File details come from the government source that posted it. Updated .