Amendment_03.pdf

PDF 66 KB Posted

Attached to
BAS Replacement at the Roswell Federal Building
Solicitation number
GS-07-P-16-HT-C-7005
Issued by

About this file

Amendment 03

View the file

Other files

File Type Posted
Amendment_04.pdf PDF
Roswell_Points_List.xlsx XLSX spreadsheet
Inventory_Report_Roswell.xlsx XLSX spreadsheet
Amendment_02.pdf PDF
Amendment_01.pdf PDF
PBS_Past_Performance_Questionnaire.docx DOCX document
Pre-Proposal_Attendee_Registration_Form.pdf PDF
GS-07-P-16-HT-C-7005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

7PQD

See the attached.

7PQD

Energy & Acquisition Support Branch

819 TAYLOR ST

FORT WORTH, TX 76102-6124 United States

Energy & Acquisition Support Branch

819 TAYLOR ST

FORT WORTH, TX 76102-6124 United States

GS-07-P-16-HT-C-7005

1 2

06/16/2016

05/23/2016

Amendment No. 3 – Solicitation No. GS-07-P-16-HT-C-7005 for BAS Replacement at the Roswell Federal Building in Roswell, NM

This amendment is issued to respond to questions and to provide the Points List (separate document).

1. Are there any abatement or do not disturb concerns related to building construction materials? Yes and it will be handled under a separate contract vehicle.

2. Do we need to perform Test and Balance on this project? The scope of work does not mention Test and Balance but there is a Test and Balance specification. If so do you want air and water both? Not a true test and balance but to ensure plant functionality.

3. On other GSA projects we had to supply a UPS on each JACE 700. I don’t see that in this scope of work. Do we need to supply this? No UPS is needed.

4. On the 144 Fan Coils, are we going to do a group enable and leave all controls pneumatic? The fan coils control will remain the same. There are two groups per floor, are we to tie into where the old time clocks are currently controlling the fan coils?

Remove time clocks and integrate into the BAS.

File details come from the government source that posted it. Updated .