1442Amendment0002.pdf
PDF 282 KB Posted
- Attached to
- Construction MACC 8(a) Federal contract opportunity
- Solicitation number
- GS-08P-08-JB-D-0048
About this file
Amendment 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 8a bidders conference.pdf | ||
| 1442 Amendment.0003.pdf | ||
| 1442 Amendment 0004.pdf | ||
| Questions Set 3.doc | DOC document | |
| EXHIBITGWageDetermination.doc | DOC document | |
| ExhibitB-PastPerformanceQuestionnaireOfferor.doc | DOC document | |
| A-WALLSEC.pdf | ||
| 2008GSAIDIQSolicitation8(a)RFP.doc | DOC document | |
| M-1.pdf | ||
| E-400106E2.pdf | ||
| E-400106E1.pdf | ||
| A-MILLWORK.pdf | ||
| 1442Amendment0001.pdf | ||
| ExhibitGSpecs.pdf | ||
| A-FLOORPLAN.pdf | ||
| A-INTELEV.pdf | ||
| 8(a)IDIQMACCSolicitationGS-08P-08-JB-D-0048.pdf | ||
| E-400106E3.pdf | ||
| A-COVER.pdf | ||
| E-400106E4.pdf | ||
| A-WALLSEC2.pdf | ||
| ExhibitF-IDIQPriceProposalFormat.xls | XLS spreadsheet | |
| A-REFCLGPLAN.pdf |
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATiON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED
(SEE
ITEM
11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
GS-08P-08-JB-D-0048
Amendment 0002 Questions & Answers through 3/18/2008
Q1. GSA solicitation Pg. 6 Item 3: “Proposal must be clearly marked on outside of package...” Is there a form (proposal) that should be used to attach to the outside of package or ?
A1. Please make sure the solicitation number is marked on the outside of the envelope or package. No special form is needed.
Q2. Exhibit “C”: Can additional sheets be attached to this exhibit? If so, is there maximum?
A2. No additional sheets should be attached to Exhibit C – Key Personnel Resumes.
Any additional sheets that are submitted will not be evaluated.
Q3. SF1442 Page Nos. 3, 4 & 5: Half of the items have a value of 50.00 in the ‘Quantity’ column w/ ‘JB’ in the ‘Unit’ column. What do these column entries refer to?
A3. Each Task Order that we authorize under the contract will be considered one “job”, and we anticipate up to 50 jobs per fiscal year under these line items. We will discuss the SF1442 and present an example at the Bidder’s Conference.
Q4. IDIQ Price Proposal/ Bid Format Overhead & Profit: What is the GSA anticipated percentage for Contractor OH&P, if any?
A4. Price factors proposed in Exhibit E are to be determined by the Offeror. These factors will be evaluated to establish the competitive range, and are a significant factor for contract award. (See page 9, Factor 3: Price Factors.)
The percentages and rates that are submitted on Exhibit E- Price Factors will become a “ceiling” for future Task Orders. Bids for future Task Orders cannot exceed these amounts. Contractors may elect to submit rates that are lower, if appropriate, for individual Task Orders.
Q5. Solicitation Page 61 Section 00810.g Task order types: What percentage can an Offerer suppose for a given contract term for each task type, if any?
A5. These percentages are unknown. Based on recent history, we would expect Tenant Finishes and Repair & Alterations to be the majority of potential Task Orders.
Q6. Solicitation Page 59 Section 00800.1 Performance of Work/ Limitations on Subcontracting: Which condition (service-supply contract or indefinite quantity 8(a) award) applies to this solicitation? What constitute ‘applicable’ costs?
A6. The Indefinite Quantity 8(a) award terms apply to this contract. Applicable costs are labor costs.
Q7. Please clarify the 50% rule that the company has to perform with its own forces.
A7. In any 6 month period, 50% of the total labor costs for all Task Orders completed must have been self-performed.
Q8. When reviewing Solicitation #GS-08P-08-JB-D-0048, it seemed that the bulk of the Past Performance Questionnaire was missing. Should there be more to the Exhibit B form beyond page 68?
A8. Yes, pages were inadvertently omitted. This has been corrected on Amendment 0002.
Q9. I am unable to open the drawing file “E-400106E4.pdf.” Can this be reposted on the website?
A9. This file is posted on FedBizOpps. It has been verified, and appears to be fully accessible.
Q10. Is there a Wage Determination for the Sample Project?
A10. Yes. Wage Determination CO20080004 03/07/2008 for Denver, Colorado has been incorporated in Amendment 0002.
| IDCode: |
| EffDate: MAR 18, 2008 |
| ReqNo: 8PC-C-08-0031 |
| ProjNo: |
| IssuedBy: GSA PBS COLORADO SVS CTR 8PC |
BLDG 41 DFC PO BOX 25546
W 6TH AVE & KIPLING ST
DENVER CO 80225-0546
| AdminBy: See Block 6 |
| NoCopies: 1 |
| Amended: Yes |
| ChgeOrder: |
| Modify: Off |
| SuppAuth: |
| OthrSpec: |
| Require: Off |
| Copies: |
| Descript: A. This amendment incorporates Exhibit G - Davis Bacon Wage Determination for the Sample Project. |
B. This amendment deletes the sentence "Task Orders pertaining to secondary service areas will be permitted a travel allowance" from page 3, Section 00010.
C. This amendment corrects Exhibit B Past Performance Questionnaire by adding pages 2 and 3.
D. This amendment adds the following language to Section 00810e, "GSA will provide a standard format for proposal submission. A price that is found to be either unreasonably high or unrealistically low in relation to the proposed work may be indicative of an inherent lack of understanding of the solicitation requirements and may result in the proposal being rated lower or considered unacceptable.
Any inconsistency, whether real or apparent, between proposed performance and price must be clearly explained in the price proposal. For example, if unique and innovative approaches are the basis for an apparently unbalanced/inconsistently priced proposal, the nature of these approaches and their impact on price must be completely documented. The burden of proof of price realism rests solely with the Offeror."
E. This Amendment incorporates answers to questions received through March 18, 2008.
| SignName: |
| SignTitl: |
| ContDate: |
| CODate: |
| OffrExt: Off |
| OffrNoEx: No |
| ChgeOrd: Off |
| SuppAgre: Off |
| ModOthr: Off |
| NoReq: Off |
| ContractorCode: |
| FacCode: |
| ContractorPOC: |
| AwdChg: Off |
| SolChg: Yes |
| SolNo: GS-08P-08-JB-D-0048 |
| SolDate: MAR 11, 2008 |
| AwdNo: |
| IssuedByCode: 8PC |
| AdminByCode: |
| ContrOfficerInfo: |
| DocNo: 0002 |
| AwdDate: |
| text1: 10B. DATED (SEE ITEM 13) |
| block 14: 14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.) |
| pageblock: PAGE OF PAGES |
| block13: 13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14. |
| Contractor: |
| ContratorInfo: |
| ModAmount: |
| block12: 12. ACCOUNTING AND APPROPIATION DATA (If required) |
| ApprData: See Schedule |
| Pages: 3 |
| Page: 1 |
File details come from the government source that posted it. Updated .