EXAMPLE_CSI_Master_Format.pdf
PDF 218 KB Posted
- Attached to
- Bob Casey Restroom Upgrade - Side "A" Federal contract opportunity
- Solicitation number
- GS-07P-15-UR-C-0004
About this file
Example CSI Master Format
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Drawings_50__-_Bob_Casey_Restroom.pdf | ||
| SF_1442_-_BC_RR_(Solicitation).pdf | ||
| W D_-_dated_11.7.14_(Harris_County).pdf | ||
| FSRS_Reporting_Requirement_Form.pdf | ||
| C301_BC_RR_(Side_A).pdf | ||
| Key_Personnel_Resume.pdf | ||
| ELECTRICAL_SET_50__-_Bob_Casey_Restroom.pdf | ||
| C101-SB_-_BC_RR_(Side_A).pdf | ||
| A-Side_Restrooms_SOW_Design-Build_11-14-14.pdf | ||
| C201-SB__BC_RR_(side_A).pdf | ||
| Past_Performance_Sheet.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: Example Project #1 Project Duration: 2 Weeks
Agency: Company Name Estimator: Names of Lead Estimator
Address: 1234 Main St. Suite 1 Project Manager: Name of Lead Project Manager
Date: 6/1/2014
01 General Conditions
01 31 Project Management and Coordination 1 LS 2,557$ -$ -$ 2,557$
01 51 Temporary Utilities 1 LS 1,500$ 800$ -$ 2,300$
01 55 Vehicular Access and Parking 1 LS -$ 250$ -$ 250$
01 76 Protecting Installed Construction 1 LS 2,200$ 300$ 250$ 2,750$
01 General Conditions 7,857$
02 Existing Conditions
02 41 Demolition 2500 SF 3,000$ -$ 2,700$ 5,700$
02 42 Removal and Salvage of Construction Material 1 LS 800$ -$ 925$ 1,725$
02 82 Asbestos Remediation 1500 SF 1,500$ 1,200$ -$ 2,700$
02 Existing Conditions 10,125$
08 Openings
08 11 Metal Doors and Frames 5 EA 325$ 2,100$ -$ 2,425$
08 71 Door Hardware 1 LS 185$ 800$ -$ 985$
08 74 Access Controlled Hardware 1 LS 200$ 250$ -$ 450$
08 Openings 3,860$
09 Finishes
09 05 Common Work Results and Demolition for Finishes 1 LS 125$ -$ -$ 125$
09 29 Gypsum Board 20 SF 150$ 55$ -$ 205$
09 68 Carpeting 800 SF 350$ 950$ -$ 1,300$
09 72 Wall Covering 400 SF 275$ 625$ -$ 900$
09 91 Painting 250 SF 125$ 80$ -$ 205$
09 Finishes 2,735$
21 Fire Suppression
21 13 Fire Suppression Sprinkler System 1 LS 200$ 50$ -$ 250$
21 Fire Suppression 250$
23 Heating, Ventilating, & Air Conditioning
23 37 Air Outlets and Inlets 1 LS 180$ 80$ -$ 260$
23 Heating, Ventilating, & Air Conditioning 260$
26 Electrical
26 05 Common Work Results and demolition for Electrical 1 LS 210$ -$ -$ 210$
Description Quantity Division TotalsTotal Labor Total
Material
Total
Equipment
Line Item
Totals
26 05 Common Work Results and demolition for Electrical 1 LS 210$ -$ -$ 210$
26 29 Low-Voltage Controllers 1 EA 210$ 250$ -$ 460$
26 51 Interior Lighting 3 EA 175$ 75$ -$ 250$
26 Electrical 920$
27 Communications
27 15 Communications Horizontal Cabling 1 LS 210$ 150$ -$ 360$
27 Communications 360$
28 Electrical Safety & Security
28 13 Access Control 1 LS 400$ 750$ -$ 1,150$
28 31 Fire Detection and Alarm 1 LS 140$ -$ -$ 140$
28 Electrical Safety & Security 1,290$
Subtotal of work above 27,657$
Subcontractor 1 Overhead & Profit 10.0% Total 1,600$
Subcontractor 2 Overhead & Profit 10.0% Total 1,200$
Subcontractor 3 Overhead & Profit 10.0% Total 350$
Design Fees 2.5% Total 2,504$
Subcontractor Total Fees 5,654$
Insurance 5.0% Total 1,702$
Bond 0.5% Total 170$
Overhead 1.0% Total 340$
Profit 0.5% Total 170$
General Contractor Total Fees 2,382$
GSA Building Security Supervision 40 Hours Total 4,000$
Additional Total Mark Ups 4,000$
Estimate Total 39,693$
JasonRCook Text Box For Example Only.
Totals do not represent real values.